road_245_low water crossings roadlogl.xls

XLS spreadsheet 97 KB Posted

Attached to
Forest Road 245 Low Water Crossings Paving
Solicitation number
AG-83D5-S-09-011
Issued by

About this file

Road Log.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

NATIONAL FOREST ROAD 245 - ROAD MAINTENANCE LOG
MILEPOST FROM NFR 245APPLICABLE SPECIFICATIONNOTESWORK ITEMS AT EACH SITE
0.000BEGIN PROJECT - At National Forest Boundary clean cattleguard. Construct and pave 14' X 100' long asphalt grade dip before reaching cattleguard. Outslope grade dip at 2% toward charred R/W fence post. Construct and pave 14' X 50' asphalt approach after cattleguard, outslope at 2%.Outslope road 100' before cattleguard. Install drain dip 65' before cattleguard. Grade toward charred R/W post. Inslope road 50' after cattleguard.Prep subgrade to drain prior to placement of asphalt. Place asphalt in 2-2" lifts with tack coat between lifts. At drainage inlet and outlet key asphalt at a 3:1 slope to prevent undercutting into roadway.
0.028Construct and pave 14' wide X 100' long asphalt low water crossing. Inslope at 2%.Inslope road before and after low water crossing.Prep subgrade to drain prior to placement of asphalt. Place asphalt in 2-2" lifts with tack coat between lifts. At drainage inlet and outlet key asphalt at a 3:1 slope to prevent undercutting into roadway.Remove existing riprap at drainage prior to construction of Low Water Crossing. Place riprap at inlet and outlet edge of tapers.
0.197Construct and pave 14' wide X 75' long asphalt low water crossing. Outslope at 2%.Outslope road before and after low water crossing.Prep subgrade to drain prior to placement of asphalt. Place asphalt in 2-2" lifts with tack coat between lifts. At drainage inlet and outlet key asphalt at a 3:1 slope to prevent undercutting into roadway.Remove existing riprap at drainage prior to construction of Low Water Crossing. Place riprap at inlet and outlet edge of tapers.
0.903Construct and pave 14' wide X 75' long asphalt low water crossing. Outslope at 2%.Outslope road before and after low water crossing.Prep subgrade to drain prior to placement of asphalt. Place asphalt in 2-2" lifts with tack coat between lifts. At drainage inlet and outlet key asphalt at a 3:1 slope to prevent undercutting into roadway.Remove existing riprap at drainage prior to construction of Low Water Crossing. Place riprap at inlet and outlet edge of tapers.
2.102Construct and pave 14' wide X 75' long asphalt low water crossing. Outslope at 2%.Outslope road before and after low water crossing.Prep subgrade to drain prior to placement of asphalt. Place asphalt in 2-2" lifts with tack coat between lifts. At drainage inlet and outlet key asphalt at a 3:1 slope to prevent undercutting into roadway.Remove existing riprap at drainage prior to construction of Low Water Crossing. Place riprap at inlet and outlet edge of tapers.
2.260Construct and pave 14' wide X 50' long asphalt low water crossing. Outslope at 2%.Outslope road before and after low water crossing.Prep subgrade to drain prior to placement of asphalt. Place asphalt in 2-2" lifts with tack coat between lifts. At drainage inlet and outlet key asphalt at a 3:1 slope to prevent undercutting into roadway.Remove existing riprap at drainage prior to construction of Low Water Crossing. Place riprap at inlet and outlet edge of tapers.
2.670Construct and pave 14' wide X 100' long grade dip. Outslope at 2%.Outslope road before and after low water crossing.Prep subgrade to drain prior to placement of asphalt. Place asphalt in 2-2" lifts with tack coat between lifts. At drainage inlet and outlet key asphalt at a 3:1 slope to prevent undercutting into roadway.Remove existing riprap at drainage prior to construction of Low Water Crossing. Place riprap at inlet and outlet edge of tapers.
3.350Construct and pave 20' wide X 200' long grade dip. Outslope at 2%.Outslope road before and after low water crossing.Prep subgrade to drain prior to placement of asphalt. Place asphalt in 2-2" lifts with tack coat between lifts. At drainage inlet and outlet key asphalt at a 3:1 slope to prevent undercutting into roadway.Remove existing riprap at drainage prior to construction of Low Water Crossing. Place riprap at inlet and outlet edge of tapers.
3.450Construct and pave 20' wide X 200' long grade dip. Outslope at 2%.Outslope road before and after low water crossing.Prep subgrade to drain prior to placement of asphalt. Place asphalt in 2-2" lifts with tack coat between lifts. At drainage inlet and outlet key asphalt at a 3:1 slope to prevent undercutting into roadway.Remove existing riprap at drainage prior to construction of Low Water Crossing. Place riprap at inlet and outlet edge of tapers.
4.330Construct and pave 16' wide X 100' long grade dip. Outslope at 2%.Outslope road before and after low water crossing.Prep subgrade to drain prior to placement of asphalt. Place asphalt in 2-2" lifts with tack coat between lifts. At drainage inlet and outlet key asphalt at a 3:1 slope to prevent undercutting into roadway.Remove existing riprap at drainage prior to construction of Low Water Crossing. Place riprap at inlet and outlet edge of tapers.
4.640Construct and pave 16' wide X 100' long grade dip. Outslope at 2%.Outslope road before and after low water crossing.Prep subgrade to drain prior to placement of asphalt. Place asphalt in 2-2" lifts with tack coat between lifts. At drainage inlet and outlet key asphalt at a 3:1 slope to prevent undercutting into roadway.Remove existing riprap at drainage prior to construction of Low Water Crossing. Place riprap at inlet and outlet edge of tapers.
4.690Construct and pave 16' wide X 100' long grade dip. Outslope at 2%.Outslope road before and after low water crossing.Prep subgrade to drain prior to placement of asphalt. Place asphalt in 2-2" lifts with tack coat between lifts. At drainage inlet and outlet key asphalt at a 3:1 slope to prevent undercutting into roadway.Remove existing riprap at drainage prior to construction of Low Water Crossing. Place riprap at inlet and outlet edge of tapers.

Sheet2

Sheet3

File details come from the government source that posted it. Updated .