Fire_Plan_ _General_Wage_Decision.pdf
PDF 741 KB Posted
- Solicitation number
- AG-9AC7-S-15-0006
About this file
Fire Plan General Wage Determination
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment_0001.pdf | ||
| Bid_Bond_SF_24-98.pdf | ||
| Solicitation.pdf | ||
| Special_Project_Specs_ _Plans.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FIRE PLAN FOR CONSTRUCTION AND SERVICE CONTRACTS
03/06/2013
1. SCOPE:
The provisions set forth below outline the responsibility for fire prevention and suppression activities and establish a suppression plan for fires within the contract area. The contract area is delineated by map in the contract. The provisions set forth below also specify conditions under which contract activities will be curtailed or shut down.
2. RESPONSIBILITIES:
A. Contractor
(1) Shall abide by the requirements of this Fire Plan.
(2) Shall take all steps necessary to prevent his/her employees, subcontractors and their employees from setting fires not required in completion of the contract, shall be responsible for preventing the escape of fires set directly or indirectly as a result of contract operations, and shall extinguish all such fires which may escape.
(3) Shall permit and assist in periodic testing and inspection of required fire equipment. Contractor shall certify compliance with specific fire precautionary measures in the fire plan, before beginning operations during Fire Precautionary Period and shall update such certification when operations change.
(4) Shall designate in the Fire Plan and furnish on Contract Area, during operating hours, a qualified fire supervisor authorized to act on behalf of Contractor in fire prevention and suppression matters.
B. Forest Service
The Forest Service may conduct one or more inspections for compliance with the Fire Plan. The number, timing, and scope of such inspections will be at the discretion of agency employees responsible for contract administration. Such inspections do not relieve the Contractor of responsibility for correcting violations of the fire plan or for fire safety in general, as outlined in paragraph 2.A above.
3. DEFINITIONS:
The following definitions shall apply:
Active Landing: A location the contractor may be skidding logs into, or performing other operations such as delimbing, log manufacturing, and chipping logs. Except for EV and E days, loading logs or stockpiling chips only, on a cleared landing, does not constitute an Active Landing.
Hot Saw: A harvesting system that employs a high-speed (>1100 rpm) rotating felling head, i.e., full rotation lateral tilt head.
Mechanical Operations: The process of felling, skidding, chipping, shredding, masticating, piling, log processing and/or yarding which requires the use of motorized power which includes, chainsaws, chippers, motorized carriages, masticators, stroke delimbers, skidders , dozers etc.
4. TOOLS AND EQUIPMENT:
The Contractor shall comply with the following requirements during the fire precautionary period, as defined by unit administering contracts:
The Fire Precautionary Period is set by the State of California which is April 1 through December 1 of any year.
Beaver Fire BAER Solicitation No. AG-9AC7-S-15-0006 1
• This contract requires, does not require, a Fire Box and associated Fire Tools according to CPRC Section 4428.
A. Fire Tools and Equipment: Contractor shall meet minimum requirements of Section 4428 of the California Public Resources Code (C.P.R.C.). Fire tools kept at each operating landing shall be sufficient to equip all employees in the felling, yarding, loading, chipping, and material processing operations associated with each landing. Fire equipment shall include two tractor headlights for each tractor dozer used in Contractor's Operations. Tractor headlights shall be attachable to each tractor and served by an adequate power source. All required fire tools shall be maintained in suitable and serviceable condition for fire fighting purposes.
Trucks, tractors, skidders, pickups and other similar mobile equipment shall be equipped with and carry at all times a size 0 or larger shovel with an overall length of not less than 46 inches and a 2-1/2 pound axe or larger with an overall length of not less than 28 inches.
Where cable yarding is used, Contractor shall provide a size 0 or larger shovel with an overall length of not less than 46 inches and a filled backpack can (4 or 5 gallon) with hand pump within 25 feet of each tail and corner block.
B. Fire Extinguishers: Contractor shall equip each internal combustion yarder, fuel truck, and loader with a fire extinguisher for oil and grease fires (4-A:60-B:C).
Skidders and tractors shall be equipped with a minimum 5-BC fire extinguisher.
All Fire Extinguishers shall be mounted, readily accessible, properly maintained and fully charged.
Contractor shall equip each mechanized harvesting machine with hydraulic systems, powered by an internal combustion engine (chipper, feller/buncher, harvester, forwarder, hot saws, stroke delimber, etc), except tractors and skidders, with at least two 4-A:60-B:C fire extinguishers or equivalent.
C. Spark Arresters and Mufflers: Contractor shall equip each operating tractor and any other internal combustion engine with a spark arrester, except for motor vehicles equipped with a maintained muffler as defined in C.P.R.C. Section 4442 or tractors with exhaust-operated turbochargers. Spark Arresters shall be a model tested and approved under Forest Service Standard 5100-1a as shown in the.
National Wildlife Coordinating Group Spark Arrester Guide, Volumes 1 and 2, and shall be maintained in good operating condition. Every motor vehicle subject to registration shall at all times be equipped with an adequate exhaust system meeting the requirements of the California Vehicle Code.
D. Power Saws: Each power saw shall be equipped with a spark arrester approved according to C.P.R.C. Section 4442 or 4443 and shall be maintained in effective working order. An Underwriters Laboratories (UL) approved fire extinguisher containing a minimum 14 ounces of fire retardant shall be kept with each operating power saw. In addition, a size 0 or larger shovel with an overall length of not less than 38 inches shall be kept with each gas can but not more than 300 feet from each power saw when used off cleared landing areas.
• This contract requires, does not require, Section 4E of the Fire Plan.
E. Tank Truck or Trailer: Contractor shall provide a water tank truck or trailer on or in proximity to Contract Area during Contractor's Operations hereunder during Fire Precautionary Period.
When Project Activity Level B or higher is in effect, a tank truck or trailer shall be on or immediately adjacent to each active landing, unless otherwise excepted when Hot Saws or Masticators are being used. See Section 6 for specific contract requirements.
The tank shall contain at least 300 gallons of water available for fire suppression. Ample power and hitch shall be readily available for promptly and safely moving tank over roads serving Contract Area.
Tank truck or trailer shall be equipped with the following:
(1) Pump, which at sea level, can deliver 23 gallons per minute at 175 pounds per square inch measured at the pump outlet. Pumps shall be tested on Contract Area using a 5/16 inch orifice in the Forester One Inch In-Line Gauge test kit. Pump shall meet or exceed the pressure value in the following table for nearest temperature and elevation:
Beaver Fire BAER Solicitation No. AG-9AC7-S-15-0006 2
T e m p
Sea
Level
Feet
10000
55 179 23 174 23 169 23 165 22 161 22 157 22 153 22 150 21 146 21 142 21 139 21 70 175 23 171 23 166 22 162 22 158 22 154 22 150 21 147 21 143 21 139 21 136 20 85 171 23 168 23 163 22 159 22 155 22 151 21 147 21 144 21 140 21 136 20 133 20
100 168 23 164 23 159 22 155 22 152 22 148 21 144 21 141 21 137 20 133 20 131 20 P
S I
G P M
P S I
G P M
P S I
G P M
P S I
G P M
P S I
G P M
P S I
G P M
P S I
G P M
P S I
G P M
P S I
G P M
P S I
G P M
P S I
G P M
The pump outlet shall be equipped with 1-1/2 inch National Standard Fire Hose thread. A bypass or pressure relief valve shall be provided for other than centrifugal pumps.
(2) 300 feet of 3/4-inch inside diameter rubber-covered high-pressure hose mounted on live reel attached to pump with no segments longer than approximately 50 feet, when measured to the extreme ends of the couplings. Hose shall have reusable compression wedge type 1-inch brass or lightweight couplings (aluminum or plastic). One end of hose shall be equipped with a coupling female section and the other end with a coupling male section. The hose shall, with the nozzle closed, be capable of withstanding 200 PSI pump pressure without leaking, distortions, slipping of couplings, or other failures.
(3) A shut-off combination nozzle that meets the following minimum performance standards when measured at 100 P.S.I. at the nozzle:
G.P.M. Horizontal Range Straight Stream 10 38 feet Fog Spray 6 - 20 N/A
(4) Sufficient fuel to run the pump at least 2 hours and necessary service accessories to facilitate efficient operation of the pump.
When Contractor is using Hot Saws or Masticators, an additional 250 feet of light weight hose, approved by the Forest Service, shall be immediately available for use and be capable of connecting to the 300 feet of hose and appurturances in (2) and (3) above.
This equipment and accessories shall be deliverable to a fire in the area of operations and is subject to the requirements for each specific activity level identified in Section 6.
F. Compressed Air Foam System: A Compressed Air Foam System (CAFS) is a fire suppression system where compressed air is added to water and a foaming agent. By agreement, Contractor may substitute a CAFS or functional equivalent in lieu of the tank truck, trailer or fire extinguishers, provided it meets or exceeds the following specifications and requirements:
1. Variable foam expansion ratio – 10:1 to 20:1.
2. Units shall be kept fully charged with air; water and foam concentrate as recommended by the manufacturer and have the appropriate tools to service the system.
3. The unit shall contain enough energy to empty tank and clear hose prior to exhausting propellent.
4. The unit shall be capable of being completely recharged within 10 minutes.
5. When used on cable yarding landings, the unit shall be outfitted for immediate attachment to carriage and transported without damage to the unit.
Beaver Fire BAER Solicitation No. AG-9AC7-S-15-0006 3
Fire extinguishers required for Hot Saws, Masticators and similar equipment identified in Section 4 B.
above may be substituted with a 3 gallon CAFS.
Tank truck, trailer or equivalent may be substituted with a 30 Gallon CAFS with at least 550 feet of one inch hose and an adjustable nozzle with enough water, air and foam concentrate for at least one recharge.
This equipment and accessories shall also be deliverable to a fire in the area of operations and subject to the requirements for each specific activity level identified in Section 6.
5. GENERAL
A. State Law: In addition to the requirements in this Fire Plan, the Contractor shall comply with all applicable laws of the State of California. In particular, see California Public Resource Codes.
B. Permits Required: The Contractor must secure a special written permit from the District Ranger or designated representative before burning, welding or cutting metal or starting any warming fires. If contract requires Blasting and Storing of Explosives and Detonators, an Explosives Permit may be required pursuant to the California Health and Safety Code, Section 12101.
C. Blasting: Contractor shall use electric caps only unless otherwise agreed in writing. When blasting is necessary in slash areas, a Fire Patrolperson equipped with a size 0 or larger shovel with an overall length of not less than 46 inches and a filled backpack can (4 or 5 gallon) with hand pump shall remain in the immediate area for an hour after blasting has been completed.
D. Smoking: Smoking shall not be permitted during fire season, except in a barren area or in an area cleared to mineral soil at least three feet in diameter. In areas closed to smoking, the CO may approve special areas to be used for smoking. The Contractor shall sign designated smoking areas. Contractor shall post signs regarding smoking and fire rules in conspicuous places for all employees to see.
Contractor's supervisory personnel shall require compliance with these rules. Under no circumstances shall smoking be permitted during fire season while employees are operating light or heavy equipment, or walking or working in grass and woodlands.
E. Storage and Parking Areas. Equipment service areas, parking areas, and gas and oil storage areas shall be cleared of all flammable material for a radius of at least 10 feet unless otherwise specified by local administrative unit. Small mobile or stationary internal combustion engine sites shall be cleared of flammable material for a slope distance of at least 10 feet from such engine. The COR shall approve such sites in writing.
F. Reporting Fires: As soon as feasible but no later than 15 minutes after initial discovery, Contractor shall notify Forest Service of any fires on Contract Area or along roads used by Contractor.
Contractor's employees shall report all fires as soon as possible to any of the following Forest Service facilities and/or personnel listed below, but not necessarily in the order shown:
Name Office Address Telephone Number Dispatch Center Yreka Dispatch 530-841-4600 Nearest FS Station Happy Camp RD 63822 Hwy 96 Happy Camp 530-493-2243 Inspector Ken Bigelow 530-841-4473 COR Dave Seiler 530-841-4448 District Ranger Tom Mutz 63822 Hwy 96 Happy Camp 530-493-1712
When reporting a fire, provide the following information:
Your Name Call back telephone number Project Name Location: Legal description (Township, Range, Section); and Descriptive location
(Reference point) Fire Information: Including Acres, Rate of Spread and Wind Conditions.
Beaver Fire BAER Solicitation No. AG-9AC7-S-15-0006 4
This contract requires, does not require, Section 5G of the Fire Plan.
G. Communications: Contractor shall furnish a serviceable telephone, radio-telephone or radio system connecting each operating side with Contractor's headquarters. When such headquarters is at a location which makes communication to it clearly impractical, Forest Service may accept a reasonable alternative location. The communication system shall provide prompt and reliable communications between Contractor's headquarters (or agreed to alternative) and Forest Service via commercial or Forest Service telephone.
This contract requires, does not require, Section 5H of the Fire Plan.
H. Fire Patrolperson: Contractor shall furnish a qualified fire patrolperson each operating day when Project Activity Level C or higher is in effect. When on duty, sole responsibility of patrolperson shall be to patrol the operation for prevention and detection of fires, take suppression action where necessary and notify the Forest Service as required. This Fire patrol is required on foot, unless otherwise agreed.
By agreement, one patrolperson may provide patrol on this and adjacent projects. No patrolperson shall be required on Specified Road construction jobs except during clearing operations unless otherwise specified.
The Contractor shall, prior to commencing work, furnish the following information relating to key personnel:
Title Name Telephone Number Fire Supervisor Fire Patrolperson
I. Clearing of Fuels: Contractor shall clear away, and keep clear, fuels and logging debris as follows:
Welding equipment and stationary log loaders, yarders and other equipment listed in California State Law:
10 feet slope radius
Tail or corner haulback blocks: All running blocks shall be located in the center of an area cleared to mineral soil at least 15 feet in diameter.
Lines near, between or above blocks: Sufficient clearing to prevent line from rubbing on snags, down logs and other dead woody material.
6. EMERGENCY PRECAUTIONS
Contractor's Operations shall conform to the limitations or requirements in the Project Activity Level (PAL) table below. Project Activity Levels applicable to this project shall be the predicted activity levels for the Fire Danger Rating Area(s), or fire weather station(s) stated in the Contract Area Map Legend on Integrated Resource Service Contracts (IRSC’s), and other contracts where applicable.
Fire Danger Rating Area/Fire Weather Station for Project 530-841-4588
The Forest Service, in its sole discretion, may change the predicted activity level if the current fire suppression situation, weather and vegetation conditions warrant an adjustment. If practicable, Forest Service will determine the following day’s activity level by 6:00 PM. Contractor shall obtain the predicted Project Activity Level from the appropriate Ranger District Office before starting work each day.
Phone Number or Website to obtain Predicted Activity Levels: 530-841-4588
Forest Service may change the Project Activity Level Table to other values upon revision of the National Fire Danger Rating System. When Contractor is notified, the revised Project Activity Levels will supersede the levels in the Project Activity Level Table below.
Beaver Fire BAER Solicitation No. AG-9AC7-S-15-0006 5
PROJECT ACTIVITY LEVEL
Level Project Activity Minimum Requirements and Restrictions. Restrictions at each level are cumulative.
A Minimum requirements noted above in Sections 4 and 5.
B 1. Tank truck, trailer, or approved CAFS substitute shall be on or adjacent to the Active Landing.
C 1. When Hot Saws or Masticators are operating, a tank truck, trailer, or approved CAFS substitute shall be within ¼ mile of these operations. Effective communications shall exist between the operator and the Active Landing.
2. Immediately after Mechanical Operations cease, Fire patrol is required for two hours.
D 1. Immediately after Hot Saw or Masticator operations cease, Fire patrol is required for three hours.
2. No Dead Tree felling after 1:00 PM, except recently dead.
3 No burning, blasting, welding or cutting of metal after 1:00 PM, except by special permit.
Ev 1. The following activities may operate all day:
a) Loading and hauling logs decked at approved landings.
b) Loading and hauling chips stockpiled at approved landings.
c) Servicing equipment at approved sites.
d) Dust abatement, road maintenance (Chainsaw use prohibited), culvert installation within cleared area, chip sealing, paving, earth moving or rock aggregate stock pile loading and installation (does not include pit or quarry development).
e) Chainsaw and log processing operations associated with loading logs or other forest products at approved landings.
2. Hot Saws or Masticators may operate until 1:00 PM; provided that:
a) A tractor with a blade or other equipment capable of constructing fireline is on or adjacent to the active landing or within ¼ mile of the operating equipment. This piece of equipment shall have effective communication with the Hot Saw or Masticator.
b) Any additional restrictions specified by the Forest.
3. All other conventional Mechanical Operations are permitted until 1:00 PM.
4. Some operations may be permitted after 1:00 PM, on a case-by-case basis, under the terms of a PAL Ev Variance Agreement. Activities for which a Variance may be issued are:
• Rubber Tire Skidding
• Chipping on Landings
• Helicopter Yarding
• Fire Salvage
When approved by a Line Officer, a Variance Agreement can be implemented when the criteria specified in the agreement are met and mitigation measures are in place. This approval is good for ten
(10) days unless cancelled sooner or extended by the Contracting Officer for an additional ten (10) days.
Variance approval can be withdrawn at the sole discretion of the Forest Service. Variance approval is contingent on the 7-day fire weather forecast, fuel conditions, site characteristics, current fire situation, state of Contractor’s equipment for prevention and suppression readiness, type of operation and social and community considerations etc. (See attached Project Activity Level Variance Agreement).
E The following activities may operate all day:
1. Loading and hauling logs decked at approved landings.
2. Loading and hauling chips stockpiled at approved landings.
3. Servicing Equipment at approved sites.
4. Dust abatement, road maintenance (chainsaw use prohibited) or loading stock piles and rock aggregate installation (does not include pit or quarry development).
5. Chainsaw operation associated with loading at approved landings.
All other activities are prohibited.
Beaver Fire BAER Solicitation No. AG-9AC7-S-15-0006 6
This Project utilizes “The Project Activity Level” (PAL), an industrial operation’s fire precaution system. The following Climatology Chart indicates the Historic Activity Levels for the Project Fire Danger Rating Area or Fire Weather Station utilized on this Project. This is only a historical average of the Activity Levels for the identified Fire Danger Rating Area or Weather Station.
Beaver Fire BAER Solicitation No. AG-9AC7-S-15-0006 7
Fire Danger Rating Area/Fire Weather Station for Project Slater Butte
Phone Number or Website to obtain Predicted Activity Levels: 530-841-4588
Project Activity Level Climatology
Fire Danger Rating Area/Weather Station
KNF PAL WEST Years Analyzed 2011-2013
A B C D Ev E Days Month Expected Days per Month at Each PAL Value Analyzed April 19.7 6.3 3.7 0.3 0.0 0.0 90 May 6.7 9.0 13.3 2.0 0.0 0.0 93 June 4.0 5.3 14.0 6.3 0.3 0.0 90 July 0.3 2.0 13.0 9.7 6.0 0.0 93 August 0.3 1.0 9.3 12.0 8.3 0.0 93 September 2.0 1.7 6.0 8.0 12.3 0.0 90 October 6.3 9.0 13.0 1.3 1.3 0.0 93
Beaver Fire BAER Solicitation No. AG-9AC7-S-15-0006 8
2013 PROJECT ACTIVITY LEVEL TABLE
Level Project Activity Minimum Requirements and Restrictions.
Restrictions at each level are cumulative.
A Minimum required by C(T)7.2# .
B 1. Tank truck, trailer, or approved CAFS substitute shall be on or adjacent to the Active Landing.
C 1. When Hot Saws or Masticators are operating, a tank truck, trailer or approved CAFS substitute shall be within mile of these operations.
Effective communications shall exist between the operator and the Active Landing.
2 . Immediately after Mechanical Operations cease, Fire Patrol is required for two hours.
D 1. Immediately after Hot Saw or Masticator operations cease, Fire patrol is required for three hours.
2. No Dead Tree felling after 1:00 PM, except recently dead.
3. No Welding or cutting of metal after 1:00 PM, except by special permit.
Ev 1. The following activities may operate all day:
a) Loading and hauling logs decked at approved landings.
b) Loading and hauling chips stockpiled at approved landings.
c) Servicing equipment at approved sites.
d) Dust abatement, road maintenance (Chainsaw use prohibited), culvert installation within cleared area, chip sealing, paving, earth moving or rock aggregate stock pile loading and installation (does not include pit or quarry development) .
e) Chainsaw and log processing operations associated with loading logs or other forest products at approved landings.
2. Hot Saws or Masticators may operate until 1:00 PM ; provided that :
a) A tractor or other equipment with a blade capable of constructing fireline is on or adjacent to the active landing or within mile of the operating equipment. This piece of equipment shall have effective communication with the Hot Saw or Masticator.
b) Any additional restrictions specified by the Forest.
3. All other conventional Mechanical Operations are permitted until
1:00 PM.
4. Some operations may be permitted after 1:00 PM, on a case-by-case basis, under the terms of a PAL Ev Variance Agreement. Activities for which a Variance may be issued are:
• Rubber Tire Skidding
• Chipping on Landings
• Helicopter Yarding
• Fire Salvage
Beaver Fire BAER Solicitation No. AG-9AC7-S-15-0006 9
When approved by a Line Officer, a Variance Agreement can be implemented when the criteria specified in the agreement are met and mitigation measures are in place. This approval is good for ten (10) days unless cancelled sooner or extended by the Contracting Officer for an additional ten (10) days. Variance approval can be withdrawn at the sole discretion of Forest Service. Variance approval is contingent on the 7-day fire weather forecast, fuel conditions, site characteristics , current fire situation, state of Purchaser's equipment for prevent ion and suppression readiness, type of operation and social and community considerations etc. (See attached Project Activity Level Variance Agreement) .
E The following activities may operate all day:
1. Loading and hauling logs decked at approved landings.
2. Loading and hauling chips stockpiled at approved landings.
3. Servicing Equipment at approved sites.
4. Dust abatement, road maintenance (chainsaw use prohibited) or loading stock piles and rock aggregate installation (does not include pit or quarry development) .
5. Chainsaw operation associated with loading at approved landings.
All other activities are prohibited.
Beaver Fire BAER Solicitation No. AG-9AC7-S-15-0006 10
General Decision Number: CA140009 10/03/2014 CA9
Superseded General Decision Number: CA20130009
State: California
Construction Types: Building, Heavy (Heavy and Dredging) and Highway
Counties: Alpine, Amador, Butte, Colusa, El Dorado, Glenn, Lassen, Marin, Modoc, Napa, Nevada, Placer, Plumas, Sacramento, Shasta, Sierra, Siskiyou, Solano, Sonoma, Sutter, Tehama, Trinity, Yolo and Yuba Counties in California.
BUILDING CONSTRUCTION PROJECTS (excluding Amador County only);
DREDGING CONSTRUCTION PROJECTS (does not include hopper dredge work); HEAVY CONSTRUCTION PROJECTS (does not include water well drilling); AND HIGHWAY CONSTRUCTION PROJECTS
Modification Number Publication Date 0 01/03/2014 1 01/10/2014 2 01/24/2014 3 03/07/2014 4 04/11/2014 5 05/23/2014 6 05/30/2014 7 06/06/2014 8 06/13/2014 9 06/20/2014 10 07/04/2014 11 07/11/2014 12 07/18/2014 13 07/25/2014 14 08/01/2014 15 08/08/2014 16 08/15/2014 17 08/22/2014 18 09/05/2014 19 09/26/2014 20 10/03/2014
ASBE0016-001 01/01/2014
AREA 1: ALAMEDA, CONTRA COSTA, LAKE, MARIN, MENDOCINO,
MONTEREY, NAPA, SAN BENITO, SAN FRANCISCO, SAN MATEO, SANTA
CLARA, SANTA CRUZ, SOLANO, & SONOMA COUNTIES
AREA 2: ALPINE, AMADOR, BUTTE, CALAVERAS, COLUSA, DEL NORTE,
EL DORADO, FRESNO, GLENN, HUMBOLDT, KINGS, LASSEN, MADERA,
MARIPOSA, MERCED, MODOC, MONO, NEVADA, PLACER, PLUMAS,
SACRAMENTO, SAN JOAQUIN, SHASTA, SIERRA, SISKIYOU, STANISLAU,
SUTTER, TEHEMA, TRINITY, TULARE, TUOLUMNE, YOLO, & YUBA COUNTIES
Rates Fringes
Beaver Fire BAER Solicitation No. AG-9AC7-S-15-0006 1
Asbestos Workers/Insulator (Includes the application of all insulating materials, Protective Coverings, Coatings, and Finishes to all types of mechanical systems) Area 1......................$ 57.15 18.72 Area 2......................$ 44.05 18.62
ASBE0016-007 01/01/2013
Rates Fringes
Asbestos Removal worker/hazardous material handler (Includes preparation, wetting, stripping, removal, scrapping, vacuuming, bagging and disposing of all insulation materials from mechanical systems, whether they contain asbestos or not)....$ 31.13 6.95
BOIL0549-002 01/01/2013
Rates Fringes
BOILERMAKER
(1) Marin & Solano Counties.$ 42.06 33.43
(2) Remaining Counties......$ 38.37 31.32
BRCA0003-001 08/01/2013
Rates Fringes
MARBLE FINISHER..................$ 28.05 14.01
BRCA0003-004 05/01/2013
AREA 1: ALPINE, AMADOR, BUTTE, COLUSA, EL DORADO, GLENN,
LASSEN, MODOC, NEVADA, PLACER, PLUMAS, SACRAMENTO, SHASTA,
SIERRA, SUTTER, TEHAMA, YOLO AND YUBA COUNTIES
AREA 2: MARIN, NAPA, SISKIYOU, SOLANO, SONOMA AND TRINITY
COUNTIES
BRICKLAYER
AREA 1......................$ 36.48 19.59
AREA 2......................$ 39.96 23.79
SPECIALTY PAY:
(A) Underground work such as tunnel work, sewer work, manholes, catch basins, sewer pipes and telephone conduit shall be paid $1.25 per hour above the regular rate. Work in direct contact with raw sewage shall receive $1.25 per hour in addition to the above.
Beaver Fire BAER Solicitation No. AG-9AC7-S-15-0006 2
(B) Operating a saw or grinder shall receive $1.25 per hour above the regular rate.
(C) Gunite nozzle person shall receive $1.25 per hour above the regular rate.
BRCA0003-008 07/01/2013
Rates Fringes
TERRAZZO FINISHER................$ 33.15 13.93
TERRAZZO WORKER/SETTER...........$ 39.95 24.39
BRCA0003-010 04/01/2014
Rates Fringes
TILE FINISHER
Area 1......................$ 22.58 10.04 Area 2......................$ 22.58 12.50 Area 3......................$ 22.76 12.37 Area 4......................$ 22.26 11.85 Tile Layer Area 1......................$ 38.13 11.98 Area 2......................$ 36.43 13.74 Area 3......................$ 40.59 13.79 Area 4......................$ 37.46 13.74
AREA 1: Butte, Colusa, El Dorado, Glenn, Lassen, Modoc, Nevada, Placer, Plumas, Sacramento, Shasta, Sierra, Sutter, Tehema, Yolo, Yuba AREA 2: Alpine, Amador AREA 3: Marin, Napa, Solano, Siskiyou AREA 4: Sonoma
BRCA0003-014 08/01/2013
Rates Fringes
MARBLE MASON.....................$ 39.30 22.48
CARP0034-001 07/01/2014
Rates Fringes
Diver Assistant Tender, ROV Tender/Technician...........$ 39.60 30.73 Diver standby...............$ 44.56 30.73 Diver Tender................$ 43.56 30.73 Diver wet...................$ 89.12 30.73 Manifold Operator (mixed gas)........................$ 48.56 30.73 Manifold Operator (Standby).$ 43.56 30.73
DEPTH PAY (Surface Diving):
050 to 100 ft $2.00 per foot 101 to 150 ft $3.00 per foot 151 to 220 ft $4.00 per foot
Beaver Fire BAER Solicitation No. AG-9AC7-S-15-0006 3
SATURATION DIVING:
The standby rate shall apply until saturation starts. The saturation diving rate applies when divers are under pressure continuously until work task and decompression are complete. The diver rate shall be paid for all saturation hours.
DIVING IN ENCLOSURES:
Where it is necessary for Divers to enter pipes or tunnels, or other enclosures where there is no vertical ascent, the following premium shall be paid: Distance traveled from entrance 26 feet to 300 feet: $1.00 per foot. When it is necessary for a diver to enter any pipe, tunnel or other enclosure less than 48" in height, the premium will be $1.00 per foot.
WORK IN COMBINATION OF CLASSIFICATIONS:
Employees working in any combination of classifications within the diving crew (except dive supervisor) in a shift are paid in the classification with the highest rate for that shift.
CARP0034-003 07/01/2014
Rates Fringes
Piledriver.......................$ 40.60 30.73
CARP0035-001 08/01/2014
AREA 1: MARIN, NAPA, SOLANO & SONOMA
AREA 3: SACRAMENTO, WESTERN EL DORADO (Territory west of an including highway 49 and the territory inside the city limits of Placerville), WESTERN PLACER (Territory west of and including highway 49), & YOLO
AREA 4: ALPINE, BUTTE, COLUSA, EASTERN EL DORADO, GLENN,
LASSEN, MODOC, NEVADA, EASTERN PLACER, PLUMAS, SHASTA, SIERRA,
SISKIYOU, SUTTER, TEHAMA, TRINITY, & YUBA
Drywall Installers/Lathers:
Area 1......................$ 40.35 27.97 Area 3......................$ 34.97 27.97 Area 4......................$ 33.62 27.97 Drywall Stocker/Scrapper Area 1......................$ 20.18 16.30 Area 3......................$ 17.49 16.30 Area 4......................$ 16.81 16.30
CARP0035-009 07/01/2014
Marin County
Beaver Fire BAER Solicitation No. AG-9AC7-S-15-0006 4
CARPENTER
Bridge Builder/Highway Carpenter...................$ 40.35 27.53 Hardwood Floorlayer, Shingler, Power Saw Operator, Steel Scaffold & Steel Shoring Erector, Saw Filer.......................$ 40.50 27.53 Journeyman Carpenter........$ 40.35 27.53 Millwright..................$ 40.45 29.12
* CARP0035-010 07/01/2014
AREA 1: Marin, Napa, Solano & Sonoma Counties
AREA 2: Monterey, San Benito and Santa Cruz
AREA 3: Alpine, Butte, Colusa, El Dorado, Glenn, Lassen, Modoc, Nevada, Placer, Plumas, Sacramento, Shasta, Sierra, Siskiyou, Sutter, Tehama, Trinity, Yolo & Yuba counties
Modular Furniture Installer Area 1 Installer I................$ 23.36 18.31 Installer II...............$ 19.93 18.31 Lead Installer.............$ 26.81 18.81 Master Installer...........$ 31.03 18.81 Area 2 Installer I................$ 20.71 18.31 Installer II...............$ 17.76 18.31 Lead Installer.............$ 23.68 18.81 Master Installer...........$ 27.31 18.81 Area 3 Installer I................$ 19.76 18.31 Installer II...............$ 16.99 18.31 Lead Installer.............$ 22.56 18.81 Master Installer...........$ 29.58 18.81
CARP0046-001 07/01/2014
El Dorado (West), Placer (West), Sacramento and Yolo Counties
Rates Fringes
Carpenters Bridge Builder/Highway Carpenter...................$ 40.35 27.53 Hardwood Floorlayer, Shingler, Power Saw Operator, Steel Scaffold & Steel Shoring Erector, Saw Filer.......................$ 34.62 27.53 Journeyman Carpenter........$ 34.47 27.53 Millwright..................$ 36.97 29.12
Footnote: Placer County (West) includes territory West of and
Beaver Fire BAER Solicitation No. AG-9AC7-S-15-0006 5 including Highway 49 and El Dorado County (West) includes territory West of and including Highway 49 and territory inside the city limits of Placerville.
CARP0046-002 07/01/2014
Alpine, Colusa, El Dorado (East), Nevada, Placer (East), Sierra, Sutter and Yuba Counties
Carpenters Bridge Builder/Highway Carpenter...................$ 40.35 27.53 Hardwood Floorlayer, Shingler, Power Saw Operator, Steel Scaffold & Steel Shoring Erector, Saw Filer.......................$ 33.27 27.53 Journeyman Carpenter........$ 33.12 27.53 Millwright..................$ 35.62 29.12
CARP0152-003 07/01/2014
Amador County
Rates Fringes
Carpenters Bridge Builder/Highway Carpenter...................$ 40.35 27.53 Hardwood Floorlayer, Shingler, Power Saw Operator, Steel Scaffold & Steel Shoring Erector, Saw Filer.......................$ 33.27 27.53 Journeyman Carpenter........$ 33.12 27.53 Millwright..................$ 35.62 29.12
CARP0180-001 07/01/2014
Solano County
Rates Fringes
Carpenters Bridge Builder/Highway Carpenter...................$ 40.35 27.53 Hardwood Floorlayer, Shingler, Power Saw Operator, Steel Scaffold & Steel Shoring Erector, Saw Filer.......................$ 40.50 27.53 Journeyman Carpenter........$ 40.35 27.53 Millwright..................$ 40.45 29.12
CARP0751-001 07/01/2014
Beaver Fire BAER Solicitation No. AG-9AC7-S-15-0006 6
Napa and Sonoma Counties
Carpenters Bridge Builder/Highway Carpenter...................$ 40.35 27.53 Hardwood Floorlayer, Shingler, Power Saw Operator, Steel Scaffold & Steel Shoring Erector, Saw Filer.......................$ 40.50 27.53 Journeyman Carpenter........$ 40.35 27.53 Millwright..................$ 40.45 29.12
CARP1599-001 07/01/2014
Butte, Glenn, Lassen, Modoc, Plumas, Shasta, Siskiyou, Tehama and Trinity Counties
Carpenters Bridge Builder/Highway Carpenter...................$ 40.35 27.53 Hardwood Floorlayer, Shingler, Power Saw Operator, Steel Scaffold & Steel Shoring Erector, Saw Filer.......................$ 33.27 27.53 Journeyman Carpenter........$ 33.12 27.53 Millwright..................$ 35.62 29.12
ELEC0180-001 06/01/2014
NAPA AND SOLANO COUNTIES
Rates Fringes
CABLE SPLICER....................$ 50.97 3%+20.13
ELECTRICIAN......................$ 45.31 3%+20.13
ELEC0180-003 12/01/2013
NAPA AND SOLANO COUNTIES
Rates Fringes
Sound & Communications Installer...................$ 31.32 3%+15.30 Technician..................$ 35.66 3%+15.30
SCOPE OF WORK INCLUDES-
SOUND & VOICE TRANSMISSION (Music, Intercom, Nurse Call, Telephone); FIRE ALARM SYSTEMS [excluding fire alarm work when installed in raceways (including wire and cable pulling) and when performed on new or major remodel building projects or jobs], TELEVISION & VIDEO SYSTEMS, SECURITY SYSTEMS, COMMUNICATIONS
Beaver Fire BAER Solicitation No. AG-9AC7-S-15-0006 7
SYSTEMS that transmit or receive information and/or control systems that are intrinsic to the above.
EXCLUDES-
Excludes all other data systems or multiple systems which include control function or power supply; excludes installation of raceway systems, line voltage work, industrial work, life-safety systems (all buildings having floors located more than 75' above the lowest floor level having building access); excludes energy management systems.
ELEC0340-002 12/01/2013
ALPINE, AMADOR, BUTTE, COLUSA, EL DORADO, GLENN, LASSEN,
NEVADA, PLACER, PLUMAS, SACRAMENTO, TRINITY, YOLO, YUBA COUNTIES
Communications System Sound & Communications Installer...................$ 24.68 3%+12.85 Sound & Communications Technician..................$ 28.38 3%+12.85
SCOPE OF WORK
Includes the installation testing, service and maintenance, of the following systems which utilize the transmission and/or transference of voice, sound, vision and digital for commercial, education, security and entertainment purposes for the following TV monitoring and surveillance, background-foreground music, intercom and telephone interconnect, inventory control systems, microwave transmission, multi-media, multiplex, nurse call system, radio page, school intercom and sound, burglar alarms, and low voltage master clock systems.
A. SOUND AND VOICE TRANSMISSION/TRANSFERENCE SYSTEMS
Background foreground music Intercom and telephone interconnect systems, Telephone systems, Nurse call systems, Radio page systems, School intercom and sound systems, Burglar alarm systems, Low voltage master clock systems, Multi-media/multiplex systems, Sound and musical entertainment systems, RF systems, Antennas and Wave Guide.
B. FIRE ALARM SYSTEMS
Installation, wire pulling and testing
C. TELEVISION AND VIDEO SYSTEMS Television monitoring and surveillance systems, Video security systems, Video entertainment systems, Video educational systems, Microwave transmission systems, CATV and CCTV
D. SECURITY SYSTEMS Perimeter security systems Vibration sensor systems Card access systems Access control systems Sonar/infrared monitoring equipment
Beaver Fire BAER Solicitation No. AG-9AC7-S-15-0006 8
E. COMMUNICATIONS SYSTEMS THAT TRANSMIT OR RECEIVE
INFORMATION AND/OR CONTROL SYSTEMS THAT ARE INTRINSIC TO
THE ABOVE LISTED SYSTEMS SCADA (Supervisory Control and Data Acquisition) PCM (Pulse Code Modulation) Inventory Control Systems Digital Data Systems Broadband and Baseband and Carriers Point of Sale Systems VSAT Data Systems Data Communication Systems RF and Remote Control Systems Fiber Optic Data Systems WORK EXCLUDED Raceway systems are not covered (excluding Ladder-Rack for the purpose of the above listed systems). Chases and/or nipples (not to exceed 10 feet) may be installed on open wiring systems. Energy management systems. SCADA (Supervisory Control and Data Acquisition) when not intrinsic to the above listed systems (in the scope). Fire alarm systems when installed in raceways (including wire and cable pulling) shall be performed at the electrician wage rate, when either of the following two
(2) conditions apply:
1. The project involves new or major remodel building trades construction.
2. The conductors for the fire alarm system are installed in conduit.
ELEC0340-003 12/01/2013
ALPINE (West of Sierra Mt. Watershed), AMADOR, BUTTE, COLUSA, EL DORADO (West of Sierra Mt. Watershed), GLENN, LASSEN, NEVADA (West of Sierra Mt. Watershed), PLACER, PLUMAS, SACRAMENTO, SHASTA, SIERRA (West of Sierra Mt. Watershed), SUTTER, TEHAMA, TRINITY, YOLO & YUBA COUNTIES
ELECTRICIAN
Remaining area..............$ 39.06 18.54 Sierra Army Depot, Herlong..$ 48.83 18.54 Tunnel work.................$ 41.01 18.54
CABLE SPLICER: Receives 110% of the Electrician basic hourly rate.
ELEC0401-005 07/01/2013
ALPINE (east of the main watershed divide), EL DORADO (east of the main watershed divide), NEVADA (east of the main watershed), PLACER (east of the main watershed divide) and SIERRA (east of the main watershed divide) COUNTIES:
ELECTRICIAN......................$ 37.00 14.62
ELEC0551-004 06/01/2014
MARIN AND SONOMA COUNTIES
Beaver Fire BAER Solicitation No. AG-9AC7-S-15-0006 9
ELECTRICIAN......................$ 47.20 16.76
ELEC0551-005 12/01/2013
MARIN & SONOMA COUNTIES
Rates Fringes
Sound & Communications Installer...................$ 31.32 16.23 Technician..................$ 35.66 16.36
SCOPE OF WORK INCLUDES-
SOUND & VOICE TRANSMISSION (Music, Intercom, Nurse Call, Telephone); FIRE ALARM SYSTEMS [excluding fire alarm work when installed in raceways (including wire and cable pulling) and when performed on new or major remodel building projects or jobs], TELEVISION & VIDEO SYSTEMS, SECURITY SYSTEMS, COMMUNICATIONS
SYSTEMS that transmit or receive information and/or control systems that are intrinsic to the above.
EXCLUDES-
Excludes all other data systems or multiple systems which include control function or power supply; excludes installation of raceway systems, line voltage work, industrial work, life-safety systems (all buildings having floors located more than 75' above the lowest floor level having building access); excludes energy management systems.
ELEC0659-006 01/01/2013
DEL NORTE, MODOC and SISKIYOU COUNTIES
Rates Fringes
ELECTRICIAN......................$ 30.27 14.81
ELEC0659-008 02/01/2013
DEL NORTE, MODOC & SISKIYOU COUNTIES
Rates Fringes
Line Construction
(1) Cable Splicer...........$ 51.09 4%+13.30
(2) Lineman, Pole Sprayer, Heavy Line Equipment Man....$ 45.62 4%+13.30
(3) Tree Trimmer............$ 32.07 4%+9.80
(4) Line Equipment Man......$ 45.62 4%+9.80
(5) Powdermen, Jackhammermen...............$ 34.22 4%+9.80
(6) Groundman...............$ 31.31 4%+9.80
ELEC1245-004 06/01/2013
Beaver Fire BAER Solicitation No. AG-9AC7-S-15-0006 10
ALL COUNTIES EXCEPT DEL NORTE, MODOC & SISKIYOU
LINE CONSTRUCTION
(1) Lineman; Cable splicer..$ 50.30 15
(2) Equipment specialist (operates crawler tractors, commercial motor vehicles, backhoes, trenchers, cranes (50 tons and below), overhead & underground distribution line equipment)...........$ 40.17 14.56
(3) Groundman...............$ 30.73 13.48
(4) Powderman...............$ 44.91 13.48
HOLIDAYS: New Year's Day, M.L. King Day, Memorial Day, Independence Day, Labor Day, Veterans Day, Thanksgiving Day and day after Thanksgiving, Christmas Day
ELEV0008-001 01/01/2014
Rates Fringes
ELEVATOR MECHANIC................$ 59.19 26.785
FOOTNOTE:
PAID VACATION: Employer contributes 8% of regular hourly rate as vacation pay credit for employees with more than 5 years of service, and 6% for 6 months to 5 years of service.
PAID HOLIDAYS: New Years Day, Memorial Day, Independence Day, Labor Day, Veterans Day, Thanksgiving Day, Friday after Thanksgiving, and Christmas Day.
ENGI0003-008 07/01/2013
Rates Fringes
Dredging: (DREDGING:
CLAMSHELL & DIPPER DREDGING;
HYDRAULIC SUCTION DREDGING:)
AREA 1:
(1) Leverman...............$ 40.53 27.81
(2) Dredge Dozer; Heavy duty repairman.............$ 35.57 27.81
(3) Booster Pump Operator; Deck Engineer; Deck mate;
Dredge Tender; Winch Operator...................$ 34.45 27.81
(4) Bargeman; Deckhand;
Fireman; Leveehand; Oiler..$ 31.15 27.81
AREA 2:
(1) Leverman...............$ 42.53 27.81
(2) Dredge Dozer; Heavy duty repairman.............$ 37.57 27.81
(3) Booster Pump
Beaver Fire BAER Solicitation No. AG-9AC7-S-15-0006 11
Operator; Deck Engineer; Deck mate;
Dredge Tender; Winch Operator...................$ 36.45 27.81
(4) Bargeman; Deckhand;
Fireman; Leveehand; Oiler..$ 33.15 27.81
AREA DESCRIPTIONS
AREA 1: ALAMEDA,BUTTE, CONTRA COSTA, KINGS, MARIN, MERCED,
NAPA, SACRAMENTO, SAN BENITO, SAN FRANCISCO, SAN JOAQUIN,
SAN MATEO, SANTA CLARA, SANTA CRUZ, SOLANO, STANISLAUS,
SUTTER, YOLO, AND YUBA COUNTIES
AREA 2: MODOC COUNTY
THE REMAINGING COUNTIES ARE SPLIT BETWEEN AREA 1 AND AREA 2
AS NOTED BELOW:
ALPINE COUNTY:
Area 1: Northernmost part Area 2: Remainder
CALAVERAS COUNTY:
Area 1: Remainder Area 2: Eastern part
COLUSA COUNTY:
Area 1: Eastern part Area 2: Remainder
ELDORADO COUNTY:
Area 1: North Central part Area 2: Remainder
FRESNO COUNTY:
Area 1: Remainder Area 2: Eastern part
GLENN COUNTY:
Area 1: Eastern part Area 2: Remainder
LASSEN COUNTY:
Area 1: Western part along the Southern portion of border with Shasta County Area 2: Remainder
MADERA COUNTY:
Area 1: Except Eastern part Area 2: Eastern part
MARIPOSA COUNTY
Area 1: Except Eastern part Area 2: Eastern part
MONTERREY COUNTY
Area 1: Except Southwestern part Area 2: Southwestern part
Beaver Fire BAER Solicitation No. AG-9AC7-S-15-0006 12
NEVADA COUNTY:
Area 1: All but the Northern portion along the border of Sierra County Area 2: Remainder
PLACER COUNTY:
Area 1: Al but the Central portion Area 2: Remainder
PLUMAS COUNTY:
Area 1: Western portion Area 2: Remainder
SHASTA COUNTY:
Area 1: All but the Northeastern corner Area 2: Remainder
SIERRA COUNTY:
Area 1: Western part Area 2: Remainder
SISKIYOU COUNTY:
Area 1: Central part Area 2: Remainder
SONOMA COUNTY:
Area 1: All but the Northwestern corner Area 2: Remainder
TEHAMA COUNTY:
Area 1: All but the Western border with Mendocino & Trinity Counties Area 2: Remainder
TRINITY COUNTY:
Area 1: East Central part and the Northeastern border with Shasta County Area 2: Remainder
TUOLUMNE COUNTY:
Area 1: Except Eastern part Area 2: Eastern part
ENGI0003-018 06/30/2014
"AREA 1" WAGE RATES ARE LISTED BELOW
"AREA 2" RECEIVES AN ADDITIONAL $2.00 PER HOUR ABOVE AREA 1
RATES.
SEE AREA DEFINITIONS BELOW
OPERATOR: Power Equipment
(AREA 1:)
GROUP 1.....................$ 39.85 27.44
GROUP 2.....................$ 38.32 27.44
Beaver Fire BAER Solicitation No. AG-9AC7-S-15-0006 13
GROUP 3.....................$ 36.84 27.44
GROUP 4.....................$ 35.46 27.44
GROUP 5.....................$ 34.19 27.44
GROUP 6.....................$ 32.87 27.44
GROUP 7.....................$ 31.73 27.44
GROUP 8.....................$ 30.59 27.44
GROUP 8-A...................$ 28.38 27.44
OPERATOR: Power Equipment (Cranes and Attachments -
AREA 1:)
GROUP 1
Cranes.....................$ 40.73 27.44 Oiler......................$ 33.76 27.44 Truck crane oiler..........$ 37.33 27.44
GROUP 2
Cranes.....................$ 38.97 27.44 Oiler......................$ 33.50 27.44 Truck crane oiler..........$ 37.04 27.44
GROUP 3
Cranes.....................$ 37.23 27.44 Hydraulic..................$ 32.87 27.44 Oiler......................$ 33.26 27.44 Truck Crane Oiler..........$ 36.77 27.44
GROUP 4
Cranes.....................$ 34.19 27.44 OPERATOR: Power Equipment (Piledriving - AREA 1:)
GROUP 1
Lifting devices............$ 41.07 27.44 Oiler......................$ 31.81 27.44 Truck crane oiler..........$ 34.09 27.44
GROUP 2
Lifting devices............$ 39.25 27.44 Oiler......................$ 31.54 27.44 Truck Crane Oiler..........$ 33.84 27.44
GROUP 3
Lifting devices............$ 37.57 27.44 Oiler......................$ 31.32 27.44 Truck Crane Oiler..........$ 33.55 27.44
GROUP 4
Lifting devices............$ 35.80 27.44
GROUP 5
Lifting devices............$ 34.50 27.44
GROUP 6
Lifting devices............$ 33.16 27.44 OPERATOR: Power Equipment (Steel Erection - AREA 1:)
GROUP 1
Cranes.....................$ 41.70 27.44 Oiler......................$ 32.15 27.44 Truck Crane Oiler..........$ 34.38 27.44
GROUP 2
Cranes.....................$ 39.93 27.44 Oiler......................$ 31.88 27.44 Truck Crane Oiler..........$ 34.16 27.44
GROUP 3
Cranes.....................$ 38.45 27.44 Hydraulic..................$ 32.67 27.44 Oiler......................$ 31.66 27.44 Truck Crane Oiler..........$ 33.89 27.44
Beaver Fire BAER Solicitation No. AG-9AC7-S-15-0006 14
GROUP 4
Cranes.....................$ 36.43 27.44
GROUP 5
Cranes.....................$ 35.13 27.44 OPERATOR: Power Equipment (Tunnel and Underground Work
- AREA 1:)
SHAFTS, STOPES, RAISES:
GROUP 1....................$ 35.95 27.44
GROUP 1-A..................$ 38.32 27.44
GROUP 2....................$ 34.59 27.44
GROUP 3....................$ 33.36 27.44
GROUP 4....................$ 32.22 27.44
GROUP 5....................$ 31.08 27.44
UNDERGROUND:
GROUP 1....................$ 35.85 27.44
GROUP 1-A..................$ 38.32 27.44
GROUP 2....................$ 34.59 27.44
GROUP 3....................$ 33.26 27.44
GROUP 4....................$ 32.12 27.44
GROUP 5....................$ 30.98 27.44
FOOTNOTE: Work suspended by ropes or cables, or work on a Yo-Yo Cat: $.60 per hour additional.
POWER EQUIPMENT OPERATOR CLASSIFICATIONS
GROUP 1: Operator of helicopter (when used in erection work);
Hydraulic excavator, 7 cu. yds. and over; Power shovels, over 7 cu. yds.
GROUP 2: Highline cableway; Hydraulic excavator, 3-1/2 cu.
yds. up to 7 cu. yds.; Licensed construction work boat operator, on site; Power blade operator (finish); Power shovels, over 1 cu. yd. up to and including 7 cu. yds.
m.r.c.
GROUP 3: Asphalt milling machine; Cable backhoe; Combination backhoe and loader over 3/4 cu. yds.; Continuous flight tie back machine assistant to engineer or mechanic; Crane mounted continuous flight tie back machine, tonnage to apply; Crane mounted drill attachment, tonnage to apply;
Dozer, slope brd; Gradall; Hydraulic excavator, up to 3 1/2
cu. yds.; Loader 4 cu. yds. and over; Long reach excavator;
Multiple engine scraper (when used as push pull); Power shovels, up to and including 1 cu. yd.; Pre-stress wire wrapping machine; Side boom cat, 572 or larger; Track loader 4 cu. yds. and over; Wheel excavator (up to and including 750 cu. yds. per hour)
GROUP 4: Asphalt plant engineer/box person; Chicago boom;
Combination backhoe and loader up to and including 3/4 cu.
yd.; Concrete batch plant (wet or dry); Dozer and/or push cat; Pull- type elevating loader; Gradesetter, grade checker (GPS, mechanical or otherwise); Grooving and grinding machine; Heading shield operator; Heavy-duty drilling equipment, Hughes, LDH, Watson 3000 or similar;
Heavy-duty repairperson and/or welder; Lime spreader;
Loader under 4 cu. yds.; Lubrication and service engineer
Beaver Fire BAER Solicitation No. AG-9AC7-S-15-0006 15
(mobile and grease rack); Mechanical finishers or spreader machine (asphalt, Barber-Greene and similar); Miller Formless M-9000 slope paver or similar; Portable crushing and screening plants; Power blade support; Roller operator, asphalt; Rubber-tired scraper, self-loading (paddle-wheels, etc.); Rubber- tired earthmoving equipment (scrapers); Slip form paver (concrete); Small tractor with drag; Soil stabilizer (P & H or equal); Spider plow and spider puller;
Tubex pile rig; Unlicensed constuction work boat operator, on site; Timber skidder; Track loader up to 4 yds.;
Tractor-drawn scraper; Tractor, compressor drill combination; Welder; Woods-Mixer (and other similar Pugmill equipment)
GROUP 5: Cast-in-place pipe laying machine; Combination slusher and motor operator; Concrete conveyor or concrete pump, truck or equipment mounted; Concrete conveyor, building site; Concrete pump or pumpcrete gun; Drilling equipment, Watson 2000, Texoma 700 or similar; Drilling and boring…