Final_Carpet_2.pdf

PDF 691 KB Posted

Attached to
Replacement of carpet/ Flooring at the Northern California Training Center
Solicitation number
AG-9A73-S-13-0005
Issued by

About this file

Solicitation Package - Carpet

View the file

Other files

File Type Posted
Final_Carpet_4.pdf PDF
Final_Carpet_Mod_3.pdf PDF
Final_Mod._2.pdf PDF
0026_001_(2).pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR QUOTATION PAGE OF PAGES

(THIS IS NOT AN ORDER) THIS RFQ IS IS NOT A SMALL BUSINESS SET- ASIDE 1 28

1. REQUEST NO. 2. DATE ISSUED 3. REQUISITION/PURCHASE REQUEST NO. 4. CERT. FOR NAT.DEF. RATING

AG-9A73-S-13-0005 03/15/2013 622632

5a. ISSUED BY 6. DELIVER BY (Date)

USDA FOREST SERVICE, Northern California Operations 6101 Airport Road – Operations Building Redding, CA 96002

5b. FOR INFORMATION CALL (NO COLLECT CALLS) 7. DELIVERY FOB DESTINATION

NAME TELEPHONE NUMBER OTHER (See Schedule)

AREA CODE NUMBER 9. DESTINATION

Redding, CA Jeannie Vaughn 530 226-2702 a. NAME OF CONSIGNEE

8. TO: USDA, Forest Service - NCTC

a. NAME b. COMPANY b. STREET ADDRESS 6101 Airport Road

c. STREET ADDRESS c. CITY Redding

d. CITY e. STATE f. ZIP CODE d. STATE e. ZIP CODE

CA 96002

10. PLEASE FURNISH QUOTATIONS TO THE

ISSUING OFFICE IN BLOCK 5A ON OR

BEFORE CLOSE OF BUSINESS

IMPORTANT: This is a request for information, and quotations furnished are not offers. If you are unable to quote, please so indicate on this form and return it to the address in BLOCK 5A.

This request does not commit the Government to pay any costs incurred in the preparation of the

04/15/2013 - 4:30 Local Time submission of this quotation or to contract for supplies or services. Supplies are of domestic origin unless otherwise indicated by quoter. Any representations and/or certifications attached to this Request for Quotations must be completed by the quoter.

11. SCHEDULE (Include applicable Federal, State and local taxes)

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

(a) (b) (c) (d) (e) (f)

This project requires the Contractor to furnish and install all labor, materials and supervision for removal and disposal of old flooring and installation of new flooring at the USFS Northern California Training Center.

SEE

SCHEDULE

OF ITEMS

SEE SCHEDULE

OF ITEMS

Contractor MUST have active registration in SAM to be awarded a federal government contract. Website can be found at:

http://www.sam.gov

Please provide the following information:

DUNS: __________________________

TIN: ____________________________

a. 10 CALENDAR DAYS (%) b. 20 CALENDAR DAYS c. 30 CALENDAR DAYS d. CALENDAR DAYS

NUMBER PERCENTAGE

NOTE: Additional provisions and representations are are not attached.

13. NAME AND ADDRESS OF QUOTER 14. SIGNATURE OF PERSON AUTHORIZED TO 15. DATE OF

a. NAME OF QUOTER SIGN QUOTATION QUOTATION

b. STREET ADDRESS 16. SIGNER

a. NAME (Type or print) b. TELEPHONE

c. COUNTY AREA CODE

d. CITY e. STATE f. ZIP CODE c. TITLE (Type or Print) NUMBER

NSN 7540-01-152-8084

Previous edition not usable

18-121 STANDARD FORM 18 (Rev. 6-95) Prescribed by GSA-FAR (48 CFR) 53.215-1(a)

CONSTRUCTION RFQ SOL NO: AG-9A73-S-13-0005

UNIT: USDA Forest Service

Fire and Aviation Management PROJ NAME: NCTC flooring Replacement

PART 1, SCHEDULE OF ITEMS

SECTION B

SUPPLIES OR SERVICES, AND PRICES/COSTS

PROJECT Northern California Training Center – Carpet Replacement

UNIT R-5, Fire and Aviation Management

SOL. # AG-9A73-S-13-0003

METHOD OF PAY

ITEM NO. DESCRIPTION MEASURE UNIT QUANTITY UNIT PRICE TOTAL PRICE

01010 (01)

Installation of New Carpet and four inch Base in 1 LS 1 $ $

01010 (2)

Training Center – Approx. 3,000 Sq. Ft.

Installation of new Resilient Flooring and four 1 LS 1 $ $

01010 (3) inch Base – Transient Waiting Room – Approx. 200 Sq. Ft.

OPTION ITEMS

Simulation Room – Carpet Tiles 1 LS 1 $ $

01010 (4)

Approx. 700 Sq. Ft.

Installation of New Carpet and four inch Base in 1 LS 1 $ $

Training Center Offices – Approx. 2,000 Sq. Ft.

TOTAL $

1)If award is made in excess of $30,000, bonds will be required, and must be furnished in original, NO FACIMILIE See Section I.)

2) Provide a price breakdown of the quote.

3) THIS SOLICITATION AND ANY RESULTANT AWARD IS SET ASIDE 100 PERCENT FOR SMALL BUSINESS. THE NAICS CATEGORY FOR THIS SOLICITATION IS 238330 – FLOORING CONTRACTORS WHICH HAVE A SBA SIZE DETERMINATION OF $14.0 MILLION.

PRICE SUBMITTED BY:

Signature Phone

Vendor Name

FAX

Address

Email mailto:hh@deadend.com

SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

PART 1 GENERAL

1.01 SCOPE: The work under this solicitation includes furnishing all necessary tools, materials, labor, supervision and incidentals to install new flooring at the U.S. Forest Service, Northern California

Training Center. All work is to be completed as specified herein, and as needed for a complete and proper glue-down installation that meets the Carpet and Rug Institute’s (CRI) Green Label Plus ratings.

All work and products provided under this contract shall be in accordance with the USDA Biobased

Products listing under service and construction contracts. See Federal Acquisition Regulation clauses

52.223-1 and 52.223-2.

The majority of the flooring to be installed is to be a commercial grade, stain resistant carpet see Section

C, Part 2, for product information. The transient waiting room carpet needs to be replaced with a resilient floor covering. The Training Center offices are listed as an option item. If this option is awarded, it will be replaced with the same carpet installed in the Training Center. The Simulation Room is listed as an option item. If this option is awarded, it will be replaced with carpet tiles.

1.02 SUBMITTALS:

A. Product Data: The Contractor shall submit the following:

1. Materials list of items proposed to be provided under this Section

2. Manufacturer’s specifications and other data needed to prove compliance with the specified requirements;

3. Shop Drawings showing locations of seams and locations and types of carpet metal and accessories.

4. Samples of the full ranger of colors and patterns of carpet and of exposed accessories available from the proposed manufacturers in the specified qualities.

5. Manufacturer’s recommended installation procedures which, when approved by the

Contracting Officer, will become the basis for accepting or rejecting actual installation.

B. Provide flooring and base samples to Contracting Officer within 1 week of contract award.

After the Contracting Officer has selected the color and pattern, submit three samples each of specified color and pattern from the stock proposed to be installed. Secure the

Contracting Officer’s approval of these samples prior to installation.

1.03 PRODUCT HANDLING: Comply with the manufacturer’s handling recommendations and protect all products and materials from damage until the work is complete, the project has been inspected and the Contracting Officer has accepted the work.

1.04 MEASUREMENT AND PAYMENT: No separate measurement or payment will be made for the work specified in this Section.

PART 2 PRODUCTS

2.01 CARPET:

A. Provide “Philadelphia Commercial, Camden Harbor II Unitary” as manufactured by Shaw or provide equal products of other manufacturers when approved in advance by the Contracting

Officer. Carpet shall carry the Green Label of the Carpet and Rug Institute (CRI).

B. Provide carpeting with at least the following minimum attributes:

1. Recycled Content: 25% minimum

2. Pattern: Repeat

3. Surface: Textured Loop

4. Stiches: 7.66 per inch

5. Pile Height

6. Gauge: 1/8

7. Face Yarn weight: 28.0 ounces per square yard

8. Fiber/Brand: 100% ECO Solution Q (R) Premium Branded Nylon.

9. Backing Material: Polypropylene (Primary), CERTILOK (Secondary).

10. Dye Method: Static 1, Type Static Control permanent conductive fiber.

11. Static: 300 V at 20 percent relative humidity at 70 degrees Fahrenheit.

12. Smoke Developed: 190 flaming, 153 non-flaming.

13. Warranty: 10 year commercial quality assurance, 10 year limited warranty for unitary.

14. Installation method: Glue-down.

2.02 OTHER MATERIALS

A. Adhesives/Sealants: Adhesives and sealants shall comply with California’s South Coast Air

Quality Management District (SCAQMD) #1168 and shall be rated Green Label Plus by

CRI.

1. Provide carpet adhesive such as Mapei, Ultrabond ECO 85, solvent free or equal.

2. Provide seam adhesive such as W.W. Henry Company No. 248 (VOC: 30 g/L) or an equal approved by the Contracting Officer and recommended for the purpose by the manufacturer of the proposed carpet.

B. At intersection of carpet and floor tile, provide Mercer Plastics Company, Inc., “Custom

Edge Carpet Bar No. 90,” Vinyl, or equal, in color selected by the Contracting Officer.

C. Provide other materials, not specifically described but required for a complete and proper installation, as selected by the Contractor subject to the approval of the Contracting Officer.

PART 3 EXECUTION

3.01 SURFACE PREPARATION:

A. Immediately prior to installation of the work of this Section, thoroughly clean surface and remove oil, grease, paint, varnish, hardeners, and other items which would adversely affect the bond of adhesive.

B. Make surface level and free from irregularities by filling low spots and grinding high spots as required.

3.02 INSTALLATION

A. General:

1. Glue directly to floor, using no pads and no foam.

2. Scribe the carpet accurately to vertical surfaces.

3. Align the lines of carpet, as woven, using no fill strips less than six inches wide, laying all carpet in the same direction unless specifically directed otherwise by the Contracting

Officer.

B. Seams:

1. Locate seams only where shown on the approved Shop Drawings, or where specifically otherwise approved by the Contracting Officer.

2. Locate seams to the maximum extent practicable out of the way of traffic.

3. Fabricate seams by the compression method, using a butt joint, and properly bead and seal.

4. Do not stretch seams.

C. In addition to the cleaning requirements stated elsewhere, thoroughly clean carpet and adjacent surfaces prior to final acceptance of the carpeted areas by the Government.

3.03 PROTECTION: Provide a heavy non-staining paper or plastic walkway as required over carpeting in direction of traffic, maintaining intact until carpeted space is accepted by the Contracting

Officer.

3.04 SURPLUS MATERIAL: Allow the Government to inspect and select from scrap carpet remaining after the installation. Bundle, wrap in burlap, and deliver to the Government the carpet scraps selected.

RESILIENT FLOORING

PART 1 – General

101 SCOPE

A. Extent of resilient flooring and accessories is shown on drawings and in schedules

1.02 QUALITY ASSURANCE

A. Manufacturer: Provide each type of resilient flooring and accessories as produced by a single manufacturer, including recommended primers, adhesives, sealants and leveling compounds.

B. Fire Test Performance: Provide resilient flooring which complies with the following fire test performance criteria as determined by an independent testing laboratory acceptable to authorities having jurisdiction.

1. Critical Radiant Flux (CRF): Not less than the following rating per ASTM E 648.

A. 0.45 watts per sq. cm.

2. Flame Spread: Not more than 75 per ASTM E 84.

3. Smoke Density: Not more than 450 per NFPA258.

1.03 SUBMITTALS

A. Product Data: Submit manufacturer’s technical data for each type of resilient flooring and accessory.

B. Samples for Initial Selection Purposes: Submit manufacturer’s technical data for each type of resilient flooring, including accessories, showing full range of colors and patterns available, for each type of resilient flooring required.

C. Samples for Verification Purposes: Submit the following samples of each type, color, and patter of resilient flooring required, showing full-range of color and patter variations.

1. Full size tile samples.

2. Full size rubber base samples

3. 6 x 6 inch size of sheet sample.

D. Certification for Fire Test Performance: Submit certification from an independent testing laboratory acceptable to authorities having jurisdiction that resilient flooring complies with fire test performance requirements.

E. Maintenance Instructions: Submit two copies each of manufacturer’s recommended maintenance practices for each type of resilient flooring and accessory required.

1.04 PROJECT CONDITIONS

A. Maintain minimum temperature of 65 degrees F – (18 degrees C) in spaces to received resilient flooring for at least 48 hours prior to installation, during installation, and for not less than 48 hours after installation. Store resilient flooring materials in spaces where they will be installed for at least 48 hours before beginning installation. Subsequently, maintain minimum temperature of 55 degrees F (13degrees C) in areas where work is completed.

B. Install resilient flooring and accessories after other finishing operations, including painting, have been completed. Do not install resilient flooring over concrete slabs until the latter have been cured and are sufficiently dry to achieve bond with adhesive as determined by resilient flooring manufacturer’s recommended bond and moisture test.

PART 2 – PRODUCTS

2.01 ACCEPTABLE MANUFACTURERS

A. Available Manufacturers: Subject to compliance with the requirements, manufacturers offering products which may be incorporated in the work include, but are not limited to the following:

1. Manufacturers of Vinyl Composition Tile:

a. Armstrong World Industries.

b. Azrock Floor Products, Div. Azrock Industries, Inc.

c. Tarkett, Inc.

2. Manufacturers of Vinyl Sheet Flooring:

a. Armstrong World Industries.

b. Azrock Floor Products, Div. Azrock Industries, Inc.

c. Tarkett, Inc.

3. Manufacturers of Rubber base:

a. Roppe

b. Burke

c. Allstate

2.02 RESILIENT FLOORING COLORS AND PATTERNS

A. Provide color and patterns as indicated, or if not otherwise, indicated, as selected by the

Contracting Officer from manufacturer’s standards.

2.03 TILE FLOORING:

A. Vinyl Composition Tile: FS SS-T-312, Type IV; 12” x 12” and as follows:

1. Composition 1 – Asbestos Free.

2. Gauge 1/8”.

B. Rubber Base, 4” high as follows:

1. Composition – Asbestos Free.

2.04 VINYL SHEET FLOORING:

A. Commercial grade, 0.080” gauge, 15-year limited warranty.

B. Inlaid color vinyl flooring with no-wax surface.

C. Subfloor overlay-STURD-I-FLOOR or approved equal.

PART 3 EXECUTION

3.01 INSPECTION:

A. Require installer to inspect subfloor surfaces to determine that they are satisfactory. A satisfactory subfloor surface is defined as one that is smooth and free from cracks, holes, ridges, coatings preventing adhesive bond, and other defects impairing performance or appearance.

B. Perform bond and moisture tests on concrete subfloors to determine if surfaces are sufficiently cured and dry as well as to ascertain presence of curing compounds.

C. Do not allow resilient flooring work to proceed until subfloor surfaces are satisfactory.

3.02 PREPARATION:

A. Prepare subfloor surfaces as follows:

1. Overlay all subfloor surfaces to receive vinyl sheet flooring with 1/4 inch structure board.

Before placing structure board scrape, broom clean or vacuum the subfloor to remove all dirt, debris and lumps. Structure board shall be installed perpendicular to the subflooring and all joints shall be staggered. Nail structure board securely in place to provide a uniform smooth surface for the vinyl sheet flooring.

2. Use leveling and patching compounds as recommended by resilient flooring manufacturer for filling small cracks, holes and depressions in structure board.

3. Remove coatings from structure board surfaces that would prevent adhesive bond, including taping compounds, paint, etc., incompatible with resilient flooring adhesives.

B. Broom clean or vacuum surfaces to be covered, and inspect subfloor.

C. Apply concrete slab primer if recommended by flooring manufacturer, prior to application of adhesive. Apply in compliance with manufacturer’s directions.

3.03 INSTALLATION- GENERAL

A. Install resilient flooring using method indicated in strict compliance with manufacturer’s printed instructions. Extend resilient flooring into toe spaces, door reveals, and into closets and similar openings. In all rooms receiving resilient flooring extend the flooring up the walls 6 inch high to create a wall base (flash coving).

B. Scribe, cut, and fit resilient flooring to permanent fixtures, built-in furniture and cabinets, pipes, outlets and permanent columns, walls and partitions.

C. Maintain reference markers, holes, or openings that are in place or plainly marked for future cutting by repeating on finish flooring as marked on subfloor. Use chalk or other non-permanent marking device.

D. Install resilient flooring on covers for telephone and electrical ducts, and similar items occurring within finished floor areas. Maintain overall continuity of color and pattern with pieces of flooring installed on these covers. Tightly cement edges to perimeter of floor around covers and to covers.

E. Tightly cement resilient flooring to sub-base without open cracks, voids, raising and puckering at joints, telegraphing of adhesive spreader marks, or other surface imperfections.

Hand roll resilient flooring at perimeter of each covered area to assure adhesion.

3.04 CLEANING AND PROTECTION

A. Perform following operations immediately upon completion of resilient flooring:

1. Sweep or vacuum floor thoroughly.

2. Do not wash floor until time period recommended by resilient flooring manufacturer has elapsed to allow resilient flooring to become well-sealed in adhesive.

3. Damp-mop floor being careful to remove black marks and excessive soil.

4. Remove any excess adhesive or other surface blemishes, using appropriate cleaner recommended by resilient flooring manufacturers.

B. Protect flooring against damage during construction period to comply with resilient flooring manufacturer’s directions.

1. Apply protective floor polish to resilient flooring surfaces free from soil, excess adhesive or surface blemishes. Use commercial available metal cross-linked acrylic product acceptable to resilient flooring manufacturer.

2. Protect resilient flooring against damage from rolling loads for initial period following installation by covering plywood or hardboard. Use dollies to move stationary equipment or furnishings across floors.

3. Cover resilient flooring with undyed, untreated building paper until inspection for substantial completion.

C. Clean resilient flooring not more than 4 days prior to date scheduled for inspections intended to establish date of substantial completion in each area of project. Clean resilient flooring by method recommended by resilient flooring manufacturer.

RESILIENT BASE

PART 1 – GENERAL

1.1 SUMMARY

A. Section includes: Provide resilient base and accessories as required for complete finished installation.

1.2 SYSTEM DESCRIPTION

A. Performance Requirements: Provide materials tested under ASTM E648, Flooring Radiant

Panel Test, with results of 0.45 watts/sq. cm or higher.

1.3 SUBMITTALS

A. Product Data: Furnish manufacturer’s product literature.

B. Samples: Furnish samples of each base color and type.

1.4 PROJECT CONDITIONS

A. Maintain minimum 70 degree F air temperature at installation area for 3 days prior to, during, and for 24 hours after installation.

B. Store materials in area of application; allow three days for material to reach same temperature as area.

PART 2 – PRODUCTS

2.1 MATERIALS

A. Resilient Base: conform to ASTM F1861, 1/8” gage; provide coved base at hard floor surfaces, straight base at carpet unless otherwise indicated.

1. Type: Extruded vinyl, available in 150’ rolls.

2. Manufacturers:

a. Flexco Co.

b. Johnsonite, Inc.

c. Burke-Mercer Flooring Products.

3. Height: 4” unless otherwise indicated.

4. Color: Contracting Officer will determine color – based on samples provide.

PART 3 – EXECUTION

3.1 INSTALLATION

A. Apply to walls, columns, pilasters, casework, and other permanent fixtures in rooms and areas where base is required.

1. Fit base joints tight and vertical

2. Joints are not allowed. If run of base exceeds 150 feet, locate joint at an inside corner.

B. Install base on solid backing, adhere tightly to wall and floor surfaces; fill voids along top edge of base with manufacturer’s recommended adhesive filler.

C. Scribe and fit to door frames and other obstructions.

D. Install straight and level to variation of plus or minus 1/8” over 10’-0”.

3.2 CLEAN-UP

A. Remove excess adhesive from floor, base and wall surfaces without causing damage.

B. Clean surfaces in accordance with manufacturer’s recommendations.

END OF SECTION

The Contractor is required to visit the site to verify the square footage of each area prior to submitting a quote. Offers will not be considered for those contractor’s that did not visit the site to verify measurements prior to submitting a quote. Contact Jeannie Vaughn at: jvaughn@fs.fed.us to schedule site visit.

Project Location

The project is located at the U.S. Forest Service, Northern California Training Center, 6101 Airport

Road, Redding, California 96002.

NOTE: Any prospective bidder desiring an explanation or interpretation of the solicitation or specifications, etc., must request it in writing soon enough to allow a reply to reach all prospective bidders before submission of their bids. Oral explanations or instructions given before the award of a contract will not be binding. In no event shall failure to inspect the site constitute grounds for a claim after contract award. (See Section L, 52.236-27, SITE VISIT.)

Price Range

The Government's estimate is:

[×] $25,000 to $100,000

Estimated Start Date The estimated start work date is May 1, 2013. The contract time will be 15 days. Contract time includes delays for weather; locating and transporting supplies and materials; and final site clean-up

Contractor must begin work within 10 days of the effective date of the Notice to Proceed.

See Section F for additional information.

Restrictions on Work The Contractor shall coordinate all work with the Contracting Officer or Training Officer. Due to scheduled training, the successful contractor may be required to schedule work after hours or during the weekend to accommodate the training schedule.

The Contractor and the Contractor’s employees will not be permitted to have dogs or other pets on the project site at any time.

Worker's Compensation Insurance The Contractor shall provide evidence of Worker's Compensation Insurance or a written explanation as to why the Contractor is exempt from the requirement. NOTE: The Contractor working alone is not required to carry the insurance.

mailto:jvaughn@fs.fed.us

SECTION E--INSPECTION AND ACCEPTANCE

FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

www.acquisition.gov/far/

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

FAR 52.246-12 Inspection of Construction (AUG 1996)

Inspections

Government inspections are for the purpose of satisfying the Government that the supplies and/or services are acceptable and do not relieve the Contractor of the responsibility for maintaining quality control. The Contracting Officer's Representative or designated inspector will conduct all inspections.

The Contractor (or designated representative) is encouraged to be present to observe inspections

SECTION F--DELIVERIES OR PERFORMANCE

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

52.242-14 Suspension of Work (APR 1984)

FAR 52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984)

The Contractor shall be required to (a) commence work under this contract within _ 10 _ calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than _ 15 _after the effective date of the notice to proceed. The time stated for completion shall include final cleanup of the premises.

http://www.acquisition.gov/far/ http://www.arnet.gov/far/

SECTION G--CONTRACT ADMINISTRATION DATA

GOVERNMENT-FURNISHED PROPERTY

The Government will provide the following item(s) of Government property to the Contractor for use in the performance of this contract. This property shall be used and maintained by the Contractor in accordance with the provisions of the "Government Property" FAR clause contained elsewhere in the contract.

NONE

Invoices

Payment will be processed based upon receipt of a correct invoice from the contractor. Progress payments will be allowed if necessary. Submittal of an invoice shall be made with necessary supporting documentation to U.S. Forest Service, Attn: Jeannie Vaughn, 6101 Airport Road, Redding, CA 96002.

Payment for Materials Off Site

In accordance with Clause 52.232-5, progress payments may include payment for materials stored off site. Contractor shall provide a copy of the paid invoice; provide evidence that the material will be included in the finished project; and identify the location where the materials are stored, so that the government may make visual inspection if the Contracting Officer deems it necessary. The Contractor shall be liable for loss, damage, or destruction of the materials until such time as the materials are physically in the possession and control of the government. The Contractor will not be held liable to the extent that the Contracting Officer determines that the loss, damage, or destruction occurred through the fault or negligence of the government or its agents.

Incidental Items

The intent of the contract is to provide for the completion of the project described in the contract. Unless otherwise provided, the Contractor shall furnish all labor, materials, equipment, tools, transportation, and supplies and perform all work required to complete the project in accordance with the specifications, and provisions of the contract. Payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work and materials will be considered as incidental to and included in the payment of items shown.

Preconstruction Conference

There is not a site visit scheduled for a specific date or time. However, contractors are required to visit the site to verify square footage of areas to be re-floored. Site visits can be schedule by contacting

Jeannie Vaughn at: jvaughn@fs.fed.us. No phone calls will be allowed.

SECTION H--SPECIAL CONTRACT REQUIREMENTS

Emergencies Fire Plan

[ ]See Section J, Fire Plan

[X ]Not applicable; however, Contractors are required to comply with State law during fire season.

Area of Responsibility for Fire. Unless otherwise noted elsewhere in the contract, the following define the limits of a contractor's area of responsibility for fire under the terms of the Fire Plan (Section J):

[ ](a) Trail Construction - 100 meters on either side of the centerline

[ ](b) Construction of Structures - 100 meters around the perimeter of the project

[ ](c) Road Construction - 400 meters on either side of the centerline

[ ](d) Special for this project:

Utility Services

Potable water and electrical power are available on site and will be provided without charge to the contractor.

Superintendence by Contractor In addition to Clause 52.236-6, the following applies: The name and the specific authorities of the foreman or superintendent must be designated in writing to the Contracting Officer. The Contractor may use his/her own prepared letterhead stationery or a "Designation of Contractor's Representative" form available from the Contracting Officer. If the Contractor or the designee is not present when work is being performed on the contract, a Suspend Work Order may be issued with contract time continuing to run. The Contractor shall have a person on-site that is fully conversant in the English language.

Loss, Damage or Destruction Equipment Furnished with Operator. The Government shall not be liable for loss, damage, or destruction of equipment furnished under this contract except for such loss, damage, or destruction resulting from the negligent or wrongful act(s) of Government employee(s) while acting within the scope of their employment.

Other. Even though this contract may provide for performing services at the direction of Government personnel, the contract is not for personal services, and neither the Contractor nor his or her personnel are

Government employees. The Government assumes no liability for injury occurring to Contractor personnel or to third parties, or for loss, damage, or destruction involving third parties' property as a result of the

Contractor's operation. Except that the Government is liable for such loss, damage, or destruction resulting from the negligent or wrongful act(s) of Government employee(s) acting within the scope of their employment.

PART II--CONTRACT CLAUSES

SECTION I--CONTRACT CLAUSES

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address (es):

www.usda.gov/procurement/policy/agar.html

52.204-7 Central Contractor Registration (DEC 2012)

52.204-8 Annual Representations and Certifications (DEC 2012)

52.204-9 Personal Identity Verification of Contractor Personnel (JAN 2011)

52.211-18 Variation in Estimated Quantity (APR 1984)

52.213-4 Terms and Conditions-Simplified Acquisition (Other than Commercial Items)

(AUG 2012)

52.219-1 Small Business Program Representations (APR 2012)

52.219-6 Notice of Total Small Business Set-aside (NOV 2011)

52.222-3 Convict Labor (JUN 2003)

52.222-6 Davis-Bacon Act (JUL 2005)

52.222-7 Withholding of Funds (FEB 1988)

52.222-8 Payrolls and Basic Records (JUN 2010)

52.222-9 Apprentices and Trainees (JUL 2005)

52.222-10 Compliance with Copeland Act Requirements (FEB 1988)

52.222-11 Subcontracts (Labor Standards) (JUL 2005)

52.222-12 Contract Termination - Debarment (FEB 1988)

52.222-13 Compliance with Davis-Bacon and Related Act Regulations (FEB 1988)

52.222-14 Disputes Concerning Labor Standards (FEB 1988)

52.222-15 Certification of Eligibility (FEB 1988)

52.222-21 Prohibition of Segregated Facilities (FEB 1999)

52.222-26 Equal Opportunity (MAR 2007)

52.222-27 Affirmative Action Compliance Requirements for Construction (FEB 1999)

52.222-36 Affirmative Action for Workers with Disabilities (OCT 2010) Applicable if contract exceeds $15,000.00

52.222-50 Combating Trafficking In Persons (FEB 2009)

52.223-1 Biobased Product Certification (MAY 2012)

52.223-2 Affirmative Procurement of Biobased Products under Service and Construction Contracts

(JUL 2012)

52.223-5 Pollution Prevention and Right-to-Know Information (MAY 2011)

52.223-6 Drug-Free Workplace (MAY 2001) (Applicable if contract is awarded to an individual)

52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving (AUG 2011)

52.225-13 Restrictions on Certain Foreign Purchases (JUN 2008) http://www.usda.gov/procurement/policy/agar.html

52.227-4 Patent Indemnity -- Construction Contracts (DEC 2007)

52.228-2 Additional Bond Security (OCT 1997) (Applicable if contract exceeds $30,000)

52.228-11 Pledges of Assets (JAN 2012) (Applicable if contract exceeds $30,000)

52.228-14 Irrevocable Letter of Credit (DEC 1999) (Applicable if contract exceeds $30,000)

52.232-5 Payments Under Fixed-Price Construction Contracts (SEP 2002)

52.232-23 Assignment of Claims (JAN 1986)

52.232-27 Prompt Payment for Construction Contracts (OCT 2008)

52.232-33 Payment by Electronic Funds Transfer—Central Contractor Registration (OCT 2003)

52.233-1 Disputes (JUL 2002)

52.233-3 Protest After Award (AUG 1996)

52.233-4 Applicable Law for Breach of Contract Claim (OCT 2004)

52.236-2 Differing Site Conditions (APR 1984)

52.236-3 Site Investigation and Conditions Affecting the Work (APR 1984)

52.236-5 Material and Workmanship (APR 1984)

52.236-6 Superintendence by the Contractor (APR 1984)

52.236-7 Permits and Responsibilities (NOV 1991)

52.236-8 Other Contracts (APR 1984)

52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements

(APR 1984)

52.236-10 Operations and Storage Areas (APR 1984)

52.236-11 Use and Possession Prior to Completion (APR 1984)

52.236-12 Cleaning Up (APR 1984)

52.236-13 Accident Prevention (NOV 1991)

52.236-14 Availability and Use of Utility Services (APR 1984)

52.236-26 Preconstruction Conference (FEB 1995)

52.242-14 Suspension of Work (APR 1984)

52.243-5 Changes and Changed Conditions (APR 1984)

52.244-6 Subcontracts for Commercial Items (DEC 2010)

52.246-21 Warranty of Construction (MAR 1994)

Alternate I (APR 1984)

52.249-1 Termination for Convenience of the Government (Fixed-Price) (Short From) (APR 1984)

52.249-10 Default (Fixed-Price Construction) (APR 1984)

52.253-1 Computer Generated Forms (JAN 1991)

AGRICULTURE ACQUISITION REGULATION (48 CFR CHAPTER 4) CLAUSES

452.209-70 Representations by Corporations Regarding an Unpaid Delinquent Liability or a Felony

Conviction

452.209-71 Assurance Regarding Felony Convictions or Tax Delinquent Status for Corporate Applicants.

Alternate 1 (Feb 2012)

452.232-70 Reimbursement for Bond Premiums – Fixed-Price Construction Contracts (MAY 1998)

452.236-71 Prohibition Against the Use of Lead-Paint (NOV 1996)

452.236-72 Use of Premises (NOV 1996)

452.236-73 Archeological or Historic Sites (FEB 1988)

452.236-74 Control of Erosion, Sedimentation and Pollution (NOV 1996)

452.236-76 Samples and Certificates (FEB 1988)

452.236-77 Emergency Response (NOV 1996)

FAR 52.225-9 Buy American Act—Construction Materials (JAN 2005)

(a) Definitions. As used in this clause- "Component" means an article, material, or supply incorporated directly into a construction material.

"Construction material" means an article, material, or supply brought to the construction site by the

Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.

"Cost of components" means-

(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or

(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction materials.

"Domestic construction material" means-

(1) An unmanufactured construction material mined or produced in the United States; or

(2) A construction material manufactured in the United States, if the cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic.

"Foreign construction material" means a construction material other than a domestic construction material.

"United States" means the 50 States, the District of Columbia, and outlying areas.

(b) Domestic preference.

(1) This clause implements the Buy American Act (41 U.S.C. 10a - 10d) by providing a preference for domestic construction material. The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.

(2) This requirement does not apply to the construction material or components listed by the

Government as follows:

NONE

[Contracting Officer to list applicable excepted materials or indicate "none"]

(3) The Contracting Officer may add other foreign construction material to the list in paragraph

(b)(2) of this clause if the Government determines that-

(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the Buy American Act is unreasonable when the cost of such material exceeds the cost of foreign material by more than 6 percent;

(ii) The application of the restriction of the Buy American Act to a particular construction material would be impracticable or inconsistent with the public interest; or

(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.

(c) Request for determination of inapplicability of the Buy American Act.

(1)(i) Any Contractor request to use foreign construction material in accordance with paragraph

(b)(3) of this clause shall include adequate information for Government evaluation of the request, including-

(A) A description of the foreign and domestic construction materials;

(B) Unit of measure;

(C) Quantity;

(D) Price;

(E) Time of delivery or availability;

(F) Location of the construction project;

(G) Name and address of the proposed supplier; and

(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.

(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.

(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).

(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.

(2) If the Government determines after contract award that an exception to the Buy American Act applies and the Contracting Officer and the Contractor negotiate adequate consideration, the

Contracting Officer will modify the contract to allow use of the foreign construction material.

However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.

(3) Unless the Government determines that an exception to the Buy American Act applies, use of foreign construction material is noncompliant with the Buy American Act.

(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:

Foreign and Domestic Construction Materials Price Comparison

Construction Material Description Unit of Measure Quantity Price (Dollars)*

Item 1:

Foreign construction material _______ _______ _______

Domestic construction material _______ _______ _______

Item 2: _______ _______ _______

Foreign construction material _______ _______ _______

Domestic construction material

[List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.] [Include other applicable supporting information.] [* Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued).]

FAR 52.228-1 BID GUARANTEE (SEP 1996)

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds –

(1) To unsuccessful bidders as soon as practicable after the opening of bids, and (2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.

(c) The amount of the bid guarantee shall be 20 percent of the bid price or $ , whichever is less.

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.

(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

Order of Precedence--Construction

Any inconsistency in this solicitation or contract shall be resolved by giving precedence in the following order:

(1) The Schedule (excluding the specifications)

(2) Representations and Other Instructions

(3) Contract Clauses

(4) Other Documents, Exhibits, and Attachments

(5) The Specifications

PART III--LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS

SECTION J--LIST OF ATTACHMENTS

DAVIS BACON WAGE DETERMINATION See below

DAVIS BACON RATES FOR STATE OF CALIFORNIA

COUNTY NAME(S): Shasta

GENERAL DECISION NUMBER CA09

MODIFICATION NUMBER PUBLICATION DATE

4 03/08/13

DESCRIPTION OF

WORKER

LABOR

CLASSIFICATION

RATES FRINGE AREA

(1,2, N/A)

Carpenter CARP1599-001 $38.50 $25.68 N/A

Journeyman Carpenter CARP1599-001 $31.27 $25.68 N/A

Laborer LAB00067-006 – Group 4 $20.58 $15.82 B

NOTE: The classifications listed above are the classifications of workers that are anticipated to be used for this particular project. If in preparing the bid or during the course of the contract you have a need for labor classifications other than those listed above, locate the complete Wage Determination from http://www.wdol.gov http://www.wdol.gov/

PART IV--REPRESENTATIONS AND INSTRUCTIONS

SECTION K--REPRESENTATIONS, CERTIFICATIONS, AND

OTHER STATEMENTS OF OFFERORS OR RESPONDENTS

AGAR 452.219-70 Size Standard and NAICS Code Information (JAN 2005)

The North American Industrial classification System Code(s) and business size standard(s) describing the products and/or services to be acquired under this solicitation are listed below:

Contract line item(s): All

--NAICS Code 238330 Flooring Contractors____

--Size Standard $14.0 Million ______

The small business size standard for a concern which submits an offer in its own name, other than on a construction or service contract, but which proposes to furnish a product which it did not itself manufacture, is 500 employees.

FAR 52.204-8 Annual Representations and Certifications (DEC 2012) a)(1) The North American Industry Classification System (NAICS) code for this acquisition is 238330_______ ].

(2) The small business size standard is ___$14.0 Million.

(3) The small business size standard for a concern which submits an offer in its own name, other than on a construction or service contract, but which proposes to furnish a product which it did not itself manufacture, is 500 employees.

(b)(1) If the clause at 52.204-7, Central Contractor Registration, is included in this solicitation, paragraph (d) of this provision applies.

(2) If the clause at 52.204-7 is not included in this solicitation, and the offeror is currently registered in CCR, and has completed the ORCA electronically, the offeror may choose to use paragraph (d) of this provision instead of completing the corresponding individual representations and certifications in the solicitation. The offeror shall indicate which option applies by checking one of the following boxes:

[ ] (i) Paragraph (d) applies.

[ ] (ii) Paragraph (d) does not apply and the offeror has completed the individual representations and certifications in the solicitation.

(c)(1) The following representations or certifications in ORCA are applicable to this solicitation as indicated:

https://www.acquisition.gov/far/current/html/52_200_206.html#wp1137850 https://www.acquisition.gov/far/current/html/52_200_206.html#wp1137850

SECTION L--INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS OR

RESPONDENTS

FAR 52.252-1 Solicitation Provisions Incorporated by Reference (FEB 1998)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address (es):

www.usda.gov/procurement/policy/agar.html

Offeror(s) shall identify the biobased products to be purchased and used under this contract. For each biobased product, the offeror shall specify the percentage of biobased content, and for the USDA-designated biobased content products, the offeror shall demonstrate that the products to be used under this contract will contain the percentage specified in the USDA recommendations or the highest level of biobased material practicable, consistent with USDA’s recommended percentages of biobased content.

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1)

52.204-6 Data Universal Numbering System (Duns) (OCT 2003)

AGRICULTURE ACQUISITION REGULATIONS (48 CFR CHAPTER 4) CLAUSES

452.204-70 Inquiries (FEB 1988)

FAR 52.216-1 Type of Contract (APR 1984)

The Government contemplates award of a fixed-price contract resulting from this solicitation.

FAR 52.222-23 Notice of Requirement for Affirmative Action to Ensure Equal Employment

Opportunity for Construction (FEB 1999)

(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action

Compliance Requirements for Construction clause of this solicitation.

(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered are, are as follows:

Goals for minority participation for each trade Goals for female participation for each trade

6.8% for Shasta County 6.9% nationwide http://www.usda.gov/procurement/policy/agar.html

These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.

(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41

CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative actions obligations required by the clause entitled "Affirmative Action Compliance

Requirements for Construction," and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to

Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4.

Compliance with the goals will be measured against the total work hours performed.

(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal

Contract Compliance, U. S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the--

(1) Name, address, and telephone number of the subcontractor;

(2) Employer's identification number of the subcontractor;

(3) Estimated dollar amount of the subcontract;

(4) Estimated starting and completion dates of the subcontract; and

(5) Geographical area in which the subcontract is to be performed.

(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is

Redding, Shasta County, California 96002.

FAR 52.225-10 Notice of Buy American Act/Balance of Payments Program Requirement –

Construction Materials (MAY 2002)

(a) Definitions. "Construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American

Act-Construction Materials" (Federal Acquisition Regulation (FAR) clause 52.225-9).

(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American Act should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .