Amend 02.doc
DOC document 77 KB Posted
- Attached to
- RFQ Current BLM Fuels Reduction IDIQ Contract Holders - Arbaney Mesa Fuels Reduction, Colorado
- Solicitation number
- AG-82X9-S-11-0182
About this file
Amendment TWO 3 pages
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amend 01.doc | DOC document | |
| unit30_map_contract_acres.pdf | ||
| Attach 3 - SCA 1976-1351 Rev 37 .doc | DOC document | |
| AG-82X9-S-11-0182Solicitation.doc | DOC document | |
| Arbaney Vicinity Map.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
| 1. CONTRACT ID CODE |
| PAGE OF PAGES |
| 1 |
| 3 |
| 2. AMENDMENT/MODIFICATION NO. |
| 3. EFFECTIVE DATE |
| 4. REQUISITION/PURCHASE REQ. NO. |
| 5. PROJECT NO. (If applicable) |
| Amendment TWO |
| 08/30/2011 |
| 6. ISSUED BY |
| CODE |
| 7. ADMINISTERED BY (If other than Item 6) |
| CODE |
USDA Forest Service
Southern Tier Contracting 2840 Kachina Dr Pueblo, Colorado 81008
| 8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State, and ZIP Code) |
| (X) |
| 9A. AMENDMENT OF SOLICITATION NO. |
FORMCHECKBOX
AG-82X9-S-11-0182
9B. DATED (SEE ITEM 11)
08/11/2011
FORMCHECKBOX
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
| CODE |
| FACILITY CODE |
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FORMCHECKBOX
The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of
Offers , is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
| (X) |
| A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN |
THE CONTRACT ORDER NO. IN ITEM 10A.
FORMCHECKBOX
FORMCHECKBOX
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
FORMCHECKBOX
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
FORMCHECKBOX
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor FORMCHECKBOX is not, FORMCHECKBOX is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.
Project: Arbaney Mesa Fuels Reduction - White River National Forest Purpose of this amendment is to document prebid meeting/site visit and incorporate changes.
No change in proposal due date of September 06, 2011, 4:00pm local time.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
| 15A. NAME AND TITLE OF SIGNER (Type or print) |
| 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print) |
Ida Marino Contract Specialist
| 15B. CONTRACTOR/OFFEROR |
| 15C. DATE SIGNED |
| 16B. UNITED STATES OF AMERICA |
| 16C. DATE SIGNED |
| /s/ Ida Marino |
| 08/30/2011 |
(Signature of person authorized to sign)
(Signature of Contracting Officer)
NSN 7540-01-152-8070
Previous edition unusable
| 30-105 |
| STANDARD FORM 30 (REV. 10-83) |
Prescribed by GSA
FAR (48 CFR) 53.243
Page 2/3
AMENDMENT TWO, SOLICITATION AG-82X9-S-11-0182
Arbaney Mesa FUELS REDUCTION – WHITE RIVER NATIONAL FOREST
A pre-bid meeting was held on August 24, 2011, @ 7:30am, followed by a field tour of each project area until 2:30pm. In attendance for the Forest Service were Jim Genung, Phil Nyland, and Toni Toelle.
Topics discussed:
The vegetation treatment units are primarily mixed mountain shrubs. The objective of the treatments at both areas is to remove some of this vegetation that is decadent, of poor form, and old, in order to facilitate regeneration. The contractor is required to clean his/her equipment before moving into work areas on NFS lands, as specified in the statement of work. A Forest Service representative will be present to inspect work and provide guidance to the contractor at each treatment area. Add-on 08/25/2011. See H.5 Noxious Weeds of contract package.
Work camps/spike camps are allowed on National Forest Lands.
The Arbaney Mesa project specs does not limit the type of equipment used to conduct the treatment; mastication and or hand thinning and scattering are acceptable as stated in the specifications. The specifications states no system roads are available for vehicle access, thus the Forest Service anticipates ground access will be by foot, and hand thinning and scattering will be the method used to conduct the treatment.
Questions and Answers:
Q. Can an ATV or other mechanical/motorized vehicle be used to access Arbaney Mesa?
A. The specifications state that walk-in access is available. The trail access crosses county and BLM jurisdiction and the FS has not secured vehicle access across those ownerships for this contract.
Q. Can the Forest Service pursue permission from the county and BLM for administrative access for motorized vehicles, in order to conduct the Arbaney Mesa treatment?
A. Walk in access is guaranteed. No permission for any other types of access has been granted.
Q. Can a bidder submit a quote for conducting the work at Arbaney if motorized access is given to facilitate use of mechanical equipment and another quote if motorized access is not available, thus requiring hand thinning and scattering?
A. In order to be considered responsive to this request for proposal, bidders shall submit price information and all other information as required by the terms of the contract and as stated. If an offeror chooses to submit a separate proposal using motorized access, this proposal will be considered as an alternate bid.
Q. Can the Arbaney Mesa work period be extended into 2013, if there are unforeseen delays or other factors? And what about reducing the stop periods for migratory birds to increase the period of work in summer 2012?
A. Refer to F.1 Period of Performance. Paragraphs one and two. The contract time is 365 calendar days, and takes in account weather and other unforeseen delays. All work shall be completed by October 31, 2012.
Q. Will FS representatives be available for on-site inspections?
A. Yes.
Page 3/3
AMENDMENT TWO, SOLICITATION AG-82X9-S-11-0182
Arbaney Mesa FUELS REDUCTION – WHITE RIVER NATIONAL FOREST
Q. Can equipment be secured on-site at Arbaney Mesa?
A. On NFS Lands. Refer to page 9, Security of Materials. As stated in the specs “the contractor may leave equipment at the work site. The Contractor is responsible for the contractor’s equipment if it should be lost, stolen or damaged.
NO CHANGES RESULT AS OF THIS AMENDMENT