SPS 619.pdf
PDF 17 KB Posted
- Attached to
- Williams Dam Restoration
- Solicitation number
- AG-82B1-S-10-0427
About this file
SPS 619
View the file
Other files
| File | Type | Posted |
|---|---|---|
| AG-82B1-S-10-0427 SF 1442.pdf | ||
| Experience Questionnaire.pdf | ||
| Construction Specifications.pdf | ||
| WilliamsDam-001.pdf | ||
| AG-82B1-S-10-0427 Body.pdf | ||
| GENERAL DECISION .pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SPECIAL PROJECT SPECIFICATION
619 Fences, Gates and Cattleguards:
Add the following
Fences
The fence location as shown on plan sheet #3 shall be staked by Forest Service.
The required corner panels and line braces shall not be measured separately but shall be considered incidental to the pay item 619 as listed in the schedule of items.
Gates
The pedestrian gates (2) location shown on plan sheet #3 shall be staked by Forest
Service. The contractor shall provide and install pedestrian gate as shown on plan sheet
#10. All costs for gate installation shall not be measured seperately but shall be considered incidental to the pay item 619 as listed in the schedule of items.
The wire bypass gate (1) as shown on sheets 3 and 10 of the plans shall have a Gate
Closure-Metal Gate closures shall be "Sure Shut" or approval equal. Gate Closure shall be approved by COR. Possible source for gate closure-B&B Fabrications, Grass Range, Montana
(406) 428-2355. No separate measurement shall be made and all costs for providing and installing shall be incidental to pay item 619 as listed in the schedule of items.
Cattle Guards
The existing cattleguard to be moved and the one (1) new cattleguard to be installed shall have the locations staked by the Forest Service.