Revised Page 3 as indicated in Amendment No. 1 dated 14 July 2010.

View the file

Other files

File Type Posted
38_Amd.1.AG-9702-S-10-0393.pdf PDF
AG-9702-S-10-0393 Pt 1.pdf PDF
AG-9702-S-10-0393 Pt 3.pdf PDF
AG-9702-S-10-0393 Pt 2.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOL NO AG-9702-S-10-0393

APACHE-SITGREAVES NATIONAL FOREST

REMOVE AND DISPOSE OF FLUSH TOILET BUILDINGS

PART I—THE SCHEDULE

SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS

SCHEDULE OF ITEMS

ITEM

NO.

DESCRIPTION

Quantity

Unit

MM

Price per

Unit

Total Cost

Demolish and dispose of existing flush toilet.

Building, including any interior furnishings, utilities, etc., footings, foundation, screen walls, and attached concrete sidewalks. Dispose of at land file. Regrade site at completion of demolition and disposal, in preparation for aggregate base pad.

9 EA

AQ

02 Prepare aggregate pad for new CXT Flush toilet Building, pad to be 40’ x 26’ (includes extra size to accommodate walkways around building), and aggregate base for concrete walkways and hydrant pads. Aggregate material, ¾” crushed road surfacing aggregate.

(120 C.Y. per building)

1080 CY AQ $ $

03 Furnish and install utility stub ups per plans provided by building manufacturer. Utilities to be stubbed out 30 feet from building wall and hooked to existing supply lines. Utility hook ups include water, sewer and electric. Final hook up from stub ups to building to be performed by building supplier.

9 EA AQ $ $

04 Concrete sidewalks and concrete hydrant pads.

9000 SF AQ $ $

05 Journey Level Electrician – analyze existing electrical supply to each building from transformer for adequate capacity and for any code deficiencies per Navapache Electric Coop and NEC. Electrician to supply calculations, wire size and material, provide materials lists if modifications are required.

40 HR AQ $ $

06 Water Hydrant – Furnish and install per plans and manufacturer specifications. Bid item to include min. 12” square catch basin with ADA compliant grate as manufactured by ADS or approved equal for installation in concrete pad and furnishing 30’ of 4” pipe to drain catch basin, daylight to ground, install insect screen and riprap on outlet per specification.

9 EA $ $

07 Backhoe with operator for miscellaneous work as directed bythe forest service including removal and reinstallation of information boards at toilet buildings, trenching and backfilling for utilities outside of the building footprint.

40 HR AQ $ $

08 Sawyer with equipment. Tree and brush removal as directed by the forest Service to provide access for bulding and crane setting equipment.

40 HR AQ $ $

SOL NO AG-9702-S-10-0393

APACHE-SITGREAVES NATIONAL FOREST

REMOVE AND DISPOSE OF FLUSH TOILET BUILDINGS