AG-9AC7-S-15-0155_Technical_Specifications.pdf
PDF 7 MB Posted
- Solicitation number
- AG-9AC7-S-15-0155
About this file
Technical Specifications Maps and Diagrams
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Wage_Determination_CA150009_17Jul15_CA9.pdf | ||
| AG-9AC7-S-15-0155.pdf | ||
| Supplies_for_Soda_Creek _Swain_and_Flone_Aspen.pdf | ||
| Fire_Plan.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Soda Creek, Swain and Flone Aspen Fencing
Technical Specifications, Maps and Diagrams
AG-9AC7-S-15-0155
SUMMARY OF ITEMS
1) SODA CREEK FENS AND RARE PLANT FENCING
OBJECTIVE 3
SCOPE 3
PROJECT LOCATIONS 3
TECHNICAL REQUIREMENTS 5
SODA CREEK MAPS 7
SODA CREEK DIAGRAMS 9
2) SWAIN VERNAL POOL FENCE ADDITION
OBJECTIVE 15
SCOPE 15
PROJECT LOCATIONS 15
TECHNICAL REQUIREMENTS 16
SWAIN MAPS 18
SWAIN DIAGRAMS 20
3) FLONE ASPEN STAND FENCING
OBJECTIVE 22
SCOPE 22
PROJECT LOCATIONS 22
TECHNICAL REQUIREMENTS 22
FLONE ASPEN MAPS AND DIAGRAMS 23
ITEMS APPLICABLE TO ALL AREAS
PROTECTION MEASURES 36
AG-9AC7-S-14-0155 Technical Specifications, Maps and Diagrams - Page 1 of 36
TECHNICAL SPECIFICATIONS
SUMMARY OF ITEMS
This contract is for the installation of various fencing types at multiple project locations in
Plumas County. The fence types and locations are summarized as follows:
1. Soda Creek Fens and Rare Plant Fencing
a. Construction of 8 split cedar rail fences using stacked/zig-zag design to exclude livestock
b. Combined total of 1,780 feet (0.34 miles) of split cedar rail fence
c. Locations:
i. 1 fence at North Fork Willow Creek
ii. 2 fences at Milkhouse Flat
iii. 4 fences at LT Creek
iv. 1 fence at Horseshoe Fen
2. Swain Vernal Pool Fence Addition
a. Construction of 2 buck and rail fence additions to an existing fence
b. Combined total of 720 feet (0.14 miles) of buck and pole fence construction
c. Locations:
i. Upper Swain Meadow East Side
ii. Upper Swain Meadow West Side
3. Flone Aspen Stand Fencing
a. Construction of deer-proof fence to exclude deer from aspen stand
b. 25,740 linear feet (78 rolls x 330 feet each) of 7.5 foot high deer fence is
Government-provided. The constructed fence must encircle the entire stand and be spaced between 25 and 50 feet away from the aspen.
c. Locations:
i. Hwy 36 along Plumas County road 311 (Warner Valley Road)
ii. Hwy 36 to Hwy 32 and Skyway in proximity to Philbrook Lake (Butte
County)
AG-9AC7-S-14-0155 Technical Specifications, Maps and Diagrams - Page 2 of 36
1) SODA CREEK FENS AND RARE PLANT FENCING
OBJECTIVE
The Soda Creek Fens and Rare Plant Fencing Project is intended to address protection of selected areas with sensitive features including fens and rare plant habitat for Botrychium or other species. The project is within the Soda Creek/North Butte Allotment on the Lassen
National Forest.
SCOPE
The project consists of constructing eight split cedar rail fences using the stacked/ zig-zag design to exclude livestock. The scope of work includes constructing a combined total of 1,780 ft. feet
(0.34 miles) of split cedar rail fence. The eight exclosures are within 1 to two miles of each other and within 0.15 miles of Forest Service roads. The project area where the fences will be constructed has a moderate grade and wet meadow conditions.
The Contractor shall, considering the specific tasks and critical subtasks involved, develop a plan of operations to accomplish the tasks and critical subtasks, and organize and direct all of the operations and personnel needed to fully accomplish the work. All terms and conditions of the parent contract are applicable unless otherwise specified. The Contractor shall furnish all technical expertise, labor, equipment, supervision, transportation, operating supplies, and incidentals necessary to complete the project, except for that which the Contract clearly states is to be furnished by the Government.
PROJECT LOCATIONS
The project is located on the Almanor Ranger District of the Lassen National Forest in Plumas
County, California. It entails four locations (A-D) and eight items. Refer to attached maps.
Location A: North Fork Willow Creek: T. 26 N., R.5E, Section. 15.
Item 1: One split cedar rail fence exclosure (map reference - pFESC4) around the spring and drainage (approx. 100 ft. x 50 ft.
Location B: Milkhouse Flat: T. 26 N., R. 6 E Section 19:
Item 2: One split cedar rail exclosure fence (pFESC5a) around the spring (approx. 50 ft.
x 50 ft.)
Item 3: One split cedar rail exclosure fence (pFESC5b) in the upper area of Milkhouse
Flat around some willows (approx. 70 ft. x 70 ft.)
Location C: LT Creek: T. 26 N., R. 6 E. Section 19
Item 4: One interior split cedar rail exclosure fence (pFESC2a) within an existing
(electric) LT fence area (approx. 50 ft. x 50 ft.)
AG-9AC7-S-14-0155 Technical Specifications, Maps and Diagrams - Page 3 of 36
Item 5: One interior split cedar rail exclosure fence (pFESC2b) within an existing
(electric) LT fence area (approx. 50 ft. x 50 ft.)
Item 6: One interior split cedar rail exclosure fence (pFESC2c) within an existing
(electric) LT fence area (approx. 50 ft. x 50 ft.)
Item 7: One interior split cedar rail exclosure fence (pFESC2d) within an existing
(electric) LT fence area (approx. 50 ft. x 50 ft.
Location D: Horseshoe Fen T. 26 N., R. 6 E., Section 20:
Item 8: One split cedar rail exclosure fence (pFESC6) (approx. 50 ft. x 50 ft.)
To reach the general vicinity of the four locations and central portion of Soda Creek/North Butte
Allotment from Chester, California the following routes are suggested:
From Chester, travel west 1 mile on State Highway 36, then 4 miles south east on State Highway
89. Turn south on County road 308 (Yellow Creek Campground/ Humbug Valley road). Travel approximately ½ mile to the junction of county roads 308 and 309. Take county road 309 south
1 mile to the junction of 309 and County Road 307 (the Humbug Road). Continue on the
Humbug Road South 4½ miles across Humbug Valley, past Little Grizzly Valley and over
Humbug Summit to the Cold Springs turnout/parking area (pacific crest trail crossing).
From the Cold Springs turnout area, Location A may be accessed from the Humbug Road as follows:
Location A: North Fork Willow Creek: T. 26 N., R.5E, Section. 15.
Travel approximately ¼ mile west of Cold Springs turnout/ parking area along the
Humbug Road to Forest Service road 26N84 (North Fork of Willow Creek). Take 26N84 north approximately one mile past the junction of 26N84A to a bend in the road. The spring area (item 1) is approximately 200 feet from the east side of road 26N84.
From Location A, Locations B-D may be accessed from various directions and routes connecting to the Humbug Road, including 26N02 (Willow Creek), 26N31 (Slate/Sawmill Tom), or 26N35
(Rock Creek). The following (loop) route is suggested:
Location B: Milkhouse Flat: T. 26 N., R. 6 E., Section 19:
From the Cold Springs parking area, travel approximately 1/2 mile southwest along the
Humbug Road to 26N02 (Willow Creek), then travel southeast to 26N31A and continue approximately ½ mile to Milkhouse Flat. The spring area (item 2) is on the north side of road 26N31A and the meadow/willow area (item 3) is on the south side.
Location C: LT Creek: T. 26 N., R. 6 E., Section 19:
From the Milkhouse Flat area, travel back to 26N31 and head south approximately ¼ mile to 26N35. Travel east about 0.25 mile on 26N35 and walk down about 0.15 mile to
LT Creek and the meadow area (items 4-7) within an existing electric fence. Another
AG-9AC7-S-14-0155 Technical Specifications, Maps and Diagrams - Page 4 of 36 option is to park at 26N35A which is a dead end/ water drafting area and walk in about the same distance to reach the meadow area.
The current electric fence (FESC2) at LT Creek may be energized at times during the grazing season. This electric fence is also planned to be realigned (rFESC2). Fence construction in this area will be coordinated with the permittee and other ongoing activities as needed.
Location D: Horseshoe Fen (pFESC6): T. 26 N., R. 6 E., Section 20
From the LT Creek area, travel along 26N35 about ½ mile east to the Horseshoe fen area
(item 8). The meadow is located along the north side of road 26N35 and the fen can be reached by walking in a short distance.
Maps and Site Specific Locations: The maps are intended to show only the general size, shape, and location of the fence areas. If the maps conflict with the field marking, the field markings shall govern. Approximate fence locations in Items 1-8 will be flagged with yellow or white flagging. Should boundaries of the work units be unclear to the Contractor, the Contractor shall notify the COR or Inspector. The Contractor may elect to make slight changes in the location of the fences; however, these changes must be approved by the Forest Service prior to erecting the fence. See attached maps.
TECHNICAL REQUIREMENTS
Work Schedule /Operations: The Contractor will notify the COR two days in advance of where and when work will start. Forest Service personnel will be available to answer questions or check areas Monday - Friday, 8:00 am to 5:00 pm. Contractor may work other than these hours and on weekends. Contractor may accompany the Forest Service inspector when conducting final inspections for acceptance and payment. The Forest Service may set the order in which the fences are constructed depending on permittee coordination needs. Camping is allowed as per forest policy.
Fence Materials/ Locations: Materials can be stored and picked up by the Contractor at the
Almanor Ranger District Office, or the Contractor and the COR will agree upon the location of the delivery point or accessible point for any storage of fence materials at the pre-work conference.
Vehicle Operations: Forest roads are generally accessible by two-wheel drive vehicle during the normal operating season but four wheel drive may be recommended for some areas or time periods. For dispensing of fence material, most sites are accessible by truck and ATV/OHV.
However, other equipment for fence construction may include a skid steer and/or a four wheel drive tractor.
No vehicles will be permitted to operate off system roads without approval of the COR. Where allowed, vehicles may approach the area cleared for the fence but vehicles may not cross interior areas of fence.
AG-9AC7-S-14-0155 Technical Specifications, Maps and Diagrams - Page 5 of 36
Fence Clearing: The Contractor will clear a path of brush, forest debris, or other obstructions less than six feet wide. This path, which will lie outside the fence, serves as the access corridor for erecting the fence, and serves as an access for maintenance of the fence.
It may not however be necessary to disturb the ground around the entire perimeter. In meadow areas and in cases where the ground is generally level and free of brush or debris, ground disturbance will not take place.
All clearing will be done by the contractor using a power saw or other hand tools. Material so removed shall be scattered outside the clearing limits. If trees greater than 8 inches dbh need to be removed contact the COR for approval prior to removing. The Contractor shall not use tractor or dozer for clearing. Grading along fence line is not allowable.
Fence Construction – For the Soda Creek project fences, split rails that will be used are western red cedar, ten feet long. Split members will be at least 18 -20” girth (super jumbo size) up to a cross-sectional area at the small end of eight to ten inches. The ten foot length will allow for one foot of overhang on each end. A minimum of four rails per section will be used for a fence height of 4.6 to five feet. The distance between the zig zags will be approximately 16.5 feet and the angle of zigzag will be approximately 130 degrees.
To keep the bottom rails off the ground some of the ten foot rails will be cut into five two foot length “chocks”. One chock will be put under each joint in fence at every zig zag to keep the bottom rails twelve inches off the ground. The chocks are laid out about eight feet apart.
Nails, spikes (80d), or lag screws (5/8 - 7") or 1/2" rebar may be used to secure the rails together.
Drills may be used for rebar to provide 5/8" holes in the center of the rails at each end and in the center of the chocks. A sledge hammer may be used to hit down spikes or rebar.
Tie posts are not necessary if the fence is well zig-zagged. Rails larger than super jumbo size (or greater than ten inches across) may be notched as well as secured with spike or rebar. Notches would be approximately three inches deep.
AG-9AC7-S-14-0155 Technical Specifications, Maps and Diagrams - Page 6 of 36
SODA CREEK MAPS 1 of 2
AG-9AC7-S-14-0155 Technical Specifications, Maps and Diagrams - Page 7 of 36
SODA CREEK MAPS 2 of 2
AG-9AC7-S-14-0155 Technical Specifications, Maps and Diagrams - Page 8 of 36
SODA CREEK DIAGRAMS 1 of 6
AG-9AC7-S-14-0155 Technical Specifications, Maps and Diagrams - Page 9 of 36
SODA CREEK DIAGRAMS 2 of 6
AG-9AC7-S-14-0155 Technical Specifications, Maps and Diagrams - Page 10 of 36
SODA CREEK DIAGRAMS 3 of 6
AG-9AC7-S-14-0155 Technical Specifications, Maps and Diagrams - Page 11 of 36
SODA CREEK DIAGRAMS 4 of 6
AG-9AC7-S-14-0155 Technical Specifications, Maps and Diagrams - Page 12 of 36
SODA CREEK DIAGRAMS 5 of 6
AG-9AC7-S-14-0155 Technical Specifications, Maps and Diagrams - Page 13 of 36
SODA CREEK DIAGRAMS 6 of 6
AG-9AC7-S-14-0155 Technical Specifications, Maps and Diagrams - Page 14 of 36
2) SWAIN VERNAL POOL FENCE ADDITION
The Swain Vernal Pool Fencing Addition Project is intended to address protection of rare plant habitat for Orcuttia tenuis in the Swain Meadow area of the Robbers Creek Allotment on the
Lassen National Forest.
SCOPE
The project consists of constructing two buck and rail fence additions to an existing fence at
Swain Meadow to exclude vehicle access. The scope of work of the two items totals 720 feet
(0.14 miles) of buck and pole fence construction.
The Contractor shall, considering the specific tasks and critical subtasks involved, develop a plan of operations to accomplish the tasks and critical subtasks, and organize and direct all of the operations and personnel needed to fully accomplish the work. All terms and conditions of the parent contract are applicable unless otherwise specified. The Contractor shall furnish all technical expertise, labor, equipment, supervision, transportation, operating supplies, and incidentals necessary to complete the project, except for that which the Contract clearly states is to be furnished by the Government.
PROJECT LOCATIONS
The project is located on the Almanor Ranger District of the Lassen National Forest in Plumas
County, California. Refer to attached maps.
Location: Upper Swain Meadow (Swain Vernal Pool) additions to FERC5: T. 30 N., R. 8 E.
NWSW Section 22
Item 1:
East side (390 ft.) buck and pole fence (pFERC5a) connecting to existing Swain fence
Item 2:
West side (330 ft.) buck and pole fence (pFERC5b) connecting to existing Swain fence
To Access the Upper Swain Meadow (Swain Vernal Pool) (pFERC5 a-b) in the Robbers Creek
Allotment and Location E: T. 30 N., R. 8 E. NWSW Section 22: From Chester travel east on highway 36 12 miles to Westwood, turn north up A21 and travel approximately 9 miles to Swain
Mountain Snowmobile park. Turn east on Forest road 30N07 and travel to the existing buck and pole fence along the road.
Maps and Site Specific Locations: The maps are intended to show only the general size, shape, and location of the fence areas. If the maps conflict with the field marking, the field markings shall govern. Approximate fence locations in Items 1-2 will be flagged with yellow or white flagging. Should boundaries of the work units be unclear to the Contractor, the Contractor shall
AG-9AC7-S-14-0155 Technical Specifications, Maps and Diagrams - Page 15 of 36 notify the COR or Inspector. The Contractor may elect to make slight changes in the location of the fence; however, these changes must be approved by the Forest Service prior to erecting the fence. See attached maps.
Maps and Site Specific Locations: The maps are intended to show only the general size, shape, and location of the fence areas. If the maps conflict with the field marking, the field markings shall govern. Approximate fence locations in Items 1-8 will be flagged with yellow or white flagging. Should boundaries of the work units be unclear to the Contractor, the Contractor shall notify the COR or Inspector. The Contractor may elect to make slight changes in the location of the fences, however these changes must be approved by the Forest Service prior to erecting the fence. See attached maps.
TECHNICAL REQUIREMENTS
Work Schedule /Operations: The Contractor will notify the COR two days in advance of where and when work will start. Forest Service personnel will be available to answer questions or check areas Monday - Friday, 8:00 am to 5:00 pm. Contractor may work other than these hours and on weekends. Contractor may accompany the Forest Service inspector when conducting final inspections for acceptance and payment. The Forest Service may set the order in which the fences are constructed depending on permittee coordination needs. Camping is allowed as per forest policy.
Fence Materials/ Locations: Materials can be stored and picked up by the Contractor at the
Almanor Ranger District Office, or the Contractor and the COR will agree upon the location of the delivery point or accessible point for any storage of fence materials at the pre-work conference.
Vehicle Operations: Forest roads are generally accessible by two-wheel drive vehicle during the normal operating season but four wheel drive may be recommended for some areas or time periods. For dispensing of fence material, most sites are accessible by truck and ATV/OHV.
However, other equipment for fence construction may include a skid steer and/or a four wheel drive tractor.
No vehicles will be permitted to operate off system roads without approval of the COR. Where allowed, vehicles may approach the area cleared for the fence but vehicles may not cross the interior area of Swain Meadow.
Fence Clearing: The Contractor will clear a path of brush, forest debris, or other obstructions less than six feet wide. This path, which will lie outside the fence, serves as the access corridor for erecting the fence, and serves as an access for maintenance of the fence.
It may not however be necessary to disturb the ground around the entire perimeter. In meadow areas and in cases where the ground is generally level and free of brush or debris, ground disturbance will not take place.
All clearing will be done by the contractor using a power saw or other hand tools. Material so removed shall be scattered outside the clearing limits. If trees greater than eight inches
AG-9AC7-S-14-0155 Technical Specifications, Maps and Diagrams - Page 16 of 36 dbh need to be removed contact the COR for approval prior to removing. The Contractor shall not use tractor or dozer for clearing. Grading along fence line is not allowable.
Fence Construction (Buck and Pole): For the Swain Meadow/Robbers Creek Allotment addition fence, buck and pole fence material will be of well-seasoned pine material or other sound wood free of knots and has the bark stripped from at least one side for quick seasoning. A panel section of buck and pole fence will consist of two A-frame bucks, spaced an average of eight feet apart, with one brace and four rider poles rails attached perpendicular to the standing A-frames.
Bucks - The A-frame buck posts (also called buck sticks) will be a minimum three to six inches in diameter and six feet long. Bucks may be constructed from standard commercially pressure treated wooden posts 6.5 feet long with a 3.5 inch-minimum-top diameter.
Rider Poles - The fence will have four rider poles which will be a minimum three to five inches in diameter and eight to ten feet long, allowing for a maximum one foot of overhang on each end. One rider pole will go on the top, two on the front and one (also called rub pole) on the back.
Cross Braces - The cross brace poles for the bottom of the A-frame bucks will be at least two to three inches in diameter and six feet long. They can be cut from rider poles or other wood pieces (2” x 4”). For wet meadow areas, two cross pieces may be placed on each side at the base of the buck for stability (also called mud stilts).
The A-frames will be set at a 60-degree angle with the notches locked together. Notching Posts may be done with a chainsaw or axe and should be approximately three inches deep. A miter box with a 30° or 40° angle, constructed out of two- by ten-inch lumber may be used to cut the correct angle to join the buck members. The height of the top rider pole will be at least 42 inches or 4.6 feet in height. The bottom rider pole will be attached to the bottom of the A-frame, about eight inches from the bottom of each post. The crosspiece should extend beyond the posts, on the outside of the frame so that the lowest pole can be placed on top of the crosspiece. The lowest rider pole should be no higher than 8-10 to 14 inches above the ground.
To nail posts for A-frame bucks together, 60D-80D nails may be used depending on the size. A single six or eight inch spike may be driven through the center of the intersecting buck posts.
70D spikes may also be used and for nailing rider poles to the bucks. To nail the bottom cross pieces to the bucks, depending on the size 60D common nails may be used. Nails should extend a minimum of two inches into rider poles or cross pieces.
AG-9AC7-S-14-0155 Technical Specifications, Maps and Diagrams - Page 17 of 36
SWAIN MAPS 1 of 2
AG-9AC7-S-14-0155 Technical Specifications, Maps and Diagrams - Page 18 of 36
SWAIN MAPS 2 of 2
AG-9AC7-S-14-0155 Technical Specifications, Maps and Diagrams - Page 19 of 36
SWAIN DIAGRAMS 1 of 2
AG-9AC7-S-14-0155 Technical Specifications, Maps and Diagrams - Page 20 of 36
SWAIN DIAGRAMS 2 of 2
AG-9AC7-S-14-0155 Technical Specifications, Maps and Diagrams - Page 21 of 36
3) FLONE ASPEN STAND FENCING
The identified aspen stands shall have deer proof fence constructed around them to prevent deer from browsing the new growth.
SCOPE
The fence shall be constructed between 25 and 50 ft away from the aspen stems and shall surround the stand completely. The fence may incorporate natural physical barriers such as rivers, cliffs or boulders as long as the fence is constructed in such a way that deer cannot enter the stand. Rocks or logs shall be used to block gaps in the bottom of the fence where deer might be able to get under. The fence shall be constructed of 8 ft t-posts spaced 20 feet apart and inserted into the ground approximately 1-2 feet. The fence shall be a letdown fence so that it can withstand heavy snow loads in the winter. The deer mesh and wire shall be easily laid down in the winter months and easily put up in the spring. The deer mesh shall be attached around smooth wire that spans the top and bottom of the fence. The wire shall be secured to the t-posts with letdown fence clips and a nail. The mesh shall not be attached to the t-posts. Zip-ties or hog rings shall secure the deer mesh around the wire. Corners may be constructed using existing live trees (6 in dbh and larger), rock cribs or h-braces (See project specifications for details).
Corner trees shall be protected with wood braces so that the wire does not cut into and damage the tree.
PROJECT LOCATIONS
The project is located in two general areas on the Lassen National Forest, Almanor Ranger
District. Area 1 ( is in Plumas County located North of Chester CA and Hwy 36 along Plumas
County road 311 (or Warner Valley Road) in Township 29N Range 6E section 21 and T29, R5E sections 15,22,23.
Area 2 is located in Butte County. From Chester CA, South of Hwy 36 to Hwy 32 and the
Skyway in proximity to Philbrook Lake. Township 25N, Range 4E, sections 10 and 11.
TECHNICAL REQUIREMENTS
Support T-posts shall be in the ground about 2 feet and spaced every 20 feet. Smooth wire shall be used to support the deer fence and secure the fence to the t-posts (see pictures #6 and 8). The deer mesh shall be wrapped over the top smooth wire about 6 inches and secured to itself with hog clips or zip ties. The bottom smooth wire secures the fence to the bottom fence clip. Deer mesh shall be wrapped in the same way as the top with 6 in overlap and secured with hog clips or zip ties (see pictures #7 and 8). Two fence clips (see picture #9) per t-post, tree or wooden post is enough to secure the fence. Wire shall be held in the clip. The deer fence is not strong enough to hold the weight of the fence. When the fence turns a corner the appropriate support shall be
AG-9AC7-S-14-0155 Technical Specifications, Maps and Diagrams - Page 22 of 36 installed. Live conifer trees are the preferred support but h-braces or rock cribs may also be installed where suitable trees don’t exist. Trees selected as corners shall be live conifers (snags and aspen trees are not suitable) and at least 10 inches or greater diameter at breast height. The tree shall only support the corner t-post. To protect the tree from damage use pieces of 2X4s or suitable found logs, cut to 6-12 inches, (logs shall be approximately 3-4 in dbh) between the wire wrap and the tree (see pictures 3, 4 and 5). Then use wire to secure the top of the corner t-post
(see picture #1). If no tree is available install a rock crib or an h-brace or suitable wood post (see figure 1 and pictures #1, 2 and 6). If there is a straight away longer than 300 ft (about 15 t-posts) then use a wooden fence post or tree to add extra support. The fence is a letdown fence so use a chain link brace band placed over the corner t-post. The top smooth wire shall be secured to the brace band allowing for the entire mesh/wire fence to be laid down on the ground. This brace band should easily slide up and down the corner t-post for easy let down and put up. The deer mesh may then be loosely attached, via large zip ties at the corner posts or wrapped around the corner t-post and secured to itself. The wire and deer mesh shall move easily to the up position or the down position and the mesh should not be attached to the support t-post put held up with the fence clips.
FLONE ASPEN MAPS AND DIAGRAMS
Continue on following page.
AG-9AC7-S-14-0155 Technical Specifications, Maps and Diagrams - Page 23 of 36
Philbrook Creek
West Branch Feather Rive r
Bolt Creek
Fish Creek
Philbrook Reservoir
Snag Lake
BU 91513
26N74
BU 92523
25N05
25N15
26N17
25N07
N2
25N05B
25N36
26N01
26N74B
25N05C 25N05A
26N17A
25N 36A
25N05D
12 6
11 12
25 30
13 1814
Flone Aspen Fencing Contract
Project Area Map 1 of 2 Almanor Ranger District Lassen National Forest
0 0.5 10.25 Miles
Legend Aspen Stands to Fence
Land Ownership Forest Service Other Owner ±
R4E
SN01
PL01
PL12
PL15
PL18
PL14
PL24
PL19
PL30
PL13
T25N T26N
R5E
PL25 PL20
AG-9AC7-S-14-0155 Technical Specifications, Maps and Diagrams - Page 24 of 36
North Fork Feather River
Wi llow Creek
Stump Ranch
Domingo Lake
PL 311
29N18
29N33
29N16
29N79
29N95
29N97
29N14
29N96
29N83
29N76
29N92
29N43Y
29N71Y
29N
29N70
29N 39Y
29N
N2
2Y
29N40Y
29N17
29N95A
29N17F
29N95B
29N79B
28N
29N18H
29N79F
29N53B
29N27
29N79D
29N79A
N1
6C
29N45A
29N17G
29N53A
28N 61G
1 28N61E
29N12Y
29N34B
29N79C
29N33E
29N97A
29N79B1
29N63D
14 18
2 13
Flone Aspen Fencing Contract
Project Area Map 1 of 2 Almanor Ranger District Lassen National Forest
0 0.5 10.25 Miles
Legend Aspen Stands to Fence
Land Ownership Forest Service Other Owner ±
WD16
WD31
WI01
WD32
WD34
WD33
WD02
WD11
WD21
T26N, R6ET26N, R5E
AG-9AC7-S-14-0155 Technical Specifications, Maps and Diagrams - Page 25 of 36
Deer Fence Construction
Support T-posts should be in the ground about 2 ft and spaced every 20 ft. Smooth wire will be used to support the deer fence and secure the fence to the t-posts (see pictures #6 and 8 ).The deer mesh should be wrapped over the top smooth wire about 6 inches and secured to itself with hog clips or zip ties. The bottom smooth wire secures the fence to the bottom fence clip. Deer mesh should be wrapped in the same way as the top with 6 in overlap and secured with hog clips or zip ties (see pictures #7 and 8). Two fence clips (see picture #9) per t-post, tree or wooden post is enough to secure the fence. Make sure the wire is held in the clip the deer fence is not strong enough to hold the weight of the fence.
When the fence turns a corner the appropriate support should be installed. Live conifer trees are the preferred support but h-braces or rock cribs may also be installed where suitable trees don’t exist. Trees selected as corners would be live conifers (snags and aspen trees are not suitable) and at least 10 inches or greater diameter at breast height. The tree should only support the corner t-post. To protect the tree from damage use pieces of 2X4s or suitable found logs, cut to 6-
12 inches, (logs should be approximately 3-4 in dbh) between the wire wrap and the tree (see pictures 3, 4 and 5). Then use wire to secure the top of the corner t-post (see picture #1). If no tree is available install a rock crib or an h-brace or suitable wood post (see figure 1 and pictures #1, 2 and 6. If there is a straight away longer than 300 ft (about 15 t-posts) exists then use a wooden fence post or tree to add extra support. The fence is a let down fence so use a chain link brace band placed over the corner t-post. The top smooth wire is then secured to the brace band allowing for the entire mesh/wire fence to be laid down on the ground. This brace band should easily slide up and down the corner t-post for easy let down and put up. The deer mesh can then be loosely attached, via large zip ties at the corner posts or wrapped around the corner t-post and secured to itself. The wire and deer mesh should move easily to the up position or the down position and the mesh should not be attached to the support t-post put held up with the fence clips.
AG-9AC7-S-14-0155 Technical Specifications, Maps and Diagrams - Page 26 of 36
6 in steel Nails
A: 6x6X8 pressure treated post
B: 2x4X8 pressure treated lumber
Ground ft b u ried
4 ft
A A
A
B
B B
B B
Ground ft
Smooth wire
Post Corner H- Brace Detail Figure #1
Note: No cement, only compacted dirt and rocks or use of a rock basket as shown in Picture #1.
H-braces can be made with two posts rather than three. If two post design is used then the h-brace needs to be place perpendicular to the fence line. As shown in Picture #2.
AG-9AC7-S-14-0155 Technical Specifications, Maps and Diagrams - Page 27 of 36
Picture #1
AG-9AC7-S-14-0155 Technical Specifications, Maps and Diagrams - Page 28 of 36
Picture #2
H-brace with two posts should be installed perpendicular to the fence to help support the weight of the fence.
AG-9AC7-S-14-0155 Technical Specifications, Maps and Diagrams - Page 29 of 36
A
B
B
Tree Corner Brace Detail Figure #2
½ f t
A: Cut found logs approx. 3 in diameter or 2x4 lumber cut into 6-12 inches pieces. Pieces are not attached to the tree. Held to tree with wire.
Wire then supports t post #1. See Pictures 3, 4, 5 B: 8 ft steel t-post spaced 20 ft appart.
Fence clip
Smooth wire
Plastic deer mesh
Zip Ties or Hog clips
Deer mesh folds over wire 6 in.
and clips hold mesh together
Chain Link Brace Band
Wood fence clip detail
Steel fence clip detail
Chain link brace band and log detail
A A
A
A
A
#1
AG-9AC7-S-14-0155 Technical Specifications, Maps and Diagrams - Page 30 of 36
Picture #3 #1. Chain link brace band allows for the fence to easily slide down the t post. T-post installed at the corners need to be positioned so that the smooth side faces the tree.
Deer mesh should be loosely secured to the t-post with zip ties (#2) or by overlapping the mesh around the t-post and securing the mesh to itself with zip ties.
#1
#2
AG-9AC7-S-14-0155 Technical Specifications, Maps and Diagrams - Page 31 of 36
Picture #4 Picture #5 Corner trees should be alive and large enough to support the weight of the fence. 8 ft t-posts are installed adjacent to the tree to support the mesh fence. The top of the t-post needs to be supported by the tree. Wire should be wrapped around the tree with either 6-12 in log supports or cut 2X4 supports to not damage the tree. The wood supports are not attached to the tree. They are held in place by the wire. The wire may be attached to the top of the t-post only (as shown in Picture #5) or at the top and the bottom (as shown in Picture #4).
AG-9AC7-S-14-0155 Technical Specifications, Maps and Diagrams - Page 32 of 36
Picture #6
Picture #6:
Rock Cribs can be constructed where live trees are not available where a corner is needed. Note 5.6 ft tall t-posts are installed to support the rock basket but 8 ft t-posts are installed to support the mesh fence. Where possible deer mesh should be stretched to close any gaps created by the rock crib.
AG-9AC7-S-14-0155 Technical Specifications, Maps and Diagrams - Page 33 of 36
Picture #7 Picture #8
Smooth wire stretches along the top and bottom of the fence and will be attached to the t-posts via steel fence clips (picture 9). T-posts are spaced every 20
ft. Mesh should not be attached to the t-posts. The smooth wire needs to be able to be dropped during winter months to help protect the fence from snow loads. The mesh will overlap the top wire and will be secured to itself with either zip ties (picture 7) or hog rings (picture 8).
Picture #9
AG-9AC7-S-14-0155 Technical Specifications, Maps and Diagrams - Page 34 of 36
Topography created gaps between the ground and deer mesh greater than 6 inches should be filled in with rock or logs to prevent deer from entering exclosure underneath the wire.
Picture #10
Picture #11
AG-9AC7-S-14-0155 Technical Specifications, Maps and Diagrams - Page 35 of 36
ITEMS APPLICABLE TO ALL AREAS
PROTECTION MEASURES
Sensitive Areas: Sensitive areas, cultural resources sites, wetland, species habitat and native vegetation may exist within the project area. Operating areas, equipment ingress and egress will be approved by the COR in advance of work in each area.
Deer Drive: Prior to closing up each fence area, the Contractor shall conduct a deer drive to chase out any deer within the fence area. The Contractor shall time the drive so that the fence is closed a short time after the drive is completed (e.g. the same day).
Safety: The Contractor shall take all necessary precautions for the protection of the work and safety of the public. The Contractor will direct traffic if fence construction operations interfere with the use of roads.
The Contractor will ensure that all personnel use appropriate personal protective clothing and equipment. Appropriate clothing shall be based on the type and characteristics of the task anticipated (for example, felling hazard trees). Appropriate clothing shall be but is not limited to: protective chaps, hardhats, eye protection, hearing protection, boots and gloves.
It is the contractor’s responsibility to ensure that the work environment is safe for themselves as well as their employees. If the contractor feels that a requirement of this contract would place them or their employees in an unsafe environment, then work should stop on that area of work and the contractor should contact the COR. Work on other areas of the contract that the contractor does not view as unsafe should continue.
Final Clean-up: Before final acceptance, all areas occupied or used by the Contractor in connection with the work shall be cleaned of all Contractor’s rubbish, excess materials, temporary structures, and equipment, and all parts of the work area shall be left in a neat and presentable condition. The Contractor is responsible for the disposal of materials in a legal manner and the payments of all disposal fees. Burning of the removed material is not permitted on the work site.
AG-9AC7-S-14-0155 Technical Specifications, Maps and Diagrams - Page 36 of 36