SRD_PreSolicitation_Meeting_Questions.docx
DOCX document 13 KB Posted
- Attached to
- Road Maintenance
- Solicitation number
- AG-82X9-S-16-0010
About this file
Pre-Solicitation/Pre-Bid Meeting Q A
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amend_2.pdf | ||
| Drawings-Parent.pdf | ||
| WD_Grand_County_Hiway.txt | TXT text file | |
| Supplemental_Specs.pdf | ||
| B-M_AG-82X9-S-16-0010.docx | DOCX document | |
| AG-82X9-S-16-0010.pdf | ||
| Fire_Plan.pdf | ||
| SCA_Grand_County.txt | TXT text file | |
| Map-Parent.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SRD Road Work IDIQ – Pre-Solicitation Meeting Notes
· Is this a multi-award? No. It is a single award IDIQ. The solicitation will be updated.
· Only a D6 dozer is listed. In the event a D3 dozer is needed for a project, it may be added to the particular task order’s Schedule of Items and hourly price will be negotiated.
· Clarification on the due date: Friday May 27th? Is this long enough to include pre solicitation and solicitation timeline?
· Will weed control be added to the Schedule of Items? No.
· What are the specifications for buck-and-rail fence? A drawing will be added to the solicitation. Dead and down material onsite may be used for construction of the fence. The solicitation will be updated.
· Will the FS identify weed-free sources for material? Unfortunately, there are no weed free gravel pits. Please request “weed free” material from pits to get the cleanest material possible.
· Construction invoices may be submitted every 14 days.
· The Schedule of Items contains 15 pages to submit prices for base year and the possible four option years following.