Amendment_1_pg_8.pdf

PDF 288 KB Posted

Attached to
Roof Replacement - Weaverville Ranger District
Solicitation number
AG-9AC7-S-16-0021
Issued by

About this file

2) AG-9AC7-S-16-0021 Amendment 1

View the file

Other files

File Type Posted
CA9 _Mod_2 _dated_01292016.pdf PDF
Amendment_1 _SF-30_signed.pdf PDF
WV_2004_BLDG_SITE_PLAN_TITLED.pdf PDF
CA9 _mod_1 _01152016.pdf PDF
AG-9AC7-S-16-0021_Solicitation.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Amendment 1 CONSTRUCTION RFQ

SECTION D--PACKAGING AND MARKING

{For this Solicitation, there are NO clauses in this Section}

SECTION E--INSPECTION AND ACCEPTANCE

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

FAR: https://www.acquisition.gov/far AGAR: http://www.dm.usda.gov/procurement/policy/agar.html

FAR 52.246-1 Contractor Inspection Requirements (APR 1984) FAR 52.246-12 Inspection of Construction (AUG 1996)

SECTION F--DELIVERIES OR PERFORMANCE

FAR 52.242-14 Suspension of Work (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives Notice to Proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 21 calendar days after receipt of Notice to Proceed. The time stated for completion shall include final cleanup of the premises.

The anticipated start work date is April 1, 2015. Note: Submittals and ordering may begin before construction starts.

Within seven (7) calendar days after receipt of a written request from the Contracting Officer, the Contractor must submit the following information in writing for approval:

(a) A schedule as required by FAR clause 52.236-15, Schedules for Construction Contracts, and

(b) The hours (including the daily starting and stopping times) and days of the week the Contractor proposed to carry out the work.

Weaverville RD Roof Replacement, Amendment 1 AG-9AC7-S-16-0021

Shasta-Trinity National Forest Page 8 of 26

AGAR 452.236-75 MAXIMUM WORKWEEK – CONSTRUCTION SCHEDULE (NOV 1996)

FAR 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

INCORPORATED BY REFERENCE

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

INCORPORATED BY REFERENCE

FAR 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

https://www.acquisition.gov/far http://www.dm.usda.gov/procurement/policy/agar.html http://acquisition.gov/far/current/html/52_246.html#wp1118709 https://acquisition.gov/far/current/html/52_246.html#wp1118901 https://acquisition.gov/far/current/html/52_246.html#wp1118901 https://acquisition.gov/far/current/html/52_241_244.html#wp1128875 http://www.dm.usda.gov/procurement/policy/agar_x/agar04/subchaph.html#23675 https://acquisition.gov/far/current/html/52_207_211.html#wp1141217 https://acquisition.gov/far/current/html/52_248_253.html#wp1120047