RFI_Document_for_AG-9AD6-S-15-0002.docx

DOCX document 14 KB Posted

Attached to
Wood Steps & Handrail, Wood ADA Ramp, Natural Stone Path and Courtyard Patio Construction
Solicitation number
AG-9AD6-S-15-0002
Issued by

About this file

RFI document for AG-9AD6-S-15-0002

View the file

Other files

File Type Posted
Updated-Corrected_Section_J-2_-_Davis_Bacon_Wagedecision_Act.pdf PDF
AG-9AD6-S-15-0002_amendment_P0001.pdf PDF
SECTION_G_-__Laupahoehoe_Wood_Steps_ _Handrail _Wood_ADA_Ramp _Natural_Stone_Path_and_Courtyard_Patio.docx DOCX document
Section_J-3_-_Drawings.pdf PDF
SECTION_L_-__Wood_steps_and_Handrail_Wood_ADA_Ramp_and_Natural_Stone_Path_and_Courtyard_Patio_Construction.docx DOCX document
SECTION_E_-__Wood_Steps_ _Handrai _l_Wood_ADA_Ramp _Natural_Stone_Path_and_Courtyard_Patio.docx DOCX document
Section_C_-___Laupahoehoe_Wood_Steps_ _Handrail __Wood_ADA_Ramp _Natural_stone_Path_and_Courtyard_Patio.docx DOCX document
Section_B_Schedule_of_Items_for_Wood_Steps_and_Handrail_Wood_ADA_Ramp_and_Natural_Stone_Path_and_Courtyard_Patio_Construction.doc DOC document
SECTION_M_-__Wood_Steps__Handrail_Wood_ADA_Ramp_and_Natural_Stone_Path_and_Courtyard_patio_Construction.docx DOCX document
PART_III_-_List_of_Documents _Exhibits _and_other_Attachments.pdf PDF
PART_II_-_Section_I_-_Laupahoehoe_Wood_Steps_ _Handrail _Wood_ADA_Ramp _Natural_Stone_Path_and_Courtyard_Patio.docx DOCX document
SF1442-14a.pdf PDF
SECTION_F_-__Wood_Steps_ _Handrail __Wood_ADA_Ramp _Natural_Stone_Path_and_Courtyard_Patio.docx DOCX document
Section_J-1_-_Definition_of_bid_items.pdf PDF
PART_IV__Section_K_-_Wood_Steps_and_Handrail_Wood_ADA_Ramp_and_Natural_Stone_Path_and_Courtyard_Patio.docx DOCX document
Section_J-2_-__Davis_Bacon_Wage_Rates_for_Laupahoehoe_Asphalt_and_Concrete.docx DOCX document
Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Contract Number:AG-9AD6-S-0002
Project:Laupahoehoe Science and Education Center Wood Steps and Handrail, Wood ADA Ramp, Natural Stone Pathway and Courtyard Patio Construction

Questions and Answers submitted by Sun Construction Inc. on January 29, 2015

1. Section J-1, Division 6-Wood: There is a mention of using Camaru for decking and Sothern Yellow Pine for stair treads/raining. Is the intention to use Camaru on stair treads and ADA ramp decking? Please advise.

Answer. Camaru shall be used for both the stair treads and the ADA ramp decking. Intent is to match existing wood decking on original patio deck for the new ADA Ramp and stair treads.

2. Would the use of Hi Bor pressure treated Douglas Fir be acceptable for railings in lieu of Southern Yellow Pine.

Answer. Hi Bor pressure treated Douglas Fir will be acceptable in lieu of Southern Yellow Pine as long as structural characteristics exceed those of the specified Southern Yellow Pine. Material sizes shall remain the same as shown on the drawings.

3. Section J-3 Drawings calls for the use of 3” compacted sand bedding below the natural stone pavers. Would #4 sand, manufactured locally from crushed rock be acceptable bedding material?

Answer. Specification for Natural Stone Path and Courtyard Patio, Part 2 Products, Aggregate Base, Section B allows for sand to be No. 4 or finer with no deleterious material. #4 sand manufactured locally is acceptable as long as it meets these requirements

4. Is there a preference for the type of sand used in the 50/50 mix of top soil being placed between gaps of natural stone pavers to promote grass growth?

Answer. Sand for mix shall be No. 4 or finer.

5. Regarding Section J-2 Davis Bacon Wage rates for Laupahoehoe Asphalt and Concrete. Shall selected contractor be limited to the use of those wage rates or shall other wage rates apply? (i.e. carpenter rate, Concrete and Masonry, Landscape laborer.

Answer. Updated/Corrected Davis Bacon Wage rates included in amendment.