Drawings_Notes.pdf

PDF 143 KB Posted

Attached to
DAKOTA PRAIRIE NATIONAL GRASSLANDS -NW Sheyenne Dugout Reclamation
Solicitation number
AG-87BJ-S-15-0017
Issued by

About this file

Drawings Notes

View the file

Other files

File Type Posted
sf_30_amend.doc DOC document
VICINITY_Maps.pdf PDF
Construction_Limits.pdf PDF
AG87BJS150017.pdf PDF
AreaMap.pdf PDF
ND15.txt TXT text file
VicinityWA.pdf PDF
Vicinity_MAPS.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bjugstad North Dugout Reclamation

SE 31-T135N-R53W

Lat. 46°27’28.63” Long. 97°23’31.38”

Water 115’

40’

6’

90’

170’

Spoil Pile

Drawing Not To Scale

CONSTRUCTION NOTES

Topsoil. Remove and conserve 4” of topsoil from the spoil piles and other areas within the construction limits. Do not disturb material and vegetation outside the construction limits. Stockpile conserved topsoil in approved location. Spread topsoil evenly over completed slopes.

Break clods and lumps with appropriate equipment to provide a uniform textured soil. Do not place topsoil when the ground or topsoil is frozen, excessively wet, or otherwise in a condition detrimental to the work.

Excavation and Embankment. Restore the dugout to approximate original ground contours. All material, including spoil piles, used to fill the dugout shall come from within the original construction limits as shown on the drawings and staked on the ground. The dimensions on the drawings are approximate and for information only. Compact the fill by operating spreading and hauling equipment over the full width and length of each layer of material. Place material in horizontal layers not exceeding 24 inches in compacted thickness. Finish slopes to provide gradual transitions in slope adjustments without noticeable breaks. Leave earth slopes with uniform roughened surfaces. An on site inspection will be made by the COR prior to acceptance of the work.

Dewatering. Remove water as necessary to perform the work. Dispose of water according to Federal, state, and local regulations.

N

5’

Spoil Pile

40’

200’

Bjugstad South Dugout Reclamation

SE 5-T134N-R53W

Lat. 46°26’43.04” Long. 97°22’17.90”

Water 160’ 130’

50’ 55’

5.5’ 5.5’

120’

180’

Spoil Pile Spoil

Pile

Drawing Not To Scale

CONSTRUCTION NOTES

Topsoil. Remove and conserve 4” of topsoil from the spoil piles and other areas within the construction limits. Do not disturb material and vegetation outside the construction limits. Stockpile conserved topsoil in approved location. Spread topsoil evenly over completed slopes.

Break clods and lumps with appropriate equipment to provide a uniform textured soil. Do not place topsoil when the ground or topsoil is frozen, excessively wet, or otherwise in a condition detrimental to the work.

Excavation and Embankment. Restore the dugout to approximate original ground contours. All material, including spoil piles, used to fill the dugout shall come from within the original construction limits as shown on the drawings and staked on the ground. The dimensions on the drawings are approximate and for information only. Compact the fill by operating spreading and hauling equipment over the full width and length of each layer of material. Place material in horizontal layers not exceeding 24 inches in compacted thickness. Finish slopes to provide gradual transitions in slope adjustments without noticeable breaks. Leave earth slopes with uniform roughened surfaces. An on site inspection will be made by the COR prior to acceptance of the work.

Dewatering. Remove water as necessary to perform the work. Dispose of water according to Federal, state, and local regulations.

N

Owego North Dugout Reclamation

NW 17-T134N-R53W

Lat. 46°25’35.49” Long. 97°22’45.41”

Water 90’ 120’

40’ 40’

7.5’ 6.5’

90’

140’

Spoil Pile Spoil

Pile

Drawing Not To Scale

CONSTRUCTION NOTES

Topsoil. Remove and conserve 4” of topsoil from the spoil piles and other areas within the construction limits. Do not disturb material and vegetation outside the construction limits. Stockpile conserved topsoil in approved location. Spread topsoil evenly over completed slopes.

Break clods and lumps with appropriate equipment to provide a uniform textured soil. Do not place topsoil when the ground or topsoil is frozen, excessively wet, or otherwise in a condition detrimental to the work.

Excavation and Embankment. Restore the dugout to approximate original ground contours. All material, including spoil piles, used to fill the dugout shall come from within the original construction limits as shown on the drawings and staked on the ground. The dimensions on the drawings are approximate and for information only. Compact the fill by operating spreading and hauling equipment over the full width and length of each layer of material. Place material in horizontal layers not exceeding 24 inches in compacted thickness. Finish slopes to provide gradual transitions in slope adjustments without noticeable breaks. Leave earth slopes with uniform roughened surfaces. An on site inspection will be made by the COR prior to acceptance of the work.

Dewatering. Remove water as necessary to perform the work. Dispose of water according to Federal, state, and local regulations.

Owego South Dugout Reclamation

SW 17-T134N-R53W

Lat. 46°24’54.87” Long. 97°22’49.95”

Water 170’ 125’

25’ 40’

5’ 5.5’

110’

240’

Spoil Pile Spoil

Pile

Drawing Not To Scale

CONSTRUCTION NOTES

Topsoil. Remove and conserve 4” of topsoil from the spoil piles and other areas within the construction limits. Do not disturb material and vegetation outside the construction limits. Stockpile conserved topsoil in approved location. Spread topsoil evenly over completed slopes.

Break clods and lumps with appropriate equipment to provide a uniform textured soil. Do not place topsoil when the ground or topsoil is frozen, excessively wet, or otherwise in a condition detrimental to the work.

Excavation and Embankment. Restore the dugout to approximate original ground contours. All material, including spoil piles, used to fill the dugout shall come from within the original construction limits as shown on the drawings and staked on the ground. The dimensions on the drawings are approximate and for information only. Compact the fill by operating spreading and hauling equipment over the full width and length of each layer of material. Place material in horizontal layers not exceeding 24 inches in compacted thickness. Finish slopes to provide gradual transitions in slope adjustments without noticeable breaks. Leave earth slopes with uniform roughened surfaces. An on site inspection will be made by the COR prior to acceptance of the work.

Dewatering. Remove water as necessary to perform the work. Dispose of water according to Federal, state, and local regulations.

Evanson Dugout Reclamation

NE 23-T135N-R54W

Lat. 46°29’50.36” Long. 97°26’14.33”

Water 125’ 100’

40’ 40’

8.5’ 6.5’

110’

175’

Spoil Pile Spoil

Pile

Drawing Not To Scale

CONSTRUCTION NOTES

Topsoil. Remove and conserve 4” of topsoil from the spoil piles and other areas within the construction limits. Do not disturb material and vegetation outside the construction limits. Stockpile conserved topsoil in approved location. Spread topsoil evenly over completed slopes.

Break clods and lumps with appropriate equipment to provide a uniform textured soil. Do not place topsoil when the ground or topsoil is frozen, excessively wet, or otherwise in a condition detrimental to the work.

Excavation and Embankment. Restore the dugout to approximate original ground contours. All material, including spoil piles, used to fill the dugout shall come from within the original construction limits as shown on the drawings and staked on the ground. The dimensions on the drawings are approximate and for information only. Compact the fill by operating spreading and hauling equipment over the full width and length of each layer of material. Place material in horizontal layers not exceeding 24 inches in compacted thickness. Finish slopes to provide gradual transitions in slope adjustments without noticeable breaks. Leave earth slopes with uniform roughened surfaces. An on site inspection will be made by the COR prior to acceptance of the work.

Dewatering. Remove water as necessary to perform the work. Dispose of water according to Federal, state, and local regulations.

West A North Dugout Reclamation

NW 26-T136N-R53W

Lat. 46°33’59.27” Long. 97°18’43.58”

Water 140’ 200’

40’

40’

5’ 7’

110’

160’

Spoil Pile

Spoil Pile

Drawing Not To Scale

CONSTRUCTION NOTES

Topsoil. Remove and conserve 4” of topsoil from the spoil piles and other areas within the construction limits. Do not disturb material and vegetation outside the construction limits. Stockpile conserved topsoil in approved location. Spread topsoil evenly over completed slopes.

Break clods and lumps with appropriate equipment to provide a uniform textured soil. Do not place topsoil when the ground or topsoil is frozen, excessively wet, or otherwise in a condition detrimental to the work.

Excavation and Embankment. Restore the dugout to approximate original ground contours. All material, including spoil piles, used to fill the dugout shall come from within the original construction limits as shown on the drawings and staked on the ground. The dimensions on the drawings are approximate and for information only. Compact the fill by operating spreading and hauling equipment over the full width and length of each layer of material. Place material in horizontal layers not exceeding 24 inches in compacted thickness. Finish slopes to provide gradual transitions in slope adjustments without noticeable breaks. Leave earth slopes with uniform roughened surfaces. An on site inspection will be made by the COR prior to acceptance of the work.

Dewatering. Remove water as necessary to perform the work. Dispose of water according to Federal, state, and local regulations.

Spoil Pile

Wall South Dugout Reclamation

SE 33-T135N-R53W

Lat. 46°27’38.24” Long. 97°20’57.78”

Water 140’ 125’

35’ 35’

5’ 6’

110’

205’

Spoil Pile Spoil

Pile

Drawing Not To Scale

CONSTRUCTION NOTES

Topsoil. Remove and conserve 4” of topsoil from the spoil piles and other areas within the construction limits. Do not disturb material and vegetation outside the construction limits. Stockpile conserved topsoil in approved location. Spread topsoil evenly over completed slopes.

Break clods and lumps with appropriate equipment to provide a uniform textured soil. Do not place topsoil when the ground or topsoil is frozen, excessively wet, or otherwise in a condition detrimental to the work.

Excavation and Embankment. Restore the dugout to approximate original ground contours. All material, including spoil piles, used to fill the dugout shall come from within the original construction limits as shown on the drawings and staked on the ground. The dimensions on the drawings are approximate and for information only. Compact the fill by operating spreading and hauling equipment over the full width and length of each layer of material. Place material in horizontal layers not exceeding 24 inches in compacted thickness. Finish slopes to provide gradual transitions in slope adjustments without noticeable breaks. Leave earth slopes with uniform roughened surfaces. An on site inspection will be made by the COR prior to acceptance of the work.

Dewatering. Remove water as necessary to perform the work. Dispose of water according to Federal, state, and local regulations.

ConstNotesBJN
Bjugstad North Dugout Reclamation�SE 31-T135N-R53W �Lat. 46°27’28.63”�Long. 97°23’31.38”
ConstNotesBJS
Bjugstad South Dugout Reclamation�SE 5-T134N-R53W �Lat. 46°26’43.04”�Long. 97°22’17.90”
ConstNotesON
Owego North Dugout Reclamation�NW 17-T134N-R53W �Lat. 46°25’35.49”�Long. 97°22’45.41”
ConstNotesOS
Owego South Dugout Reclamation�SW 17-T134N-R53W �Lat. 46°24’54.87”�Long. 97°22’49.95”
ConstNotesEva
Evanson Dugout Reclamation�NE 23-T135N-R54W �Lat. 46°29’50.36”�Long. 97°26’14.33”
ConstNotesWA
West A North Dugout Reclamation�NW 26-T136N-R53W �Lat. 46°33’59.27”�Long. 97°18’43.58”
ConstNotesWS
Wall South Dugout Reclamation�SE 33-T135N-R53W �Lat. 46°27’38.24”�Long. 97°20’57.78”