S-10-0548 Attachment 4 Pre-Bid Tour Meeting Minutes.docx

DOCX document 13 KB Posted

Attached to
RECOVERY-ECC Wastewater Disposal Improvements - Tahoe National Forest
Solicitation number
AG-9702-S-10-0548
Issued by

About this file

S-10-0548 Attachment 4 Pre-Bid Tour Meeting Minutes.docx

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment #4

EEC WASTEWATER DISPOSAL IMPROVEMENTS

TAHOE NATIONAL FOEST

PRE_BID TOUR MEETING MINUTES

Sign in Sheet:

NameFirmContact
1) Edward NavickisEdwar T. Navickis530 -432 -9226
2)Siegfried KnollEarth And Road work, INC530-292-3685
3)Steve SarantopulosCramner Engineering530-273-7284
4)Mike PutnamHansen Bros530-273-3381
5)Brian SouthQuick Response530-273-7538
6)Joe GarrisonNewland Entities530-755-1178
7)John DeshaoneDeshaone Enterprises530-274-9975
8)Kevin AtkinsHerback General Engineering775-267-6800

Government representatives present: Temoc Rios, , Jennifer Schofield, Lance Cross and Cliff Snider.

General clarifications to the plans and specs were discussed along with the requirements of the government and scope of work.

Temoc advised all parties that RFI's must be submitted in writing to Neil Belden, Contract Specialist EROC SW at nbelden@fs.fed.us to be forwarded to the Tahoe engineering technical contacts for formal answers that could be submitted to the attendee list.