Questions_and_Answers_from_Buckboard_Lift_Stations_Site_Visit.docx
DOCX document 14 KB Posted
- Attached to
- Buckboard Sewer Lift Stations Reconstruction
- Solicitation number
- AG-84N8-S-14-0067
About this file
Questions and Answers from Site Visit
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Site_Visit_Attendees.pdf | ||
| AG-84N8-S-14-0067_0002.pdf | ||
| AG-84N8-S-14-0067_0001.pdf | ||
| Attachment_03_-_Drawings.PDF | ||
| Attachment_05_-_Subcontractor_Reporting_Form.docx | DOCX document | |
| Attachment_02_-_Specifications.docx | DOCX document | |
| AG-84N8-S-14-0067.docx | DOCX document | |
| Attachment_01_-_Schedule_of_Items.xlsx | XLSX spreadsheet | |
| Attachment_06_-_AGAR_452.209-70.docx | DOCX document | |
| Attachment_04_-_Wage_Determination.PDF.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers from Buckboard Lift Stations Site Visit
AG-84N8-S-14-0067
Q1: What size is the ductile iron pipe?
A1: 4”
Q2: Will the contractor be required to install new wet wells?
A2: Yes, along with grinder pumps
Q3: What is the distance of the line with the break that will need to be dug up?
A3: 1470 ft
Q4: How many residences will require temporary sewer services?
A4: 3
Q5: Can the awardee order pumps and materials prior to the start date of September 2nd?
A5: Yes
Q6: Can the awardee do some pre-fab and electrical work ahead of time (prior to start date of Sep 2nd)?
A6: Yes; however, no work will be allowed on-site until September 2nd.
Q7: With regard to getting the pumps operational, is pump #2 the priority?
A7: Yes
Q8: What’s inside building (pump station) #3?
A8: Electrical panels and controls.