Questions_and_Answers_from_Buckboard_Lift_Stations_Site_Visit.docx

DOCX document 14 KB Posted

Attached to
Buckboard Sewer Lift Stations Reconstruction
Solicitation number
AG-84N8-S-14-0067
Issued by

About this file

Questions and Answers from Site Visit

View the file

Other files

File Type Posted
Site_Visit_Attendees.pdf PDF
AG-84N8-S-14-0067_0002.pdf PDF
AG-84N8-S-14-0067_0001.pdf PDF
Attachment_03_-_Drawings.PDF PDF
Attachment_05_-_Subcontractor_Reporting_Form.docx DOCX document
Attachment_02_-_Specifications.docx DOCX document
AG-84N8-S-14-0067.docx DOCX document
Attachment_01_-_Schedule_of_Items.xlsx XLSX spreadsheet
Attachment_06_-_AGAR_452.209-70.docx DOCX document
Attachment_04_-_Wage_Determination.PDF.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers from Buckboard Lift Stations Site Visit

AG-84N8-S-14-0067

Q1: What size is the ductile iron pipe?

A1: 4”

Q2: Will the contractor be required to install new wet wells?

A2: Yes, along with grinder pumps

Q3: What is the distance of the line with the break that will need to be dug up?

A3: 1470 ft

Q4: How many residences will require temporary sewer services?

A4: 3

Q5: Can the awardee order pumps and materials prior to the start date of September 2nd?

A5: Yes

Q6: Can the awardee do some pre-fab and electrical work ahead of time (prior to start date of Sep 2nd)?

A6: Yes; however, no work will be allowed on-site until September 2nd.

Q7: With regard to getting the pumps operational, is pump #2 the priority?

A7: Yes

Q8: What’s inside building (pump station) #3?

A8: Electrical panels and controls.