1_RFQ_AG84N8S160120_Prefabricate_Bridge_for_Hades_Creek_ANF.doc
DOC document 253 KB Posted
- Attached to
- Prefabaricate Temporary Bridge for the Ashley NF
- Solicitation number
- AG-84N8-S-16-0120
About this file
1 RFQ AG84N8S160120 Prefabricate Temporary Bridge_ANF
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SF30_Amendment_1_Prefabricate_Bridge_ANF.doc | DOC document | |
| 3_DRAWINGS_Ashley_Temp_Hades_Bridge_ANF.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AG-84N8-S-16-0120 per FAC 2005-88 effective June 15, 2016 Page 21 of 34
Instructional Cover Sheet
ISSUING OFFICE: USDA-Forest Service Utah Acquisition Support Center
2222 West 2300 South
Salt Lake City, UT 84119-2020
FAX: 801-975-3483 Phone: 801-975-3367
SOLICITATION NO: AG-84N8-S-16-0120
SET-ASIDE: SMALL BUSINESS
PROJECT NAME: Prefabricate Temporary Bridge for the Ashley National Forest
IMPORTANT NOTICE TO OFFEROR – AT A MINIMUM, OFFEROR SHALL SUBMIT THE FOLLOWING DOCUMENTS WITH THEIR OFFER:
· SF1442 – complete, sign, & date (Page 2)
· Schedule of Items (PAGE 3)
· Experience & Equipment Questionnaire (Attached 22-23)
Ensure the solicitation number is on the outside of your envelope & retain a copy of the solicitation for your records. return to address above (Issuing Office).
Attn: Elouise Fowler
Solicitation: AG-84N8-S-16-0120
FAR 52.204-7 In order to be considered for any award, it is required that contractors be REGISTERED, ACTIVE, AND VALID in the System For Award Management (SAM) Database at the time of the award. Contractors must also be registered in the SAM database under the NAICS code that this solicitation is issued under.
INSTRUCTIONS FOR REGISTERING AT SAM CAN BE FOUND AT THE FOLLOWING WEBSITES:
https://www.sam.gov or http://www.acquisition.gov
This solicitation is issued through the federal business opportunities (FBO) website at: https://www.fbo.gov, It is the Offeror’s responsibility to watch for any and all amendments to this solicitation at this website.
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30
| 1. REQUISITION NUMBER |
| PAGE 1 OF |
806818
| 2. CONTRACT NO. |
| 3. AWARD/EFFECTIVE DATE |
| 4. ORDER NUMBER |
| 5. SOLICITATION NUMBER |
| 6. SOLICITATION ISSUE DATE |
| AG-84N8-S-16-0120 |
| June 20, 2016 |
7. FOR SOLICITATION
INFORMATION CALL:
| ( |
| a. NAME |
| b. TELEPHONE NUMBER (No collect |
| 8. OFFER DUE DATE/LOCAL |
| Elouise Fowler |
| Calls) |
| 801-975-3367 |
| TIME |
| 07/06/16 @ 1:00 pm |
| 9. ISSUED BY: |
| CODE |
| 84N8 |
| 10. THIS ACQUISITION IS |
| 11. DELIVERY FOR |
FOB DESTINATION
UNLESS BLOCK IS
MARKED
SEE SCHEDULE
12. DISCOUNT TERMS
USDA-Forest Service Utah Acquisition Support Center
2222 West 2300 South
Salt Lake City, UT 84119-2020
UNRESTRICTED
SET AIDE: 100% FOR
SMALL BUSINESS
13a. THIS CONTRACT IS A RATED ORDER UNDER DPAS (15 CFR 700)
| NAICS Code: 321999 |
| 13b. RATING |
| SIZE STANDARD: 500 |
| 14. METHOD OF SOLICITATION |
RFQ
15. DELIVER TO
| 8499 |
| 16. ADMINISTERED BY |
| CODE |
| 84N8 |
| Ashley National Forest |
| Utah Acquisition Support Center |
| 17a. CONTRACTOR/ OFFEROR |
| CODE |
| FACILITY CODE |
| 18a. PAYMENT WILL BE MADE BY |
| CODE |
All invoices will be processed using the Department of Treasury’s Invoice Processing Platform (IPP), visit http://www.ipp.gov to learn more. Contractors must follow the instructions on how to register and submit invoices via IPP.
TELEPHONE NO.
DUNS#
FAX NO.
VXP#
| 17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN OFFER |
| 18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK IS CHECKED SEE ADDENDUM |
19.
ITEM NO.
20.
SCHEDULE OF SUPPLIES/SERVICES
21.
QUANTITY
22.
UNIT
23.
UNIT PRICE
24.
AMOUNT
Prefabricate Temporary Bridge for Hades Creek Project, Ashley National Forest, Vernal Ranger District, Uintah County, Utah
Please place your quote in Schedule of Items – Page 3
SITE VISIT: No Site Visit is planner for this solicitation
| 25. ACCOUNTING AND APPROPRIATION DATA |
| 26. TOTAL AWARD AMOUNT (For Govt. Use Only) |
X27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1, 52.212-4. FAR 52.212-3 AND 52.212-5 ARE ATTACHED. ADDENDA X ARE ARE NOT ATTACHED
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCES FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN COPIES
TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED HEREIN.
29. AWARD OF CONTRACT: REFERENCE OFFER
DATED. YOUR OFFER ONSOLICITATION (BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:
| 30a. SIGNATURE OF OFFEROR/CONTRACTOR |
| 31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER) |
| 30b. NAME AND TITLE OF SIGNER (Type or print) |
| 30c. DATE SIGNED |
| 31b. NAME OF CONTRACTING OFFICER (Type or print) |
| 31c. DATE SIGNED |
32a. QUANTITY IN COLUMN 21 HAS BEEN
RECEIVED INSPECTED ACCEPTED, AND CONFORMS TO
THE CONTRACT, EXCEPT AS NOTED
| 33. SHIP NUMBER |
| 34. VOUCHER NUMBER |
| 35. AMOUNT VERIFIED CORRECT FOR |
PARTIAL FINAL
| 36. PAYMENT |
| 37. CHECK NUMBER |
| 32b. SIGNATURE OF AUTHORIZED GOVT. |
| 32c. DATE |
| COMPLETE PARTIAL FORMCHECKBOX |
FINAL
| 38. S/R ACCOUNT NUMBER |
| 39. S/R VOUCHER NUMBER |
| 40. PAID BY |
42a. RECEIVED BY (Print)
41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT
| 41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER |
| 41c. DATE |
| 42b. RECEIVED AT (Location) |
| 42c. DATE REC’D (YY/MM/DD) |
| 42d. TOTAL CONTAINERS |
| AUTHORIZED FOR LOCAL REPRODUCTION |
| SEE REVERSE FOR OMB CONTROL NUMBER AND PAPERWORK BURDEN STATEMENT |
| STANDARD FORM 1449 (10-95) |
Prescribed by GSA – FAR (48 CFR) 53.212
PART I - THE SCHEDULE
SECTION B - SUPPLIES AND PRICES
Prefabricate Temporary Bridge for the Hades Creek Project Vernal Ranger District
Ashley National Forest
Uintah County, Utah B- 1 Schedule of Items
| Item No. |
| Description |
| Unit |
| Quantity |
| Unit Cost |
| Total |
| 57102 |
| Prefabricate Bridge Superstructure: Design, Fabricate, and Transport (include railing, timber deck, and bulkhead) |
| LS |
| 1 |
| $ |
| $ |
| 1 |
| Shipping & Handling |
| EA |
| 1 |
| $ |
| $ |
Note: *Next to an Item Number above indicates that the quantity shown is a Contract Quantity, per FP-03 Specification 109.02.
The Offeror shall insert a quote in each Bid Schedule opposite each pay name listed in the Schedule. A quote is not to be tendered for any item not listed. All other items are indirect to one of the above items.
B-2 NOTE: Payment for bond premiums in accordance with FAR 52.232-5, Payments under Fixed-Price Construction Contracts, shall not be in addition to the contract price. Include bond payments under 151.01 Mobilization. Payment will be made on actual work performed as described in FP-03 109.01 unless otherwise noted.
B- 3 Basis of Award - One contract will be awarded. Offerors must submit prices for all items and sub-items. See Section L for instructions for proposal preparation and Section M for the basis of award.
B- 4 Delivery - Please contract Valton Mortenson for delivery instructions at 435-781-5147.
B- 5 Written Acceptance – Any contract resulting from this solicitation will required written acceptance within 10 days of receipt by the awardee.
B- 6 Price Range – Government Cost Estimate, per FAR 36.204 is a magnitude between $25,000 and $150.000 at the lower end of the spectrum.
Point of Contacts: Valton Mortenson, COR, 435-781-5147, vmortenson@fs.fed.us Elouise Fowler, CO, 801-975-3367, efowler@fs.fd.us
| Contractor Name: |
| Duns Number: |
| Contractor Rep’s Name (print): |
| Signature: |
PART I - THE SCHEDULE
Section C - Description/Specifications/Statement of Work
GENERAL SPECIFICATIONS
Ashley NF Temporary Bridge
1.1 SCOPE OF CONTRACT
A. This project consists of the design, fabrication, and transportation to Vernal, Utah of a 35 feet long and 14 feet wide prefabricated bridge. The superstructure design shall be performed by the contractor to the geometry shown on the drawings. Design calculations and shop drawings shall be submitted to the Forest Engineer for approval two weeks prior to fabrication. The bridge shall be delivered and unloaded at the Ashley National Forest Boneyard in Vernal, Utah as directed by the Contracting Officer’s Representative (COR).
1.2 DELIVERY DATE
A. The delivery date shall be August or September 2016 and shall be coordinated with the COR.
1.3 SPECIFICATIONS
A. Materials, Construction, and Workmanship shall be in accordance with Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects FP-03 U.S. Customary Unit and applicable Forest Service Supplemental Specifications. Some sections in the schedule of items refer to other sections not listed and are subsidiary to, or are included in payment for other pay items in this contract. These items are considered incidental and no additional compensation will be made.
END OF SECTION C
June 2016
PART I - THE SCHEDULE
SECTION D - PACKAGING AND MARKING
D- 1 AGAR 452.247-71 Marking Deliverables (FEB 1988)
D- 2 AGAR 452.247-72 Packing for Domestic Shipment (FEB 1988)
Material shall be packed for shipment in such a manner that will insure acceptance by common carriers and safe delivery at destination. Containers and closures shall comply with the Interstate Commerce Commission regulations, Uniform Freight Classification Rules, or regulations of other carriers as applicable to the mode of transportation.
D- 3 Delivery
(a) The Contractor shall notify the Government 3 days before shipment is made. Deliveries will only be accepted on weekdays. Because shipments will be inspected at time of delivery, Contractors shall arrange with shippers or drivers to accept and return to place of fabrication any items rejected for noncompliance. Depending on the quantity of items delivered at one time, inspections may take more than one day.
D- 4 Deliverables
(a) Deliverables shall be clean and free of debris, inside and out, including fiberglass, dirt or foreign material.
PART I - THE SCHEDULE
SECTION E - INSPECTION AND ACCEPTANCE
E- 1 FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): Federal Acquisition Regulations - http://www.acquisition.gov/far and the Agriculture Acquisition Regulations – http://www.usda.gov/procurement/policy/agar.html.
FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES
52.246-2 Inspection of Supplies--Fixed-Price (AUG 1996) 52.246-15 Certificate of Conformance (APR 1984)
52.246-16 Responsibility for Supplies (APR 1984) E- 2 AGAR 452.246-70 Inspection and Acceptance (FEB 1988)
(a) The Contracting Officer or the Contracting Officer's duly authorized representative will inspect and accept the supplies and/or services to be provided under this contract.
(b) Inspection and acceptance will be performed at: __ Ashley National Forest Boneyard.
PART I - THE SCHEDULE
SECTION F - DELIVERIES OR PERFORMANCE
F- 1 FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998) This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
http://www.acquisition.gov/far http://www.usda.gov/procurement/policy/agar.html.
FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES
52.242-15 Stop-Work Order (AUG 1989) 52.242-17 Government Delay of Work (APR 1984) F- 2 Point of Delivery – Contact COR for instructions.
F- 4 AGAR 452.211-74 Period of Performance (FEB 1988) The period of performance of this contract is from __Notice to Proceed____ through __60 days____.
PART I - THE SCHEDULE
SECTION G - CONTRACT ADMINISTRATION DATA
G- 1 Measurement and Payment
G- 2 Basis of Payment
G- 3 Invoice Processing Platform (IPP)
The Forest Service is utilizing the Invoice Processing Platform (IPP) for the electronic submission and tracking of contracts/purchase orders, invoices, and payment information. IPP is a secure Government-wide, Web-based invoice processing service. Visit http://www.ipp.gov to learn more.
Upon award of a contract, Contractors must enroll at https://www.ipp.gov/vendors/enrollment-vendors.htm. Contractors shall submit all invoices electronically via IPP. Paper copies of invoices will no longer be accepted.
PART I - THE SCHEDULE
SECTION H - SPECIAL CONTRACT REQUIREMENTS
H- 1 AGAR 452.237-74 Key Personnel (FEB 1988)
(a) The Contractor shall assign to this contract the following key personnel: ___Project Manager___.
(b) During the first ninety (90) days of performance, the Contractor shall make no substitutions of key personnel unless the substitution is necessitated by illness, death, or termination of employment. The Contractor shall notify the Contracting Officer within 15 calendar days after the occurrence of any of these events and provide the information required by paragraph (c) below. After the initial 90-day period, the Contractor shall submit the information required by paragraph (c) to the Contracting Officer at least 15 days prior to making any permanent substitutions.
(c) The Contractor shall provide a detailed explanation of the circumstances necessitating the proposed substitutions, complete resumes for the proposed substitutes, and any additional information requested by the Contracting Officer. Proposed substitutes should have comparable qualifications to those of the persons being replaced. The Contracting Officer will notify the Contractor within 15 calendar days after receipt of all required information of the decision on substitutions. The contract will be modified to reflect any approved changes of key personnel.
PART II – CONTRACT CLAUSES
SECTION I - CONTRACT CLAUSES
I- 1 FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998) This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
http://www.acquisition.gov/far http://www.usda.gov/procurement/policy/agar.html.
FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES
52.202-1 Definitions (NOV 2013)
52.203-3 Gratuities (APR 1984)
52.203-5 Covenant Against Contingent Fees (MAY 2014)
52.203-6 Restrictions on Subcontractor Sales to the Government (SEPT 2006)
52.203-7 Anti-Kickback Procedures (MAY 2014)
52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity
(MAY 2014)
52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (MAY 2014)
52.203-12 Limitation on Payments to Influence Certain Federal Transactions (OCT 2010)
52.203-17 Contractor Employee Whistleblower Rights and Requirement to Inform Employees of Whistleblower Rights (APR 2014)
52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper (MAY 2011)
52.204-19 Incorporation by Reference of Representations and Certifications (DEC 2014)
52.209-6 Protecting the Government's Interest when Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (OCT 2015) 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (NOV 2015)
52.211-5 Material Requirements (AUG 2000) 52.215-2 Audit and Records--Negotiation (OCT 2010) 52.215-8 Order of Precedence--Uniform Contract Format (OCT 1997)
52.219-6 Notice of Total Small Business Set-Aside (NOV 2011 52.219-8 Utilization of Small Business Concerns (OCT 2014) 52.219-14 Limitations on Subcontracting (NOV 2011)
52.222-4 Contract Work Hours and Safety Standards--Overtime Compensation (MAY 2014)
52.222-19 Child Labor--Cooperation with Authorities and Remedies (FEB 2016)
52.222-20 Contracts for Materials, Supplies, Articles, and Equipment Exceeding $15,000 (MAY 2014)
52.222-21 Prohibition of Segregated Facilities (APR 2015)
52.222-26 Equal Opportunity (APR 2015)
52.222-35 Equal Opportunity for Veterans (OCT 2015)
52.222-36 Equal Opportunity for Workers with Disabilities (JUL 2014)
52.222-37 Employment Reports on Veterans (FEB 2016)
52.222-40 Notification of Employee Rights Under the National Labor Relations Act (DEC 2010)
52.222-50 Combating Trafficking in Persons (MAR 2015)
52.222-54 Employment Eligibility Verification (OCT 2015)
52.223-3 Hazardous Material Identification and Material Safety Data (JAN 1997) Alternate I (JULY 1995)
52.223-5 Pollution Prevention and Right-to-Know Information (MAY 2011)
52.223-6 Drug-Free Workplace (MAY 2001)
52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving (AUG 2011)
52.224-1 Privacy Act Notification (APR 1984)
52.225-1 Buy American - Supplies (MAY 2014) 52.225-13 Restrictions on Certain Foreign Purchases (JUNE 2008)
52.227-1 Authorization and Consent (DEC 2007)
52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement (DEC 2007)
52-227-3 Patent Indemnity (APR 1984)
52.227-14 Rights in Data--General (MAY 2014) 52.229-3 Federal, State, and Local Taxes (FEB 2013)
52.232-1 Payments (APR 1984)
52.232-8 Discounts for Prompt Payment (FEB 2002)
52.232-9 Limitation on Withholding of Payments (APR 1984)
52.232-11 Extras (APR 1984)
52.232-17 Interest (MAY 2014)
52.232-18 Availability of Funds (APR 1984)
52.232-23 Assignment of Claims (MAY 2014)
52.232-25 Prompt Payment (JUL 2013)
52.232-33 Payment by Electronic Funds Transfer—System for Award Management (JUL 2013)
52.232-39 Unenforceability of Unauthorized Obligations (JUN 2013)
52.233-1 Disputes (MAY 2014) Alternate I (DEC 1991)
52.233-3 Protest After Award (AUG 1996)
52.233-4 Applicable Law for Breach of Contract Claim (OCT 2004)
52-242-2 Production Progress Reports (APR 1991)
52.242-13 Bankruptcy (JULY 1995)
52.243-1 Changes--Fixed-Price (AUG 1987) 52.244-6 Subcontracts for Commercial Items (JUN 2016)
52.245-1 Government Property (APR 2012) 52.245-9 Use and Charges (APR 2012) 52.246-23 Limitation of Liability (FEB 1997) 52.249-1 Termination for Convenience of the Government (Fixed-Price) (Short Form) (APR 1984) 52.249-8 Default (Fixed-Price Supply and Service) (APR 1984) 52.253-1 Computer Generated Forms (JAN 1991)
AGRICULTURE ACQUISITION REGULATION (48 CFR CHAPTER 4) CLAUSES
452.224-70 Confidentiality of Information (FEB 1988)
I-2 52.204-10 – Reporting Executive Compensation and First-Tier Subcontract Awards.
(Oct 2015)
(a) Definitions. As used in this clause:
“Executive” means officers, managing partners, or any other employees in management positions.
“First-tier subcontract” means a subcontract awarded directly by the Contractor for the purpose of acquiring supplies or services (including construction) for performance of a prime contract. It does not include the Contractor’s supplier agreements with vendors, such as long-term arrangements for materials or supplies that would benefit multiple contracts and/or the costs of which are normally applied to a Contractor’s general and administrative expenses or indirect cost.
“Month of award” means the month in which a contract is signed by the Contracting Officer or the month in which a first-tier subcontract is signed by the Contractor.
“Total compensation” means the cash and noncash dollar value earned by the executive during the Contractor’s preceding fiscal year and includes the following (for more information see 17 CFR 229.402(c)(2)):
(1) Salary and bonus.
(2) Awards of stock, stock options, and stock appreciation rights. Use the dollar amount recognized for financial statement reporting purposes with respect to the fiscal year in accordance with the Financial Accounting Standards Board’s Accounting Standards Codification (FASB ASC) 718, Compensation-Stock Compensation.
(3) Earnings for services under non-equity incentive plans. This does not include group life, health, hospitalization or medical reimbursement plans that do not discriminate in favor of executives, and are available generally to all salaried employees.
(4) Change in pension value. This is the change in present value of defined benefit and actuarial pension plans.
(5) Above-market earnings on deferred compensation which is not tax-qualified.
(6) Other compensation, if the aggregate value of all such other compensation (e.g., severance, termination payments, value of life insurance paid on behalf of the employee, perquisites or property) for the executive exceeds $10,000.
(b) Section 2(d)(2) of the Federal Funding Accountability and Transparency Act of 2006 (Pub. L. No. 109-282), as amended by section 6202 of the Government Funding Transparency Act of 2008 (Pub. L. 110-252), requires the Contractor to report information on subcontract awards. The law requires all reported information be made public, therefore, the Contractor is responsible for notifying its subcontractors that the required information will be made public.
(c) Nothing in this clause required the disclosure of classified information.
(d)
(1) Executive compensation of the prime contractor. As a part of its annual registration requirement in the System for Award Management (SAM) database (FAR provision 52.204-7), the Contractor shall report the names and total compensation of each of the five most highly compensated executives for its preceding completed fiscal year, if—
(i) In the Contractor’s preceding fiscal year, the Contractor received—
(A) 80 percent or more of its annual gross revenues from Federal contracts (and subcontracts), loans, grants (and subgrants), cooperative agreements, and other forms of Federal financial assistance; and
(B) $25,000,000 or more in annual gross revenues from Federal contracts (and subcontracts), loans, grants (and subgrants), cooperative agreements, and other forms of Federal financial assistance; and
(ii) The public does not have access to information about the compensation of the executives through periodic reports filed under section 13(a) or 15(d) of the Securities Exchange Act of 1934 (15 U.S.C. 78m(a), 78o(d)) or section 6104 of the Internal Revenue Code of 1986. (To determine if the public has access to the compensation information, see the U.S. Security and Exchange Commission total compensation filings at http://www.sec.gov/answers/execomp.htm.)
(2) First-tier subcontract information. Unless otherwise directed by the contracting officer, or as provided in paragraph (g) of this clause, by the end of the month following the month of award of a first-tier subcontract with a value of $30,000 or more, the Contractor shall report the following information at http://www.fsrs.gov for that first tier subcontract. (The Contractor shall follow the instruction at http://www.fsrs.gov to report the data.)
(i) Unique identifier (DUNS Number) for the subcontractor receiving the award and for the subcontractor’s parent company, if the subcontractor has a parent company.
(ii) Name of the subcontractor.
(iii) Amount of the subcontract award.
(iv) Date of the subcontract award.
(v) A description of the products or services (including construction) being provided under the subcontract, including the overall purpose and expected outcomes or results of the subcontract.
(vi) Subcontract number (the subcontract number assigned by the Contractor).
(vii) Subcontractor’s physical address including street address, city, state, and country. Also include the nine-digit zip code and congressional district.
(viii) Subcontractor’s primary performance location including street address, city, state, and country. Also include the nine-digit zip code and congressional district.
(ix) The prime contract number, and order number if applicable.
(x) Awarding agency name and code.
(xi) Funding agency name and code.
(xii) Government contracting office code.
(xiii) Treasury account symbol (TAS) as reported in FPDS.
(xiv) The applicable North American Industry Classification System code (NAICS).
(3) Executive compensation of the first-tier subcontractor. Unless otherwise directed by the Contracting Officer, by the end of the month following the month of award of a first-tier subcontract with a value of $30,000 or more, and annually thereafter (calculated from the prime contract award date), the Contractor shall report the names and total compensation of each of the five most highly compensated executives for that first-tier subcontractor for the first-tier subcontractor’s preceding completed fiscal year at https://www.fsrs.gov , if—
(i) In the subcontractor’s preceding fiscal year, the subcontractor received—
(A) 80 percent or more of its annual gross revenues from Federal contracts (and subcontracts), loans, grants (and subgrants), cooperative agreements, and other forms of Federal financial assistance; and
(B) $25,000,000 or more in annual gross revenues from Federal contracts (and subcontracts), loans, grants (and subgrants), cooperative agreements and other forms of Federal financial assistance; and
(ii) The public does not have access to information about the compensation of the executives through periodic reports filed under section 13(a) or 15(d) of the Securities Exchange Act of 1934 (15 U.S.C. 78m(a), 78o(d)) or section 6104 of the Internal Revenue Code of 1986. (To determine if the public has access to the compensation information, see the U.S. Security and Exchange Commission total compensation filings at http://www.sec.gov/answers/execomp.htm.)
(e) The Contractor shall not split or break down first-tier subcontract awards to a value less than $30,000 to avoid the reporting requirements in paragraph (d) of this clause.
(f) The Contractor is required to report information on a first-tier subcontract covered by paragraph (d) when the subcontract is awarded. Continued reporting on the same subcontract is not required unless one of the reported data elements changes during the performance of the subcontract. The Contractor is not required to make further reports after the first-tier subcontract expires.
(g)
(1) If the Contractor in the previous tax year had gross income, from all sources, under $300,000, the Contractor is exempt from the requirement to report subcontractor awards.
(2) If a subcontractor in the previous tax year had gross income from all sources under $300,000, the Contractor does not need to report awards for that subcontractor
(h) The FSRS database at http://www.fsrs.gov will be prepopulated with some information from SAM and FPDS databases. If FPDS information is incorrect, the contractor should notify the contracting officer. If the SAM database information is incorrect, the contractor is responsible for correcting this information.
I- 3 FAR 52.204-13 System for Award Management Maintenance (JUL 2013)
(a) Definitions. As used in this clause—
“Data Universal Numbering System (DUNS) number” means the 9-digit number assigned by Dun and Bradstreet, Inc. (D&B) to identify unique business entities, which is used as the identification number for Federal contractors.
“Data Universal Numbering System+4 (DUNS+4) number” means the DUNS number assigned by D&B plus a 4-character suffix that may be assigned by a business concern. (D&B has no affiliation with this 4-character suffix.) This 4-character suffix may be assigned at the discretion of the business concern to establish additional SAM records for identifying alternative Electronic Funds Transfer (EFT) accounts (see the FAR at subpart 32.11) for the same concern.
“Registered in the System for Award Management (SAM) database” means that—
(1) The Contractor has entered all mandatory information, including the DUNS number or the DUNS+4 number, the Contractor and Government Entity (CAGE) code, as well as data required by the Federal Funding Accountability and Transparency Act of 2006 (see Subpart 4.14), into the SAM database;
(2) The Contractor has completed the Core, Assertions, Representations and Certifications, and Points of Contact sections of the registration in the SAM database;
(3) The Government has validated all mandatory data fields, to include validation of the Taxpayer Identification Number (TIN) with the Internal Revenue Service (IRS). The Contractor will be required to provide consent for TIN validation to the Government as a part of the SAM registration process; and
(4) The Government has marked the record “Active”.
“System for Award Management (SAM)” means the primary Government repository for prospective Federal awardee and Federal awardee information and the centralized Government system for certain contracting, grants, and other assistance-related processes. It includes—
(1) Data collected from prospective Federal awardees required for the conduct of business with the Government;
(2) Prospective contractor-submitted annual representations and certifications in accordance with FAR Subpart 4.14; and
(3) Identification of those parties excluded from receiving Federal contracts, certain subcontracts, and certain types of Federal financial and non-financial assistance and benefits.
(b) The Contractor is responsible for the accuracy and completeness of the data within the SAM database, and for any liability resulting from the Government’s reliance on inaccurate or incomplete data. To remain registered in the SAM database after the initial registration, the Contractor is required to review and update on an annual basis, from the date of initial registration or subsequent updates, its information in the SAM database to ensure it is current, accurate and complete. Updating information in the SAM does not alter the terms and conditions of this contract and is not a substitute for a properly executed contractual document.
(c) (1)
(i) If a Contractor has legally changed its business name, doing business as name, or division name (whichever is shown on the contract), or has transferred the assets used in performing the contract, but has not completed the necessary requirements regarding novation and change-of-name agreements in subpart 42.12, the Contractor shall provide the responsible Contracting Officer a minimum of one business day's written notification of its intention to—
(A) Change the name in the SAM database;
(B) Comply with the requirements of subpart 42.12 of the FAR; and
(C) Agree in writing to the timeline and procedures specified by the responsible Contracting Officer. The Contractor shall provide with the notification sufficient documentation to support the legally changed name.
(ii) If the Contractor fails to comply with the requirements of paragraph (c)(1)(i) of this clause, or fails to perform the agreement at paragraph (c)(1)(i)(C) of this clause, and, in the absence of a properly executed novation or change-of-name agreement, the SAM information that shows the Contractor to be other than the Contractor indicated in the contract will be considered to be incorrect information within the meaning of the “Suspension of Payment” paragraph of the electronic funds transfer (EFT) clause of this contract.
(2) The Contractor shall not change the name or address for EFT payments or manual payments, as appropriate, in the SAM record to reflect an assignee for the purpose of assignment of claims (see FAR subpart 32.8, Assignment of Claims). Assignees shall be separately registered in the SAM. Information provided to the Contractor’s SAM record that indicates payments, including those made by EFT, to an ultimate recipient other than that Contractor will be considered to be incorrect information within the meaning of the “Suspension of Payment” paragraph of the EFT clause of this contract.
(3) The Contractor shall ensure that the DUNS number is maintained with Dun & Bradstreet throughout the life of the contract. The Contractor shall communicate any change to the DUNS number to the Contracting Officer within 30 days after the change, so an appropriate modification can be issued to update the data on the contract. A change in the DUNS number does not necessarily require a novation be accomplished. Dun & Bradstreet may be contacted
(i) Via the internet at http://fedgov.dnb.com/webform or if the contractor does not have internet access, it may call Dun and Bradstreet at 1-866-705-5711 if located within the United States; or
(ii) If located outside the United States, by contacting the local Dun and Bradstreet office.
(d) Contractors may obtain additional information on registration and annual confirmation requirements at http://www.acquisition.gov.
I-4 52.204-18 Commercial and Government Entity Code Maintenance. (Jul 2015)
(a) Definition. As used in this clause—
“Commercial and government Entity (CAGE)” means—
(1) An identifier assigned to entities located in the United States or its outlying areas by the Defense Logistics Agency (DLA) Contractor and Government Entity (CAGE) Branch to identify a commercial or Government entity, or
(2) An identifier assigned by a member of the North Atlantic Treaty Organization (NATO) or by the NATO Support Agency (NSPA) to entities located outside the United States and its outlying areas that the DLA Contractor and Government Entity (CAGE) Branch records and maintains in the CAGE master file. This type of code is known as the NCAGE code.
(b) Contractors shall ensure that the CAGE code is maintained throughout the life of the contract. For contractors registered in the System for Award Management (SAM), the DLA Contractor and Government Entity (CAGE) Branch shall only modify data received from SAM in the CAGE master file if the contractor initiates those changes via update of its SAM registration. Contractors undergoing a novation or change-of-name agreement shall notify the contracting officer in accordance with subpart 42.12. The contractor shall communicate any change to the CAGE code to the contracting officer within 30 days after the change, so that a modification can be issued to update the CAGE code on the contract.
(c) Contractors located in the United States or its outlying areas that are not registered in SAM shall submit written change requests to the DLA Contractor and Government Entity (CAGE) Branch. Requests for changes shall be provided on a DD Form 2051, Request for Assignment of a Commercial and Government Entity (CAGE) Code, to the address shown on the back of the DD Form 2051. Change requests to the CAGE master file are accepted from the entity identified by the code.
(d) Contractors located outside the United States and its outlying areas that are not registered in SAM shall contact the appropriate National Codification Bureau or NSPA to request CAGE changes. Points of contact for National Codification Bureaus and NSPA, as well as additional information on obtaining NCAGE codes, are available at http://www.dlis.dla.mil/nato/ObtainCAGE.asp.
(e) Additional guidance for maintaining CAGE codes is available at http://www.dlis.dla.mil/cage_welcome.asp.
I- 5 FAR 52.209-1 Qualification Requirements (FEB 1995)
(a) Definition: "Qualification requirement," as used in this clause, means a Government requirement for testing or other quality assurance demonstration that must be completed before award.
(b) One or more qualification requirements apply to the supplies or services covered by this contract. For those supplies or services requiring qualification, whether the covered product or service is an end item under this contract or simply a component of an end item, the product, manufacturer, or source must have demonstrated that it meets the standards prescribed for qualification before award of this contract. The product, manufacturer, or source must be qualified at the time of award whether or not the name of the product, manufacturer, or source is actually included on a qualified products list, qualified manufacturers list, or qualified bidders list. Offerors should contact the agency activity designated below to obtain all requirements that they or their products or services, or their subcontractors or their products or services, must satisfy to become qualified and to arrange for an opportunity to demonstrate their abilities to meet the standards specified for qualification.
(Name)*_____________________________________________________________________
(Address)____________________________________________________________________
(c) If an offeror, manufacturer, source, product, or service covered by a qualification requirement has already met the standards specified, the relevant information noted below should be provided.
Offeror's Name ____________________________________________________________
Manufacturer's Name _______________________________________________________
Source's Name ____________________________________________________________
Item Name _______________________________________________________________
Service Identification _______________________________________________________
Test Number _________________________________________*(to the extent known)
(d) Even though a product or service subject to a qualification requirement is not itself an end item under this contract, the product, manufacturer, or source must nevertheless be qualified at the time of award of this contract. This is necessary whether the Contractor or a subcontractor will ultimately provide the product or service in question. If, after award, the Contracting Officer discovers that an applicable qualification requirement was not in fact met at the time of award, the Contracting Officer may either terminate this contract for default or allow performance to continue if adequate consideration is offered and the action is determined to be otherwise in the Government's best interests.
(e) If an offeror, manufacturer, source, product, or service has met the qualification requirement but is not yet on a qualified products list, qualified manufacturers list, or qualified bidders list, the offeror must submit evidence prior to award of this contract. Unless determined to be in the Government's interest, award of this contract shall not be delayed to permit an offeror to submit evidence of qualification.
(f) Any change in location or ownership of the plant where a previously qualified product or service was manufactured or performed requires reevaluation of the qualification. Similarly, any change in location or ownership of a previously qualified manufacturer or source requires reevaluation of the qualification. The reevaluation must be accomplished before the date of award.
I- 6 AGAR 452.209-71 Assurance Regarding Felony Conviction or Tax Delinquent Status for Corporate Applicants (FEB 2012) Alternate I (FEB 2012)
(a) This award is subject to the provisions contained in section 433 and 434 of the Consolidated Appropriations Act, 2012 (P.L. No. 112-74), Division E, as amended and/or subsequently enacted, regarding corporate felony convictions and corporate federal tax delinquencies. Accordingly, by accepting this award the contractor acknowledges that it –
(1) does not have a tax delinquency, meaning that it is not subject to any unpaid Federal tax liability that has been assessed, for which all judicial and administrative remedies have been exhausted or have lapsed, and that is not being paid in a timely manner pursuant to an agreement with the authority responsible for collecting the tax liability, and
(2) has not been convicted (or had an officer or agent acting on its behalf convicted) of a felony criminal violation under any Federal law within 24 months preceding the award, unless a suspending and debarring official of the United States Department of Agriculture has considered suspension or debarment of the awardee, or such officer or agent, based on these convictions and/or tax delinquencies and determined that suspension or debarment is not necessary to protect the interests of the Government.
(b) If the awardee fails to comply with these provisions, the Forest Service may terminate this contract for default and may recover any funds the awardee has received in violation of sections 433 or 434, amended and/or subsequently enacted.
I-7 AGAR 452.215-73 Post Award Conference (NOV 1996) A post award conference with the successful offeror is required. It will be scheduled within ___10___ days after the date of contract award. The conference will be held at: __TBD________________.
I-8 FAR 52.216-21 Requirements (OCT 1995)
(a) This is a requirements contract for the supplies or services specified, and effective for the period stated, in the Schedule. The quantities of supplies or services specified in the Schedule are estimates only and are not purchased by this contract. Except as this contract may otherwise provide, if the Government's requirements do not result in orders in the quantities described as "estimated" or "maximum" in the Schedule, that fact shall not constitute the basis for an equitable price adjustment.
(b) Delivery or performance shall be made only as authorized by orders issued in accordance with the Ordering clause. Subject to any limitations in the Order Limitations clause or elsewhere in this contract, the Contractor shall furnish to the Government all supplies or services specified in the Schedule and called for by orders issued in accordance with the Ordering clause. The Government may issue orders requiring delivery to multiple destinations or performance at multiple locations.
(c) Except as this contract otherwise provides, the Government shall order from the Contractor all the supplies or services specified in the Schedule that are required to be purchased by the Government activity or activities specified in the Schedule.
(d) The Government is not required to purchase from the Contractor requirements in excess of any limit on total orders under this contract.
(e) If the Government urgently requires delivery of any quantity of an item before the earliest date that delivery may be specified under this contract, and if the Contractor will not accept an order providing from the accelerated delivery, the Government may acquire the urgently required goods or services from another source.
(f) Any order issued during the effective period of this contract and not completed within that period shall be completed by the Contractor within the time specified in the order. The contract shall govern the Contractor's and Government's rights and obligations with respect to that order to the same extent as if the order were completed during the contract's effective period; provided, that the Contractor shall not be required to make any deliveries under this contract after *_____________.
I-9 FAR 52.219-13 Notice of Set-Aside of Orders (NOV 2011) The Contracting Officer will give notice of the order or orders, if any, to be set aside for small business concerns identified in 19.000(a)(3) and the applicable small business program. This notice, and its restrictions, will apply only to the specific orders that have been set aside for any of the small business concerns identified in 19.000(a)(3).
I-10 FAR 52.219-28 Post-Award Small Business Program Rerepresentation (JUL 2013)
(a) Definitions. As used in this clause—
Long-term contract means a contract of more than five years in duration, including options. However, the term does not include contracts that exceed five years in duration because the period of performance has been extended for a cumulative period not to exceed six months under the clause at 52.217-8, Option to Extend Services, or other appropriate authority.
Small business concern means a concern, including its affiliates that is independently owned and operated, not dominant in the field of operation in which it is bidding on Government contracts, and qualified as a small business under the criteria in 13 CFR part 121 and the size standard in paragraph (c) of this clause. Such a concern is “not dominant in its field of operation” when it does not exercise a controlling or major influence on a national basis in a kind of business activity in which a number of business concerns are primarily engaged. In determining whether dominance exists, consideration shall be given to all appropriate factors, including volume of business, number of employees, financial resources, competitive status or position, ownership or control of materials, processes, patents, license agreements, facilities, sales territory, and nature of business activity.
(b) If the Contractor represented that it was a small business concern prior to award of this contract, the Contractor shall rerepresent its size status according to paragraph (e) of this clause or, if applicable, paragraph (g) of this clause, upon the occurrence of any of the following:
(1) Within 30 days after execution of a novation agreement or within 30 days after modification of the contract to include this clause, if the novation agreement was executed prior to inclusion of this clause in the contract.
(2) Within 30 days after a merger or acquisition that does not require a novation or within 30 days after modification of the contract to include this clause, if the merger or acquisition occurred prior to inclusion of this clause in the contract.
(3) For long-term contracts—
(i) Within 60 to 120 days prior to the end of the fifth year of the contract; and
(ii) Within 60 to 120 days prior to the date specified in the contract for exercising any option thereafter.
(c) The Contractor shall rerepresent its size status in accordance with the size standard in effect at the time of this rerepresentation that corresponds to the North American Industry Classification System (NAICS) code assigned to this contract. The small business size standard corresponding to this NAICS code can be found at http://www.sba.gov/content/table-small-business-size-standards.
(d) The small business size standard for a Contractor providing a product which it does not manufacture itself, for a contract other than a construction or service contract, is 500 employees.
(e) Except as provided in paragraph (g) of this clause, the Contractor shall make the rerepresentation required by paragraph (b) of this clause by validating or updating all its representations in the Representations and Certifications section of the System for Award Management (SAM) and its other data in SAM, as necessary, to ensure that they reflect the Contractor’s current status. The Contractor shall notify the contracting office in writing within the timeframes specified in paragraph (b) of this clause that the data have been validated or updated, and provide the date of the validation or update.
(f) If the Contractor represented that it was other than a small business concern prior to award of this contract, the Contractor may, but is not required to, take the actions required by paragraphs (e) or (g) of this clause.
(g) If the Contractor does not have representations and certifications in SAM, or does not have a representation in SAM for the NAICS code applicable to this contract, the Contractor is required to complete the following rerepresentation and submit it to the contracting office, along with the contract number and the date on which the rerepresentation was completed:
The Contractor represents that it FORMCHECKBOX is, FORMCHECKBOX is not a small business concern under NAICS Code ______________ assigned to contract number ______________.
[Contractor to sign and date and insert authorized signer’s name and title].
I-11 FAR 52.236-7 Permits and Responsibilities (NOV 1991)
The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses and permits, and for complying with any Federal, State, and municipal laws, codes, and regulations applicable to the performance of the work. The Contractor shall also be responsible for all damages to persons or property that occur as a result of the Contractor's fault or negligence. The Contractor shall also be responsible for all materials delivered and work performed until completion and acceptance of the entire work, except for any completed unit of work which may have been accepted under the contract.
I-12 FAR 52.252-6 Authorized Deviations in Clauses (APR 1984)
(a) The use in this solicitation or contract of any Federal Acquisition Regulation (48 CFR Chapter 1) clause with an authorized deviation is indicated by the addition of “(DEVIATION): after the date of the clause.
(b) The use in this solicitation or contract of any Agriculture Acquisition Regulation (48 CFR Chapter 4) clause with an authorized deviation is indicated by the addition of “(DEVIATION)” after the name of the regulation.
PART III - LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS
SECTION J - LIST OF ATTACHMENTS
The following attachments are a part of this solicitation and any resulting contract (see separate document(s)).
Exhibits/Attachments:
J- 1 Experience Questionnaire, Page 22-23
J- 2 Forest Service Supplemental Specifications
J- 3 DRAWINGS_Ashley Temp Hades Bridge USDA Forest Service
EXPERIENCE QUESTIONNAIRE
Instructions: See Box 11, Remarks, if extra space is needed to answer any item below, Mark “X: in appropriate boxes.
1. Contractor Name, Address, and Telephone Number
2. Submitted to (Office Name and Address)
3. Business
[ ] Company [ ] Co-partnership
[ ] Corporation [ ] Individual
[ ] Non-profit Organization
4. How many years do you or your firm have in the line of work contemplated by this solicitation?
5. How many years experience have you or your business had as a (a) prime contractor ____ and/or (b) sub-contractor ____?
6. List below the projects your business has completed within the last three years:
| Contract Amount |
| Type of Project |
| Date Completed |
| Name, Address, and Telephone No. of Owner/Person to Contact for Project Information |
7. List below all of your firm’s contractual commitments running concurrently with the work contemplated by this solicitation:
| Contract Number |
| Dollar Amt. of Award |
| Name, Address, and Telephone No. of Business/Government Agency Involved |
| Awarded (Units) |
| Percent Completed |
| Date Contract Complete |
8a. Have you ever failed to complete any work awarded to you? [ ] Yes [ ] No
8b. Has work ever been completed by performance bond? [ ] Yes [ ] No
8c. Did you look at the project site(s) on-the-ground? [ ] Yes [ ] No
8d. If “Yes” to either item 8a. or 8b., specify location(s) and reason(s) why:
EXPERIENCE QUESTIONNAIRE CONTINUED
9. Employees and equipment that will be available for this project:
a. (1) Minimum number of employees:________ and (2) Maximum number of employees:_________
b. Are employees regularly on your payroll: [ ] Yes [ ] No
c. Specify equipment available for this contract:___________________________________________________________
d. Estimate rate of progress below (such as 2.0 acres/man/day):
(1) Minimum progress rate:__________________ and (2) Maximum progress rate:_______________________
10. List below the experience of the principal individuals of your business (Who will directly be involved in this contract?)
| Individual’s Name |
| Present Position |
| Years of Experience |
| Magnitude and Type of Work |
11. Remarks --…