Amen 3 - AG-82B1-S-10-0425.pdf

PDF 46 KB Posted

Attached to
RECOVERY Aquarius Asphalt, Clearwater National Forest, Idaho
Solicitation number
AG-82B1-S-10-0425
Issued by

About this file

SF30

View the file

Other files

File Type Posted
Amendment 3 - Wage Determination.pdf PDF
_ Amendment 3 Aquarius Asphalt.pdf PDF
Amend2_SF30.doc DOC document
Amend1_SF30.doc DOC document
sol_pkg.doc DOC document
WageDeterminationDB_ID100015.docx DOCX document
FSSS.docx DOCX document
Drawings_Aquarius Asphalt.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. CONTRACT ID CODE PAGE OF PAGES

AMENDMENT OF SOLICITATION OF CONTRACT 1 1

2. AMENDMENT NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable) Three (3)) 7/15/10 395779

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

USDA Forest Service

Intermountain EROC

740 Simms Street

Golden CO 80401

USDA Forest Service

Intermountain EROC

740 Simms Street

Golden CO 80401

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State, and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NO.

AG-82B1-S-10-0425

9B. DATED (SEE ITEM 11)

6/14/10

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

XX The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt offers _ _ is extended, _is not extended. Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing Items 8 and 15, and returning 0 copies of the amendment; (b)By acknowledging the receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE

RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

(�) A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify Authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.

RECOVERY: Aquarius & Road 247 Pavement Rehabilitation (Asphalt), North Fork Ranger District, Clearwater NF, is hereby amended as follows:

Clarifications attached

Replace Wage Determination with attached ID100015 07/02/2010 ID15, dated 7/2/10

Bid Date extended to July 26, 2010, 2:00 p.m. (mountain)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

RITA J. LOPER, CO

15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED

BY

(Signature of person authorized to sign) (Signature of Contracting Officer)

NSN 7540-01-152-8070 30-10 STANDARD FORM 30 (REV. 10-83)

PREVIOUS EDITION UNUSABLE Prescribed by GSA

FAR (48 CFR) 53.24

Amendment No. 3, RECOVERY: Aquarius & Road 247 Pavement Rehabilitation (Asphalt) Questions and Answers for Clarification

Q. SPS 414.06 Temperature Limitations, Is 35ºF-68ºF correct?

A. Yes, these are the correct temperatures. Most of the work is at higher elevations, in shaded areas.

Q. The Quantities on Sheets 3 through 6, do not match up with the quantities in the Schedule of Items. Is this a typo?

A. The quantities in Sheets 3 through 6 have been factored up for the Schedule to allow for some contingency in estimating. The quantities will be agreed upon before the work is accomplished and paid by AQ. See SPS 109.02.

Q. Schedule of Items, line 20310 and SPS 203 states to remove asphalt by SY, but Sheet 7 states to be removed by Equipment Rental, Which is correct?

A. Asphalt will be removed by SY. Any remaining aggregrate under the Asphalt Pavement will be removed by Equipment Rental.

Q. Does the FS have a designated waste site?

A. No, there is no designated waste site for asphalt removal or any other unsuitable material.

Q. Sheet 7 refers to SPS 202, Will SPS 202 be provided?

A. Correct Sheet 7, Note 8, pen and ink change 202 to 204.

Q. Work is to be complete by September 3, 2010?

A. Section F FAR 52.211-10, change September 3, 2010 to August 15, 2011. Add statement “ No work shall be performed between September 21, 2010 to July 11, 2011.

File details come from the government source that posted it. Updated .