Addendum Changes 5-4.docx

DOCX document 11 KB Posted

Attached to
Rainbow Pool Paving
Solicitation number
AG-97902-S-10-0343
Issued by

About this file

AG-9702-S-10-0343 -- Addendum Changes

View the file

Other files

File Type Posted
Est_Schedule 5-4 - Rainbow.xlsx XLSX spreadsheet
Specification 5-4.docx DOCX document
Rainbowpool_Plans 5-4.pdf PDF
Amdt No. 02.pdf PDF
Amdt No. 01 AG 9702-S-10-0343.docx DOCX document
AG 9702-S-10-0343 Rainbow Pool.doc DOC document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Addendum Changes

-Concrete Curb/Dike: “Asphalt Concrete Curb” changed to “7.5” Concrete Curb / Dike” in Schedule of Items. Pay Unit has been changed to Lump Sum.

-Curb Stop: 12” Curb Stop changed to 6” Curb Stop on Plans Sheet C1.1

-Landscape Area Spec 02542: Handicap Signs and Redwood Header Boards added to Landscape Area Specification

-Minor Hot Bitumious Concrete: “Minor Hot Bitumious Concrete” changed to “Minor Hot Asphalt Concrete” in Schedule of Items. Quantity changed from 80 Tons to 130 Tons.

-Feathered A.C.: Note changed from “2” A.C. Overlay” to “Feather to match existing pavement” in the Section A-A Detail of Sheet 4A of the Plans.

-Parallel Parking: A Parallel Parking Striping Detail has been added to sheet 3 of the Plans.

-Pavement Markings: Line Item No. 634(1) has had its Quantity changed from 500 LF to 550 LF.

-Culvert Cleaning: Added “Clean Culvert” Item 607(04) to Schedule of Items.