Unauth Route Specifications

View the file

Other files for this federal contract opportunity

Show all 18

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Unauthorized Routes 2016

Section 202

Section 202 - Removal of Structures & Obstructions

Description

202.01 Work. Salvage, remove, and/or dispose of buildings, fences, structures, pavements, culverts, utilities, curbs, sidewalks, and other obstructions as SHOWN ON THE DRAWINGS.

Salvage designated materials and backfill the resulting trenches, holes, pits, or as SHOWN ON

THE DRAWINGS.

Construction

202.02 Salvaging Material. Use reasonable care to salvage all material designated to be salvaged. Salvage in readily transportable sections or pieces. Replace or repair all members, pins, nuts, plates, and related hardware damaged, lost, or destroyed during the salvage operations.

Wire all loose parts to adjacent members or pack them in sturdy boxes with the contents clearly marked.

Carefully remove culvert, taking precautions to avoid damage. Store culverts to be relaid, when necessary, to prevent loss or damage before relaying. Replace without additional compensation all sections lost from storage or damaged by use of improper methods.

Matchmark members of salvaged structures. Furnish the CO with one set of drawings identifying the members and their respective matchmarks.

Stockpile salvaged material in a designated area.

202.03 Removing Material. Saw cut sidewalks, curbs, pavements, and structures when partial removal is required.

Raze and remove all buildings, foundations, pavements, sidewalks, curbs, fences, structures, and other obstructions that interfere with the work and are not designated to remain.

Existing culverts may be left in an embankment, provided that no portion of the culvert is within 2 feet of the subgrade, the embankment slope, or a new culvert or structure. Crush culvert ends.

Remove structures and obstructions in the roadbed to 12 inches below subgrade elevation.

Remove structures and obstructions outside the roadbed to 12 inches below finished ground or to the natural stream bottom.

Prior to removal, place rock and soil material located on the bridge deck, or structure so that it does not enter a stream.

Remove the substructures of existing structures down to the natural stream bottom, and remove the parts outside of a stream down to at least 12 inches below natural ground surface or finished groundline, whichever is lower. Remove portions of existing structures that lie wholly or in part within the limits for a new structure to accommodate construction of the proposed structure.

Except in excavation areas, fill cavities left by structure removal with material to the level of the finished ground, and compact. Place and compact the type of backfill material that is SHOWN ON THE DRAWINGS, designated in the SPECIAL PROJECT SPECIFICATIONS, or approved by the CO.

202.04 Disposing of Material or Structures Not Designated for Salvage.

Dispose of material and structures as SHOWN ON THE DRAWINGS or designated in the SPECIAL PROJECT SPECIFICATIONS, using one or more of the following methods:

(a) Removal From Project. Make necessary arrangements with property owners, and haul debris to suitable disposal locations as approved by the CO. Furnish a signed copy of the disposal agreement. Hazardous materials must be properly disposed of.

(b) Burning. Burn debris using high-intensity burning processes that produce few emissions.

Examples include incinerating, high stacking, or pit and ditch burning. Provide a watchperson during burning operations.

When burning is complete, extinguish the fire so no smoldering debris remains. Dispose of unburned material in accordance with Subsection 202.04(c).

(c) Burying. Bury debris in trenches or pits in approved areas within the right-of-way. Do not bury debris inside the roadway prism limits, beneath drainage ditches, or in any riparian areas.

Place debris with earth material in alternating layers consisting of 3 feet of debris covered by 2 feet of earth. Distribute stumps, logs, and other large pieces to form a compact mass and minimize air voids. Fill all voids. Cover the top layer of buried debris with at least 12 inches of compacted earth. Grade and shape the area.

Measurement

202.05 Method. Use the method of measurement that is DESIGNATED IN THE SCHEDULE

OF ITEMS.

Payment

202.06 Basis. The accepted quantities will be paid for at the contract unit price for each PAY

ITEM DESIGNATED IN THE SCHEDULE OF ITEMS.

Payment will be made under:

Pay Item Pay Unit

202(01) Removal of structures and obstructions .................................Lump Sum

202(02) Removal of _______ .............................................................Each

202(03) Removal of _______ .............................................................Linear Foot

202(04) Removal of _______ .............................................................Square Yard

202(05) Removal of _______ .............................................................Lump Sum

Section 602

Section 602 - Minor Concrete Structures

602.01 Work. Construct reinforced or unreinforced minor concrete structures.

Materials

602.02 Requirements. Furnish materials that meet the requirements specified in the following subsections:

Air-Entraining Admixtures .........................................................711.02 Cement ........................................................................................701.01 Chemical Admixtures .................................................................711.03 Coarse Aggregate for Portland Cement Concrete .......................703.02 Curing Material ...........................................................................711.01 Fine Aggregate for Portland Cement Concrete ...........................703.01 Fly Ash ........................................................................................725.04 High-Strength Nonshrink Grout .................................................701.02 Latex Modifier ............................................................................711.04 Reinforcing Steel ........................................................................709.01 Water ...........................................................................................725.01

602.03 Concrete Composition. Use the concrete composition method DESIGNATED IN THE

SCHEDULE OF ITEMS.

(a) Method A. Furnish to the CO a mix design showing the proposed weights of aggregate, water, and cement per cubic yard of concrete a minimum of 7 days prior to beginning placement.

Proportion the cement, aggregate, and water to obtain concrete with good workability. Ensure that slump is 4 inches or less, as determined by AASHTO T 119. Ensure that air-entrainment is 6 ± 1 percent, as determined by AASHTO T 152 or T 196.

Ensure that the concrete develops a 28-day minimum compressive strength of 3,000 psi, unless otherwise SHOWN ON THE DRAWINGS. Furnish concrete for specimens. Strength will be determined by test cylinders made and cured in accordance with AASHTO T 23 and tested in accordance with AASHTO T 22.

Failure of any test cylinder to meet the required strength, for any structural element tested, will be considered evidence of noncompliance with the strength requirement of this specification.

(b) Method B. Submit for approval the following information a minimum of 7 days prior to beginning placement:

(1) Type, grading, and sources of aggregate.

(2) Type and source of cement, blended cement, or fly ash.

(3) Saturated surface dry weights of the fine and coarse aggregate in pounds per cubic yard of concrete.

(4) Weight of mixing water in pounds per cubic yard of concrete.

(5) Weight of cement in pounds per cubic yard of concrete.

(6) Admixture type, quantity, and certification by manufacturer.

(7) Air content.

(8) Slump.

(9) 28-day compressive strength.

Ensure that the concrete contains not less than 611 pounds per cubic yard. Ensure that slump is 4 inches or less, as determined by AASHTO T 119.

When a commercial supplier is used, furnish a certification with each truckload of concrete certifying that the material and mix proportions used are in conformance with the approved mixture.

(c) Method C. Make the concrete using a dry, preproportioned, blended, and bagged mix meeting the requirements of ASTM C 387 and mixed at the jobsite in accordance with the manufacturer’s recommendations.

(d) Fly Ash- or Pozzolan-Modified Concrete. Fly ash may be substituted for cement at the rate of 1.2 pounds of fly ash per 1.0 pound of Portland cement. After substitution, reduce the design aggregate volumes by an amount equal to the net increase in volume of the combined cement and fly ash. Replace no less than 10 percent and no more than 20 percent of the weight of Portland cement required with fly ash at the above rate. For purposes of controlling the maximum water/cement ratio of 0.49, make the water/cement ratio for fly-ash-modified concrete the ratio of the weight of water to the combined weights of Portland cement and 60 percent of the weight of the fly ash.

Extend the standard 28-day curing period for compressive-strength tests for fly-ash modified concrete by 1 day (rounded to the nearest whole day) for each 1.5 percent of Portland cement replaced with fly ash at the selected rate. (Example: If the maximum of 20 percent cement is replaced, the curing period for cylinders is 41 days.)

Construction

602.04 Forms. Design and construct forms so they can be removed without damaging the concrete. Make them free of bulge and warp, and constructed so that the finished concrete has the form and dimensions SHOWN ON THE DRAWINGS and is true to line and grade. Concrete may be placed without forms where SHOWN ON THE DRAWINGS.

Design forms for concrete that contains a retarding admixture, fly ash, or other pozzolan replacement for cement so that the lateral pressures exerted by the full anticipated height of fluidized concrete are contained, unless documented information in regard to initial set is provided by the manufacturer.

602.05 Placing Concrete. Place all reinforcing steel in position as SHOWN ON THE DRAWINGS, and ensure that it is securely held in place by approved supports during placing of concrete. Do not place concrete until the grading, forms, and steel reinforcements have been inspected and approved by the CO. Give the CO 24 hours written notice prior to placement of any concrete.

Ensure that reinforcing steel material and construction requirements are in accordance with Section 554.

Discharge all concrete prepared using methods A and B into the forms within the time limits shown in Table 602-1. These time limits are based on jobsite ambient air temperature, cement type, and admixture used. Begin counting time from when the cement is introduced into the aggregate. Discharge concrete prepared using method C into the forms within 1-1/2 hours after introducing water to the mixture. Do not retemper concrete. Cement must be added to the mixer at the jobsite when required in the SPECIAL PROJECT SPECIFICATIONS. Do not mix or place concrete when the daily minimum atmospheric temperature is, or is expected to be, less than 40 °F unless adequate provisions are made to protect the concrete.

Place concrete to avoid segregation. Use high-frequency internal vibrators for consolidating concrete in the forms. Operate vibrators to produce concrete free of voids, but do not hold them in one place long enough to result in segregation or formation of laitance on the surface.

Method C concrete may be rodded instead of internally vibrated as necessary to remove voids.

Do not use aluminum pipe, conduit, or troughs for transporting concrete. When concrete is pumped, take samples from the discharge stream at the point of placement.

602.06 Finishing. Perform finishing of concrete surfaces as follows:

(a) Formed Surfaces. Unless otherwise SHOWN ON THE DRAWINGS, remove all fins and irregular projections exceeding ¼ inch from the exposed surfaces. Fill holes produced by removing form ties with dry-pack mortar or other approved patching compounds.

(b) Unformed Surfaces. Strike off unformed surfaces with a straightedge, and finish them to a smooth uniform texture by floating and troweling. Prepare final finish of the surface as SHOWN

ON THE DRAWINGS.

Table 602-1. - Concrete discharge time limits.

Cement Type With and Without Admixtures

Time limit (hour) < 86 oFa ≥ 86 oFa

Type I, IA, II, or IIA 2.0 1.5 Type I, IA, II, or IIA with water reducing or retarding admixture 3.0 2.0

Type III 1.5 1.0 Type III with water reducing or retarding admixture 2.0 1.5

a. Ambient air temperature.

602.07 Curing Concrete. Beginning immediately after finishing, cure all concrete a minimum of 7 days or, if high-early-strength cement is used, a minimum of 3 days. For fly-ash-modified concrete placed in structures, the required moisture-controlled curing period shall be:

Percentage of Cement Replaced by Weight

Required Curing Period

10% 9 days 11–15% 10 days 16–20% 11 days

For cold weather concreting, maintain a controlled temperature for the required curing period.

The above requirement for an extended curing period may be waived if a compressive strength of 65 percent of the specified 28-day design strength is achieved in 6 days.

Cure by maintaining a minimum concrete temperature of 40 °F and keeping the concrete continuously moist. Keep moist by supplying additional moisture or preventing moisture loss.

Acceptable methods of supplying additional moisture are ponding or sprinkling, and covering with burlap cloth that is kept saturated. Surfaces SHOWN ON THE DRAWINGS may be covered with saturated sand or 6 inches of saturated hay or straw to retain moisture.

Acceptable methods of preventing moisture loss are applying liquid membrane forming compounds, or waterproof paper or polyethylene sheet materials. Apply liquid membrane forming compounds by spraying at the coverage rates and patterns recommended by the manufacturer. Ensure that sheet material has overlapped sealed joints and forms a complete waterproof cover over the entire concrete surface.

602.08 Backfilling. Backfill in accordance with Subsection 206A.10. Do not backfill concrete until it has completed the required curing period.

Measurement

602.09 Method. Use the method of measurement that is DESIGNATED IN THE SCHEDULE

OF ITEMS.

Payment

602.10 Basis. The accepted quantities will be paid for at the contract unit price for each PAY

ITEM DESIGNATED IN THE SCHEDULE OF ITEMS.

602(01) Concrete, method____ ...........................................................Cubic Yard

602(02) Concrete, method____ ...........................................................Lump Sum

Section 602-1 SPS

SPECIAL PROJECT SPECIFICATION

602-1 MINOR CONCRETE STRUCTURES

602.10 Basis.

Delete Pay Items shown in Specification Section 602 and insert the following:

No payment will be Materials under this item. Payment for these materials will be considered incidental to Section 607-2, 607-3, 633 and 862-2 described as SPS Unauthorized Route Barrier Installation, SPS Pipe Rail Barrier Gate, Signs and Gate Installation respectively.

Section 607-2 SPS

SPECIAL PROJECT SPECIFICATIONS

607-2 UNAUTHORIZED ROUTE BARRIER INSTALLATION (11-03)

607-2.01

This work consists of furnishing and installing Barrier Assemblies. The contractor shall furnish all labor, equipment, and transportation necessary to perform the work in this specification.

607-2.02 Materials

1. The contractor shall furnish OHV Barrier Assemblies manufactured to conform to the drawings.

2. Materials shall conform to notes on the drawings.

3. The contractor shall construct concrete footings as shown on the drawings.

4. Contractor furnished concrete used for barrier installation shall meet the standard specification

Section 602 either Method B or Method C.

a. Method B: The contractor shall submit for approval the mix information. The concrete shall contain not less than 5.5 sacks of cement per cubic yard. Slump shall not be more than 4 inches.

b. Method C: The concrete shall be made using a dry, pre-proportioned, blended, and bagged mix meeting the requirements of ASTM C 387, and mixed at the job site in accordance with the manufacturer’s recommendation.

5. All other materials, labor, and incidentals necessary for Barrier installation shall be furnished by the contractor, and shall be included in the contract price.

607-2.03 Barrier Installation

1. Gate posts shall be erected plumb and in accordance with the details SHOWN ON THE

DRAWINGS.

2. Exact locations will be staked by the COR.

607-2.04 Measurement

The quantity to be measured will be the completed Barriers listed in the SCHEDULE OF ITEMS and accepted under this Section.

607-2.05

A. The accepted quantities will be paid at the contract unit price shown in the SCHEDULE OF

ITEMS.

Section 607-2 SPS

B. Payment will be made under:

607-2(1) Construct and Install Barrier Assembly LF (Steel Pipe)

607-2(2) Furnish and Install Barrier Posts, 4 feet long EA (Concrete posts)

Section 607-3 SPS

607-3 PIPE RAIL BARRIER GATE (12-15)

607-3.01

This work consists of fabricating, furnishing and installing Removable Steel Pipe Barrier Assemblies. This work also consists of fabricating, furnishing and installing steel Pipe Horse Gates.

The contractor shall furnish all labor, equipment, and transportation necessary to perform the work in this specification.

607-3.02

1. The contractor shall furnish Removable Barrier Assemblies fabricated to conform to the drawings.

2. Materials shall conform to notes on the drawings.

3. The contractor shall construct concrete footings as shown on the drawings.

4. Contractor furnished concrete used for barrier installation shall meet the standard specification

Section 602 either Method B or Method C.

a. Method B: The contractor shall submit for approval the mix information. The concrete shall contain not less than 5.5 sacks of cement per cubic yard. Slump shall not be more than 4 inches.

b. Method C: The concrete shall be made using a dry, pre-proportioned, blended, and bagged mix meeting the requirements of ASTM C 387, and mixed at the job site in accordance with the manufacturer’s recommendation.

5. All other materials, labor, and incidentals necessary for Removable Barrier installation shall be furnished by the contractor, and shall be included in the contract price.

607-3.03 Removable Steel Pipe Barrier Installation

1. Vertical barrier posts shall be erected plumb and installed in accordance with the details SHOWN

ON THE DRAWINGS.

607-3.04 Horse Gate Installation

1. All vertical pipe members shall be erected plumb and installed in accordance with the details

SHOWN ON THE DRAWINGS.

3. Reflective signs and stickers shall be furnished and installed by contractor.

607-3.05

The quantity to be measured will be the completed number of Removable Steel Pipe Barrier Assemblies and Horse Gates listed in the SCHEDULE OF ITEMS and accepted under this Section.

607-3.06

A. The accepted quantities will be paid at the contract unit price shown in the SCHEDULE OF

ITEMS.

607-3(1) Construct and install Removable Steel Pipe Fence Assembly EA

607-3(2) Construct and install Horse Gate EA

Section 633

Section 633. — PERMANENT TRAFFIC CONTROL

633.01 This work consists of constructing permanent traffic control signs, supports, delineators, and object markers, and removing and resetting permanent traffic control devices.

Sign panels are designated as plywood, aluminum, steel, plastic, or fiberglass reinforced plastic.

Sign retroreflective sheeting type is designated according to Subsection 718.01.

Posts are designated as wood, aluminum, galvanized steel, or corrosion resistant steel.

Material

633.02 Conform to the MUTCD and the following Section and Subsections:

Aluminum panels 718.05 Concrete 601 Delineator and object marker retroreflectors 718.12 Extruded aluminum panels 718.07 Fiberglass reinforced plastic panels 718.06(b) Hardware 718.10 Letters, numerals, arrows, symbols, and borders 718.11 Object marker and delineator posts 718.09 Plastic panels 718.06(a) Plywood panels 718.03 Retroreflective sheeting 718.01 Signposts 718.08 Steel panels 718.04

Construction Requirements

633.03 General. Furnish traffic control devices according to the MUTCD and Standard Highway Signs published by FHWA. Submit the sign list for approval before ordering.

633.04 Supports. Sign locations may be changed to fit field conditions as approved by the CO.

Determine sign support lengths at time of staking. Install supports plumb and according to the manufacturer's instructions. Make all supports within the clear zone crashworthy.

Drive posts with a suitable driving head or set posts in drilled or punched holes. Replace all damaged posts.

Construct concrete footings according to Section 601. Excavate and backfill according to Section 209.

633.05 Panels. Use type III, VII, VIII, or IX retroreflective sheeting. For permanent sign panels, use type L-1 letters, numerals, arrows, symbols, and borders. Cut panels to size and shape and drill or punch all holes. Make panels flat and free of buckles, warp, dents, cockles, burrs, and other defects.

Clean and degrease the face of metal panels using methods recommended by the retroreflective sheeting manufacturer. Abrade, clean, and degrease the face of the plywood panels using methods recommended by the retroreflective sheeting manufacturer. Treat the edges of the plywood panel with an approved edge sealant. Apply the retroreflective sheeting material to the panels. Package sign panels in protective material and transport them in a vertical position.

Mount sign panels with the legend horizontal. Where multiple panels adjoin, limit the gap between adjacent panels to 1/16 inch. To reduce specular glare (mirror reflection), turn the sign panel 3 degrees away from the road in the direction of travel.

Use oversized bolt heads and neoprene or nylon washers for fastening plastic sign panels.

Do not field drill holes in any part of the panel. Use antitheft fasteners where possible. Paint all bolt heads, screw heads, and washers that are exposed on the sign face. Match the color of the paint to the color of the background or message area at the point where the fitting is exposed.

If a sign message is not applicable, completely cover the face of the sign with an opaque material.

Maintain the covering in good condition until the message becomes applicable. Do not use adhesive tape on the sign face.

Repair or replace damaged parts including sheeting.

633.06 Delineators and Object Markers. Attach delineators and object markers to posts according to the manufacturer's recommendation.

633.07 Removing and Resetting Permanent Traffic Control Devices. Remove and store the existing signs, delineators, and object markers. Replace all devices, posts, and hardware damaged during removal, storage, and raising.

633.08 Acceptance. Material (including signs panels, retroreflective sheeting, supports, delineators, object markers, and hardware) for traffic control devices will be evaluated under Subsections 106.02 and 106.03.

Installation of traffic control devices will be evaluated under Subsections 106.02 and 106.04.

Excavation and backfill will be evaluated under Section 209.

Concrete will be evaluated under Section 601.

Measurement

633.09 Measure the Section 633 items listed in the bid schedule according to Subsection 109.02 and the following as applicable.

Measure sign systems by the square foot of front face of sign panel as follows:

(a) When a sign system is measured by the each, measure each system as one sign regardless of the number of sign panels or posts.

(b) When a sign system is measured by the square foot, measure the nominal dimensions of all the sign panels.

(c) A sign system includes the supports.

Measure sign panel by the square foot of front face.

Measure each sign panel in a multiple configuration.

Measure removing and resetting permanent traffic control devices after they are reset. Measure based on the number of devices reset in their final position as described in (a) above.

Payment

633.10 The accepted quantities will be paid at the contract price per unit of measurement for the Section 633 pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05.

Section 813

813 SPOT SURFACING (3/96)

1. DESCRIPTION

This work consists of placing surface aggregate as staked on the ground. It includes preparing the area, furnishing, hauling, and placing all necessary materials and other work necessary to blend with the adjacent road cross section.

2. MATERIALS

a. Materials will be Government furnished only when stated in Schedule of Items.

b. Materials furnished by the Contractor shall conform to the gradation requirements and the quality requirements of Section 893.

3. MAINTENANCE REQUIREMENTS

a. The area to be spot surfaced shall be thoroughly loosened to a minimum depth of one (1) inch prior to placement of aggregate.

b. Mixing and Placing

1. When scheduled coincident with work under Section 811, spot surfacing and existing aggregate, when ordered, shall be mixed with water until a uniform mixture is obtained prior to final shaping and compaction.

2. The material shall otherwise be spread on the prepared area in layers no more than four (4) inches in depth. When more than one (1) layer is required, each layer shall be shaped and compacted before the succeeding layer is placed. Upon completion, the spot surfacing shall reasonably conform to the adjacent cross section and provide smooth transition in the road profile.

3. Compaction shall be accomplished by using Method A. Compaction Method A is considered incidental. Compaction Method B shall be used when ordered.

Compaction methods are:

Compaction Method A: By breaking track while operating equipment on the bladed surface. Compaction shall cover the full width bladed surface.

Compaction Method B: 8-10 ton pneumatic, steel or equivalent vibrating roller, operated to cover the full width of each layer two (2) times.

4. MEASUREMENT

Section 813

a. The quantity will be the number of cubic yards measured in the vehicles, or square yards of aggregate placed, or tonnage verified by weight slips whichever is shown in the Schedule of Items.

b. Hauling is considered incidental when materials are furnished by the Contractor and when the haul distance is less than one (1) mile for Government furnished materials. When the haul distance exceeds one (1) mile for Government furnished materials haul will be ordered and paid under 832(3).

5. PAYMENT

a. The accepted quantities will be paid for at the contract unit prices shown in the Schedule of Items.

b. Payment will be made under:

813(1) Spot Surfacing, Grading ____ Cubic Yard 813(2) Spot Surfacing, Grading ____ Square Yard 813(3) Spot Surfacing, Grading ____ Ton 813(4) Spot Surfacing, Government Furnished Materials Cubic Yard 813(5) Compaction Method B Square Yard

Section 819

819 RIPRAP (11/07)

This work shall consist of furnishing, hauling and placing erosion resistant and protective materials for use on embankments, streambanks, culvert inlets and outlets, channel bottoms and side slopes, abutment wings, structure foundations, and other designated locations.

2. EQUIPMENT

All methods employed in performing the work and all equipment, tools and machinery used for handling the material and executing any part of the work shall be subject to the approval of the Government before the work is started, and whenever unsatisfactory, they shall be changed or improved as required.

3. MATERIALS

Unless shown in the Schedule of Items, all materials shall be furnished by the Contractor and shall meet the following requirements:

a. Riprap

Rock used for riprap shall be hard angular rock with a Durability Absorption Ratio greater than 23 or between 10 – 23 if the Durability Index is greater than 52.

Durability Absorption Ratio = Durability Index (Course) AASHTO T 210 Percent Aborption + 1 AASHTO T 85

Neither the breadth nor thickness of any piece of riprap shall be less than one-third its length.

Rock shall be free from overburden, spoil, shale, and organic material; shall meet the following gradation requirements for the class specified; and shall be delivered to designated locatons.

Rock for grouted riprap shall be free of fines that prevent penetration of grout.

Size of Rock (Pounds)

Percent of Total Weight Smaller Than the Given Size

Class I 50 100 35 80 10 50 2 Not to exceed 10

Class II

(Pounds)

Percent of Total Weight Smaller Than the Given Size

100 100 60 80 25 50 2 Not to exceed 10 Class III 250 100 150 80 50 50 10 Not to exceed 10

Class IV 400 100 250 70 100 30 20 Not to exceed 10

Class V 700 100 400 70 200 30 25 Not to exceed 10

Class VI 1,600 100 800 70 400 30 50 Not to exceed 10

Class VII

2.700 100 1,600 70 800 30 100 Not to exceed 10

Class VIII 4,000 100 2,000 80 500 50 100 Not to exceed 10

Class IX 6,000 100

(Pounds)

Percent of Total Weight Smaller Than the Given Size

3,000 80 1,000 50 200 Not to exceed 10

Each load of riprap shall be well graded from the smallest to the maximum size specified.

b. Grout

Grout for riprap shall be delivered to designated sites. Grout for riprap shall consist of concrete containing 5 sacks of cement per cubic yard, aggregate with a maximum size of ¾ inches, and water limited to that necessary to ensure good workability. Reasonably clean and strong aggregate of appropriate size gradation, as approved by the CO, shall be used.

A water reducer, set retarder shall be submitted for approval and will include recommended dosage for 2, 3, and 4 hour hauls.

4. MEASUREMENT

The quantity will be the number of cubic yards measured in the hauling vehicles, or tonnage verified by certified weight slips whichever is shown in the Schedule of Items.

Hauling is considered incidental when materials are furnished by the Contractor and when the haul distance is less than one (1) mile for Government furnished materials. When the haul distance exceeds one (1) mile for Government furnished materials haul will be ordered and paid under 832(3).

Application of grout will be measured by the hour for mixer truck standby starting when application begins. On site mixing and setup will be considered incidental to grout cost.

6. PAYMENT

The accepted quantity will be paid for at the contract unit price shown in the Schedule of Items.

The loading and hauling of Govermnet furnished riprap will be paid for under Section 832.

Payment will be made under:

Pay Item Pay Unit

819(1) Riprap, Class _____ Ton 819(2) Riprap, Government Furnished Cubic Yard 819(3) Grout Cubic Yard 819(4) Grout Application Hour

Route Decommissioning 2016

Section 836-8 SPS

SPECIAL PROJECT SPECIFICATION

836-8 Route Decommissioning

836-8.01 Description This work consists of performing Route Decommissioning through the methods of Chunking and Ripping within the former unauthorized travelled way. This work also consists of Slashing whereby brush is spread over disturbed areas as described below. Work includes all labor and equipment and transportation necessary to perform the work in this specification.

836-8.02 Chunking (a.k.a pocking or gouging ) is a method used to intercept and trap sediment on a micro-scale. Chunking also collects moisture, which improves vegetation establishment and consequently prevents erosion. This method is highly recommended for moderate to steep slopes. But it is also useful for flat or gently sloping areas with erosive soils and arid climates. Chunking is most practical for use on small disturbed areas of fewer than fifty acres or for critical portions of large disturbances, such as highly erosive soils and areas adjacent to streams. When soils are shallow and bedrock is prominent, it may be necessary to add water bars and/or lead off ditches.

Basic Design and Construction

1. Use a small excavator or backhoe to create micro basins.

2. Dig a bucket load of soil to depth of 18-24 inches.

3. Drop bucket load 2-3 feet above the soil.

4. Repeat this process in a random and overlapping pattern throughout the site, making it impossible for water to flow down slope.

5. Finished roughened soil should be difficult to walk over.

6. Additional description may be found in Restoration of Forests, Grasslands, and Wetlands Damaged by Off-Highway Vehicles, available from the U.S. Government Printing Office.

836-8.03 Ripping is a method used to create intercepting ditches on a compacted surface along a contour line such that water will not readily travel along the ditch.

1. Shank Type Rippers

a. This work shall consist of ripping an existing roadbed with a shank type ripper.

b. The distance between the ripper shanks shall not exceed 36 inches. Rippers shall have a minimum of two shanks.

c. The minimum ripping depth shall be 20 inches. The Government may agree to a lesser depth when excessive rock is encountered.

d. Equipment shall not be operated on ripped areas.

2. Wing Rippers

a. This work shall consist of subsoiling an existing roadbed by ripping with a winged ripper.

b. The distance between ripper shanks shall not exceed 36 inches. Each shank shall be equipped with a shoe and wings which have a total width of at least 18 inches.

The design of the shank and wing will be such that the treated soils are slightly lifted and well fractured rather than plowed, mixed or displaced.

c. Ripping shall be accomplished to a minimum depth of 20 inches. The Government may agree to a lesser depth when excessive rock is encountered.

d. Equipment shall not be operated on ripped areas.

836-8.04 Outsloping/Recontouring

1. Designated routes or segments of routes to remain shall be outsloped by pulling the fill shoulder towards the cut bank. Excavated material shall be spread over the route forming a minimum outslope equal to the existing road grade percent. The Government may agree to a lesser outslope percent if soil conditions warrant.

2. Any existing ditches at the toe of the cut shall be filled with the material excavated during outsloping.

836-8.05 Slashing

1. This work shall consist of placing woody material over the disturbed route to discourage vehicle or other traffic.

2. Woody material shall be dead timber and slash removed from an area within twenty five (25) feet of the road shoulders in the vicinity of the areas where it is to be placed.

3. Material shall be placed randomly over the routes to give a similar appearance of the surrounding area and may include rocks and other material.

836-8.06 Measurement

The quantity to be measured will be the completed number of miles of Route Decommissioning based upon an average eight to ten foot wide swaths listed in the SCHEDULE OF ITEMS measured and accepted under this section.

836-8.05 Payment

Payment will be made for the Actual Quantity of accepted quantities at the contract unit price shown in the SCHEDULE OF ITEMS.

Pay Item Description Unit 836-8(1) Route Decommissioning (RIPPING) MILE 836-8(2) Route Decommissioning (SLASHING) MILE 836-8(3) Route Decommissioning (CHUNKING) MILE

Section 862-2 SPS

862-2 GATE INSTALLATION

862-2.01

This work consists of furnishing and installing gates and appurtenances. The contractor shall furnish all labor, equipment, and transportation necessary to perform the work in this specification.

862-2.02

1. The contractor shall furnish gates, gate posts and hinges, lock open posts and appurtenances manufactured to conform with the drawings.

2. Materials shall conform to notes on the drawings.

3. The contractor shall furnish and install barricade marker signs (B-M-L-R and B-M-R-

R) and object marker signs (OM-2-B) conforming to the drawings and MUTCD specifications.

4. The contractor shall construct concrete footings as shown on the drawings.

5. Contractor furnished concrete used for gate installation shall meet the standard specification Section 602 either Method B or Method C.

a. Method B: The contractor shall submit for approval the mix information. The concrete shall contain not less than 5.5 sacks of cement per cubic yard. Slump shall not be more than 4 inches.

b. Method C: The concrete shall be made using a dry, pre-proportioned, blended, and bagged mix meeting the requirements of ASTM C 387, and mixed at the job site in accordance with the manufacturer’s recommendation.

6. All other materials, labor, and incidentals necessary for sign installation shall be furnished by the contractor, and shall be included in the contract price.

862-2.03 Gate Installation

Gate posts shall be erected plumb and in accordance with the details SHOWN ON THE DRAWINGS. The gate and lock mechanisms shall operate freely. Contractor is to furnish all reflective signs shown on drawings and securely fasten the sign panels to the posts as SHOWN ON THE DRAWINGS.

862-2.04

The quantity to be measured will be the completed number of gates, fully installed and functioning listed in the SCHEDULE OF ITEMS and accepted under this Section.

Section 862-2 SPS

862-2.05

A. The accepted quantities will be paid at the contract unit price shown in the

SCHEDULE OF ITEMS.

862-2(1) Construct and install gate and appurtenances Each

Section 881

881 MOBILIZATION (2/94)

This Section consists of one or more mobilizations of personnel, equipment, supplies, and incidentals to the project site, or sites listed in the Schedule of Items.

2. MEASUREMENT

When the contract establishes separate work periods within the contract time any additional mobilization included as a Bid Item will be retained until the actual work period.

3. PAYMENT

a. Progress payments will be made on the basis of the Bid Items contained in the Schedule of Items as follows:

1. When five (5) percent of the estimated contract amount in the work period is earned, fifty (50) percent of the amount of mobilization will be paid.

2. When twenty-five (25) percent of the estimated contract amount in the work period is earned, one hundred (100) percent of the amount for mobilization will be paid.

3. The total sum of all payments under this Section shall not exceed 10% of the total contract amount.

4. The contract amount for mobilization shall include full compensation for furnishing all labor, materials, tools, equipment and incidentals involved in mobilization.

b. Payment will be made under:

Pay Item Description Pay Unit

881(1) Mobilization Each

Section 883

SECTION 883 CLEANING OF EQUIPMENT (3/10)

This work consists of removing all soil and other foreign matter from equipment upon moving into and out of work areas to prevent the spread of noxious weeds.

2. REQUIREMENTS

A. All equipment shall be clean when mobilized onto the Forest or moved from area to another.

B. Cleaning shall consist of the removal of all soil from equipment by steam cleaning or the use of high pressure cleaning equipment. Areas for cleaning of equipment will be designated by the Government.

C. Cleaning will be inspected and accepted by the Government prior to the equipment moving into and leaving the area.

3. MEASUREMENT AND PAYMENT

No separate measurement or payment will be made for meeting requirements of this Section. All work and materials shall be incidental to paid work in this contract.

Section 893

893 AGGREGATE (3/96)

1. Gradations for aggregates are included in Table 1 for contracts where the aggregates are not provided by the Government.

2. The inclusion of aggregate gradations does not constitute a warranty by the Government that commercial sources in the area are producing the gradation indicated. Aggregates commercially produced to meet State or County gradations and specifications for similar materials will be considered an equal alternate to the gradation in the contract provided the following quality requirements are met. Contractor shall provide testing and certification of supplied materials.

3. Aggregate for Bituminous Plant-Mix

a. Coarse Aggregate - Coarse aggregate (retained on the No. 8 sieve) shall be crushed stone or crushed or natural gravel and shall conform to the quality requirements of AASHTO M

63. Gradation shall conform to the provisions of Table 1.

b. Fine Aggregate - Fine aggregate (passing the No. 8 sieve) shall be manufactured and conform to the quality requirements of AASHTO M 29 (ASTM D 1073). It shall be of such a gradation that when combined with the other required aggregate fractions in the proper proportion, the resultant mixture will meet the gradation required.

4. Aggregate for Spot Surfacing

a. Aggregates for spot surfacing shall be crushed stone, crushed slag, or crushed gravel which conforms to the quality requirements of AASHTO M 147, except as noted below: The requirements of M 147 shall apply, except that the liquid limit shall not exceed 35 and the plasticity index shall be not be less than 4 nor more than 9.

b. Aggregate gradation shall conform to the provisions of Table 1 and AASHTO M 147.

c. When crushed gravel is used, not less than 50 percent by weight of the particles retained on the No. 4 sieve shall have at least one fractured face.

d. Gradations of each designated size of aggregates shall be obtained by crushing, screening, and blending processes as may be necessary.

e. Materials otherwise meeting the requirements of this subsection will be acceptable whenever the gradations of such materials are within the tolerances corresponding to the selected sieve sizes required by Table 1. Aggregates shall be graded from course to fine within the gradation band.

5. Aggregate for Bituminous Concrete - General

a. Coarse Aggregate

1. Coarse aggregate (retained on the No. 8 sieve) shall be crushed stone, crushed slag, or crushed or natural gravel, and unless otherwise stipulated, shall conform to the quality requirements of AASHTO M 79.

2. Lightweight aggregate, if required or permitted by the Special Project Specifications, shall meet the requirements of AASHTO M 195.

3. When crushed gravel is used, it shall also meet the requirements of Section 2.1 of AASHTO M 62 and not less than 50 percent by weight of the particles retained on the No. 4 sieve shall have at least one fractured face. The coarse aggregate shall be of such gradation that when combined with other required aggregate fractions in proper proportion, the resultant mixture shall meet the gradation required under the composition of mixture for the specific type under contract.

b. Fine Aggregate

1. Fine aggregate (passing the No. 8 sieve) shall consist of natural sand, stone screenings, or slag screenings, or a combination thereof, and unless otherwise stipulated shall conform to the quality requirements of AASHTO M 29 (ASTM D 1073). Fine aggregate shall be of such gradation that when combined with other required aggregate fractions in proper proportion, the resultant mixture shall meet the gradation required under the composition of mixture for the specific type under contract.

2. Lightweight aggregate if required or permitted by the Specifications, shall meet the requirements of AASHTO M 195.

6. Aggregate for Bituminous Hot Plant-Mix

a. The provisions of 5(a) and 5(b) herein shall apply.

b. The several aggregate fractions for the mixture shall be sized, and blended to meet one of the grading requirements of Table 1 as specified on the drawings.

7. Aggregate for Cold Plant-Mix Bituminous Pavement

a. The provisions of 5(a) and 5(b) herein shall apply.

1. Aggregate for Pavement - The several aggregate fractions for the mixture shall be sized, graded, and combined in such proportions that the resulting composite blend meets one of the grading requirements of Table 1 as specified on the drawings.

2. Aggregate for Top Dressing

a. The material for the top dressing shall consist of dry sand, stone screenings, or slag screenings meeting the grading requirements of Table 1 as specified on the drawings.

b. Lightweight aggregate, if required or permitted by the Specifications, shall meet the pertinent requirements of AASHTO M 195.

9. Aggregate for Cover Coats, Surface Treatments, and Bituminous Preservative

Treatment

a. Aggregates shall meet the quality requirements of AASHTO M 78.

b. When tested in accordance with AASHTO T 182 (ASTM D 1664), aggregate shall have a retained bituminous film above 95 percent.

c. Aggregates which do not meet this requirement may be used for bituminous surface treatments and seal coats provided an approved chemical additive or wetting agent is used to provide a water resistant film.

d. Lightweight aggregate, if required or permitted by the Specifications, shall meet the pertinent requirements of AASHTO M 195.

e. When crushed gravel is used, not less than 50 percent by weight of the particles retained on the No. 4 sieve shall have at least one fractured face. Aggregates shall meet one of the grading requirements of Table 1.

TABLE 1 - AGGREGATE GRADATION REQUIREMENTS

Spot Surfacing Grading Requirements

Percent Passing (AASHTO T 11 and T 22) Sieve Grading 1 Grading 2 2 inch 100 - 1 1/2 inch 90-100 - 1 inch - 100 3/4 inch 50-85 90-100 No. 4 25-45 35-60 No. 30 10-25 10-30 No. 200 2-9 2-9

Bituminous Plant Mix Grading requirements

Hot Mix Cold Mix Grading DG-3 Sieve (1/2 in. Maximum) Dense Graded 1 inch - 100 3/4 inch - 80-100 1/2 inch 100 60-85 3/8 inch 95-100 - No. 4 67-83 35-60 No. 8 52-69 23-44 No. 30 23-40 9-25 No. 200 3-10 2-8

Surface Treatment Grading Requirements

Grading Medium Sieve (3/8in. X No. 6) 3/4 inch - 1/2 inch 100 3/8 inch 90-100 No. 4 5-30 No. 8 0-10 No. 16 0-5 No. 30 - No. 200 0-2

Section 202
Section 202 - Removal of Structures & Obstructions
Section 602
Section 602 - Minor Concrete Structures
Section 602-1 SPS
Section 607-2 SPS
Barrier Installation
Section 607-3 Removable Steel Pipe Fencing
Removable Steel Pipe Barrier Installation
Horse Gate Installation
Section 633
Section 633. — PERMANENT TRAFFIC CONTROL
Section 813 SPOT SURFACING
Section 819 RIPRAP
Section 836-8 Road Decommissioning
Section 862-2 F.S. Gate Spec
Gate Installation
Section 881 MOBILIZATION
Section 883 CLEANING OF EQUIPMENT
Section 893 AGGREGATE