SiteVisitNotes 6-6-10.docx
DOCX document 21 KB Posted
- Solicitation number
- AG-84N8-S-10-0094
About this file
Modification 2 - Site Visit Notes (2 pages)
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SF 30 Contract Modification 02.pdf | ||
| updated map 08052010.pdf | ||
| Amendment B - Wage Determination.docx | DOCX document | |
| Cover Sheet.doc | DOC document | |
| Construction RFQ.doc | DOC document | |
| Amendment A - Project Specifications.docx | DOCX document | |
| Attachment C - Location Map.pdf | ||
| SF 30 Contract Modification 01.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Terry Shoal Creek Fence Construction
AG-84N8-S-10-0094
August 6, 2010 @ 9:00 a.m. Site Visit Notes
Attendees:
| Name |
| Business Name |
| Address |
| City, State |
| Phone Number |
| Paul Snyder |
| P.C.I. |
| P.O. Box 1930 |
| St. George, UT |
| 435-628-6662 |
| John Slack |
| P.C.I. |
| P.O. Box 1930 |
| St. George, UT |
| 435-628-6662 |
| Ron Gardner |
| Gardner & Platt Fence |
| 2445 N. Hwy 18 |
| Beryl, UT |
| 435-680-1649 |
| Leon Platt |
| Gardner & Platt Fence |
| 2445 N. Hwy 18 |
| Beryl, UT |
| 435-680-1649 |
Notes to reference at Site Visit
· Solicitation closes August 13, 2010 @ 4:30 p.m.
· Faxes will not be accepted for this project. All quotes must be received at:
Fremont River Ranger District ATTN: Tamera Draper PO Box 90 Teasdale, UT 84773-0090 By the reply due date of August 13, 2010 @ 4:30 p.m. Hand delivered quotes are acceptable.
· Proposal must include Page 1-2 (SF-1442), Page 3 (Schedule of Items), Technical Package, and any pages of the RFQ that the offeror has modified with updated information
· This project is a Small Business set-aside
· Section L gives instructions on what is requested in the Technical Package. Section M has the evaluation criteria for award.
· Bid bond is required for awards exceeding $30,000.00.
· Estimated range for the job is over $25,000.00.
· Contract is under Davis Bacon and will require certified payrolls.
· Buy American Act applies.
· Pay attention to Section C. Has a lot of important information in it.
· Section H includes some Special Clauses to be aware of.
Questions/Answers from pre-bid meeting on site held August 6, 2010 Q Is a bid bond required?
A Only if award is for over $100,000.
Q Clarification on the bond, is it a bid bond or a performance bond?
A If the construction quote is $30,000 to $100,000, then it will be a Request for Quote and either a Payment Bond or an Irrevocable Letter of Credit (ILC) is required.
· The Payment Bond must be valued at 100% of the quote and guarantees that any labor or materials the contractor has used, will be paid for in the event of a default or other action of that nature.
The payment bond must be obtained within 10 days of the contract being awarded.
Q Does the fire box need to be transported with the workers along the fenceline?
A No, it can be kept at the vehicles.
Q How do the end posts need to be constructed?
A Given the rocky terrain, it is recommended that rock baskets be used. Easy braces may be used in some locations.
Q Is there additional ATV access?
A ATV access is limited due to terrain. However, it will be allowed along the fence corridor for transportation of materials and equipment. ATV access is likely near Parker Canyon and on the west end of fence project.
Q Where new fence is on line with old fence, can the existing posts be used?
A Yes. They may need to be straightened and pounded in further.
Q How much of the new fence is on line with the old?
A About half of the new fence is on line with the old. The old fence contains both metal and cedar posts. Existing posts may be used. Existing posts may need to be straightened and pounded deeper in order to meet fence specifications. New metal posts will need to be placed near cedar posts to ensure that 16’ spacing requirement is met.
Q Can existing stays be used?
A Yes, if they are sound and meet the fence specifications of 2-3” diameter.
Q Do existing braces need to be replaced?
A Yes, they need to be replaced with rock baskets (preferred) or easy braces.
Q Is it okay to tie off to rocks and trees?
A Yes. If wire is tied off on trees, slats or stays are needed to prevent wire from cutting into the tree.
Q Availability of stays for half of the fence appears limited, who will provide them?
A Contractor will need to cut stays from east end of the fence to the bottom of Park Canyon. Stays will be provided by the permittees/Forest Service for the section from the bottom of Park Canyon to the west end of the fence.