About this file

Specifications

View the file

Other files

File Type Posted
Ltr of Intent to Award.Transfer.Aspen.pdf PDF
Aspen_GS_Plans.pdf PDF
Experience Questionnaire.pdf PDF
SF 30 AG82B1S100235000001.pdf PDF
SF 1442_AG-82B1-S-10-0235.pdf PDF
Wage Determination_CO100013_03122010_ Heavy.pdf PDF
AG-82B1-S-10-0235 Schedule.pdf PDF
Exp. Qstnr.docm DOCM document
Tranfer_Park_Plans.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

San Juan National Forest Transfer Park CG and Aspen GS Water System 2010 1 CSI Specifications

CSI Specifications

Transfer Park CG and Aspen GS Water System

No. of Pages

DIVISION 1 – GENERAL REQUIREMENTS

Section 01110 - Summary of Work Section 01141 - Use of Site and Public Closures Section 01180 - Project Utility Sources Section 01291 - Measurement and Payment Section 01330 - Submittal Procedures Section 01450 - Quality Control Section 01641 - Government Furnished Products Section 01660 - Product Storage and Handling Requirements Section 01721 - Construction Surveying and Staking Section 01732 - Mobilization Section 01740 - Cleaning Section 01780 - Closeout Submittals

DIVISION 2 – SITE CONSTRUCTION

Section 02081 - Galvanized Steel Piping Section 02082 - Valves and Boxes Section 02083 - Water Hydrants Section 02084 - High Density Polyethylene Piping Section 02086 - Brass Piping / Nipples Section 02220 - Site Demolition Section 02230 - Site Clearing Section 02315 Excavation and Fill Section 02316 - Trenching, Backfilling, and Compacting Section 02317 - Excavating and Backfilling for Structures Section 02510 - Water Distribution Section 02521 - Water Supply Well Section 02522 - Water Well Pump Installation Section 02730 - Aggregate Surfacing Section 02921 - Seeding

DIVISION 3 – CONCRETE

Section 03301 - Concrete, Formwork and Reinforcement Section 03302 - Concrete from Packaged Dry Mix

DIVISION 7 – THERMAL AND MOISTURE PROTECTION

Section 07920 - Joint Sealants

2010 2 CSI Specifications

No. of Pages

DIVISION 11 – EQUIPMENT

Section 11260 - Disinfectant Feed Equipment

DIVISION 13 – SPECIAL CONSTRUCTION

Section 13121 - Prefabricated Concrete Treatment Building Section 13200 - Storage Tanks Section 13441 - Liquid Level Sensors

DIVISION 15 – MECHANICAL

Section 15141 - Building Plumbing

DIVISION 16 – ELECTRICAL

Section 16050 - Basic Electrical Materials and Methods Section 16201 - Wiring Systems Section 16800 - Photovoltaic Power System

San Juan National Forest Transfer Park CG & Aspen GS Water System 2010 01110 - 1 Summary of Work

SECTION 01110

SUMMARY OF WORK

PART 1 GENERAL

1.01 INTENT OF CONTRACT

A. The intent of the contract is to provide for the complete construction of the project described in the contract. Unless otherwise provided, furnish all labor, materials, equipment, tools, transportation, and supplies, and perform all work required to complete the project in reasonably close conformity with drawings and specifications, and in accordance with provisions of the contract.

B. Sections of Division 1 – General Requirements govern the execution of the work of all sections of the specifications.

1.02 DRAWINGS

A. Contract drawings accompany these specifications and form a part of this contract.

1.03 LOCATION OF WORK

A. Transfer Park Campground is located in La Plata County, Colorado. The campground can be access by traveling east on County Road 240 to County Road

243. Continue north on County Road 243 past Lemon Reservoir to the Forest Service boundary and turn west (left) on to Nation Forest Service Road 596.

After crossing the bridge you will turn left and Continue through Florida Campground and Transfer Park Trailhead. The site is located approximately 16 miles northeast of Durango, Colorado. Transfer Park campground is comprised of two loops; however the scope of this project will include an area near the Transfer Park Trailhead.

B. Aspen Guard Station is located in Montezuma County, Colorado. The Guard

Station can be accessed from US Highway 160 in Mancos, Colorado by turning north on to State Highway 184 for approximately 0.03 miles. Then turn east (right) on to County Road 42. Follow County Road 42 for approximately 5 miles to 561. Travel NFSR 561 for approximately 6 miles to Aspen Guard Station. The entrance will have a gate and the Guard Station is visible from the road.

1.04 DESCRIPTION OF THE WORK

2010 01110 - 2 Summary of Work

A. Transfer Park Campground : Construction of a potable water distribution and treatment system. The principal features of work to be performed include, but are not limited to the following:

1. Demolition of 2 existing 2,500 gallon concrete storage tanks.

2. Demolition of an existing masonry treatment building including a concrete well pad.

3. Installation of a Government supplied precast concrete treatment building.

Installation shall include site pad preparation, installation of sweeps through the building floor, building placement, construction of a concrete apron, and final grading of treatment building site.

4. Installation of all treatment building plumbing and controls (AS SHOWN

IN THE DRAWINGS).

5. Retrofit and protect well head for exterior operations meeting sanitary standards to Include installation of a steel outer well casing, and installation of all necessary appurtenances and piping from well to treatment building.

6. Design and installation of photovoltaic powered pumping system including but not limited to: stainless steel pump, solar panels to be mounted on the roof of the prefabricated concrete treatment building, wiring and controls.

7. Installation of underground 2,000 gal. potable water storage tank, plumbing, drains, and controls (AS SHOWN IN THE DRAWINGS).

8. Trench and Install 1” high density polyethylene pipe for distribution and supply lines, and daylight drains (AS SHOWN IN THE DRAWINGS).

9. Installation of point of use hydrants and associated concrete pad, hydrant post, valves, drains, and finish grading (AS SHOWN IN THE

DRAWINGS).

10. Seeding of all areas disturbed by construction with seed mixture specified by Columbine Ranger District.

B. Aspen Guard Station: Construction of a potable water supply and treatment system. The principal features of work to be performed include, but is not limited to the following:

1. Drill and install a well for use with a potable water system per State of Colorado Regulations and these specifications.

2. Abandon existing water system in place, backfilling existing concrete water storage tanks in-place, capping water line at ends and all breaks, and daylight draining spring box to existing natural drainage.

3. Installation of a potable submersible pump and controls.

4. Installation of water supply piping and appurtenances from well supply to treatment system located in the basement of the Guard Station.

5. Installation of all treatment system and pressure tanks plumbing in Guard

Station basement.

6. Design and installation of photovoltaic wiring system to be mounted on a separate support structure.

2010 01110 - 3 Summary of Work

7. Connect the supply and treatment system to the Guard Station plumbing and exterior faucet.

8. Seeding and repair of areas disturbed by construction with seed mixture specified for Dolores Ranger District.

1.05 GENERAL SITE CONDITIONS

A. Rock outcrops, surface cobbles, and boulders are evident at the site.

B. Thick oak brush, Aspen trees, clay soils are evident at the site.

PART 2 PRODUCTS

2.01 GOVERNMENT FURNISHED MATERIALS

A. Section 01641 – Government Furnished Products

PART 3 EXECUTION

Not Used

END OF SECTION

San Juan National Forest Transfer Park CG and Asp en GS Water System 2010 01141 - 1 Use of Site and Public Closures

SECTION 01141

USE OF SITE AND PUBLIC CLOSURES

1.01 USE OF SITE BY PUBLIC

A. Construction at Transfer Park Campground shall be phased to allow one loop of the campground to remain open to the public at all times. Aspen Guard Station shall be closed to the public during construction.

B. There shall not be access to potable water.

1.02 USE OF SITE BY CONTRACTOR

A. Storage Area: An area within the site shall be made available for use as a storage area. The CO shall approve the location of the area prior to its use.

Toilet buildings shall not be used for storage.

B. Work Camp: An area at the site shall be approved by the CO as a work camp for the Contractor’s personnel at no cost to the contractor. The contractor and all personnel shall comply with Forest Service regulations relative to such use.

C. Sanitary Facilities:

1. The contractor shall have use of public toilet facilities as located the site.

The toilet building shall be cleaned periodically, and when work is stopped or delayed for an extended period of time as directed by the CO. Prior to final acceptance of the project, the toilet building shall be cleaned and the vault(s) pumped as directed by the CO. Toilet buildings shall not be used for storage, OR

2. The contractor shall provide portable toilet. Forest Service Toilet buildings shall not be used for storage.

PART 2 PRODUCTS

Not Used

2010 01180 - 1 Project Utility Sources

SECTION 01180

PROJECT UTILITY SOURCES

1.01 ELECTRIC

A. Electricity is not available on-site. Contractor shall be responsible for supplying electricity required for contract work.

1.02 POTABLE WATER

A. Contractor shall be responsible for supplying potable water as needed.

1.03 NON-POTABLE WATER

A. Non-potable water is not available on-site.

1.04 SANITARY FACILITIES

A. Section 01141 – Use of Site and Public Closures.

1.05 WASTE DISPOSAL

A. Contractor shall be responsible for disposal of all wastes. See Section 02220 –

Site Demolition, and Section 01740 – Cleaning.

2010 01291 - 1 Measurement and Payment

SECTION 01291

MEASUREMENT AND PAYMENT

1.01 MEASUREMENT AND PAYMENT

A. Compensation provided for in the contract is full payment for performing all contract work in a complete and acceptable manner. All risk, loss, damage, or expense arising out of the nature or prosecution of the work is included in the compensation provided by the contract.

B. Work required by the contract will not be paid for directly unless a pay item for the work is designated in the SCHEDULE OF ITEMS.

C. Work referenced for measurement under another section will not be paid for directly unless a pay item for the work is designated in the SCHEDULE OF ITEMS for the referenced section.

D. Work not paid for directly is considered to be included under the other contract pay items.

E. Unless otherwise shown, work measured and paid for under one pay item will not be paid for under any other pay item.

F. The quantity to be paid for is the quantity designated in the SCHEDULE OF

ITEMS. No payment will be made for work performed in excess of that staked, ordered, or otherwise authorized.

G. When more than one class, size, or thickness is specified in the SCHEDULE OF

ITEMS for any pay item, suffixes will be added to the item number to differentiate between the items.

1.02 DETERMINATION OF QUANTITIES

The following measurements and calculations are used to determine contract quantities:

A. For individual construction items, longitudinal and lateral measurements for area computations shall be made horizontally or corrected to horizontal measurement unless otherwise specified. Measurements for seeding, mulching, geotextiles, netting, erosion control blankets, and sodding shall be along slope lines.

2010 01291 - 2 Measurement and Payment

B. The average end area method shall be used to compute volumes of excavation or embankment. However, if in the judgment of the CO the average end area method is impractical, measurement shall be made by volume in hauling vehicles, or by other three-dimensional methods.

C. Structures shall be measured according to neat lines SHOWN ON THE

DRAWINGS, or as altered by the CO in writing to fit field conditions.

D. For items that have linear measurements, such as pipes, pipe culverts, fencing, guardrails, and underdrains, measurements shall be made parallel to the base or foundation upon which the structures are placed. Pipe and pipe arch culverts shall be measured along center of invert, and arches shall be measured at spring line.

E. For aggregates weighed for payment, the tonnage weight shall not be adjusted for moisture content, unless otherwise provided for elsewhere in these specifications.

F. For standard manufactured items – such as fence, wire, plates, rolled shapes, and pipe conduits – identified by gauge, weight, section dimensions, and so forth, such identifications shall be considered the nominal weights or dimensions.

Unless controlled by tolerances in cited specifications, manufacturer’s tolerances shall be accepted.

1.03 UNITS OF MEASUREMENT

Payment will be by units defined and determined according to measure. Unless otherwise specified, the meanings of the following terms are as follows:

A. Cubic Yard in Place (yd3): Measure solid volumes by the average end area method as follows:

1. Measure cross sections of the original ground and use with design or staked templates, or take other comparable measurements to determine the end areas. Do not measure work outside of the established lines or slopes.

2. If any portion of the work is acceptable, but is not completed to the established lines and slopes, remeasure cross sections or comparable measurements of the portion of the work. Deduct any quantity outside the designated or staked limits. Use these measurements to calculate new end areas.

3. Compute the quantity using the average end areas multiplied by the horizontal distance along a centerline or reference line between the end areas. Deduct any quantity outside the designed or staked limits.

Where it is impractical to measure material by the average end area method, other methods involving three-dimensional measurements may be used.

2010 01291 - 3 Measurement and Payment

Measure liquid volumes in accordance with Subsection 01291-1.03-H.

B. Cubic Yard in the Hauling Vehicle: Measure the cubic yard volume in the hauling vehicle using three-dimensional measurements at the point of delivery.

Use vehicles bearing a legible identification mark with the body shaped so the actual contents may be readily and accurately determined. Before use, mutually agree in writing upon the volume of material to be hauled by each vehicle.

Vehicles carrying less than the agreed volume may be rejected or accepted at the reduced volume.

Level selected loads. If leveling reveals that the vehicle was hauling less than the approved volume, reduce the quantity of all material received since the last leveled load by the same ratio as the ratio of the current leveled load volume to the agreed volume. Payment will not be made for material in excess of the agreed volume.

Material measured in the hauling vehicle may be weighed and converted to cubic yards for payment purposes if the conversion factors are mutually agreed to in writing.

Compute measurement using measurements of material in the hauling vehicles at the point of delivery. Load vehicles to at least their water- level capacity.

Leveling of the loads may be required when vehicles arrive at the delivery point.

C. Each: One entire unit, which may consist of one or more parts. The quantity is the actual number of units comple ted and accepted.

D. Acre (ac): 43,560 ft2. Make longitudinal and transverse measurements for area computations horizontally. Do not make deductions from the area computation for individual exclusions having an area of 218 ft2 or less.

E. Hour (h): Measurement will be for the actual number of hours ordered and performed by the Contractor.

F. Pound (lb): If sacked or packaged material is furnished, the net weight as packed by the manufacturer may be used.

G. Station (Sta): 100 feet. Measure horizontal along the centerline of each roadway, approach road, or ramp.

H. Gallon (gal): The quantity may be measured by any of the following methods.

1. Measured volume container.

2. Metered volume. Use an approved metering system.

3. Commercially packaged volumes.

2010 01291 - 4 Measurement and Payment

I. Lump Sum (LS): Do not measure directly. The bid amount is complete payment for all work described in the contract and necessary to complete the work for that item.

J. Feet (ft): Measure from end to end, parallel to the base or foundation being measured, or horizontal.

K. Square yard (yd2): Measure on a plane parallel to the surface being measured or horizontal.

Where measurement is horizontal, make no deductions from the area computation for individual exclusions having an area of 1 yd2 or less.

L. Ton (t): 2,000 pounds

No adjustment in contract unit price will be made for variations in quantity due to differences in the specific gravity or moisture content.

Use net certified scale weights, or weights based on certified volumes.

1.04 METHODS OF MEASUREMENT

One of the following methods of measurement for determining final payment is designated in the SCHEDULE OF ITEMS for each pay item:

A. Designed Quantities (DQ): These quantities denote the final number of units to be paid for under the terms of the contract. They are based upon the original design data available prior to advertising the project. Original design data include the preliminary survey information, design assumptions, calculations, drawings, and the presentation in the contract. Changes in the number of units designated in the SCHEDULE OF ITEMS may be authorized under any of the following conditions:

1. Changes in the work authorized by the CO.

2. A determination by the CO that errors exist in the original design that cause a pay item quantity to change by 15 percent or more.

3. A written request submitted to the CO showing evidence of errors in the original design that cause the quantity of a pay item to change by 15 percent or more. The evidence must be verifiable and consist of calculations, drawings, or other data that show how the designed quantity is in error.

B. Staked Quantities (SQ): These quantities are determined from staked measurements prior to construction.

C. Actual Quantities (AQ): These quantities are determined from measurements of completed work.

2010 01291 - 5 Measurement and Payment

D. Vehicle Quantities (VQ): These quantities are measured or weighed in hauling vehicles.

E. Lump Sum Quantities (LSQ): These quantities denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job.

1.05 EARTHWORK TOLERANCES

A. Where tolerances are shown in the contract, they are intended to define

“reasonably close conformity.” Make adjustments of horizontal or vertical alignment within the tolerances specified in this contract, or shift of balance points up to 100 feet, as necessary to produce the designed roadway section and to balance earthwork. Such adjustments will not be considered “changes.”

2010 01330 - 1 Submittal Procedures

SECTION 01330

SUBMITTAL PROCEDURES

1.01 REQUIREMENTS

A. The Contractor shall submit all information necessary to insure compliance.

The contractor shall submit information at least ten business days prior to beginning the associated work.

B. Submittals and approval by the CO shall be required for all products where the contractor wishes to use an approved equal. Submittals are not required where the contractor proposes to use the exact product specified (i.e. exact model and manufacturer specified).

C. Products installed by the contractor and not approved by the CO are subject to removal and reinstallation with an approved product at the contractor’s expense.

1.02 MANUFACTURER’S LITERATURE AND SHOP DRAWINGS

A. Submit (2) two copies to the CO for approval on the items required herein.

B. Information must be adequate to determine compliance with specifications.

1.03 SAMPLES

A. Submit two samples of each color, style, and etc. of the items required herein.

2010 01450 - 1 Quality Control

SECTION 01450

QUALITY CONTROL

1.01 SUMMARY

A. Provide certification that the quality and quantity of construction conforms to the drawings, specifications, and requirements of the contract.

3.01 CERTIFICATION & MEASUREMENTS

A. Offsite-Produced Materials: Furnish certificates executed by the manufacturer supplier, or vendor, stipulating that all materials produced off site that are incorporated into the work meet the applicable requirements SHOWN ON THE DRAWINGS or stated in the specifications. Make each certificate apply to a single commodity or invoice. Certify all incidental purchases needed to remedy minor shortages of material.

B. Quantity Measurements: Make all measurements for computation of quantities for all work items, except those specified for payment by design quantity or lump sum. Compute the quantities for periodic progress payments; the CO will compute the quantities for the final payment based on measurements taken. All Contractor measurements are subject to verification. Submit all field notes, calculation sheets, and other data used to determine quantities, and certify in writing as to the accuracy of the measurements and computations submitted.

3.02 MATERIAL COMPACTION TESTING

A. The government may order compaction tests from a certified testing laboratory.

The contractor shall pay for compaction tests that fail to meet the minimum requirements out lined in these specifications. The government will pay for compaction tests meeting the requirements outlined in these specifications.

02-21-10 01641 - 1 Government Furnished Products

SECTION 01641

GOVERNMENT FURNISHED PRODUCTS

1.01 SCOPE

A. Applies to products that shall be furnished by the government and installed by the contractor. The prefabricated concrete treatment building shall be furnished and placed by the government on a surface constructed by the contractor.

1.02 INSPECTION

A. The contractor shall notify the CO at least 5 calendar days prior to picking up or returning government furnished products.

B. The contractor and the CO shall jointly inspect all products during the loading operation (picking up products) and the unloading operation (returning products) from the storage area.

1.03 LIABILITY

A. The contractor’s liability for government furnished products shall start at the time the products are accepted at the storage area, and shall terminate upon completion and final acceptance of the work.

B. The contractor shall provide all labor, equipment, and incidentals necessary to transport the government furnished products between the project and storage area.

1.04 REPLACEMENT AND/OR SUPPLEMENTAL PRODUCTS

A. Any defective products discovered prior to the contractor’s acceptance of the products will be replaced by the Government.

B. If the quantity of government furnished products accepted by the contractor is insufficient to complete the specified work, supplemental products complying with these specifications will be provided by the government at no expense to the Contractor.

C. The government shall not replace any products that, in the opinion of the CO, are damaged or lost due to the contractor’s negligence after the contractor accepts the products. Such products shall be replaced at the contractor’s expense.

02-21-10 01641 - 2 Government Furnished Products

1.05 SURPLUS PRODUCTS

A. After completion and final acceptance of the work, surplus government furnished products shall be returned to the storage area in the same mechanical and physical condition as originally accepted.

B. Damaged surplus products shall be replaced at the contractor’s expense.

C. The contractor’s liability for surplus products shall terminate upon unloading at the storage area.

1.01 PREFABRICATED CONCRETE TREATEMENT BUILDING – GOVERNMENT

FURNISHED AND PLACED.

A. The government shall furnish a prefabricated 12’ by 10’ concrete treatment building at no cost to the contractor. The contractor shall construct the surface for placement of the treatment building prior to delivery and place the building upon arrival.

1.01 GENERAL

A. Installation and testing of government furnished products shall comply with the applicable contract specifications covering work requiring the use of such products.

B. The prefabricated concrete treatment building and concrete toilet building delivery date will be agreed upon between the government, the manufacturer, and the contractor upon award of this contract.

2010 01660 - 1 Product Storage and Handling Requirements

SECTION 01660

PRODUCT STORAGE AND HANDLING REQUIREMENTS

A. The Contractor shall be responsible for protecting all equipment and supplies intended for use in the project. The Contractor shall pay all costs related to such protection.

B. Equipment and supplies, approved by the CO and in storage, shall be installed in the same physical and mechanical condition as when approved by the CO.

2010 01721 - 1 Construction Surveying & Staking

SECTION 01721

CONSTRUCTION SURVEYING & STAKING

A. Construction staking of waterlines, storage tank, and treatment building shall be in accordance with Section 02510 – Water Distribution, Subsection 3.03 – General Installation Procedures, Subpart A.

B. Construction staking shall not be required to be under the direction of a licensed professional engineer or land surveyor.

2.01 STAKES

A. Furnish stakes of the type and quality normally used in highway survey work, and suitable for the intended use. Furnish stakes and hubs of sufficient length to provide a solid set in the ground with sufficient surface area above ground for necessary legible markings.

3.01 GENERAL

A. Furnish all labor, equipment, instruments, materials, transportation, and other incidentals necessary to complete the construction surveying and staking in accordance with these specifications and acceptable engineering practice.

2010 01732 - 1 Mobilization

SECTION 01732

MOBILIZATION

A. Move personnel, equipment, material, and incidentals to the project, and perform all activities necessary to accomplish work at the project site. Obtain permits, insurance, and bonds.

1.02 MEASUREMENT

A. Method: Measure mobilization by the lump sum.

1.03 PAYMENT

A. The accepted quantity, measured as provided above, will be paid at the contract price per unit of measurement for the pay item listed below that is designated in the SCHEDULE OF ITEMS.

B. The mobilization lump sum will be paid as follows:

1. If applicable, bond premiums will be reimbursed according to FAR clause

52.232-5, Payment Under Fixed-Price Construction Contracts, after receipt of evidence of payment.

2. Fifty percent of the lump sum, not to exceed 5 percent of the original contract amount, will be paid following completion of 5 percent of the original contract amount, not including mobilization.

3. Payment of the remaining portion of the lump sum, up to 10 percent of the original contract amount, will be paid following completion of 10 percent of the original contract amount, not including mobilization.

4. Any portion of the lump sum in excess of 10 percent of the original contract amount will be paid after final acceptance.

C. Payment will be made under:

Pay Item Pay Unit

01732 (01) Mobilization (Transfer Park).................................. Lump Sum 01732 (02) Mobilization (Aspen GS) ....................................... Lump Sum

2010 01732 - 2 Mobilization

2010 01740 - 1 Cleaning

SECTION 01740

CLEANING

1.01 CLEAN UP

A. The work site shall be maintained in a neat condition during construction. The work site shall be kept free from accumulation of waste materials and rubbish resulting from the work.

B. If work is stopped or delayed for an extended period of time, the Contractor shall clean up the site as determined by the C.O.

C. Before final acceptance of the project, the Contractor shall remove all waste materials and rubbish resulting from the work.

2010 01780 - 1 Closeout Submittals

SECTION 01780

CLOSEOUT SUBMITTALS

3.01 AS-BUILT DRAWINGS

A. Maintain a set of the contract drawings depicting as-built conditions. Maintain these drawings in current condition, and make them available for review.

Indicate all variations from contract drawings in red on the drawings. Upon completion of the contract work, submit as-built drawings to the CO.

3.02 KEYS

A. Return any keys issued to the contractor by the government, prior to final acceptance and payment.

2010 02081 - 1 Galvanized Steel Piping

SECTION 02081

GALVANIZED STEEL PIPING

1.01 SCOPE

A. Installation of galvanized steel pipe used for potable water distribution and material related to its installation.

PART 2 PRODUCTS

2.01 GALVANIZED STEEL PIPE AND FITTINGS

A. Pipe: ASTM A-120 or AWWA C-202, Schedule 40, threaded and coupled.

B. Fittings: ANSI B-16.12, threaded, galvanized.

2.02 SUCTION SCREEN/STRAINER

A. Pipe-mounted suction screens U.S Mesh size 20, part numbers F-8-20 (1”), F- 16-20 (2”) and F-24-20 (3”), as manufactured by flow Ezy Filters, Inc., Ann Arbor, MI (800) 237-1165, or approved equal.

2.03 WATER STORAGE TANK VENT

A. Fabricate using a galvanized steel tee and two Galvanized Steel elbows. Vent shall extend down and shall have suction screen/strainer as specified in subsection 2.02.

3.01 INSTALLATION

A. Exposed threaded pipe joints shall be painted with mastic per manufacturer's application procedures.

B. Field-cut ends shall be squared off by grinding or filing; ends shall be reamed with all chips and flakes removed.

C. Field cut threads or machined joints shall be made with sharp tools to sharp finished ends.

2010 02082 - 1 Valves and Boxes

SECTION 02082

VALVES AND BOXES

A. Description of valves, boxes, pits and material related to their installation.

2.01 BALL CURB VALVES

A. Ball curb valves shall be standard arch pattern.

B. Female Iron Pipe inlet by Female Iron Pipe outlet

C. Hole for attaching curb box rod or handle is provided in Tee Head.

D. Valve is water-tight with flow through in both directions.

E. Brass construction conforming to AWWA standard C800-89.

F. Quarter turn check

G. 300 psi working pressure

H. Ball curb valves shall be Mueller 300 series (Model B-20283) as manufactured by Mueller Co., Decatur, IL, phone (217) 423-4471; or approved equal.

2.02 CURB BOXES

A. Curb boxes shall have an arch base and foot piece compatible the Mueller 300 series ball curb valves. Both boxes shall be a cast iron extension type.

B. Box length when installed, shall permit adjustment between 3 inches above and below the final ground surface. Boxes located at water hydrants shall have a fully retracted length of 12-inches, and an extended length of 24- inches.

C. Lids shall be cast iron with brass pentagon plugs

D. Arch size shall be of proper size to match ball curb valve.

2010 02082 - 2 Valves and Boxes

E. Box shall be equipped with stationary rod, and have a 1 ¼-inch inside diameter upper section. The top of the stationary rod shall terminate within the 1 ¼-inch inside diameter upper section of the box, and not interfere with screwing in the pentagon plug to its full depth.

F. Curb boxes shall be Mueller Improved Extension type with Arch Pattern Base

(Model H-10385) and Optional Foot Piece (H-10397), as manufactured by Mueller Co., Decatur, IL, phone (217) 423-4471; or approved equal.

2.03 TOOLS FOR OPERATING VALVES, CURB STOPS, AND OPENING BOXES

A. The Contractor shall supply two curb box keys and two pentagon keys to operate valves, curb stops, and open box lids. Tools shall be as supplied by the valve, curb stop, or box manufacturer for each water system (4 total).

B. Curb box key shall be model H-10321, 4-feet in length as manufactured by

Mueller Co., Decatur, IL, phone (217) 423-4471; or approved equal.

C. Pentagon key shall be model H-10323 as manufactured by Mueller Co., Decatur, IL, phone (217) 423-4471; or approved equal.

2010 02083 - 1 Water Hydrants

SECTION 02083

WATER HYDRANTS

A. Provides for furnishing and installing water hydrants at locations SHOWN ON

THE DRAWINGS.

1.02 MEASUREMENT

A. Measurement sha ll be as designated in the SCHEDULE OF ITEMS. Water hydrants will be measured per each water hydrant installed complete, and functional, including all concrete, if required, and related material and labor.

B. Trail construction between hydrant and edge of existing road, spur, or turnout will not be paid for separately but will be considered subsidiary to water hydrant construction.

1.03 PAYMENT

A. Payment will be at the contract unit price for each item accepted. Payment will be made under:

02083 (01) Water Hydrant ............................................................... Each

2.01 HYDRANT POST

A. 8" x 8" x 6'-6” long, rough sawn No. 2 or better Douglas Fir, Southern Yellow

Pine, or Hem Fir; pressure-treated, installed as SHOWN ON THE DRAWINGS.

B. Wood Preservative: Pressure treatment with CCA (Type A, B, or C) in accordance with AWPA–C1, C2, and C4, with a net retention of 0.60 pcf. All CCA shall conform to ASTM–1625.

2010 02083 - 2 Water Hydrants

2.02 DRAIN ROCK

A. Material shall be clean, rounded granular material, graded from 1" - 2" in greatest dimension.

2.03 PIPE AND FITTINGS

A. Section 02081, Galvanized Steel Pipe, Schedule 40, sizes as SHOWN ON THE

DRAWINGS.

2.04 BALL VALVE CURB STOPS AND CURB BOXES

A. Section 02082 – Valves and Boxes, size and length as SHOWN ON THE

2.05 CONCRETE PAD

A. Size as SHOWN ON THE DRAWINGS, placed in conformance with Section 03301 – Concrete, Formwork and Reinforcement.

2.06 PADDLE FAUCET

A. Self-closing bib faucet with plain end. Plain end means no threads, so a garden hose cannot be attached to the end.

B. Extended "paddle" type handle for accessibility. Operation of handle shall require less than 3.5 lbs.

C. Equipped with integral 2.5 gpm flow control

D. Finish shall be non-chromed brass. Brass shall be lead free and suitable for dispensing potable water.

E. Model No. 6252EHLF, as manufactured by Haws Co., Sparks, NV, phone:

(888) 640-4297; or approved equal.

2.07 HOSE BIB WITH INTEGRATED VACUUM BREAKER

A. Finish shall be brass.

B. Inlet connection shll abe ¾-inch female hose thread, and outlet connection shall be ¾-inch male hose thread.

C. Shall meet ASSE 1011 and ANSI A112.1.3.

D. Model No. 363LF as manufactured by Arrowhead Brass Products, (323) 221-

2010 02083 - 3 Water Hydrants

9137, or approved equal

3.01 GENERAL

A. Wood posts shall be cut and drilled to the lengths and chamfered, as SHOWN

ON THE DRAWINGS. All posts shall be pressure treated with wood preservative. All field cuts, abrasions, and holes made in the timbers after treatment shall be given three (3) brush coats of 9% copper napthenate preservative (equivalent to 1% metallic copper).

B. The post and riser pipe shall be placed in the trench, plumb and to the elevations

SHOWN ON THE DRAWINGS, and backfilled with material meeting the requirements of Section 02316 – Trenching, Backfilling, and Compacting, Part

2.02 Subsequent Backfill. Backfill shall be deposited and carefully compacted in layers not to exceed 12” in thickness (thickness measured before compaction).

Each layer shall be compacted by not less than three passes over the entire surface with a mechanical vibrating tamper.

C. Prior to construction, the CO shall approve exact location and orientation of hydrants.

D. Elevation of edge of concrete pad shall be the same as adjacent finished surface of edge of road, spur, or trail. Concrete pads not meeting this requirement shall be removed by the contractor and replaced at no cost to government. Backfill and fine grade around the outside of the concrete pad.

E. Drain rock shall be loosely placed to the dimensions SHOWN ON THE

2010 02084 - 1 High Density Polyethylene Piping

SECTION 02084

HIGH DENSITY POLYETHYLENE PIPING

A. Provides for furnishing and installing High Density Polyethylene (HDPE) pipe used for potable water distribution and material related to its installation.

2.01 HIGH DENSITY POLYETHYLENE (HDPE) PIPE, TEES, & REDUCERS

A. All waterlines (pipe and fittings) shall be new and unused, of the type, pressure rating or class, and size (nominal diameter) specified and as SHOWN ON THE

B. All material must meet applicable National Sanitation Foundation (NSF) standards for public drinking water. Pipe shall bear the NSF seal. The pipe manufacturer shall provide certification that the pipe meets this specification.

C. High Density Polyethylene (HDPE) plastic pipe shall be PE-3408 as defined in

ASTM D-1248, with a minimum cell classification of 345464C in accordance with ASTM D 3350. The pipe shall be SDR7 (200 PSI) pipe and comply dimensionally with ASTM D 2737. Pipe shall comply with AWWA C901 standard for Polyethylene Pressure Pipe. The pipe shall be listed for potable water to ANSI/NSF standard 61.

D. Rolled Pipe

1. HDPE pipe equal to 1” diameter shall be provide in rolls of 100 ft or 300 ft length.

3. HDPE pipe equal to 2" diameter shall be provided in rolls of 100 ft or 200 ft length.

2. HDPE pipe larger than 2" diameter shall be provided in 40' lengths rather than in rolls.

E. HDPE pipe shall be as manufactured by JM Eagle, 4501 W. 49th Street, Tulsa

OK, 74107, 1-800-962-1514, and supplied by Grand Junction Pipe & Supply Co., Durango, CO, phone (970) 385-6733; or approved equal.

F. HDPE tees and reducers shall be as manufactured by Mueller Company, 500 W.

Eldorado ST., Decatur IL, 62522, and supplied by Grand Junction Pipe &

2010 02084 - 2 High Density Polyethylene Piping

Supply Co., Durango, CO, phone (970) 385-6733; or approved equal.

2.02 TRANSITION FITTINGS - COMPRESSION

A. Fittings shall be as manufactured by Mueller Company, 500 W. Eldorado ST., Decatur IL, 62522, and supplied by Grand Junction Pipe & Supply Co., Durango, CO, phone (970) 385-6733; or approved equal.

B. Fittings shall be compression x female iron pipe thread.

3.01 LAYING PIPE

A. HDPE pipe sha ll be weaved in the trench to provide horizontal slack in the line for expansion and contraction.

B. Pipe shall be allowed to cool to within 20o F of the shaded trench bottom temperature before backfilling.

3.03 PIPE JOINING

A. The joining method for pipe, tees, and reducers shall be installed in accordance with the manufacturer's recommendations.

3.04 PIPE TRANSITIONS

A. Transitions for making connections from HDPE pipe to other threaded pipe or connections shall be per:

1. Subsection 2.02 – Transition Fittings – Compression

San Juan National Forest Transfer Park CG and Aspen GS Water system 2010 02086 - 1 Brass Piping / Nipples

SECTION 02086

BRASS PIPING / NIPPLES

A. Installation of red brass pipe / nipples used in Building Plumbing.

2.01 BRASS PIPE / NIPPLES

A. ASTM B 687 and ASTM B 43.

B. Temper shall be annealed temper (061).

2.02 RELATED SECTIONS

A. Section 15141 – Building Plumbing.

3.01 INSTALLATION

A. Exposed threaded pipe joints shall be painted with mastic per manufacturer's application procedures.

B. Field-cut ends shall be squared off by grinding or filing; ends shall be reamed with all chips and flakes removed.

C. Field cut threads or machined joints shall be made with sharp tools to sharp finished ends.

2010 02220 - 1 Site Demolition

SECTION 02220

SITE DEMOLITION

A. Applies to the removal and backfilling of existing underground utilities within trenching limits of new construction.

B. Removal and disposal of existing hydrants, treatment building, and storage tanks.

C. In-place demolition and backfilling of exiting concrete storage tanks.

D. Removal and capping of existing water lines.

1.02 DISPOSAL

A. Remove from project all debris and non-salvageable materials designated for removal in accordance with federal and local regulations. Make necessary arrangements with property owners, and haul debris and non-salvageable materials off of Forest Service lands to suitable disposal locations as approved by the CO. Furnish a signed copy of the disposal agreement.

2.01 BACKFILL

A. Backfill material shall be pit run comprised of 6-inch minus material with a relatively uniform gradation from coarse to fine and a minimum of 50% passing the No. 4 sieve.

3.01 GENERAL REMOVAL

A. Demolition and removal of treatment building, concrete storage tanks, and hydrants shall be done so as to minimize damage to the surrounding vegetation and contamination to the well and ground water. Damage to other structures and utilities not designated for removal, shall be repaired by the contractor at no expense to the government.

2010 02220 - 2 Site Demolition

B. Concrete storage tanks demolished in-place shall have the tops collapsed and tank bottom sufficiently broken to prevent water retention. Backfill material as specified in Section 2.01 – Backfill shall be completed in 12- inch compacted layers and mounded to approximately 6 inches above the natural grade to promote drainage.

C. Cap existing water lines and abandon old water system in place. Remove existing abandoned water lines to be abandoned where new water lines cross.

D. Cap existing water lines at spring box and tanks. Drain spring box to natural drainage.

E. Holes created from removals shall be backfilled and compacted in layers not to exceed 12” in thickness. Each layer shall be compacted at optimum moisture content by not less than three passes over the entire surface with a mechanical vibrating tamper. The top 6” of backfill shall be topsoil, and remain loose enough to allow plant growth.

F. Restore grade in area of removals, to approximate natural contours.

3.02 PAYMENT

A. Costs for vault pumping and waste disposal shall be incidental to the Vault Toilet Removal and Disposal Pay Items 02120(01) through 02120(06) described below.

Pay Item Description Pay Unit 02220 (01) Site Demolition (Transfer Park) ................... Lump Sum 02220 (02) Site Demolition (Aspen Guard Station)…… Lump Sum

2010 02230 - 1 Site Clearing

SECTION 02230

SITE CLEARING

A. This Section includes clearing, grubbing, and disposal of trees, brush, stumps, and rubbish within the clearing limits of construction.

3.01 CLEARING

A. Clearing Limits: Clearing limits shall not exceed 12 feet for utility lines and shall be performed in such a manner so as not to leave straight & uniform vegetation lines. Clearing limits shall be 5 feet from exterior walls of buildings, concrete slabs, and excavation limits; or as SHOWN ON THE DRAWINGS.

B. Clear small trees, brush, snags, underbrush, and rubbish within the clearing limits.

C. Individual marked trees, within the clearing limits, shall be left standing and uninjured.

E. All designated timber cut during clearing operations having a minimum diameter of 6 inches inside bark shall be cut into the longest lengths possible with any of the following combinations of lengths: 8’6”, 10’6”, 12’6”, 16’6”, 18’6”, 20’6”, 23’, 25’, 27’, 29’, 31’, or 33’. Butt logs should be cut to the longest length possible. Conifer logs will be bucked to a minimum top diameter of 6” inside bark. Aspen logs will be bucked to a minimum top diameter of 4” inside bark.

Timber will be neatly stacked at a location designated by the CO on the construction site. Conifer and aspen will be decked separately. Deck depth shall not exceed three layers of logs. They shall be constructed with shorter log lengths on the top layers. Title to all such timber shall remain with the Government.

2010 02230 - 2 Site Clearing

F. All conifer timber removed during clearing operations having a diameter between 3” and 6”, or not meeting the minimum length specified in 3.01.E, shall be trimmed of limbs and top and neatly decked at a location designated by the CO on the construction site. Title to all such timber shall remain with the Government.

G. Limbs with a diameter of less than 3 in. and brush shall be considered vegetative debris and treated in accordance with subsection 3.03.

3.02 GRUBBING

A. Utility lines: Inside the clearing limits, cut stumps and projecting roots flush with the natural ground.

B. Structures, Buildings, and Areas to be Graded: Inside the clearing limits, Grub and remove all stumps. Grub and remove all roots to a depth of at least 18 in.

below the natural ground when fill is required for site grading. When excavation is required for site grading, grub and remove all roots to a depth of at least 18 in. below finished grade.

3.03 DISPOSAL

A. Disposal of vegetative debris shall be accomplished by scattering the debris within the project site as directed by the CO.

B. Stumps shall be buried in the unsuitable and excess excavation area. See

Section 02315 – Excavation and Fill, Part 3.02, Subpart A.

C. Rubbish (non-vegetative) shall be disposed of by removal from project in accordance with federal and local regulations.

2010 02315 - 1 Excavation and Fill

SECTION 02315

EXCAVATION AND FILL

A. Defines suitable, unsuitable, and excess excavation. Explains procedures for handling excess excavation and unsuitable excavation.

1.02 DEFINITIONS

A. Suitable Excavation: Excavated material suitable for use as backfill. Suitable excavation does not contain rock greater in size than that approved for the specific backfill purpose, frozen earth, clods, debris, or material with an exceptionally high void content (vegetative matter). The size of rock is dependent on the purpose and location of the backfill. Refer to the individual sections for backfill definitions.

A. Unsuitable Excavation: The opposite of suitable excavation. Excavated material not suitable for use as backfill.

C. Excess Excavation: Surplus excavation that is not needed to complete construction. Excess excavation can be either suitable or unsuitable excavation.

1.03 RELATED SECTIONS

A. Section 02316 – Trenching, Backfilling, and Compacting

B. Section 02317 – Excavating and Backfilling for Structures

C. Section 02510 – Water Distribution

D. Section 16201 – Wiring Systems

2010 02315 - 2 Excavation and Fill

PART 3 EXECUTION

3.01 SHORTAGE OF SUITABLE EXCAVATION

A. Unsuitable excavation may be processed onsite by the contractor, by screening or other methods to produce suitable excavation.

B. In lieu of processing unsuitable excavation, contractor may import suitable excavation at no cost to the government.

3.02 DISPOSAL OF UNSUITABLE AND EXCESS EXCAVATION

A. Dispose of unsuitable and excess excavation in an area within the campground designated by the CO.

B. Disposal site shall be stripped of 150mm (6”) of topsoil and stockpiled prior to disposal operations.

C. Excess and unsuitable excavation shall be end dumped, and spread to approximate natural contours.

D. After disposal operations are complete, spread stockpiled topsoil 150mm (6”) deep over site to approximate natural contours.

2010 02316 - 1 Trenching, Backfilling, and Compacting

SECTION 02316

TRENCHING, BACKFILLING, AND COMPACTING

A. Includes excavation of trenches, installation of detection and marking tape, and backfill and compaction of trenches for the installation of utility lines to the depths and dimensions AS SHOWN ON THE DRAWINGS.

1.02 PROTECTION

A. Maintain the excavations to guard against and prevent injury to employees and the public. Provide adequate shoring and bracing as required by OSHA and other local governing regulations.

B. Protect the excavation from frost action. Compact ground that has frozen and subsequently thawed as specified herein.

C. Prevent water accumulation in excavations. If clay soil becomes saturated, compact after it has dried as specified herein.

D. Minimum depth of soil cover for utility lines (measured from the top of the pipe, conduit, or cable to final construction ground elevation required) is AS SHOWN

ON THE DRAWINGS.

1.03 REFERENCES

A. Standard Moisture Density Test, AASHTO T-99, Method C or D.

1.04 CLASS OF MATERIAL

A. All material to be excavated for installation of utilities is unclassified.

1.05 APPROVALS

A. Notify the CO when excavation is completed. Do not place pipe, bedding or backfill until the excavation is approved by the CO. Do not cover pipe until placement has been approved by the CO.

2010 02316 - 2 Trenching, Backfilling, and Compacting

2.01 BEDDING AND INITIAL BACKFILL

A. Well-graded, rounded or angular stone or gravel, sand, or other materia l approved by the CO. Bedding may be processed from onsite-excavated material or imported from offsite. 100% of the material shall pass the 1/2" sieve, and no more than 12% of the material shall pass the No. 200 sieve. Material shall not contain frozen earth, clods, debris, or material with an exceptionally high void content (vegetative matter).

2.02 SUBSEQUENT BACKFILL

A. Earth material free from large rock greater than 6” in its largest dimension, frozen earth, clods, debris, or material with an exceptionally high void content (vegetative matter).

2.04 FREE DRAINING GRAVEL

A. Clean, rounded gravel material 3/4" - 1-1/2" in greatest dimension. AASHTO

M 43-88, Size No. 4.

2.05 UNDERGROUND DETECTION AND MARKING TAPE

A. General: Buried utilities shall require detection OR marking tape (as specified in Part 2.05-B & C) with the following inscription permanently written on a colored background as shown below:

UTILITY COLOR INSCRIPTION

Water Blue Caution Buried Water Line Below Sewer Green Caution Buried Sewer Line Below Electric Red Caution Buried Electric Line Below Telephone Orange Caution Buried Phone Line Below

For the inscription, similar wording with identical meaning will be approved.

The inscription shall be repeated, consecutively, along the entire length of tape.

Color substitution shall not be permitted.

B. Non-metallic Piping Systems and Telephone: Use Detection tape 3" wide, 1-1/2 mil thick aluminum foil with a polyethylene covering on the inscription side, non- luminescent, and colorfast.

C. Metallic Piping Systems and Electric: Use detection tape as outlined above or marking tape 6" wide, 4-mil thick, low-density polyethylene, non-luminescent, and colorfast.

2010 02316 - 3 Trenching, Backfilling, and Compacting

D. The tape shall be as manufactured by C.H. Hanson Company, 3630 North Wolf

Road, Franklin Park, IL 60131, (800) 827-3398 or approved equal.

3.01 EXCAVATION

A. All excavation shall be by open-cut from ground surface except when boring or tunneling is expressly called for on the drawings.

B. The sides of trenches shall be kept as nearly vertical as practicable. In no instance shall the trench from 6” above the top of the pipe to the bottom of the trench be more than 16” wider than the outside diameter of the pipe. Maximum trench width shall be 24".

3.02 ROCK BLASTING

A. There will be no rock blasting allowed.

3.03 BACKFILLING

A. Electrical Control Cable: Place 4" of fine material in electrical cable trenches prior to installation of conduit and cable. After installation of conduit and cable, place 4" of fine material along sides and over top of conduit. Compact each layer to 90 percent of maximum dry density in accordance with ASSHTO T-99, Method C.

B. Trenches shall be dry prior to placing bedding. Trenches shall not be frozen or have snow in them prior to placing bedding. Depressions in the trench bottom shall be excavated with hand tools to accommodate valves, fittings, etc.

C. Bedding shall be installed to the full width of the trench bottom to a minimum depth of 1/4 the pipe (or conduit) outer diameter (O.D.) below the pipe and across the trench 4" minimum depth in any case, and around the pipe to fully…