AG-82X9-S-17-0023.pdf
PDF 287 KB Posted
- Attached to
- Bessey Nursery Greenhouse 6 & 7
- Solicitation number
- AG-82X9-S-17-0023
About this file
Solicitation
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment_-_J.1..pdf | ||
| Attachment_-_J.2..pdf | ||
| Attachment_-_J.5..pdf | ||
| Attachment_-_J.3..pdf | ||
| Attachment_-_J.4..pdf | ||
| Synopsis.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION, OFFER,
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
PAGE OF PAGES
7. ISSUED BY CODE 8. ADDRESS OFFER TO
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO. 3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
CALL:
FOR
SEALED BID (IFB)
NEGOTIATED (RFP)
865649
USDA FOREST SERVICE
ROCKY MOUNTAIN REGIONAL OFFICE
1617 COLE BLVD
LAKEWOOD CO 80401
82X9
HOWARD REDDEN (303)275-5288
1x 07/12/2017
AG-82X9-S-17-0023
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
Project Title: Bessey Nursery Greenhouse 6 and 7.
Description: Work for this project consists of designing and constructing one, 30' x 96' clear span Quonset style greenhouse with twin wall polycarbonate sheeted roof and end walls (Greenhouse #6). Other greenhouse equipment/features include: an aggregate surfaced floor, exhaust fan and motor operated shutters, propane unit heaters, horizontal air flow fans, personnel and service doors, irrigation system and controls, lighting, outlets, and electrical and control circuits.
Subject to the Availability of Funds and other terms and conditions of this contract, one additional 30' x 96' greenhouse of the same design and with the same features may be constructed under this procurement (Greenhouse #7).
Location: This project is located at the Charles E. Bessey Nursery, located in
Thomas County, Nebraska, 16 miles east of Thedfore, Nebraska on Highway 2. The address is: 40637 River Loop, Halsey, NE 96142.
NAICS: 236220 - Commercial and Institutional Building Construction, 238220 -
Plumbing, Heating, and Air-Conditioning Contractors.
Continued ...
11. The Contractor shall begin performance
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and is not required.is, b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
d. Offers providing less than
12b. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in Item 12b.)
10 0 calendar days and complete it within ________________ ________________ calendar days after receiving
07/25/2017
NSN 7540-01-155-3212
x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________
STANDARD FORM 1442 (Rev. 4-85)
Prescribed by GSA
FAR(48 CFR) 53.236-1(d)
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than item 14.)
CODE FACILITY CODE
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
OFFER (Must be fully completed by offeror)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this document and return (Contractor is not required to sign this document.)
Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.
No further contractual document is necessary.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE
BY
2PAGE OF
USDA FOREST SERVICE
ROCKY MOUNTAIN REGIONAL OFFICE
1617 COLE BLVD
LAKEWOOD CO 80401
82X9
HOWARD D. REDDEN
28. NEGOTIATED AGREEMENT 29. AWARD
Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, copies to issuing office.)
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
STANDARD FORM 1442 (REV. 4-85) BACK
Continued...
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
3 56
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
AG-82X9-S-17-0023
NOTE: As per FAR 36.204 Disclosure of the
Magnitude of Construction Projects - The estimated range for this project is between
$100,000 - $250,000.
NNF&G - BN - Bessey Nursery Green Houses 6 & 7
Delivery: 07/21/2017
Delivery Location Code: 65NZ
DEPT OF AGRICULTURE FOREST SERVICE
BESSEY NURSERY
40637 RIVER LOOP
HALSEY NE 69142 US
FOB: Destination
Period of Performance: 08/01/2017 to 08/31/2018
001 NNF&G - BN - Bessey Nursery Green Houses 6 & 7
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
Bessey Nursery Greenhouse 6 & 7 AG-82X9-S-17-0023 Contract Solicitation Page 4 of 56
PART I – THE SCHEDULE
SECTION B – SUPPLIES OR SERVICES AND PRICES/COSTS
SCHEDULE OF ITEMS
Nebraska National Forest – Bessey Nursery Greenhouse 6 & 7 design/build -- Price should be
- total cost to the Government, including; salary, travel, per diem, equipment, supplies, reporting, computer use, publishing, photographs, telephone, fax, office services, and all other related expenses.
END OF SECTION B
Contract Solicitation Page 5 of 56
SECTION C - STATEMENT OF WORK
C.1. PURPOSE
Provide design/build construction of one, and possibly two greenhouses for the USDA Forest Service, Nebraska-Samuel R. McKelvie National Forest, Bessey Nursery.
The USDA Forest Service is seeking a collaborative solution for a project that consists of designing and constructing one, 30’ x 96’ clear span Quonset style greenhouse with twin wall polycarbonate sheeted roof and end walls (Greenhouse #6). Other greenhouse equipment/features include: an aggregate surfaced floor, exhaust fan and motor operated shutters, propane unit heaters, horizontal air flow fans, personnel and service doors., irrigation system and controls, lighting, outlets, and electrical and control circuits. Site work includes an aggregate surfaced equipment access, underground electrical service, emergency underground electrical service, propane tank and service, and non-potable water service (see Specifications, Summary of Work). All contract activities will occur in compliance with all applicable laws, regulations, and USDA Forest Service policies and procedures and in close coordination with the USDA Forest Service Contracting Officer’s Representatives.
The anticipated award resulting from this solicitation is the design/build of Greenhouse #6, at the Bessey Tree Nursery. Subject to the Availability of Funds, the contract may include the design/build of Greenhouse #7, and additional aggregate surfacing. Contractor is responsible for supplying all labor and equipment to complete the work.
Optional items may be awarded at the time of award of the base contract subject to funds availability and other terms and conditions of the contract. However, Optional Items may also be exercised up to 6 months after award of the Base Items. Contractor must guarantee pricing for 6 months after award of Base Items.
C.2. SITE DESCRIPTIONS AND LOCATIONS
This project is located at the Charles E. Bessey Nursery, located in Thomas County Nebraska, 12 miles east of Thedford, NE on Highway 2. The address is 40637 River Loop, Halsey, NE 96142. Driving instruction can be obtained from the nursery by calling (303) 533-2257.
C.3. PRE-BID MEETING
A pre-bid/pre-proposal site visit will be conducted in accordance with Section L.7. of this solicitation. Offeror may choose to visit the site at no cost or obligation to the Government on their own schedule. Proposal due date and deadline will not be extended to accommodate offeror-initiated site visit(s).
Contract Solicitation Page 6 of 56
An onsite, pre-work meeting will be held with the successful bidder during the course of contract implementation.
C.4. AGAR 452.211-72 Statement of Work/Specifications (FEB 1988)
The Contractor shall furnish the necessary personnel, material, equipment, services and facilities (except as otherwise specified), to perform the Statement of Work/Specifications referenced in Section J.
(End of Clause)
C.5. AGAR 452.211-73 Attachments to Statement of Work/Specifications (FEB 1988)
The attachments to the Statement of Work/Specifications listed in Section J.
are hereby made part of this solicitation and any resultant contract.
END OF SECTION C
Contract Solicitation Page 7 of 56
SECTION D – PACKAGING AND MARKING
D.1. AGAR 452.247-71 Marking Deliverables (FEB 1988)
(a) The contract number shall be placed on or adjacent to all exterior mailing or shipping labels of deliverable items called for by the contract.
(b) Mark deliverables, except reports, for:
I. Identifies the contract by number under which the item is being delivered.
II. Identifies the contract by project name (Bessey Nursery Greenhouse #6 and #7 Project).
III. Identifies the deliverable Item Number or Report Requirement which requires the delivered item(s).
IV. Indicates whether the Contractor considers the delivered item to be a partial or full satisfaction of the requirement.
D.2. AGAR 452.247-72 Packing for Domestic Shipment (FEB 1988)
(a) Material shall be packed for shipment in such a manner that will insure acceptance by common carriers and safe delivery at destination. Containers and closures shall comply with the Interstate Commerce Commission regulations, Uniform Freight Classification Rules, or regulations of other carriers as applicable to the mode of transportation.
END OF SECTION D
Contract Solicitation Page 8 of 56
SECTION E - INSPECTION AND ACCEPTANCE
E.1. FAR 52.246-12 Inspection of Construction. (AUG 1996)
(a) Definition. "Work" includes, but is not limited to, materials, workmanship, and manufacture and fabrication of components.
(b) The Contractor shall maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the contract conforms to contract requirements. The Contractor shall maintain complete inspection records and make them available to the Government.
All work shall be conducted under the general direction of the Contracting Officer and is subject to Government inspection and test at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract.
(c) Government inspections and tests are for the sole benefit of the Government and do not -
(1) Relieve the Contractor of responsibility for providing adequate quality control measures;
(2) Relieve the Contractor of responsibility for damage to or loss of the material before acceptance;
(3) Constitute or imply acceptance; or
(4) Affect the continuing rights of the Government after acceptance of the completed work under paragraph (i) of this section.
(d) The presence or absence of a Government inspector does not relieve the Contractor from any contract requirement, nor is the inspector authorized to change any term or condition of the specification without the Contracting Officer's written authorization.
(e) The Contractor shall promptly furnish, at no increase in contract price, all facilities, labor, and material reasonably needed for performing such safe and convenient inspections and tests as may be required by the Contracting Officer. The Government may charge to the Contractor any additional cost of inspection or test when work is not ready at the time specified by the Contractor for inspection or test, or when prior rejection makes re-inspection or retest necessary. The Government shall perform all inspections and tests in a manner that will not unnecessarily delay the work. Special, full-size, and performance tests shall be performed as described in the contract.
Contract Solicitation Page 9 of 56
(f) The Contractor shall, without charge, replace or correct work found by the Government not to conform to contract requirements, unless in the public interest the Government consents to accept the work with an appropriate adjustment in contract price. The Contractor shall promptly segregate and remove rejected material from the premises.
(g) If the Contractor does not promptly replace or correct rejected work, the Government may -
(1) By contract or otherwise, replace or correct the work and charge the cost to the Contractor; or
(2) Terminate for default the Contractor's right to proceed.
(h) If, before acceptance of the entire work, the Government decides to examine already completed work by removing it or tearing it out, the Contractor, on request, shall promptly furnish all necessary facilities, labor, and material. If the work is found to be defective or nonconforming in any material respect due to the fault of the Contractor or its subcontractors, the Contractor shall defray the expenses of the examination and of satisfactory reconstruction. However, if the work is found to meet contract requirements, the Contracting Officer shall make an equitable adjustment for the additional services involved in the examination and reconstruction, including, if completion of the work was thereby delayed, an extension of time.
(i) Unless otherwise specified in the contract, the Government shall accept, as promptly as practicable after completion and inspection, all work required by the contract or that portion of the work the Contracting Officer determines can be accepted separately. Acceptance shall be final and conclusive except for latent defects, fraud, gross mistakes amounting to fraud, or the Government's rights under any warranty or guarantee.
E.2. AGAR 452.246-70 INSPECTION AND ACCEPTANCE (FEB 1988)
(a) The Contracting Officer or the Contracting Officer’s duly authorized representative will inspect and accept the supplies and/or services to be provided under this contract.
(b) Inspection and acceptance will be performed at: Bessey Nursery Packing Shed, 40637 River Loop, Halsey, Nebraska 96142.
Contract Solicitation Page 10 of 56
Addendum to 452.246-70 – Formal acceptance or rejection of all work will be accomplished by the Contract Officer or Contracting Officer Representative upon completion of this project on a certified USDA Forest Service Form FS-6300-15 Certification of Final Inspection. After final payment has been received by the Contractor, the Contractor will certify by signing the USDAS Forest Service Form FS-6300-16 Contract Release, and provide the original to the Contracting Officer.
END OF SECTION E
Contract Solicitation Page 11 of 56
SECTION F - DELIVERIES OR PERFORMANCE
F.1. FAR 52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the Contractor receives the Notice to Proceed (FS-6300-8), (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than August 31, 2018. The time stated for completion shall include final cleanup of the premises.
Alternate I (Apr 1984). If the completion date is expressed as a specific calendar date, computed on the basis of the contractor receiving the notice to proceed by a certain day, add the following paragraph to the basic clause:
The completion date is based on the assumption that the successful offeror will receive the notice to proceed by August 1, 2017. The completion date will be extended by the number of calendar days after the above date that the Contractor receives the notice to proceed, except to the extent that the delay in issuance of the notice to proceed results from the failure of the Contractor to execute the contract and give the required performance and payment bonds within the time specified in the offer.
NOTE concerning FAR Clause 52.211-10:
(1) It is the Contractor’s due diligence to ensure this clause is in the contract when reviewing the Request for Quotation (RFQ) or Proposal (RFP) or Invitation for Bid (IFB), to ensure that a set start time and completion time are established in the contract.
(2) Should the clause not be written in the contract, then this note becomes effective and the Contractor shall commence work within 10 calendar days after the notice to proceed is issued, which shall not occur until the Government accepts in writing the bonds if they are required, and complete it by the delivery date listed on the SF 33, the form used for the contract.
(3) This note is not applicable to contracts that have FAR 52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984) in them.
* The Government recognizes that seasonal climatic conditions may occur that restrict or prohibit normal construction activities. The anticipated length of the seasonal delay for this project is 10 days. This number of days has
Contract Solicitation Page 12 of 56 been included in calculating the stated period of performance. Therefore, the contract period of performance will not be extended due to normal seasonal weather delays.
F.2. FAR 52.211-12 Liquidated Damages – Construction (SEP 2000)
(a) If the Contractor fails to complete the work within the time specified in this contract, the Contractor shall pay liquidated damages to the Government in the amount of $485.32 for each calendar day of delay until the work is completed or accepted.
(b) If the Government terminates the Contractor’s right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.
F.3. FAR 52.236-1 Performance of Work by the Contractor (APR 1984)
The Contractor shall perform on the site, and with its own organization, work equivalent to at least 15 percent of the total amount of work to be performed under the contract. This percentage may be reduced by a supplemental agreement to this contract if, during performing the work, the Contractor requests a reduction and the Contracting Officer determines that the reduction would be to the advantage of the Government.
F.4. AGAR 452.211-74 Period of Performance (FEB 1988)
The period of performance of this contract is from August 1, 2017 through August 31, 2018.
F.5. AGAR 452.236-75 Maximum Workweek--Construction Schedule. (NOV 1996)
Within 10 calendar days after receipt of a written request from the Contracting Officer, the Contractor must submit the following in writing for approval:
(a) A schedule as required by FAR clause 52.236-15, Schedules for Construction Contracts, and
(b) The hours (including the daily starting and stopping times) and days of the week the Contractor proposes to carry out the work.
The maximum workday that will be approved is 10 Hrs. per day.
Contract Solicitation Page 13 of 56
F.7. Reports and Plans
Unless otherwise specified, the Contractor shall electronically submit all Contract Data Requirements List Items (CDRL)(contract plans, reports, etc.)
in the specified format using Microsoft Office Excel, Word, PDF, or other specified software. If no format is specified, the Contractor may use its own format. Unless otherwise specified, all CDRL items shall be submitted to the Government via electronic submission (e-mail).
F.7.1. The Contractor shall provide all reports, plans, and submittals that are specified in this Section. The Contractor is accountable for assuring that reports contain accurate and complete data. The Contractor shall prepare written procedures describing the source of information as well as the specific steps followed in the collection and preparation of data for each report. All reports must be supported with sufficient documentation and audit trails. The reports shall be titled as listed. The Contractor shall submit a negative report if there is no data to report. Required reports are include in the Specifications at: Section J-1. Bessey Nursery Packing Shed Refrigeration System Replacement – Specifications.
END OF SECTION F
Contract Solicitation Page 14 of 56
SECTION G - CONTRACT ADMINISTRATION DATA
G.1. INVOICES:
G.1.1. Contractor shall be registered, and submit invoices through IPP (Invoice Processing Platform).
G.1.2. As provided by FAR 52.232-16 Progress Payments (APR 2012) incorporated into Section I., Progress Payments will be allowed no more frequent than monthly for a total of 12 payment in a calendar year.
G.2. AGAR 452.215-73 POST AWARD CONFERENCE (NOV 1996)
A Post Award Conference with the successful offeror is required. It will be scheduled within 10 days after the date of contract award. The Conference will be held at: Charles E. Bessey Nursery, 40637 River Loop, Halsey, Nebraska 96142 .
G.3. GOVERNMENT FURNISHED PROPERTY:
The Government may provide items of Government property to the Contractor for use in the performance of this contract. This property shall be used and maintained by the Contractor in accordance with the provisions of FAR 52.245-1 Government Property (AUG 2010).
G.5. FOREST SERVICE REPRSENTATIVES:
G.5.1. The Procuring Contracting Officer (PCO) is responsible for the administration of this contract and is solely authorized to take action on behalf of the Government. Unless specified otherwise within this contract, the PCO is referred to as the Contracting Officer. The Contracting Officer for this contract is:
HOWARD D. REDDEN, CONTRACT SPECIALIST
PHONE: 303-275-5288
FAX: 303-275-5453
EMAIL: hredden@fs.fed.us US Department of Agriculture Forest Service, Rocky Mountain Region 1617 Cole Boulevard, Bldg. 17 Lakewood, Colorado 80401-3305
G.5.2. The Contracting Officer Representative is responsible for the on-site administration of this contract. The delegated authority and responsibilities will be defined on a delegation letter issued after contract award. The Contracting Officer Representative for this contract is:
Contract Solicitation Page 15 of 56
PAUL G. LANS, PE
PHONE: 308-432-0303
FAX: 308-432-0309
EMAIL: plans@fs.fed.us US Department of Agriculture Nebraska Nation Forest & Grasslands 125 North Main Street Chadron, Nebraska 69337
Paul Lans and/or Howard Redden may designate up to four Inspectors on this contract. Delegated authority and responsibilities will be defined on a delegation letter issued after contract award. This delegation will also contain contact information.
END OF SECTION G
Contract Solicitation Page 16 of 56
SECTION H - SPECIAL CONTRACT REQUIREMENTS
H.1. Use of Premises and Utilities
(a) The Contractor shall comply with the regulations governing the operation of premises which are occupied and shall perform the contract in such a manner as not to interrupt or interfere with the conduct of Government business.
(b) The following use of utilities will be noted in the contract:
(1) Parking
(2) Electric
(3) Water
(End of Provision)
H.2. AGAR 452.228-71 Insurance Coverages (NOV 1996)
Pursuant to FAR 52.228-5, Insurance – Work on a Government Installation, the Contractor will be required to present evidence to show, as a minimum, the amounts of insurance coverage indicated below:
(a) Workers’ Compensation and Employer’s Liability. The Contractor is required to comply with applicable Federal and State workers’ compensation and occupational disease statutes. If occupational diseases are not compensable under those statutes, they shall be covered under the employer’s liability section of the insurance policy, except when contract operations are so commingled with a contractor’s commercial operations that it would not be practical to require this coverage. Employer’s liability coverage of at least $100,000 shall be required, except in States with exclusive or monopolistic funds that do not permit workers’ compensation to be written by private carriers.
(b) General Liability. The contractor shall be required to provide bodily injury liability insurance coverage written on the comprehensive form of policy of at least $500,000 per occurrence.
(c) Automobile Liability. The contractor shall be required to provide automobile liability insurance written on the comprehensive form of policy.
The policy shall provide for bodily injury and property damage liability covering the operation of all automobiles used in connection with performing the contract. Policies covering automobiles operated shall provide coverage of at least $200,000 per person and $500,000 per occurrence for bodily injury and $200,000 per occurrence for property damage or loss.
(d) Aircraft Public and Passenger Liability. When aircraft are used in connection with performing the contract, the Contractor shall have aircraft
Contract Solicitation Page 17 of 56 public and passenger liability insurance. Coverage shall be at least $200,000 per person and $500,000 per occurrence for bodily injury, other than passenger injury. Coverage for passenger injury shall be at least $200,00 multiplied by the number of seats or passengers, whichever is greater.
H.3. AGAR 452.236-77 Emergency Response (NOV 1996)
(a) Contractor’s Responsibility for Fire Fighting.
(1) The Contractor, under the provisions of FAR clause 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements, shall immediately extinguish all fires on the work site other than those fires in use as a part of the work.
(2) The Contractor may be held liable for all damages and for all costs incurred by the Government for labor, subsistence, equipment, supplies, and transportation deemed necessary to control or suppress a fire set or caused by the Contractor or the Contractor’s agents or employees.
(b) Contractor’s Responsibility for Notification in Case of Fire. The Contractor shall immediately notify the Government of any fires sighted on or in the vicinity of the work site.
(c) Contractor’s Responsibility for Responding to Emergencies. When directed by the Contracting Officer, the Contractor shall allow the Government to temporarily use employees and equipment from the work site for emergency work (anticipated to be restricted to fire-fighting). An equitable adjustment for the temporary use of employees and equipment will be made under the Changes Clause, FAR 52.243-4.
H.4. AGAR 452.237-74 Key Personnel (FEB 1988)
(a) The Contractor shall assign to this contract the following key personnel:
Overall Project Manager:________________________________________
Estimator:______________________________________________________
Inspection and Quality Control Personnel:_______________________
Contractual Point of Contact:___________________________________
(b) During the first 10 calendar days of performance, the Contractor shall make no substitutions of key personnel unless the substitution is necessitated by illness, death, or termination of employment. The Contractor shall notify the
Contract Solicitation Page 18 of 56
Contracting Officer within 15 calendar days after the occurrence of any of these events and provide the information required by paragraph (c) below. After the initial 10-day period, the Contractor shall submit the information required by paragraph (c) to the Contracting Officer at least 15 calendar days prior to making any permanent substitutions.
(c) The Contractor shall provide a detailed explanation of the circumstances necessitating the proposed substitutions, complete resumes for the proposed substitutes, and any additional information requested by the Contracting Officer. Proposed substitutes should have comparable qualifications to those of the persons being replaced. The Contracting Officer will notify the Contractor within 15 calendar days after receipt of all required information of the decision on substitutions. The contract will be modified to reflect any approved changes of key personnel.
H.5. Loss, Damage, or Destruction
(a) Equipment furnished with operator. The Government shall not be liable for loss, damage, or destruction of equipment furnished under this contract except for such loss, damage, or destruction resulting from the negligent or wrongful act(s) of Government employee(s) while acting within the scope of their employment.
All claims arising under this clause will be submitted to the Contracting Officer.
H.6. Conformity With Drawings and Specifications
Unless working tolerances are specified, all work performed and materials furnished shall be in reasonably close conformity with lines, grades, cross sections, dimensions, and material requirements shown on the drawings, indicated in the specifications, or designated on the ground. "Reasonably close conformity" is compliance with reasonable and customary manufacturing and construction tolerances.
H.7. Local Material Sources
(a) Designated Sources--Sources of local materials will be designated on the drawings. The Government assumes responsibility for the quality and quantity of material in the source. The Contractor shall determine the equipment and work required to produce the specified product.
The Contractor shall utilize all suitable material in the source. The designation of source will include the rights of the Contractor to use certain area(s) for plant site, stockpiles, and haul roads. Any Contractor royalty
Contract Solicitation Page 19 of 56 payment requirements will be stated below.
When materials are subject to weight measurement, the weight/volume relationship used for determination of designed quantities will be shown on the Drawings.
Should the designated source, due to causes beyond the control of the Contractor, contain insufficient suitable material, the Government will provide another source with an equitable adjustment in accordance with the Differing Site Conditions and Changes clauses.
(b) Contractor-Furnished Sources--When the material sources are not designated as provided above or the Contractor elects not to use designated sources, the Contractor shall be responsible for providing the specified product with no adjustment in contract price, unless weight/volume relationship differences between designated source material and Contractor-furnished source material result in financial disadvantage to the Government. Quality testing shall be the responsibility of the Contractor. Test results shall be furnished to the Contracting Officer.
H.8. Samples, Tests, Cited Specifications
Reference made in the contract to specifications, standards, or test methods adopted by AASHTO, ASTM, GSA, or other recognized National technical associations, shall mean specifications, standards, or test methods (including interim or tentative issues) which are in effect on the date of the solicitation.
H.9. Barricades, Warning Signs, and Other Devices
The Contractor shall provide, erect, and maintain all necessary barricades, suitable and sufficient lights, danger signals, signs, and other traffic control devices, and shall take all necessary precautions for the protection of the work and safety of the public. Roads closed to traffic shall be protected by effective barricades, and obstructions shall be illuminated during the hours of darkness. Suitable warning signs shall be provided to properly control and direct traffic.
The Contractor shall erect warning signs in advance to any place on the project where operations may interfere with the use of the road or trail by traffic and at all intermediate points where the new work crosses or coincides with an existing road or trail. All road barricades, warning signs, lights, temporary signals, flagmen and pilot car operators and equipment, and other protective devices, except for special devices, shall conform to Part VI of the Manual on Uniform Traffic Control Devices for Streets and Highways, published by the Federal Highway Administration and applicable safety codes.
Necessary warning signs and guards shall be posted during blasting operations to safeguard the public.
Contract Solicitation Page 20 of 56
H.10. Pre-work Conference
Pre-work Conference, or Pre-Construction Meetings, shall occur prior to the “Notice to Proceed” being issued for the contract. Prior to commencement of work, the Contractor will arrange a meeting with the Contracting Officer’s Representative or Contracting Officer to discuss the contract terms and work performance requirements. Also at this meeting such things as work progress schedule, and fire prevention and suppression plans shall be developed and established in writing.
H.11. Contractor Performance Information and Contractor Performance
Assessment Reporting System (CPARS) Evaluations
In accordance with (IAW) Federal Acquisition Regulation (FAR) at 48 CFR.1502 (Policy) and 42.1503 (Procedures, and Agriculture Acquisition Regulation (AGAR) 48 CFR 442.1502 the awarded Contractor shall be required to register in the civilian Contractor Performance Information and Contractor Performance Assessment Reporting System (CPARS) maintained by the Department of Defense (DoD) at: https://cpars.cpars.gov/cpars/app/home.do .
END OF SECTION H
Contract Solicitation Page 21 of 56
PART II – CONTRACT CLAUSES
SECTION I - CONTRACT CLAUSES
I.1. FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
Regulations URLs:
http://farsite.hill.af.mil/reghtml/regs/far2afmcfars/fardfars/far/far1toc.
htm, http://www.arnet.gov/far and the Agriculture Acquisition Regulation may be accessed at http://www.usda.gov/procurement/policy/agar.html
FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES
52.203-3 Gratuities (APR 1984) 52.203-5 Covenant Against Contingent Fees (MAY 2014) 52.203-7 Anti-Kickback Procedures (MAY 2014) 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity (MAY 2014) 52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (MAY 2014) 52.203-12 Limitation on Payments to Influence Certain Federal Transactions
(OCT 2010)
52.203.17 Contractor Employee Whistleblower Rights and Requirement to Inform Employees of Whistleblower Rights (APR 2014) 52.204-9 Personal Identity Verification of Contractor Personnel (JAN 2011) 52.209-6 Protecting the Government's Interest when Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (OCT 2015) 52.211-13 Time Extensions (SEP 2000) 52.211-18 Variation in Estimated Quantity (APR 1984) 52.215-2 Audit and Records - Negotiation (OCT 2010) 52.219-8 Utilization of Small Business Concerns (NOV 2016) 52.219-9 Small Business Subcontracting Plan (JAN 2017) 52.219-14 Limitations on Subcontracting (JAN 2017) 52.219-16 Liquidated Damages--Subcontracting Plan (JAN 1999) 52.219-28 Post-Award Small Business Program Rerepresentation (JUL 2013) 52.222-3 Convict Labor (JUN 2003) 52.222-4 Contract Work Hours and Safety Standards--Overtime Compensation (MAY 2014) 52.222-6 Construction Wage Rate Requirements (MAY 2014) 52.222-7 Withholding of Funds (MAY 2014) 52.222-8 Payrolls and Basic Records (MAY 2014) 52.222-9 Apprentices and Trainees (JUL 2005)
Contract Solicitation Page 22 of 56
52.222-10 Compliance with Copeland Act Requirements (FEB 1988) 52.222-11 Subcontracts (Labor Standards) (MAY 2014) 52.222-12 Contract Termination--Debarment (MAY 2014) 52.222-13 Compliance With Construction Wage Rate Requirements and Related Regulations (MAY 2014) 52.222-14 Disputes Concerning Labor Standards (FEB 1988) 52.222-15 Certification of Eligibility (MAY 2014) 52.222-21 Prohibition of Segregated Facilities (APR 2015) 52.222-26 Equal Opportunity (SEP 2016) 52.222-27 Affirmative Action Compliance Requirements for Construction (APR 2015) 52.222-37 Employment Reports on Veterans (FEB 2016) 52.222-40 Notification of Employee Rights Under the National Labor Relations Act (DEC 2010) 52.222-50 Combating Trafficking in Persons (MAR 2015) 52.222-54 Employment Eligibility Verification (OCT 2015) 52.223-2 Affirmative Procurement of Biobased Products Under Service and Construction Contracts (SEP 2013) 52.223-5 Pollution Prevention and Right-to-Know Information (MAY 2011) 52.223-6 Drug-Free Workplace (MAY 2001) 52.223-15 Energy Efficiency in Energy-Consuming Products (DEC 2007) 52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving
(AUG 2011)
52.224-1 Privacy Act Notification (APR 1984) 52.224-2 Privacy Act (APR 1984) 52.225-13 Restrictions on Certain Foreign Purchases (JUN 2008) 52.227-1 Authorization and Consent (DEC 2007) 52.227-4 Patent Indemnity – Construction Contracts (DEC 2007) 52.228-2 Additional Bond Security (OCT 1997) 52.228-5 Insurance--Work on a Government Installation (JAN 1997) 52.228-11 Pledges of Assets (JAN 2012) 52.228-12 Prospective Subcontractor Requests for Bonds (MAY 2014) 52.228-13 Alternative Payment Protections (JUL 2000) 52.228-14 Irrevocable Letter of Credit (NOV 2014) 52.228-15 Performance and Payment Bonds--Construction (OCT 2010) 52.229-3 Federal, State, and Local Taxes (FEB 2013) 52.229-4 Federal, State, and Local Taxes (State and Local Adjustments) (FEB 2013) 52.232-5 Payments Under Fixed-Price Construction Contracts (MAY 2014) 52.232-16 Progress Payments (APR 2012) 52.232-17 Interest (MAY 2014) 52.232-18 Availability of Funds (APR 1984) 52.232-23 Assignment of Claims (MAY 2014) 52.232-27 Prompt Payment for Construction Contracts (JAN 2017) 52.232-33 Payment by Electronic Funds Transfer—System for Award Management
(JUL 2013)
52.233-1 Disputes (MAY 2014) Alternate I (DEC 1991)
Contract Solicitation Page 23 of 56
52.233-2 Service of Protest (SEP 2006) 52.233-3 Protest After Award (AUG 1996) 52.233-4 Applicable Law for Breach of Contract Claim (OCT 2004) 52.236-2 Differing Site Conditions (APR 1984) 52.236-3 Site Investigation and Conditions Affecting the Work (APR 1984) 52.236-5 Material and Workmanship (APR 1984) 52.236-6 Superintendence by the Contractor (APR 1984) 52.236-7 Permits and Responsibilities (NOV 1991) 52.236-8 Other Contracts (APR 1984) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements (APR 1984) 52.236-10 Operations and Storage Areas (APR 1984) 52.236-11 Use and Possession Prior to Completion (APR 1984) 52.236-12 Cleaning Up (APR 1984) 52.236-13 Accident Prevention (NOV 1991) 52.236-14 Availability and Use of Utility Services (APR 1984) 52.236-15 Schedules for Construction Contracts (APR 1984) 52.236-17 Layout of Work (APR 1984) 52.236-21 Specifications and Drawings for Construction (FEB 1997) 52.236-26 Preconstruction Conference (FEB 1995) 52.242-13 Bankruptcy (JUL 1995) 52.242-14 Suspension of Work (APR 1984) 52.243-4 Changes (JUN 2007) 52.243-7 Notification of Changes (JAN 2017) 52.244-2 Subcontracts (OCT 2010) 52.244-6 Subcontracts for Commercial Items (JAN 2017) 52.245-1 Government Property (JAN 2017) 52.245-9 Use and Charges (APR 2012) 52.246-21 Warranty of Construction (MAR 1994) 52.249-10 Default (Fixed-Price Construction) (APR 1984) 52.253-1 Computer Generated Forms (JAN 1991)
AGRICULTURE ACQUISITION REGULATION (48 CFR CHAPTER 4) CLAUSES
452.224-70 Confidentiality of Information (FEB 1988) 452-236-71 Prohibition Against the Use of Lead Based-Paint (NOV 1996) 452.236-72 Use of Premises (NOV 1996) 452.236-73 Archeological or Historic Sites (FEB 1988) 452.236-74 Control of Erosion, Sedimentation, And Pollution (Nov 1996) 452.236-76 Samples and Certificates (FEB 1988)
I.2. FAR 52.216-24 Limitation of Government Liability (APR 1984)
(a) In performing this contract, the Contractor is not authorized to make expenditures or incur obligations exceeding _$60,000_ dollars.
Contract Solicitation Page 24 of 56
(b) The maximum amount for which the Government shall be liable if this contract is terminated is _$60,000_ dollars.
I.3. FAR 52.216-25 Contract Definitization (OCT 2010)
(a) A Firm-Fixed Price definitive contract is contemplated. The Contractor agrees to begin promptly negotiating with the Contracting Officer the terms of a definitive contract that will include (1) all clauses required by the Federal Acquisition Regulation (FAR) on the date of execution of the letter contract, (2) all clauses required by law on the date of execution of the definitive contract, and (3) any other mutually agreeable clauses, terms, and conditions.
The Contractor agrees to submit a fixed-price proposal, including data other than certified cost or pricing data, and certified cost or pricing data, in accordance with FAR 15.408, Table 15-2, supporting its proposal.
(b) The schedule for definitizing this contract is to receive proposals by July 25, 2017, evaluate them, and make award by August 1, 2017.
(c) If agreement on a definitive contract to supersede this letter contract is not reached by the target date in paragraph (b) of this section, or within any extension of it granted by the Contracting Officer, the Contracting Officer may, with the approval of the head of the contracting activity, determine a reasonable price or fee in accordance with Subpart 15.4 and Part 31 of the FAR, subject to Contractor appeal as provided in the Disputes clause. In any event, the Contractor shall proceed with completion of the contract, subject only to the Limitation of Government Liability clause.
(1) After the Contracting Officer’s determination of price or fee, the contract shall be governed by—
(i) All clauses required by the FAR on the date of execution of this letter contract for either fixed-price or cost reimbursement contracts, as determined by the Contracting Officer under this paragraph (c);
(ii) All clauses required by law as of the date of the Contracting
Officer’s determination; and
(iii) Any other clauses, terms, and conditions mutually agreed upon.
(2) To the extent consistent with paragraph (c)(1) of this section, all clauses, terms, and conditions included in this letter contracts shall continue in effect, except those that by their nature apply only to a letter contract.
(End of Clause
Contract Solicitation Page 25 of 56
I.4. FAR 52.222-35 Equal Opportunity for Veterans (OCT 2015)
(a) Definitions. As used in this clause— “Active duty wartime or campaign badge veteran,” “Armed Forces service medal veteran,” “disabled veteran,” “protected veteran,” “qualified disabled veteran,” and “recently separated veteran” have the meanings given at FAR 22.1301.
(b) Equal opportunity clause. The Contractor shall abide by the requirements of the equal opportunity clause at 41 CFR 60-300.5(a), as of March 24, 2014.
This clause prohibits discrimination against qualified protected veterans, and requires affirmative action by the Contractor to employ and advance in employment qualified protected veterans.
(c) Subcontracts. The Contractor shall insert the terms of this clause in subcontracts of $150,000 or more unless exempted by rules, regulations, or orders of the Secretary of Labor. The Contractor shall act as specified by the Director, Office of Federal Contract Compliance Programs, to enforce the terms, including action for noncompliance. Such necessary changes in language may be made as shall be appropriate to identify properly the parties and their undertakings.
I.5. FAR 52.222-36 Affirmative Action for Workers with Disabilities
(JUL 2014)
(a) Equal opportunity clause. The Contractor shall abide by the requirements of the equal opportunity clause at 41 CFR 60-741.5(a), as of March 24, 2014.
This clause prohibits discrimination against qualified individuals on the basis of disability, and requires affirmative action by the Contractor to employ and advance in employment qualified individuals with disabilities.
(b) Subcontracts. The Contractor shall include the terms of this clause in every subcontract or purchase order in excess of $15,000 unless exempted by rules, regulations, or orders of the Secretary, so that such provisions will be binding upon each subcontractor or vendor. The Contractor shall act as specified by the Director, Office of Federal Contract Compliance Programs of the U.S.
Department of Labor, to enforce the terms, including action for noncompliance.
Such necessary changes in language may be made as shall be appropriate to identify properly the parties and their undertakings.
I.6. FAR 52.225-9 Buy American —Construction Materials (MAY 2014)
(a) Definitions. As used in this clause—
Contract Solicitation Page 26 of 56
“Commercially available off-the-shelf (COTS) item”—
(1) Means any item of supply (including construction material) that is—
(i) A commercial item (as defined in paragraph (1) of the definition at FAR 2.101);
(ii) Sold in substantial quantities in the commercial marketplace;
and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.
“Component” means an article, material, or supply incorporated directly into a construction material.
“Construction material” means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.
“Cost of components” means—
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
“Domestic construction material” means—
Contract Solicitation Page 27 of 56
(1) An unmanufactured construction material mined or produced in the United States;
(2) A construction material manufactured in the United States, if—
(i) The cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which non-availability determinations have been made are treated as domestic; or
(ii) The construction material is a COTS item.
“Foreign construction material” means a construction material other than a domestic construction material.
“United States” means the 50 States, the District of Columbia, and outlying areas.
(b) Domestic preference.
(1) This clause implements 41 U.S.C. chapter 83, Buy America, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the component test of the Buy American statute is waived for construction material that is a COTS item. (See FAR 12.505(a)(2)).
The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.
(2) This requirement does not apply to information technology that is a commercial item or to the construction materials or components listed by the Government as follows:
“none”
(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that—
(i) The cost of domestic construction material would be unreasonable.
The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 6 percent;
(ii) The application of the restriction of the Buy American statute
Contract Solicitation Page 28 of 56 to a particular construction material would be impracticable or inconsistent with the public interest; or
(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.
(c) Request for…
This is the start of the file's text. The full file is on GovTribe.