sol_pkg.doc
DOC document 352 KB Posted
- Solicitation number
- AG-82B1-S-10-0400
About this file
Solicitation Package
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SF30Amend1.doc | DOC document | |
| BC_Sheets_27-36.pdf | ||
| Wage Determination ID100015.docx | DOCX document | |
| BC_Sheet_1.pdf | ||
| BC_Sheets_16-26.pdf | ||
| BC_Sheets_37-44.pdf | ||
| BC_Sheets_9-15.pdf | ||
| FSSS FP-03 BIG CREEK FINAL 4-26-10.pdf | ||
| OWNER_Client_Survey_form.docx | DOCX document | |
| BC_Sheets_2-8.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RECOVERY Road Reconstruction, Big Creek Road, Page 30
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
RFP AG-82B1-S-10-0400
2. TYPE OF SOLICITATION
FORMCHECKBOX
SEALED BID (IFB)
FORMCHECKBOX
NEGOTIATED (RFP)
3. DATE ISSUED
05/28/2010
PAGE OF PAGES
IMPORTANT - The “offer” section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
5. REQUISITION/PURCHASE REQUEST NO.
407622
6. PROJECT NO.
7. ISSUED BY
CODE
8. ADDRESS OFFER TO
USDA, Forest Service
Intermountain EROC
740 Simms Street
Golden CO 80401 USDA, Forest Service
Intermountain EROC
740 Simms Street
Golden CO 80401
9. FOR INFORMATION
CALL:
A. NAME
RITA J. LOPER, CO
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
(208) 765-7497
SOLICITATION
NOTE: In sealed bid solicitations “offer” and “offeror” mean “bid” and “bidder.”
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date):
RECOVERY: Road Reconstruction, Big Creek Road Coeur d Alene River Ranger District, Shoshone County, Idaho, Idaho Panhandle National Forest
Price Range is between $500,000 and $1,000,000 100 percent HUBZone SBC set-aside
11. The Contractor shall begin performance within 10 calendar days and complete by November 1, 2011 after receiving
FORMCHECKBOX
award, FORMCHECKBOX notice to proceed. This performance period is FORMCHECKBOX mandatory, FORMCHECKBOX negotiable. (See Section F clause 52.211-10)
12A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If “YES,” indicate within how many calendar days after award in Item 12B.)
FORMCHECKBOX
YES
FORMCHECKBOX
NO
12B. CALENDAR DAYS
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A.
Sealed offers in original and one copies to perform the work required are due at the place specified in Item 8 by 1630 (hour) local time June 28, 2010 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror’s name and address, the solicitation number, and the date and time offers are due.
B.
An offer guarantee
FORMCHECKBOX
is, FORMCHECKBOX is not required. (If “is required” see clause 52.228-1) C.
All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D.
Offers providing less than 30 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
NSN 7540-01-155-3212
1442-101
STANDARD FORM 1442 (REV. 4-85)
Computer Generated
Prescribed by GSA
FAR (48 CFR) 53.236-1(e)
OFFER (Must be fully completed by offeror)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)
15. TELEPHONE NO. (Include area code)
| Duns No. ____________________________ |
| 16. REMITTANCE ADDRESS (Include only if different than Item 14) |
CODE
17.
The offeror agrees to perform the work at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government within
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)
20B. SIGNATURE
20C. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT
23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
FORMCHECKBOX
10 U.S.C. 2304(c)( )
FORMCHECKBOX
41 U.S.C. 253(c)( )
26. ADMINISTERED BY
CODE
27. PAYMENT WILL BE MADE BY
USDA, Forest Service
Intermountain EROC
740 Simms Street
Golden CO 80401
USDA, National Finance Center
P.O. Box 60000
New Orleans, LA 70160-0001
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
FORMCHECKBOX
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return ____ copies to issuing office.) Contractor agrees to furnish and deliver all items or perform all work, requisitions identified on this form and any continuation sheets for the consideration slated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications or incorporated by reference in or attached to this contract.
FORMCHECKBOX
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)
31A. NAME OF CONTRACTING OFFICER (Type or print)
RITA J. LOPER
30B. SIGNATURE
30C. DATE
31B. UNITED STATES OF AMERICA
BY
31C. AWARD DATE
Computer Generated
STANDARD FORM 1442 BACK (REV. 4-85)
PART I—THE SCHEDULE
SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS
RECOVERY: Road Reconstruction, Big Creek Road Coeur d’Alene River Ranger District
Idaho Panhandle National Forests
Shoshone County, Idaho
B- 1 - SCHEDULE OF ITEMS
Base Item, Schedule A, (Big Creek Road)
ITEM
NO.
| DESCRIPTION |
| PAY |
UNIT
EST.
QTY.
UNIT
PRICE
TOTAL
PRICE
| 15101(A) |
| Mobilization |
| LS |
| 1 |
| $ |
| $ |
| 15722 |
| Straw Wattle |
| FT |
| 8127 |
| $ |
| $ |
| 15713 |
| Soil erosion and pollution control |
| LS |
| 1 |
| $ |
| $ |
| 20102 |
| Clearing and grubbing |
| LS |
| 1 |
| $ |
| $ |
| 20209 |
| Removal of individual trees |
| EA |
| 11 |
| $ |
| $ |
| 20301(A) |
| Removal of existing culvert |
| EA |
| 6 |
| $ |
| $ |
| 20420 |
| Drainage excavation, type drain dip |
| EA |
| 58 |
| $ |
| $ |
| 20431 |
| Roadway excavation |
| CY |
| 10870 |
| $ |
| $ |
| 20806(A) |
| Structure excavation (Ink Creek Culvert) |
| LS |
| 1 |
| $ |
| $ |
| 25101(A) |
| Placed riprap, class 4 |
| CY |
| 60 |
| $ |
| $ |
| 25101(B) |
| Placed riprap, class 5 (Ink Creek Culvert) |
| CY |
| 75 |
| $ |
| $ |
| 25101(C) |
| Placed riprap, class 6 |
| CY |
| 83 |
| $ |
| $ |
| 25117(A) |
| Rock weir (Ink Creek Culvert) |
| EA |
| 5 |
| $ |
| $ |
| 30191(A) |
| Surface course aggregate (Government Source) |
| TON |
| 5870 |
| $ |
| $ |
| 30304 |
| Road reconditioning, ditch |
| MI |
| 0.46 |
| $ |
| $ |
| 553A01(A) |
| Precast concrete member, footing (Ink Creek Culvert) |
| FT |
| 106 |
| $ |
| $ |
| 60201 |
| 18 inch pipe culvert |
| FT |
| 346 |
| $ |
| $ |
| 60202(A) |
| 57 inch span, 38 inch rise pipe arch culvert |
| FT |
| 66 |
| $ |
| $ |
| 60202(B) |
| 71 inch span, 47 inch rise pipe arch culvert |
| FT |
| 34 |
| $ |
| $ |
| 60212 |
| Open top box culvert |
| FT |
| 330 |
| $ |
| $ |
| 60304 |
| 12’-0” span x 5’-0” rise, structural plate arch, 0.111 inch (Ink Creek Culvert) |
| FT |
| 52 |
| $ |
| $ |
| 60708 |
| Cleaning culverts in place |
| EA |
| 3 |
| $ |
| $ |
| 62201(A) |
| Large dump truck |
| HR |
| 80 |
| $ |
| $ |
| 62201(B) |
| Hydraulic excavator with thumb |
| HR |
| 80 |
| $ |
| $ |
| 62505 |
| Seeding, hydraulic method |
| LS |
| 1 |
| $ |
| $ |
| 62512 |
| Mulching, hydraulic method |
| LS |
| 1 |
| $ |
| $ |
| 63301 |
| Sign System |
| EA |
| 3 |
| $ |
| $ |
| 63501 |
| Temporary traffic control |
| LS |
| 1 |
| $ |
| $ |
| 65102(A) |
| Pit and quarry development |
| LS |
| 1 |
| $ |
| $ |
TOTAL Base Item Schedule A
Base Item, Schedule B, (Big Creek Bridge)
ITEM
NO.
| DESCRIPTION |
| PAY |
UNIT
EST.
QTY.
UNIT
PRICE
TOTAL
PRICE
| 15101(B) |
| Mobilization |
| LS |
| 1 |
| $ |
| $ |
| 20301(B) |
| Removal of existing culvert |
| EA |
| 1 |
| $ |
| $ |
| 20806(B) |
| Structure excavation |
| LS |
| 1 |
| $ |
| $ |
| 25101(D) |
| Placed riprap, class 6 |
| CY |
| 134 |
| $ |
| $ |
| 27201 |
| Geocell abutment stabilization (6” depth) |
| LS |
| 1 |
| $ |
| $ |
| 30191(B) |
| Surface course aggregate (Government Source) |
| TON |
| 100 |
| $ |
| $ |
| 553A02 |
| Precast concrete member, wingwall |
| EA |
| 4 |
| $ |
| $ |
| 553A03 |
| Precast concrete member, grade beam |
| EA |
| 2 |
| $ |
| $ |
| 55301 |
| Precast, prestressed concrete structural member, trideck beam |
| EA |
| 3 |
| $ |
| $ |
| 63306 |
| Object markers, type III (wood post) |
| EA |
| 4 |
| $ |
| $ |
TOTAL Base Item Schedule B
Base Item, Schedule C, (Material Source Option)
ITEM
NO.
| DESCRIPTION |
| PAY |
UNIT
EST.
QTY.
UNIT
PRICE
TOTAL
PRICE
| 30191(C) |
| Surface course aggregate (Commercial Source) |
| TON |
| 5970 |
| $ |
| $ |
NOTE: The Government will award both Base Item Schedule A and Base Item Schedule B with exceptions as follows: Base Item Schedule C is an Option Item and may or may not be awarded. If Base Item Schedule C is awarded, the following base items contained in Schedule A and B will NOT be awarded.
· 30191(A) – SURFACE COURSE AGGREGATE (GOVERNMENT SOURCE)
· 65102(A) – PIT AND QUARRY DEVELOPMENT
· 30191(B) – SURFACE COURSE AGGREGATE (GOVERNMENT SOURCE)
OPTION Item, Schedule 1 (STA 130 + 91 Open Bottom Option)
ITEM
NO.
| DESCRIPTION |
| PAY |
UNIT
EST.
QTY.
UNIT
PRICE
TOTAL
PRICE
| 15101(C) |
| Mobilization |
| LS |
| 1 |
| $ |
| $ |
| 20806(C) |
| Structure excavation |
| LS |
| 1 |
| $ |
| $ |
| 25101(E) |
| Placed riprap, class 4 |
| CY |
| 38 |
| $ |
| $ |
| 25117(B) |
| Rock weir |
| EA |
| 3 |
| $ |
| $ |
| 553A01(B) |
| Precast concrete member, footing |
| FT |
| 50.5 |
| $ |
| $ |
| 60306 |
| 11’-11” span x 3’-7” rise corrugated aluminum box culvert with headwall and wingwalls |
| FT |
| 24.75 |
| $ |
| $ |
TOTAL Option Item Schedule 1
OPTION Item, Schedule 2 (STA 130 + 91 Culvert Option)
ITEM
NO.
| DESCRIPTION |
| PAY |
UNIT
EST.
QTY.
UNIT
PRICE
TOTAL
PRICE
| 15101(D) |
| Mobilization |
| LS |
| 1 |
| $ |
| $ |
| 25101(F) |
| Placed riprap, class 5 |
| CY |
| 25 |
| $ |
| $ |
| 60202(C) |
| 77 inch span, 52 inch rise pipe arch culvert |
| FT |
| 28 |
| $ |
| $ |
TOTAL Option Item Schedule 2
OPTION Item, Schedule 3 (STA 186 + 00 to 468 + 88 Surfacing Option)
ITEM
NO.
| DESCRIPTION |
| PAY |
UNIT
EST.
QTY.
UNIT
PRICE
TOTAL
PRICE
| 15101(E) |
| Mobilization |
| LS |
| 1 |
| $ |
| $ |
| 30191(D) |
| Surface course aggregate (Government Source) |
| TON |
| 9420 |
| $ |
| $ |
| 65102(B) |
| Pit and quarry development |
| LS |
| 1 |
| $ |
| $ |
TOTAL Option Item Schedule 3
OPTION Item, Schedule 4 (STA 186 + 00 to 468 + 88 Surfacing Option)
ITEM
NO.
| DESCRIPTION |
| PAY |
UNIT
EST.
QTY.
UNIT
PRICE
TOTAL
PRICE
| 15101(F) |
| Mobilization |
| LS |
| 1 |
| $ |
| $ |
| 30191(E) |
| Surface course aggregate (Commercial Source) |
| TON |
| 9420 |
| $ |
| $ |
TOTAL Option Item Schedule 4
NOTE: Option Item Schedule 3 and Option Item Schedule 4 may or may not be awarded. The Government may elect to award either Option Item Schedule 3 or Option Item Schedule 4, but not both. Option Items may be awarded based upon available funding.
NOTE: One award will be made based upon the best overall value to the Government. Proposals will be evaluated in accordance with Section L and M. Payment for bond premiums in accordance with Clause 52.232-5, Payments Under Fixed-Price Construction Contracts, shall not be in addition to the contract price. Include bond payments under 15101 Mobilization.
PART I - THE SCHEDULE
SECTION C - DESCRIPTION AND SPECIFICATIONS
C- 1 - PROJECT DESCRIPTION AND LOCATION
(a) Description of Work. The intent of this project is to reconstruct portions of Big Creek Roads 264 and 2354, resurface the road with crushed aggregate surfacing, and replace existing drainage structures with new structures that allow for Aquatic Organism Passage (AOP). This project includes road excavation, clearing and grubbing, removing and replacing pipe culverts, erosion control, pit and quarry development, aggregate crushing, placing and compacting crushed aggregate surfacing, bridge construction, structural steel plate arch construction, aluminum box culvert construction, temporary traffic control, permanent traffic control, and turf establishment.
(b) Project Location. Travel from Kellogg, Idaho on Interstate 90 East for approximately 3.3 miles to the Big Creek Exit. This is the beginning of the Big Creek Road. Take Forest Service Road 264 South for approximately 3.9 miles to the beginning of the project. The project extends for approximately 8.75 miles to the Lake Elsie Campground and is located in Townships 47 and 48 North, Sections 27, 34, 3, 4, 10, 11, and 12.
C-2 - "FHWA FP-03 STANDARD SPECIFICATIONS FOR CONSTRUCTION OF ROADS AND BRIDGES ON FEDERAL HIGHWAY PROJECTS” are included in this solicitation by reference only. The requirements contained in these Specifications are hereby made a part of this Solicitation and any resultant contract.
Copies of the "FHWA FP-03 STANDARD SPECIFICATIONS FOR CONSTRUCTION OF ROADS AND BRIDGES ON FEDERAL HIGHWAY PROJECTS" are available for download at the following URL:
http://www.wfl.fha.dot.gov/design/specs/fp03.htm.
The FP-03 U.S. Customary version is only available (for sale) through the Federal Lands Highway Headquarters office.
Headquarters Washington DC David K. Green Construction Standards Engineer Internet: david.green@fhwa.dot.gov Mail: Federal Highway Administration
HFPD-3
400 Seventh Street, SW Washington D.C. 20590 The following sections of “FHWA FP-03 STANDARD SPECIFICATIONS FOR CONSTRUCTION OF ROADS AND BRIDGES ON FEDERAL HIGHWAY PROJECTS” are included in this solicitation by reference only. The requirements contained in these Specifications are hereby made a part of this solicitation and any resultant contract.
The following Standard Specifications are applicable to this contract and are included by reference:
Spec No Title Section 101 – Terms, Format, and Definitions Section 102 – Bid, Award, and Execution of Contract
Section 103 – Scope of Work
Section 104 – Control of Work
Section 105 – Control of Material
Section 106 – Acceptance of Work
Section 107 – Legal Relations and Responsibility to the Public
Section 108 – Prosecution and Progress
Section 109 – Measurement and Payment
Section 151 – Mobilization
Section 152 – Construction Survey and Staking
Section 153 – Contractor Quality Control
Section 154 – Contractor Sampling and Testing
Section 155 – Schedules for Construction Contracts
Section 156 – Public Traffic
Section 157 – Soil Erosion Control
Section 201 – Clearing and Grubbing
Section 202 – Additional Clearing and Grubbing
Section 203 – Removal of Structures and Obstructions
Section 204 – Excavation and Embankment
Section 207 – Earthwork Geotextiles
Section 208 – Structure Excavation and Backfill for Selected Major Structures
Section 209 – Structure Excavation and Backfill
Section 251 – Riprap
Section 301 – Untreated Aggregate Courses
Section 303 – Road Reconditioning
Section 552 – Structural Concrete
Section 553 – Prestressed Concrete
Section 554 – Reinforcing Steel
Section 562 – Temporary Works
Section 602 – Culverts and Drains
Section 603 – Structural Plate Structures
Section 607 – Cleaning, Reconditioning, and Repairing Existing Drainage Structures
Section 622 – Rental Equipment
Section 625 – Turf Establishment
Section 633 – Permanent Traffic Control
Section 635 – Temporary Traffic Contol
Section 703 – Aggregate
Section 704 – Soil
Section 707 – Metal Pipe
Section 712 – Joint Material
Section 713 – Roadside Improvement Material
Section 714 – Geotextile and Geocomposite Drain
Section 717 – Structural Metal Material
Section 718 – Traffic Signing and Marking Material
Section 722 – Anchor Material
Section 725 – Miscellaneous Material
C- 3 - SUPPLEMENTAL SPECIFICATIONS. The following Supplemental Specifications are applicable to this contract and are physically included in this section:
Spec No Title
Page(s)
Preface
FSSS 101 – Terms, Format, and Definitions
FSSS 102 – Bid, Award, and Execution of Contract
FSSS 103 – Scope of Work
FSSS 104 – Control of Work
FSSS 105 – Control of Material
FSSS 106 – Acceptance of Work
FSSS 107 – Legal Relations and Responsibility to the Public
FSSS 108 – Prosecution and Progress
FSSS 109 – Measurement and Payment
FSSS 151 – Mobilization
FSSS 152 – Construction Survey and Staking
FSSS 153 – Contractor Quality Control
FSSS 155 – Schedules for Construction Contracts
FSSS 156 – Public Traffic
FSSS 157 – Soil Erosion Control
FSSS 201 – Clearing and Grubbing
FSSS 203 – Removal of Structures and Obstructions
FSSS 204 – Excavation and Embankment
FSSS 208 – Structure Excavation and Backfill for Selected Major Structures
FSSS 251 – Riprap
FSSS 272 – Geocell Abutment Stabilization
FSSS 301 – Untreated Aggregate Courses
FSSS 553 – Prestressed Concrete
FSSS 553A – Precast Concrete Structures
FSSS 602 – Culverts and Drains
FSSS 603 – Structural Plate Structures
FSSS 622 – Rental Equipment
FSSS 625 – Turf Establishment
FSSS 641 – Development of Pits and Quarries
FSSS 703 – Aggregate
FSSS 704 – Soil
FSSS 725 – Miscellaneous Material
FSSS 736 – Geocell
C-4 AGAR 452.211-72 Statement Of Work/Specifications (FEB 1988) The Contractor shall furnish the necessary personnel, material, equipment, services and facilities (except as otherwise specified), to perform the Statement of Work/Specifications referenced in Section J.
C-5 AGAR 452.211-73 Attachments To Statement Of Work/Specifications (FEB 1988) The attachments to the Statement of Work/Specifications listed in Section J are hereby made part of this solicitation and any resultant contract.
SECTION E--INSPECTION AND ACCEPTANCE
FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this address www.acquisition.gov/far
FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES
52.246-12 Inspection of Construction (AUG 1996)
SECTION F--DELIVERIES OR PERFORMANCE
FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998) This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.acquisition.gov/far/
FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES
52.242-14 Suspension of Work (APR 1984)
FAR 52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984) The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than November 1, 2011. The time stated for completion shall include final cleanup of the premises.
NOTE: It is estimated that the start work date will be August 1, 2010.
SECTION G--CONTRACT ADMINISTRATION DATA
G-1 AGAR 452.215-73 POST AWARD CONFERENCE (NOV 1996). A post award conference with the successful offeror is required. It will be scheduled and held before the Notice to Proceed is issued, after the date of contract award. The conference will be held at a location to be determined as agreed upon.
G-2 GOVERNMENT-FURNISHED PROPERTY
The Government will provide the following item(s) of Government property to the Contractor for use in the performance of this contract. This property shall be used and maintained by the Contractor in accordance with the provisions of the "Government Property" FAR clause contained elsewhere in the contract.
See Section 105 Control of Material for Government furnished material and sources.
PART I - THE SCHEDULE
SECTION H - SPECIAL CONTRACT REQUIREMENTS
H-1 FAR 52.236-4 Physical Data (APR 1984) Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor. (a) The indications of physical conditions on the drawings and in the specifications are the result of site investigations by visual observation.
Weather conditions typical for this area indicate the following normal work season and fire season:
Normal work season:
June through October
Restricted work season:
October through May
Normal fire season:
June through October
H-2
SUBMITTALS
Submittals shall include the following unless otherwise required in the specification:
1. Date and revision dates.
2. Project name and contract number.
3. Names of contractor, subcontractor, supplier and manufacturer.
4. Specifications section number.
5. Field dimensions and relation to adjacent structures.
6. Applicable standards such as ASTM or Federal Specifications.
7. Contractor’s stamp, initial or signature, certifying the review of submittal, verification of field measurements and compliance with contract documents.
Provide all submittals within 14 calendar days of contract award unless otherwise required by the specification.
The following submittals, shop drawings, material certifications and/or testing reports are required. (See Supplemental Spec 153 Contractor Quality Control)
| Title |
| Referenced by Contract clause |
or Specification No.
Time of Government Approval After Submittal
| Traffic Control Plan |
| Standard specifications |
| 7 days |
| Safety Plan, including Blasting Plan where applicable |
| Accident Prevention clause |
[FAR 52.236-13]
N/A
| Engineered Spill Prevention Plan |
| Landscape Preservation and Hazardous Materials see section H |
| 2 days |
| Proposed Progress Schedule |
| Schedules For Construction Contracts |
[FAR 52.236-15 and FP-03 Section 105] N/A
| Designation of Representative |
| Superintendence By The Contractor |
[FAR 52.236-6]
N/A
| Drug Free Workplace Policy |
| Drug-Free Workplace |
[FAR 52.223-6]
N/A
| SF1413 - Statement and Acknowledgement for each Subcontractor including Owner/Operators and other Sole Proprietorship Subcontractors [not required for material suppliers] |
| Subcontracts (Labor Standards) |
[FAR 52.222-11]
N/A
| Payroll Record WH347 Certified Payrolls submitted weekly |
| Payrolls And Basic Records |
[FAR 52.222-8]
N/A
| Erosion Control Plan |
| As required by Specifications |
| 7 days |
| Shop Drawings |
| As required by Specifications |
| 7 days |
| Product and Material Certifications and Literature |
| As required by Specifications |
| 7 days |
H-3 Reference FAR 52.236-13, Accident Prevention. Alt I.
SAFETY. Contractors shall comply with OSHA regulations and provide employees a work environment that is sanitary and not hazardous, which includes providing personal protective equipment. Contractors must maintain a health and safety plan and an accident prevention program, which includes frequent and regular inspections of the project site, materials and equipment. Contractors are responsible for risk management regarding contractor/employee and public safety, which include experience of operator to handle road and terrain conditions, getting to the worksite, traffic control and coordination with other users. Contractor shall submit written safety plan before Notice to Proceed is issued.
H-4 ENVIRONMENTAL MANAGEMENT SYSTEM (EMS)
Definition. An EMS provides a systematic approach for continually improving environmental performance and identifies the major environmental aspects and associated impacts that occur on a National Forest or Grassland. There are controls in place to manage these impacts, such as NEPA analysis, best management practices (BMPs), and resource monitoring. The EMS simply documents and ensures that these controls are in place and working as intended. EMS is an ongoing process that formalizes the Forest Service’s commitment to adaptive management and continual improvement of the environment.
Environmental Objectives:
1. Invasive Weeds – Reduce invasive weed introduction or spread through improved and more effective control and management.
2. Vegetation Management – 1) Restore or maintain vegetation health including the improvement or maintenance of resilient, native wildlife habitat and 2) Reduce fuels in a pattern and location to decrease fire intensity in the proximity of Wildland Urban Interface (WUI) or Community Wildfire Protection Plan areas.
3. Travel Management – 1) Reduce the existing road systems’ contributed sediment and impairment of water quality and aquatic habitats and 2) Improve security for grizzly bears or elk through the designation of roads, trails, and areas for motor vehicle use.
H-5 AGAR 452.237-74 KEY PERSONNEL (FEB 1988)
(a) - The Contractor shall assign to this contract the following key personnel:
· Project Manager
· Superintendent
· Quality Control Officer
(b) – During the first 90 days of performance, the Contractor shall make no substitution is necessitated by illness, death, or termination of employment. The Contractor shall notify the Contracting Officer within 15 calendar days after the occurrence of any of these events and provide the information required by paragraph (c) below. After the initial 90-day period, the Contractor shall submit the information required by paragraph (c) to the Contracting Officer at least 15 days prior to making any permanent substitutions
(c) – The Contractor shall provide a detailed explanation of the circumstances necessitating the proposed substitutions, complete resumes for the proposed substitutes, and any additional information requested by the Contracting Officer. Proposed substitutes should have comparable qualifications to those of the persons being replaced. The Contracting Officer will notify the Contractor within 15 calendar days after receipt of all required information of the decision on substitutions. The contract will be modified to reflect any approved changes of key personnel.
H-6
FIRE CONTROL
(a) - Contractor's Responsibility for Contractor-Caused Fires. The Contractor, whether or not directed by the Forest Service, shall immediately extinguish, without expense to the Government, all fires on or in the vicinity of the project which are caused by Contractor's employees, whether set directly or indirectly as a result of Contractor operations. The Contractor may be held liable for all damages and costs of additional labor, subsistence, equipment, supplies, and transportation resulting from fires set or caused by the Contractor's employees or resulting from contract operations.
(b) - Other Fires. For the purpose of fighting forest fires on or in the vicinity of the project which are not caused by the Contractor or his employees, the Contractor when requested by the Contracting Officer shall place his employees and equipment temporarily at the disposal of the Forest Service. Payment for such services will be made by the Government at not less than the current rate for fire-fighting services established by the Forest Service in the area concerned.
Any employees and equipment furnished will be relieved from fire fighting as soon as the Forest Service finds that it is practicable to employ other labor and equipment adequate for the protection of the area.
An equitable adjustment in contract time may be made for this period.
(c) - Fire Protection Requirements - Fire Plan. At all times during closed fire season period, as specified by State law, the Contractor shall comply with each of the following provisions to the extent applicable to his operation under the contract.
(1) - Fire Tools. The Contractor will provide for each employee in the contract area at least one approved handtool of a type appropriate in the contract area, such as shovel, pulaski, or ax. Tools required and furnished under (2) and (4) below, shall count toward fulfillment of the above requirement. Where additional tools, beyond those required under (2) and (4) below, are to be provided, the Contractor shall seal such tools in one or more boxes painted red and marked "Tools for Fire Only." All tools required herein shall be kept sharp and in good serviceable condition and maintained at locations to be designated by the Forest Service.
(2) - Fire Extinguishers and Tools on Mobile or Stationary Equipment. Each unit of powered equipment used in connection with this contract, including automobiles, trucks, tractors, etc., shall be equipped with serviceable tools and fire extinguishers as follows:
One - fire extinguisher, dry chemical type of not less than 2-1/2 pound capacity with 4 BC or higher rating.
One - shovel, round point #0 lady or equal.
One - ax, 2 pounds or over, 26-inch minimum length, or one pulaski.
One - water container (at least 1-gallon capacity), not required with stationary equipment.
(3) - Spark Arresters. Each internal combustion engine shall be provided with a spark arrester or spark arresting device approved by the Forest Service. Exceptions where the Forest Service may approve mufflers, or other equipment in lieu of spark arresters qualified and rated under Forest Service Standard 5100-1a are: (a) small multiposition engines, such as chain saws, shall meet Society of Automotive Engineers J335b standards; (b) passenger-carrying vehicles and light trucks may have baffle-type mufflers with tail pipe; (c) heavy-duty trucks may have a vertical stack exhaust system and muffler, provided the exhaust stack extends above the cab of the vehicle. An exhaust-driven turbocharger is considered to be a satisfactory spark arrester. Internal combustion engine exhaust systems, arresters, and other devices must be properly installed and maintained.
(4) - Powersaws. For each powersaw used in connection with this contract, the following will be provided:
One - shovel, round point #0 lady or equal. Shovel must be immediately available for use.
One - Fire extinguisher, containing not less than 8 ounces of extinguisher fluid, or a dry chemical powder-type of not less than 1-pound capacity. The extinguisher must be immediately accessible to the saw operator at all times.
Any fueling or refueling of a powersaw shall only be done in an area which has first been cleared or is free of all material capable of carrying fire; powersaw shall be moved at least 10 feet from place of fueling before starting.
(5) Blasting. Fuse or prima cord shall not be used unless authorized in writing by the COR with special precautions stated.
(6) - Smoking. Smoking shall not be permitted within the contract area except on surfaced or dirt roads, at landings, within closed vehicles, in camps, or at other posted places, and shall never be allowed while working or traveling on foot.
(7) - Storage of Petroleum and Other Highly Flammable Products. Gasoline, oil, grease, or other highly flammable material will be stored either in a separate building used exclusively for such storage, or at a site where all combustible debris and vegetation is cleared away within a radius of 25 feet. Fire extinguishers and/or sand barrels may be required at such locations specified by the Forest Service when unusually hazardous conditions exist.
(8) Debris Burning and Warming Fires. Burning permits will be required for all debris burning fires. Lunch and warming fires may be allowed in fireproofed areas during periods of low fire danger if and as specified in the fire plan. Such fires must not be left burning unattended.
(9) - Precautions for Stoves. Stovepipes on all temporary buildings, trailers, and tents using wood burning stoves, will be equipped with roof jacks and serviceable spark arresters of mesh with openings no larger than 5/8 inch.
All stovepipes, inside and out, will not be closer than 2 feet from any wood or other flammable material or 1 foot if the combustible material is protected by a metal or asbestos shield.
(10) - Welding. Welding or use of cutting torches will be permitted only in areas that have been cleared or are free of all material capable of carrying fire. Flammable debris and vegetation must be removed from within a minimum of 10 feet radius of all welding and cutting torch operations. A shovel and a 5-gallon standard backpack water container (filled) with handpump attached, shall be immediately available for use in the event of a fire start.
(11) - Fire Plan. Prior to initiating work on the contract area, during the closed fire season period, a fire prevention and suppression plan will usually be prepared. The Contractor and the Forest Service will jointly prepare this plan. Such plan shall include a detailed list of men and equipment at the Contractor's disposal for implementing the plan. The fire plan shall also specify additional measures and/or special requirements, such as Hoot Owl restrictions, necessary during periods of critical fire weather conditions.
When Hoot Owl restrictions are invoked, the Forest Service may curtail or shut down all or portions of a Contractor's operations. The following requirements may be imposed:
(i) All high fire risk operations could be terminated at 1300 local time.
(ii) All burning could be stopped, including debris burning fires.
(iii) Patrolman may be required for a period of 2 hours after high fire risk operations and 1 hour after end of work shift. The Contractor shall provide the patrolman unless the contract is for equipment rental, in which case the Government will provide the patrolman.
(12) - Pump and Trailer will generally be required when the Contracting Officer determines that fuel moisture and weather conditions warrant this additional protective measure. The Contractor shall provide at a location satisfactory to the Contracting Officer, a serviceable truck or trailer, equipped with a fire fighting tanker unit to be kept ready for instant use for suppressing forest fires. The unit shall consist of a tank of not less than 100-gallon capacity upon which shall be mounted a live hose reel or live hose basket with 250 feet of at least 3/4-inch I.D. heavy-duty rubber hose; a portable or power takeoff pump with discharge capacity of at least 10 gallons per minute at 150 P.S.I. pressure. Gear type pumps shall be provided with a bypass or pressure relief valve so that the hose nozzle may be shut while the pump is operating. Each tanker unit shall have a hose nozzle of the shut-off type, adjustable for straight stream, spray or fog, at least 12 feet of 1-inch suction hose with an intake screen, an additional 250 feet of 3/4-inch heavy-duty rubber hose or 1-inch cotton jacket rubber-lined or linen hose to be carried on the unit for use as needed. Tools, adapters, accessories and fuel necessary to operate the pump and truck or trailer shall be provided. If a trailer is used, a serviceable vehicle with the proper trailer tow hitch shall be located at a point satisfactory to the Contracting Officer. Where water is available, a supply sufficient for rapidly filling the water tank shall be provided at one or more accessible points along or adjacent to the main truck roads.
(13) - Burning. Before starting any open burning, the Contractor shall comply with the following:
(i) Submit a burning plan, subject to approval by the Contracting Officer, designed to minimize the impact on air quality and to lessen any fire damage.
(ii) Obtain a burning permit from the District Ranger.
(iii) Use weather forecasts as far as possible in scheduling burning for more favorable dispersal of smoke.
(iv) Fuel shall be reasonably free of dirt and piled to facilitate rapid and complete combustion. Piles shall be tended during burning operations to maintain combustion and to eliminate unnecessary smudges. Piles shall be patrolled during off-work hours to avoid wildfires.
(v) Unless fire season controls dictate otherwise, burning shall be scheduled, as far as practicable, for the most favorable conditions during the burning period.
(vi) Under certain atmospheric conditions, smoke accumulations may become excessive and in these cases, the Regional Forester may, at his discretion, prohibit all open burning for definite periods within specific areas of the National Forest.
H.7 - Incidental Payment Items
The intent of the contract is to provide for the complete construction of the project described in the contract. Unless otherwise provided, the Contractor shall furnish all labor, materials, equipment, tools, transportation, and supplies and perform all work required to complete the project in accordance with drawings, specifications, and provisions of the contract. Payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work and materials will be considered as incidental to and included in the payment for items shown.
H.8 - Conformity With Drawings and Specifications
Unless working tolerances are specified, all work performed and materials furnished shall be in reasonably close conformity with lines, grades, cross sections, dimensions, and material requirements shown on the drawings, indicated in the specifications, or designated on the ground. "Reasonably close conformity" is compliance with reasonable and customary manufacturing and construction tolerances.
H.9 - Barricades, Warning Signs, and Other Devices
The Contractor shall provide, erect, and maintain all necessary barricades, suitable and sufficient lights, danger signals, signs, and other traffic control devices, and shall take all necessary precautions for the protection of the work and safety of the public. Roads closed to traffic shall be protected by effective barricades, and obstructions shall be illuminated during the hours of darkness. Suitable warning signs shall be provided to properly control and direct traffic.
The Contractor shall erect warning signs in advance to any place on the project where operations may interfere with the use of the road or trail by traffic and at all intermediate points where the new work crosses or coincides with an existing road or trail. All road barricades, warning signs, lights, temporary signals, flagmen and pilot car operators and equipment, and other protective devices, except for special devices, shall conform to Part VI of the Manual on Uniform Traffic Control Devices for Streets and Highways, published by the Federal Highway Administration and applicable safety codes. Necessary warning signs and guards shall be posted during blasting operations to safeguard the public.
H.10 - Subcontract Data
The Contractor shall submit an executed Statement and Acknowledgment Standard Form 1413, to the Contracting Officer for every subcontractor (including every subcontractor of the second or lower tier) that will be performing work at the construction site. This shall be submitted before the subcontractor begins work. This form provides an acknowledgment by the subcontractor that mandatory "flowdown" contract clauses have been included in their contract in accordance with FAR Clause 52.222-11. Completing this form creates no contractual relationship between subcontractors and the Government.
H-11 Landscape Preservation
(a) The Contractor shall confine operations to within the clearing limits or other areas designated in contract documents, and prevent the depositing of rocks, excavated materials, stumps, or other debris outside of these limits. Material, which falls outside of these limits, shall be retrieved, disposed of, or incorporated in the work as directed by the Contracting Officer.
(b) Operation shall be scheduled and conducted to minimize erosion of soils and to prevent silting and muddying of streams, rivers, irrigation systems, and impoundments (lakes, reservoirs, etc.).
Pollutants such as fuels, lubricants, bitumens, raw sewage, and other harmful materials shall not be discharged into or near rivers, streams, and impoundments or into natural or manmade channels leading thereto. Wash water or waste water from concrete or aggregate operations shall not be allowed to enter live streams prior to treatment by filtration, settling, or other means sufficient to reduce the sediment content to not more than that of the stream into which it is discharged.
Mechanized equipment shall not be operated in live streams without written approval by the Contracting Officer.
PART II - CONTRACT CLAUSES
SECTION I - CONTRACT CLAUSES
I- 1 FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998) This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this address: www.acquisition.gov/far
FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES
52.202-1 Definitions (JULY 2004)
52.203-3 Gratuities (APR 1984)
52.203-5 Covenant Against Contingent Fees (APR 1984)
52.203-6 Restrictions on Subcontractor Sales to the Government (SEPT 2006)
52.203-7 Anti-Kickback Procedures (JUL 1995)
52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity (JAN 1997)
52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (JAN 1997)
52.203-12 Limitation on Payments to Influence Certain Federal Transactions (SEPT 2007)
52.204-4 Printed or Copied Double-Sided on Recycled Paper (AUG 2000) 52.209-6 Protecting the Government's Interest when Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (SEPT 2006)
52.211-18 Variation in Estimated Quantity (APR 1984) 52.215-3 Notice of Total HUBZone Set-Aside (JAN 1999) 52.219-8 Utilization of Small Business Concerns (MAY 2004) 52.219-14 Limitations on Subcontracting (DEC 1996) 52.219-28 Post Award Small Business Program Representation (JUNE 2007) 52.222-3 Convict Labor (JUNE 2003)
52.222-4 Contract Work Hours and Safety Standards Act--Overtime Compensation (JULY 2005)
52.222-5 Davis-Bacon Act – Secondary Site of Work (JULY 2005) 52.222-6 Davis-Bacon Act (JULY 2005)
52.222-7 Withholding of Funds (FEB 1988)
52.222-8 Payrolls and Basic Records (JAN 2010)
52.222-9 Apprentices and Trainees (JULY 2005)
52.222-10 Compliance with Copeland Act Requirements (FEB 1988)
52.222-11 Subcontracts (Labor Standards) (JULY 2005) 52.222-12 Contract Termination - Debarment (FEB 1988)
52.222-13 Compliance with Davis-Bacon and Related Act Regulations (FEB 1988)
52.222-14 Disputes Concerning Labor Standards (FEB 1988)
52.222-15 Certification of Eligibility (FEB 1988)
52.222-21 Prohibition of Segregated Facilities (FEB 1999)
52.222-26 Equal Opportunity (MAR 2007)
52.222-27 Affirmative Action Compliance Requirements for Construction (FEB 1999)
52.222-35 Equal Opportunity for Special Disabled Veterans, Veterans of the Vietnam Era, and Other Eligible Veterans (SEPT 2006)
52.222-36 Affirmative Action for Workers with Disabilities (JUNE 1998)
52.222-37 Employment Reports on Special Disabled Veterans, Veterans of the Vietnam Era, and Other Eligible Veterans (SEPT 2006)
52.222-50 Combating Trafficking in Persons (FEB 2009)
52.222-54 Employment Eligibility Verification (JAN 2009) 52.223-2 Affirmative Procurement of Biobased Products Under Service and Construction Contracts (DEC 2007)
52.223-6 Drug-Free Workplace (MAY 2001) 52.223-14 Toxic Chemical Release Reporting (AUG 2003) 52.225-13 Restrictions on Certain Foreign Purchases (JUN 2008) 52.227-1 Authorization and Consent (DEC 2007) 52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement (DEC 2007) 52.227-4 Patent Indemnity--Construction Contracts (DEC 2007)
52.228-2 Additional Bond Security (OCT 1997) 52.228-11 Pledges of Assets (SEP 2009)
52.228-12 Prospective Subcontractor Requests for Bonds (OCT 1995)
52.228-14 Irrevocable Letter of Credit (DEC 1999)
52.229-3 Federal, State, and Local Taxes (APR 2003)
52.232-5 Payments Under Fixed-Price Construction Contracts (SEPT 2002)
52.232-17 Interest (OCT 2008)
52.232-18 Availability of Funds (APR 1984) 52.232-23 Assignment of Claims (JAN 1986)
52.232-27 Prompt Payment for Construction Contracts (OCT 2008)
52.232-33 Payment by Electronic Funds Transfer--Central Contractor Registration (OCT 2003)
52.233-1 Disputes (JULY 2002) Alternate I (DEC 1991)
52.233-3 Protest After Award (AUG 1996)
52.233-4 Applicable Law for Breach of Contract Claim (OCT 2004)
52.236-2 Differing Site Conditions (APR 1984)
52.236-3 Site Investigation and Conditions Affecting the Work (APR 1984)
52.236-5 Material and Workmanship (APR 1984)
52.236-6 Superintendence by the Contractor (APR 1984)
52.236-7 Permits and Responsibilities (NOV 1991)
52.236-8 Other Contracts (APR 1984)
52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements
(APR 1984)
52.236-10 Operations and Storage Areas (APR 1984) 52.236-11 Use and Possession Prior to Completion (APR 1984) 52.236-12 Cleaning Up (APR 1984) 52.236-13 Accident Prevention (NOV 1991) 52.236-15 Schedules for Construction Contracts (APR 1984)
52.236-17 Layout of Work (APR 1984)
52.236-21 Specifications and Drawings for Construction (FEB 1997) ALT II (APR 1984) 52.236-26 Preconstruction Conference (FEB 1995)
52.242-13 Bankruptcy (JULY 1995)
52.243-4 Changes (JUNE 2007)
52.244-5 Competition in Subcontracting (DEC 1996) 52.245-1 Government Property (JUNE 2007)
52.245-9 Use and Charges (JUNE 2007) 52.246-21 Warranty of Construction (MAR 1994) 52.248-3 Value Engineering--Construction (SEPT 2006)
52.249-2 Termination for Convenience of the Government (Fixed-Price) (MAY 2004) Alternate I (SEPT 1996)
52.249-10 Default (Fixed-Price Construction) (APR 1984)
52.252-1 Solicitation Provisions Incorporated by Reference (FEB 1998) 52.252-6 Authorized Deviations in Clauses (APR 1984) 52.253-1 Computer Generated Forms (JAN 1991)
AGRICULTURE ACQUISITION REGULATION (48 CFR CHAPTER 4) CLAUSES
452.232-70 Reimbursement for Bond Premiums – Fixed-Price Construction Contracts (NOV 1996)
452.236-71 Prohibition Against the Use of Lead-Paint (NOV 1996)
452.236-72 Use of Premises (NOV 1996)
452.236-73 Archeological or Historic Sites (FEB 1988)
452.236-74 Control of Erosion, Sedimentation and Pollution (NOV 1996)
452.236-76 Samples and Certificates (FEB 1988)
452.236-77 Emergency Response (NOV 1996)
I-2 FAR 52.203-15 Whistleblower Protections Under the American Recovery and Reinvestment Act of 2009. (Mar 2009)
(a) The Contractor shall post notice of employees rights and remedies for whistleblower protections provided under section 1553 of the American Recovery and Reinvestment Act of 2009 (Pub. L. 111-5).
(b) The Contractor shall include the substance of this clause including this paragraph (b) in all subcontracts.
I- 3 FAR 52.204-7 Central Contractor Registration (APR 2008)
(a) Definitions. As used in this clause-
"Central Contractor Registration (CCR) database" means the primary Government repository for Contractor information required for the conduct of business with the Government.
"Data Universal Numbering System (DUNS) number" means the 9-digit number assigned by Dun and Bradstreet, Inc. (D&B) to identify unique business entities.
"Data Universal Numbering System +4 (DUNS+4) number" means the DUNS number assigned by D&B plus a 4-character suffix that may be assigned by a business concern. (D&B has no affiliation with this 4-character suffix.) This 4-character suffix may be assigned at the discretion of the business concern to establish additional CCR records for identifying alternative Electronic Funds Transfer (EFT) accounts (see the FAR at Subpart 32.11) for the same concern.
"Registered in the CCR database" means that-
(1) The Contractor has entered all mandatory information, including the DUNS number or the DUNS+4 number, into the CCR database; and
(2) The Government has validated all mandatory data fields, to include validation of the Taxpayer Identification Number (TIN) with the Internal Revenue Service (IRS), and has marked the record “Active”. The Contractor will be required to provide consent for TIN validation to the Government as a part of the CCR registration process.
(b)
(1) By submission of an offer, the offeror acknowledges the requirement that a prospective awardee shall be registered in the CCR database prior to award, during performance, and through final payment of any contract, basic agreement, basic ordering agreement, or blanket purchasing agreement resulting from this solicitation.
(2) The offeror shall enter, in the block with its name and address on the cover page of its offer, the annotation "DUNS" or "DUNS +4" followed by the DUNS or DUNS +4 number that identifies the offeror's name and address exactly as stated in the offer. The DUNS number will be used by the Contracting Officer to verify that the offeror is registered in the CCR database.
(c) If the offeror does not have a DUNS number, it should contact Dun and Bradstreet directly to obtain one.
(1) An offeror may obtain a DUNS number-
(i) Via the Internet at http://fedgov.dnb.com/webform or if the offeror does not have internet access, it may call Dun and Bradstreet at 1-866-705-5711 if located within the United States; or
(ii) If located outside the United States, by contacting the local Dun and Bradstreet office. The offeror should indicate that it is an offeror for a U.S. Government contract when contacting the local Dun and Bradstreet office.
(2) The offeror should be prepared to provide the following information:
(i) Company legal business.
(ii) Tradestyle, doing business, or other name by which your entity is commonly recognized.
(iii) Company Physical Street Address, City, State, and Zip Code.
(iv) Company Mailing Address, City, State and Zip Code (if separate from physical).
(v) Company Telephone Number.
(vi) Date the company was started.
(vii) Number of employees at your location.
(viii) Chief executive officer/key manager.
(ix) Line of business (industry).
(x) Company Headquarters name and address (reporting relationship within your entity).
(d) If the Offeror does not become registered in the CCR database in the time prescribed by the Contracting Officer, the Contracting Officer will proceed to award to the next otherwise successful registered Offeror.
(e) Processing time, which normally takes 48 hours, should be taken into consideration when registering. Offerors who are not registered should consider applying for registration immediately upon receipt of this solicitation.
(f) The Contractor is responsible for the accuracy and completeness of the data within the CCR database, and for any liability resulting from the Government's reliance on inaccurate or incomplete data. To remain registered in the CCR database after the initial registration, the Contractor is required to review and update on an annual basis from the date of initial registration or subsequent updates its information in the CCR database to ensure it is current, accurate and complete. Updating information in the CCR does not alter the terms and conditions of this contract and is not a substitute for a properly executed contractual document.
(g) (1)
(i) If a Contractor has legally changed its business name, "doing business as" name, or division name (whichever is shown on the contract), or has transferred the assets used in performing the contract, but has not completed the necessary requirements regarding novation and change-of-name agreements in Subpart 42.12, the Contractor shall provide the responsible Contracting Officer a minimum of one business day's written notification of its intention to (A) change the name in the CCR database; (B) comply with the requirements of Subpart 42.12 of the FAR; and (C) agree in writing to the timeline and procedures specified by the responsible Contracting Officer. The Contractor must provide with the notification sufficient documentation to support the legally changed name.
(ii) If the Contractor fails to comply with the requirements of paragraph (g)(1)(i) of this clause, or fails to perform the agreement at paragraph (g)(1)(i)(C) of this clause, and, in the absence of a properly executed Novation or change-of-name agreement, the CCR information that shows the Contractor to be other than the Contractor indicated in the contract will be considered to be incorrect information within the meaning of the "Suspension of Payment" paragraph of the electronic funds transfer (EFT) clause of this contract.
(2) The Contractor shall not change the name or address for EFT payments or…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .