Attach_03_Road_Mant_Speadsheets.pdf

PDF 102 KB Posted

Attached to
FY16 North San Isabel NF Road Maintenance
Solicitation number
AG-82BH-S-16-0020
Issued by

About this file

Attach 03 Road Mant Spreadsheets

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USDA FOREST SERVICE

PIKE & SAN ISABEL NF ROAD MAINTENANCE CONTRACT

LEADVILLE RANGER DISTRICT 2016

Road # Name ML BMP EMP Miles Termini Grader Dozer Pay Item Start Date Comments

ANNUAL ROUTINE MAINTENANCE

101.C Cooper Lane 2 0.00 2.61 2.61 LAK-29 - NFSR 102 X 850(01) June-Aug ML2 Dozer Work.

110 Halfmoon* 3 3.4 6.74 3.37 HYW 300 - Mt. Massive TH X 860(01) June-Aug ML3 Grader Work. Check Culverts. Clean if needed.

110 Halfmoon * 3 3.37 6.74 3.37 HWY 300 - Mt. Massive TH X 860(01) June-Aug ML3 Grader Work. Check Culverts. Clean if needed.

110 Halfmoon 2 6.74 12.7 5.96 Mt Massive TH - Private X 850(01) June-Aug ML2 Dozer Work.

122 Lilly Pond 2 0.0 2.5 2.5 NFSR 125 - End X 850(01) June-Aug ML2 Dozer Work.

170 Dexter Pt. Rec Area 3 0.2 0.54 0.34 HWY 82 - Edge of water X 860(01) June-Aug ML3 Grader Work. Check Culverts. Clean if needed.

170.A Sunnyside Fishing Ac. 3 0.0 0.40 0.40 NFSR 170 - Parking area X 860(01) June-Aug ML3 Grader Work. Check Culverts. Clean if needed.

170.B Dexter Pt. Boatramp 3 0.0 0.15 0.15 NFSR 170 - Parking X 860(01) June-Aug ML3 Grader Work. Check Culverts. Clean if needed.

171 Upper Lake Access 3 0.0 1.05 1.05 HWY 82 - deception point X 860(01) June-Aug ML3 Grader Work. Check Culverts. Clean if needed.

172 Whitestar CG 3 0.0 0.22 0.22 NFSR 171 - CG X 860(01) June-Aug ML3 Grader Work. Check Culverts. Clean if needed.

172.A Whitestar CG Loop 3 0.0 0.19 0.19 NFSR 172 - NFSR 172.AA X 860(01) June-Aug ML3 Grader Work. Check Culverts. Clean if needed.

390 Clear Creek** 3 3.6 11.85 8.3 US 24 - Wingate X 860(01) June-Aug ML3 Grader Work. Check Culverts. Clean if needed.

390 Clear Creek** 3 3.6 11.85 8.3 US 24 - Wingate X 860(01) June-Aug ML3 Grader Work. Check Culverts. Clean if needed.

398 Lost Canyon 3 3.3 7.2 3.93 Forest Boundary - surface change X 860(01) June-Aug ML3 Grader Work. Check Culverts. Clean if needed.

398 Lost Canyon 2 7.2 10.1 2.9 Surface change - End X 850(01) June-Aug ML2 Grader Work. Check Culverts. Clean if needed.

422 Sawmill Ridge 2 0.0 4.1 4.1 Forest Boundary - Pt. of closure X 850(01) June-Aug ML2 Dozer Work.

Total ML2 Miles 18.070 Total ML2 Miles Maintained by Grader 2.9 Total ML3 Miles 29.620 Total Miles Maintained 47.690

* Rd 110 - Maintain Twice: First Blading To Be Completed in June; Second Blading To Be Completed in August.

** Rd 390 - Maintain Twice: First Blading To Be Completed in June; Second Blading To Be Completed in August.

USDA FOREST SERVICE

PIKE & SAN ISABEL MAINTENANCE CONTRACT

SALIDA RANGER DISTRICT 2016

Road # Name ML BMP EMP Miles Termini Grader Dozer Pay Item Start Date Comments

ANNUAL ROUTINE MAINTENANCE

101 Bear Creek 2 3.14 5.62 2.48 Enter Forest - NFST 1336 X 850(01) June-Aug ML2 Dozer Work.

108 Methodist Mtn 2 2.00 3.65 1.65 Enter Forest - Gate X 850(01) June-Aug ML2 Dozer Work.

172 Willow Creek 2 0 1.9 1.9 NFSR 175 - Closure X 850(01) June-Aug ML2 Dozer Work.

181 Federal Quarry 2 0.00 3.63 3.63 CHA 175 - Gate X 850(01) June-Aug ML2 Dozer Work.

186 Bull Gulch 2 0.00 3.32 3.32 NFSR 187 - NFSR 186 X 850(01) June-Aug ML2 Grader Work. Check Culverts. Clean if needed.

188 Castle Rock Gulch 3 0.00 5.2 5.2 NFSR 187 - NFSR 187 X 860(01) June-Aug ML3 Grader Work. Check Culverts. Clean if needed.

214 Spruce Creek 2 0.00 4.97 4.97 CHA 210 - End X 850(01) June-Aug ML2 Dozer Work.

221 Green Creek 3 1.44 2.59 1.15 Enter Forest - Green Creek TH X 860(01) June-Aug ML3 Grader Work. Check Culverts. Clean if needed.

221 Green Creek 2 2.59 6.39 3.81 Green Creek TH - End X 850(01) June-Aug ML2 Dozer Work.

224 Lost Creek 3 0.74 1.31 0.58 US 50(enter Forest) - End X 860(01) June-Aug ML3 Grader Work. Check Culverts. Clean if needed.

225 Fooses Creek 3 0.74 2.8 2.06 Enter Forest - End ML3 X 860(01) June-Aug ML3 Grader Work. Check Culverts. Clean if needed.

225 Fooses Creek 2 2.80 5.27 2.47 Begin ML2 - Very steep slope X 850(01) June-Aug ML2 Dozer Work.

225.C Fooses Creek TH 2 0.00 0.14 0.14 NFSR 225 - Trailhead X 860(01) June-Aug ML2 Grader Work. Check Culverts. Clean if needed.

228 Taylor Mtn. 3 7.18 9.98 2.80 surf change - NFSR 224 X 860(01) June-Aug ML3 Grader Work. Check Culverts. Clean if needed.

231 Monarch Park CG 4 0.00 1.35 1.35 US 50 - Campground X 860(01) June-Aug ML3 Grader Work. Check Culverts. Clean if needed.

237 Old Monarch Pass 4 0.00 1.3 1.3 US 50 - Divide X 860(01) June-Aug ML3 Grader Work. Check Culverts. Clean if needed.

252 Blank's Cabin 3 0.00 3.18 3.18 NFSR 250 - NFST 1776 X 860(01) June-Aug ML3 Grader Work. Check Culverts. Clean if needed.

272 Brown's Creek 3 0.00 3.63 3.63 CHA 270 - Cattleguard X 860(01) June-Aug ML3 Grader Work. Check Culverts. Clean if needed.

272 Brown's Creek 2 3.63 6.7 3.07 Cattleguard - Gate X 850(01) June-Aug ML2 Grader Work. Check Culverts. Clean if needed.

292 Old Chalk Creek 3 0.00 2.41 2.41 CHA 162 - Begin ML2 X 860(01) June-Aug ML3 Grader Work. Check Culverts. Clean if needed.

292 Old Chalk Creek 3 4.88 5.77 0.69 Iron City CG - CHA 162 X 860(01) June-Aug ML3 Grader Work. Check Culverts. Clean if needed.

292 Old Chalk Creek 2 2.41 4.88 2.47 Begin ML2 - Iron City CG X 850(01) June-Aug ML2 Grader Work. Check Culverts. Clean if needed.

295 Hancock 3 0.00 5.45 5.45 CHA 162 - Hancock X 860(01) June-Aug ML3 Grader Work. Check Culverts. Clean if needed.

295 Hancock 2 5.45 6.97 1.52 Hancock - NFST 1422 X 850(01) June-Aug ML2 Grader Work. Check Culverts. Clean if needed.

297 Pomeroy Gulch 2 0.00 2.71 2.71 NFSR 295 - Junct NFST 1437 X 850(01) June-Aug ML2 Dozer Work.

305 McGee Gulch 3 0.00 2.78 2.78 US 24 - NFSR 376 X 860(01) June-Aug ML3 Grader Work. Check Culverts. Clean if needed.

309 Chubb Park 3 4.47 6.80 2.34 Begin FS Bndry - NFSR 436 X 860(01) June-Aug ML3 Grader Work. Check Culverts. Clean if needed.

311 Sevenmile Creek 3 0.00 5.80 5.80 Hwy 285 - Change ML X 860(01) June-Aug ML3 Grader Work. Check Culverts. Clean if needed.

315 Shields Gulch 3 0.00 2.59 2.59 Hwy 285 - NFSR 376 X 860(01) June-Aug ML3 Grader Work. Check Culverts. Clean if needed.

344 South Cottonwood 3 3.83 6.87 3.04 Cottonwood Lake CG - Greentimber TH X 860(01) June-Aug ML3 Grader Work. Check Culverts. Clean if needed.

375 Fourmile Creek 3 0.90 6.16 5.26 Begin FS Bndry - Surface Change X 860(01) June-Aug ML3 Grader Work. Check Culverts. Clean if needed.

376 Lenhardy Cutoff 3 5.945 6.96 1.02 NFSR 315 - NFSR 305 X 860(01) June-Aug ML3 Grader Work. Check Culverts. Clean if needed.

Total ML2 Miles = 34.15 Total ML2 miles maintained by Grader = 10.52 Total ML3 Miles = 52.63

Total Miles Maintained 86.78

Attach 03 Road Mant Speadsheet Leadville
Sheet1
Attach 03 Road Mant Speadsheet Salida
Sheet1

File details come from the government source that posted it. Updated .