AG-82B1-S-10-0218

Section B: Supplies or Services/Prices

CANYON CREEK ROAD DECOMMISSIONING

Total Canyon Creek Road Decommissioning $______________

HIGHLINE BREAKS ROAD STORAGE

Total Highline Breaks Road Storage $________________

Section C: Description/Specifications

C-1 - PROJECT DESCRIPTION AND LOCATION

452.211-72 Statement of Work/Specifications. (FEB 1988)

452.211-73 Attachments to Statements of Work/Specifications. (FEB 1988)

Section D: Packaging and Marking

Section E: Inspection and Acceptance

52.246-13 -- Inspection -- Dismantling, Demolition, or Removal of Improvements. (Aug. 1996)

Section F: Deliveries or Performance

Section G: Contract Administration Data

452.215-73 Postaward Conference. (NOV 1996)

Section H: Special Contract Requirements

FAR 52.236-4 Physical Data (APR 1984)

BARRICADES, WARNING SIGNS, AND OTHER DEVICES

452.236-77 Emergency Response. (NOV 1996)

452.237-74 Key Personnel. (FEB 1988)

Section I: Contract Clauses

52.204-11 American Recovery and Reinvestment Act--Reporting Requirements. (MAR 2009)

52.209-5 -- Certification Regarding Responsibility Matters. (Dec 2008) 52.215-2 -- Audit and Records – Negotiation. Alternate I (Mar 2009)

52.219-28 Post-Award Small Business Program Rerepresentation. (APR 2009)

52.222-42 Statement of Equivalent Rates for Federal Hires. (MAY 1989)

52.223-13 -- Certification of Toxic Chemical Release Reporting. (Aug 2003) 52.223-14 -- Toxic Chemical Release Reporting. (Aug 2003) 52.225-13 -- Restrictions on Certain Foreign Purchases. (Jun 2008) 52.227-1 -- Authorization and Consent. (Dec 2007) 52.229-3 -- Federal, State, and Local Taxes. (Apr 2003) 52.232-9 -- Limitation on Withholding of Payments. (Apr 1984)

52.244-6 Subcontracts for Commercial Items. (AUG 2009)

52.252-2 Clauses Incorporated by Reference. (FEB 1998)

Section J: List of Documents, Exhibits and Other Attachments

Section K: Representations, Certifications, and Other Statements of Bidders

52.204-8 Annual Representations and Certifications. (FEB 2009)

52.222-25 Affirmative Action Compliance. (APR 1984)

52.252-1 Solicitation Provisions Incorporated by Reference. (FEB 1998)

Section L: Instructions, Conditions, and Notices to Bidders

52.215-1 Instructions to Offerors - Competitive Acquisition. (JAN 2004)

52.216-1 Type of Contract. (APR 1984)

52.233-2 Service of Protest. (SEP 2006)

52.252-1 Solicitation Provisions Incorporated by Reference. (FEB 1998)

Section M: Evaluation Factors for Award

Section B: Supplies or Services/Prices

Lochsa Ranger District Clearwater National Forest

Idaho County, Idaho

B-1

CANYON CREEK ROAD DECOMMISSIONING

ITEM

NO.

DESCRIPTION

PAY

UNIT

EST.

QTY.

PRICE

TOTAL

15101

Mobilization

Lump Sum

21103A Roadway Obliteration, Method I Mile 9.65 $________

21103B Roadway Obliteration, Method II Mile 4.13 $________

21103C Roadway Obliteration, Method III Mile 4.43 $________

21103A Roadway Obliteration, Method I

Optional Roads*

Mile XX $________ $_________

62201A Hydraulic Excavator with Thumb* Hour XX $________ $_________

62201B

Dump Truck*

Hour

XX

Total Canyon Creek Road Decommissioning $______________

HIGHLINE BREAKS ROAD STORAGE

ITEM

NO.

DESCRIPTION

PAY

EST.

QTY.

TOTAL

15101

Mobilization

Lump Sum

21103A Roadway Obliteration, Method I Mile 1.72

21103B Roadway Obliteration, Method II Mile 4.37 $________ $__________

21103C Roadway Obliteration, Method III Mile 4.07 $_________ $__________

21103A Roadway Obliteration , Method I, Additional Roads* Mile XX

$___XX____

62201A

Hydraulic Excavator with Thumb*

62201B

Dump Truck*

Total Highline Breaks Road Storage $________________

OVERALL TOTAL FOR CANYON CREEK AND HIGHLINE BREAKS $____________________

B-2 – SUBMITTING OFFER

As your offer, submit a signed Standard Form 33, a completed Schedule of Items, a Technical Proposal, and a completed Section K. See Section M for proposal instructions and evaluation/award information. You may use the following form as your technical proposal. Attach additional sheets as necessary.

Facsimile proposals are NOT acceptable.

*Contractor shall give a price per mile under Item 21103A Additional Roadway Obliteration, a price per hour under Item 62201A Hydraulic Excavator with Thumb and a price per hour under Item 62201B Dump Truck for additional work above the estimated quantities that is encountered, or determined neccessary during the contract performance.

The Government does not guarentee any additional quantities will be purchased.

Section C: Description/Specifications

C-1 - PROJECT DESCRIPTION AND LOCATION

a. Description of Work for Canyon Creek Road. The Canyon Creek Road Decommissioning project consists of decommissioning approximately 20 miles of road. These roads range from 12 feet to 30 feet wide with large fills averaging 40 feet deep. Road decommissioning treatments range from placing drainage sturcuters to strong outslopes to complete recontouring. All existing roadways will be decompacted. All fill material in draws will be removed and stream channels restored to natural grade and dimensions. Some material will be end hauled with a dump truck. All disturbed areas will be seeded. In addition, native forbs and shrubs will be transplanted from areas adjacent to the road. Grade control structures will be constructed in newly reconstructed stream channels.

b. Description of Work for Highline Breaks Road. The Highline Breaks Road Storage project consists of decommissioning approximately 10-12 miles of road. These roads range from 12 feet to 24 feet wide with fills averaging 12 feet deep. Road decommissioning treatments range from drainage structure removal to strong outslopes to complete recontouring. Roadways will be decompacted as described in worklists. All fill material in draws will be removed and stream channels restored to natural grade and dimensions. All disturbed areas will be seeded. In addition, native forbs and shrubs will be transplanted from areas adjacent to the road. Grade control structures will be constructed in newly reconstructed stream channels.

c. Project Location. Canyon Creek Road project is located approximately 37 miles northeast of Kooskia, Idaho. From Kooskia travel East on Highway 12 for 14.5 miles to the junction of road 101 (Smith Creek). Turn north on Smith Creek and travel for 21 miles to the junction with the 445. Turn east on the 445 and travel for 1.25 miles to the beginning of the project area. Highline Breaks Road project is located northeast of Kooskia, Idaho. From Kooskia travel East on Highway 12 for 14.5 miles to the junction of road 101 (Smith Creek). Turn north on Smith Creek and travel for 6.36 miles to the junction with the 418. Turn northeast on the 418 and travel for 1.20 miles to the beginning of the project area.

d. Pre-Bid Tour. No pre-bid tour. For questions call Chuck Fowlds (208-476-8369) or Anne Connor (208-476-8235).

e. Start Work. It is estimated that work will begin for both Canyon Creek and Highline Breaks on June 15, 2010. 50% of the Canyon Creek project must be completed by October 30, 2010 with all work on this project being completed no later than October 30, 2011. 100% of the Highline Breaks project must be completed no later than October 30, 2010.

f. Period of Performance (PoP). The PoP for the Canyon Creek project is June 15, 2010 to October 30, 2011. The PoP for the Highline Break project is June 15, 2010 to October 30, 2011.

C-2 - FOREST SERVICE SPECIFICATIONS

Forest Service specifications are included as Attachment A of this solicitation.

C-3 – DRAWINGS

The following drawings for HIGHLINE BREAKS ROAD DECOMMISSIONING are a part of this solicitation and any resulting contract (See attachment D):

The following drawings for CANYON CREEK ROAD DECOMMISSIONING are a part of this solicitation and any resulting contract (See attachment E):

452.211-72 Statement of Work/Specifications. (FEB 1988)

The Contractor shall furnish the necessary personnel, material, equipment, services and facilities (except as otherwise specified), to perform the Statement of Work/Specifications referenced in Section J.

(End of Clause)

452.211-73 Attachments to Statements of Work/Specifications. (FEB 1988)

The attachments to the Statement of Work/Specifications listed in Section J are hereby made part of this solicitation and any resultant contract.

(End of Clause)

Title Page of Pages

Title Sheet 1 of 5

Summary of Estimated Quantities 2 of 5

Road Decommissioning Details 3-4 of 5

Location Map 5 of 5

Road Storage Work Lists (All Roads) 1-16 of 16

Title Page of Pages

Title Sheet 1 of 5

Summary of Estimated Quantities 2 of 5

Road Decommissioning Details 3-4 of 5

Location Map 5 of 5

Road Decommissioning Work Lists (All Roads) 1-24 of 24

Section D: Packaging and Marking

There are no required clauses for this section of this solicitation.

Section E: Inspection and Acceptance

52.246-13 -- Inspection -- Dismantling, Demolition, or Removal of Improvements. (Aug. 1996)

Section F: Deliveries or Performance

F-1 Equipment Rental

Adjustment of contract prices do not apply to Section 622, Rental Equipment, Items: 62201A, Hydraulic Excavator with Thumb or 62201B, Dump Truck or to Item 21103A, Road Obliteration, Method I, Additional Roads. All work under these items will be approved by the government prior to starting with no adjustment in contract unit price.

52.242-15 Stop-Work Order. (AUG 1989)

Section G: Contract Administration Data

452.215-73 Postaward Conference. (NOV 1996)

A post award conference with the successful offeror is required. It will be scheduled within 15 days after the date of contract award. The conference will be held at a mutually agreed upon time and place.

Section H: Special Contract Requirements

FAR 52.236-4 Physical Data (APR 1984)

Data and information furnished or referred to below is for the Contractor’s information.

The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.

(a) The indications of physical conditions on the plans and in the specifications are the result of site investigations by Forest Service specialists making physical determination based on surface observations.

(b) Weather Conditions. Normal snow conditions indicate a work season from approximately June 15 to October 15.

(c) Transportation Facilities. (Canyon Creek) The project is located approximately 37 miles northeast of Kooskia, Idaho. From Kooskia travel East on Highway 12 for

14.5 miles to the junction of road 101 (Smith Creek). Turn north on Smith Creek and travel for 21 miles to the junction with the 445. Turn east on the 445 and travel for

1.25 miles to the beginning of the project area. All roads to project area are single lane, and graveled. Roads are closed by snow in late fall and winter months.

(d) Transportation Facilities. (H9ghland) All roads to project area are single lane, and graveled. Roads are closed by snow in late fall and winter months. Access to the project is from Junction of Highway 12 and FS Road 101 (Smith Creek). Turn North on 101 Road and Travel 6.36 miles to Junction with the 418 Rd. Turn Northeast on the 418 Road and travel for 1.20 Miles to the beginning of Project area.

(e) Access roads and roads to be decommissioned may be overgrown and need to be cleared to gain access before use.

BARRICADES, WARNING SIGNS, AND OTHER DEVICES

The Contractor shall provide, erect, and maintain all necessary barricades, suitable and sufficient lights, danger signals, signs, and other traffic control devices, and shall take all necessary precautions for the protection of the work and safety of the public. Roads closed to traffic shall be protected by effective barricades, and obstructions shall be illuminated during the hours of darkness. Suitable warning signs shall be provided to properly control and direct traffic.

The Contractor shall erect warning signs in advance to any place on the project where operations may interfere with the use of the road or trail by traffic and at all intermediate points where the new work crosses or coincides with an existing road or trail. All road barricades, warning signs, lights, temporary signals, flagmen and pilot car operators and equipment, and other protective devices, except for special devices, shall conform with Part VI of the Manual on Uniform Traffic Control Devices for Streets and Highways, published by the Federal Highway Administration and applicable safety codes.

Necessary warning signs and guards shall be posted during blasting operations to safeguard the public.

…As a minimum, it is anticipated that the following type and number of signs will be required:

Location

Designation

Quantity

At the beginning of each road being worked on that junctions with Rd. 445

ROAD CONSTRUCTION AHEAD

At the beginning of each road being worked on that junctions with Rd. 418 and 455

ROAD CLOSED

LANDSCAPE PRESERVATION

(a) Do not remove, deface, injure, or destroy trees, shrubs, lawn, or natural features not designated for treatment. This does not include access roads. Confine operations to within the clearing limits or other areas designated in the contract documents, and prevent the depositing of rocks, excavated materials, stumps, or other debris outside of these limits. Retrieve material which falls outside of these limits and dispose of, or incorporate in the work.

Preserve the scenic and natural environment along this construction project.

(b) Do not allow objectionable material to enter any stream, river, lake, or other body of water. Retrieve material which falls in these areas and dispose of, or incorporate in the work, and repair damage to vegetation or structures outside the project limits.

(c) Do not operate equipment or otherwise disturb the natural vegetation and soil beyond the construction limits.

ENVIRONMENTAL PROTECTION

Prevention of Oil Spills.

The contractor is required to have a spill plan. The plan will contain a description of the specific hazardous materials, procedures, and spill containment that will be used, including inventory, storage, and handling.

All vehicles carrying fuel will have specific equipment and materials needed to contain or clean up any incidental spills at the project site.

All pumps and generators used in or near streams will have appropriate spill containment structures and/or absorbent pads in place during use.

When storage facilities for oil or oil products are on site, appropriate preventive measures shall be taken to insure that any spill of such oil or oil products does not enter any stream or any other body of water. If a spill of petroleum product should occur in water, immediately notify the Contracting Officer and appropriate state agencies.

Service all equipment only in the areas approved by the Contracting Officer. If the total oil or oil products storage exceeds 1320 gallons or if any single container exceeds a capacity of 660 gallons, prepare a Spill Prevention Control and Countermeasures (SPCC) Plan. Meet all applicable EPA requirements (40 CFR 112) including certification by a registered professional engineer.

Contractor shall ensure that all personnel involved in handling and packaging the hazardous waste are trained for the level of expertise required for the proper performance of the task and, in particular, in the areas of chemical incompatibility, general first aid procedures, and spills. Provide handling and personal protective equipment appropriate to ensure safe handling of the hazardous waste according to 29 CFR 1910.120). Notify the Forest Service of all hazardous material that may be brought onto the National Forest.

The Contractor is solely responsible for all spills or leaks that occur during the performance of this contract. The contractor must clean up spills or leaks in a manner that complies with Federal, state, and local laws and regulations and to the satisfaction of the CO. Any spills resulting in a detectable sheen on water shall be reported to the EPA National Response Center (1-800-424-8802). Any spills over 25 gallons will be reported to the Idaho Division of Environmental Quality and cleanup will be initiated within 24 hours of the spill. When available provide copies of all spill related clean up and closure documentation and correspondence from regulatory agencies.

Equipment Fuel/Oil Leakage.

All equipment used for instream work will be cleaned of external oil, grease, dirt and mud; and leaks repaired; prior to arriving at the project site. All equipment will be inspected by the Contracting Officer’s Representative before unloading at site. Any leaks or accumulations of grease will be corrected before entering streams or areas that drain directly to streams or wetlands.

Equipment used for in-stream or riparian work (including chainsaws and other hand power tools) will be fueled and serviced in an area approved by the CO. When not in use, vehicles will be stored in the designated staging area. The staging area should be in an area that will not deliver fuel, oil, etc. to streams.

Oil-absorbing floating booms, and other equipment such as pads and absorbent “peanuts” appropriate for the size of the stream, will be available on-site during all phases of construction. For small streams with few pools or slack water, booms may not be effective. Use pads and straw bales to anchor booms if necessary. Booms will be placed in a location that facilitates an immediate response to potential petroleum leakage.

NOXIOUS WEED CONTROL

In order to prevent the potential spread of noxious weeds into work areas, Contractor shall be required to use weed-free equipment.

The following is considered proof of weed-free equipment:

The Contractor will be required to clean all construction equipment prior to entry on to national forest land. This cleaning shall remove all dirt and plant parts and material that could carry noxious weed seeds into the work area. Only clean construction equipment inspected by the Forest Service will be allowed to operate within the work area. All subsequent move-ins of construction equipment shall be treated in the same manner as initial move-in. "Construction equipment" does not include pickup trucks and personal vehicles.

Straw/Hay Bales shall be certified as “Weed Free”. The source field shall be inspected and certified by the county extension agent from the county that the straw/hay is grown.

Each shipment onto the forest shall be accompanied by a certification tag stating that it is weed free. The contractor shall furnish the forest service with a statement of certification.

FIRE CONTROL (FS 236-1)

(a) Contractor's Responsibility for Contractor-Caused Fires. The Contractor, whether or not directed by the Forest Service, shall immediately extinguish, without expense to the Government, all fires on or in the vicinity of the project which are caused by Contractor's employees, whether set directly or indirectly as a result of Contractor operations. The Contractor may be held liable for all damages and costs of additional labor, subsistence, equipment, supplies, and transportation resulting from fires set or caused by the Contractor's employees or resulting from contract operations.

(b) Other Fires. For the purpose of fighting forest fires on or in the vicinity of the project which are not caused by the Contractor or his employees, the Contractor when requested by the Contracting Officer shall place his employees and equipment temporarily at the disposal of the Forest Service. Payment for such services will be made by the Government at not less than the current rate for fire-fighting services established by the Forest Service in the area concerned.

Any employees and equipment furnished will be relieved from fire fighting as soon as the Forest Service finds that it is practicable to employ other labor and equipment adequate for the protection of the area. An equitable adjustment in contract time may be made for this period.

(c) Fire Protection Requirements - Fire Plan. At all times during closed fire season period, as specified by State law, the Contractor shall comply with each of the following provisions to the extent applicable to his operation under the contract.

(1) Fire Tools. The Contractor will provide for each employee in the contract area at least one approved handtool of a type appropriate in the contract area, such as shovel, pulaski, or ax. Tools required and furnished under (2) and (4) below, shall count toward fulfillment of the above requirement. Where additional tools, beyond those required under (2) and (4) below, are to be provided, the Contractor shall seal such tools in one or more boxes painted red and marked "Tools for Fire Only." All tools required herein shall be kept sharp and in good serviceable condition and maintained at locations to be designated by the Forest Service.

(2) Fire Extinguishers and Tools on Mobile or Stationary Equipment. Each unit of powered equipment used in connection with this contract, including automobiles, trucks, tractors, etc., shall be equipped with serviceable tools and fire extinguishers as follows:

One - fire extinguisher, dry chemical type of not less than 2-1/2 pound capacity with a 4 BC or higher rating.

One - shovel, round point #0 lady or equal.

One - ax, 2 pounds or over, 26-inch minimum length, or one pulaski.

One - water container (at least 1-gallon capacity), not required with stationary equipment.

(3) Spark Arresters. Each internal combustion engine shall be provided with a spark arrester or spark arresting device approved by the Forest Service. Exceptions where the Forest Service may approve mufflers, or other equipment in lieu of spark arresters qualified and rated under Forest Service Standard 5100-1a are: (a) small multiposition engines, such as chain saws, shall meet Society of Automotive Engineers J335b standards; (b) passenger-carrying vehicles and light trucks may have baffle-type mufflers with tail pipe; (c) heavy-duty trucks may have a vertical stack exhaust system and muffler, provided the exhaust stack extends above the cab of the vehicle. An exhaust-driven turbocharger is considered to be a satisfactory spark arrester. Internal combustion engine exhaust systems, arresters, and other devices must be properly installed and maintained.

(4) Powersaws. For each powersaw used in connection with this contract, the following will be provided:

One - shovel, round point #0 lady or equal. Shovel must be immediately available for use.

One - Fire extinguisher, containing not less than 8 ounces of extinguisher fluid, or a dry chemical powder-type of not less than 1-pound capacity. The extinguisher must be immediately accessible to the saw operator at all times.

Any fueling or refueling of a powersaw shall only be done in an area which has first been cleared or is free of all material capable of carrying fire; powersaw shall be moved at least 10 feet from place of fueling before starting.

(5) Blasting. Fuse or prima cord shall not be used unless authorized in writing by the COR with special precautions stated.

(6) Smoking. Smoking shall not be permitted within the contract area except on surfaced or dirt roads, at landings, within closed vehicles, in camps, or at other posted places, and shall never be allowed while working or traveling on foot.

(7) Storage of Petroleum and Other Highly Flammable Products. Gasoline, oil, grease, or other highly flammable material will be stored either in a separate building used exclusively for such storage, or at a site when all combustible debris and vegetation is cleared away within a radius of 25 feet. Fire extinguishers and/or sand barrels may be required at such locations specified by the Forest Service when unusually hazardous conditions exist.

(8) Debris Burning and Warming Fires. Burning permits will be required for all debris burning fires. Lunch and warming fires may be allowed in fireproofed areas during periods of low fire danger if and as specified in the fire plan. Such fires must not be left burning unattended.

(9) Precautions for Stoves. Stovepipes on all temporary buildings, trailers, and tents using wood burning stoves, will be equipped with roof jacks and serviceable spark arresters of mesh with openings no larger than 5/8 inch.

All stovepipes, inside and out, will not be closer than 2 feet from any wood or other flammable material or 1 foot if the combustible material is protected by a metal or asbestos shield.

(10) Welding. Welding or use of cutting torches will be permitted only in areas that have been cleared or are free of all material capable of carrying fire.

Flammable debris and vegetation must be removed from within a minimum of 10 feet radius of all welding and cutting torch operations. A shovel and a 5-gallon standard backpack water container (filled) with handpump attached, shall be immediately available for use in the event of a fire start.

(11) Fire Plan. Prior to initiating work on the contract area, during the closed fire season period, a fire prevention and suppression plan will be prepared. The Contractor and the Forest Service will jointly prepare this plan. Such plan shall include a detailed list of men and equipment at the Contractor's disposal for implementing the plan. The fire plan shall also specify additional measures and/or special requirements, such as Hoot Owl restrictions, necessary during periods of critical fire weather conditions.

When Hoot Owl restrictions are invoked, the Forest Service may curtail or shut down all or portions of a Contractor's operations. The following requirements may be imposed:

(i) All high fire risk operations could be terminated at 1300 local time.

(ii) All burning could be stopped, including debris burning fires.

(iii) Patrolman may be required for a period of 2 hours after high fire risk operations and 1 hour after end of work shift. The Contractor shall provide the patrolman unless the contract is for equipment rental, in which case the Government will provide the patrolman.

(12) Pump and Trailer. NOT USED

(13) Burning. Before starting any open burning, the Contractor shall comply with the following:

(i) Submit a burning plan, subject to approval by the Contracting Officer, designed to minimize the impact on air quality and to lessen any fire damage.

(ii) Submit a burning permit from the District Ranger.

(iii) Use weather forecasts as far as possible in scheduling burning for more favorable dispersal of smoke.

(iv) Fuel shall be reasonably free of dirt and piled to facilitate rapid and complete combustion. Piles shall be tended during burning operations to maintain combustion and to eliminate unnecessary smudges. Piles shall be patrolled during off-work hours to avoid wildfires.

(v) Unless fire season controls dictate otherwise, burning shall be scheduled, as far as practicable, for the most favorable conditions during the burning period.

(vi) Under certain atmospheric conditions, smoke accumulations may become excessive and in these cases, the Regional Forester may, at his discretion, prohibit all open burning for definite periods within specific areas of the National Forest.

452.236-77 Emergency Response. (NOV 1996)

(a) Contractor's Responsibility for Fire Fighting. (1) The Contractor, under the provisions of FAR clause 52.236-9, PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS, shall immediately extinguish all fires on the work site other than those fires in use as a part of the work. (2) The Contractor may be held liable for all damages and for all costs incurred by the Government for labor, subsistence, equipment, supplies, and transportation deemed necessary to control or suppress a fire set or caused by the Contractor or the Contractor's agents or employees.

(b) Contractor's Responsibility for Notification in Case of Fire. The Contractor shall immediately notify the Government of any fires sighted on or in the vicinity of the work site.

(c) Contractor's Responsibility for Responding to Emergencies. When directed by the Contracting Officer, the Contractor shall allow the Government to temporarily use employees and equipment from the work site for emergency work (anticipated to be restricted to fire fighting). An equitableadjustment for the temporary use of employees and equipment will be made under the CHANGES clause, FAR 52.243-4.

(End of clause)

452.237-74 Key Personnel. (FEB 1988)

(a) The Contractor shall assign to this contract the following key personnel: Site Manager

(b) During the first ninety (90) days of performance, the Contractor shall make no substitutions of key personnel unless the substitution is necessitated by illness, death, or termination of employment. The Contractor shall notify the Contracting Officer within 15 calendar days after the occurrence of any of these events and provide the information required by paragraph (c) below.

After the initial 90-day period, the Contractor shall submit the information required by paragraph

(c) to the Contracting Officer at least 15 days prior to making any permanent substitutions.

(c) The Contractor shall provide a detailed explanation of the circumstances necessitating the proposed substitutions, complete resumes for the proposed substitutes, and any additional information requested by the Contracting Officer. Proposed substitutes should have comparable qualifications to those of the persons being replaced. The Contracting Officer will notify the Contractor within 15 calendar days after receipt of all required information of the decision on substitutions. The contract will be modified to reflect any approved changes of key personnel.

Section I: Contract Clauses

52.202-1 Definitions. (JUL 2004)

52.203-3 Gratuities. (APR 1984)

52.203-5 Covenant Against Contingent Fees. (APR 1984)

52.203-6 Restrictions on Subcontractor Sales to the Government. (SEP 2006)

52.203-7 Anti-Kickback Procedures. (JUL 1995)

52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity. (JAN 1997)

52.203-10 Price or Fee Adjustment for Illegal or Improper Activity. (JAN 1997)

52.203-12 Limitation on Payments to Influence Certain Federal Transactions. (SEP 2007)

52.203-15 – Whistleblower Protections Under the American Recovery and Reinvestment Act of 2009.

(Mar 2009)

(a) The Contractor shall post notice of employees rights and remedies for whistleblower protections provided under section 1553 of the American Recovery and Reinvestment Act of 2009 (Pub. L. 111–5).

(b) The Contractor shall include the substance of this clause including this paragraph (b) in all subcontracts.

52.204-4 Printed or Copied Double-Sided on Recycled Paper. (AUG 2000)

52.204-7 Central Contractor Registration. (APR 2008)

52.204-11 American Recovery and Reinvestment Act--Reporting Requirements. (MAR 2009)

(a) Definitions. As used in this clause--

"Contract," as defined in FAR 2.101, means a mutually binding legal relationship obligating the seller to furnish the supplies or services (including construction) and the buyer to pay for them. It includes all types of commitments that obligate the Government to an expenditure of appropriated funds and that, except as otherwise authorized, are in writing. In addition to bilateral instruments, contracts include (but are not limited to) awards and notices of awards; job orders or task letters issued under basic ordering agreements; letter contracts; orders, such as purchase orders, under which the contract becomes effective by written acceptance or performance; and bilateral contract modifications. Contracts do not include grants and cooperative agreements covered by 31 U.S.C.

6301, et seq. For discussion of various types of contracts, see FAR Part 16.

"First-tier subcontract" means a subcontract awarded directly by a Federal Government prime contractor whose contract is funded by the Recovery Act.

"Jobs created" means an estimate of those new positions created and filled, or previously existing unfilled positions that are filled, as a result of funding by the American Recovery and Reinvestment Act of 2009 (Recovery Act). This definition covers only prime contractor positions established in the United States and outlying areas (see definition in FAR 2.101). The number shall be expressed as "full-time equivalent" (FTE), calculated cumulatively as all hours worked divided by the total number of hours in a full-time schedule, as defined by the contractor. For instance, two full-time employees and one part-time employee working half days would be reported as 2.5 FTE in each calendar quarter.

"Jobs retained" means an estimate of those previously existing filled positions that are retained as a result of funding by the American Recovery and Reinvestment Act of 2009 (Recovery Act). This definition covers only prime contractor positions established in the United States and outlying areas (see definition in FAR 2.101). The number shall be expressed as "full-time equivalent" (FTE), calculated cumulatively as all hours worked divided by the total number of hours in a full-time schedule, as defined by the contractor. For instance, two full-time employees and one part-time employee working half days would be reported as 2.5 FTE in each calendar quarter.

"Total compensation" means the cash and noncash dollar value earned by the executive during the contractor's past fiscal year of the following (for more information see 17 CFR 229.402(c)(2)):

(1) Salary and bonus.

(2) Awards of stock, stock options, and stock appreciation rights. Use the dollar amount recognized for financial statement reporting purposes with respect to the fiscal year in accordance with the Statement of Financial Accounting Standards No. 123 (Revised 2004) (FAS 123R), Shared Based Payments.

(3) Earnings for services under non-equity incentive plans. Does not include group life, health, hospitalization or medical reimbursement plans that do not discriminate in favor of executives, and are available generally to all salaried employees.

(4) Change in pension value. This is the change in present value of defined benefit and actuarial pension plans.

(5) Above-market earnings on deferred compensation which is not tax-qualified.

(6) Other compensation. For example, severance, termination payments, value of life insurance paid on behalf of the employee, perquisites or property if the value for the executive exceeds $10,000.

(b) This contract requires the contractor to provide products and/or services that are funded under the American Recovery and Reinvestment Act of 2009 (Recovery Act). Section 1512(c) of the Recovery Act requires each contractor to report on its use of Recovery Act funds under this contract. These reports will be made available to the public.

(c) Reports from contractors for all work funded, in whole or in part, by the Recovery Act, and for which an invoice is submitted prior to June 30, 2009, are due no later than July 10, 2009.

Thereafter, reports shall be submitted no later than the 10th day after the end of each calendar quarter.

(d) The Contractor shall report the following information, using the online reporting tool available at http://www.FederalReporting.gov.

(1) The Government contract and order number, as applicable.

(2) The amount of Recovery Act funds invoiced by the contractor for the reporting period. A cumulative amount from all the reports submitted for this action will be maintained by the government's on-line reporting tool.

(3) A list of all significant services performed or supplies delivered, including construction, for which the contractor invoiced in this calendar quarter.

(4) Program or project title, if any.

(5) A description of the overall purpose and expected outcomes or results of the contract, including significant deliverables and, if appropriate, associated units of measure.

(6) An assessment of the contractor's progress towards the completion of the overall purpose and expected outcomes or results of the contract (i.e., not started, less than 50 percent completed, completed 50 percent or more, or fully completed). This covers the contract (or portion thereof) funded by the Recovery Act.

(7) A narrative description of the employment impact of work funded by the Recovery Act. This narrative should be cumulative for each calendar quarter and only address the impact on the contractor's workforce. At a minimum, the contractor shall provide--

(i) A brief description of the types of jobs created and jobs retained in the United States and outlying areas (see definition in FAR 2.101). This description may rely on job titles, broader labor categories, or the contractor's existing practice for describing jobs as long as the terms used are widely understood and describe the general nature of the work; and

(ii) An estimate of the number of jobs created and jobs retained by the prime contractor, in the United States and outlying areas. A job cannot be reported as both created and retained.

(8) Names and total compensation of each of the five most highly compensated officers of the Contractor for the calendar year in which the contract is awarded if--

(i) In the Contractor's preceding fiscal year, the Contractor received--

(A) 80 percent or more of its annual gross revenues from Federal contracts (and subcontracts), loans, grants (and subgrants) and cooperative agreements; and

(B) $25,000,000 or more in annual gross revenues from Federal contracts (and subcontracts), loans, grants (and subgrants) and cooperative agreements; and

(ii) The public does not have access to information about the compensation of the senior executives through periodic reports filed under section 13(a) or 15(d) of the Securities Exchange Act of 1934 (15 U.S.C. 78m(a), 78o(d)) or section 6104 of the Internal Revenue Code of 1986.

(9) For subcontracts valued at less than $25,000 or any subcontracts awarded to an individual, or subcontracts awarded to a subcontractor that in the previous tax year had gross income under $300,000, the Contractor shall only report the aggregate number of such first tier subcontracts awarded in the quarter and their aggregate total dollar amount.

(10) For any first-tier subcontract funded in whole or in part under the Recovery Act, that is over $25,000 and not subject to reporting under paragraph 9, the contractor shall require the subcontractor to provide the information described in (i), (ix), (x), and (xi) below to the contractor for the purposes of the quarterly report. The contractor shall advise the subcontractor that the information will be made available to the public as required by section 1512 of the Recovery Act. The contractor shall provide detailed information on these first-tier subcontracts as follows:

(i) Unique identifier (DUNS Number) for the subcontractor receiving the award and for the subcontractor's parent company, if the subcontractor has a parent company.

(ii) Name of the subcontractor.

(iii) Amount of the subcontract award.

(iv) Date of the subcontract award.

(v) The applicable North American Industry Classification System (NAICS) code.

(vi) Funding agency.

(vii) A description of the products or services (including construction) being provided under the subcontract, including the overall purpose and expected outcomes or results of the subcontract.

(viii) Subcontract number (the contract number assigned by the prime contractor).

(ix) Subcontractor's physical address including street address, city, state, and country. Also include the nine-digit zip code and congressional district if applicable.

(x) Subcontract primary performance location including street address, city, state, and country. Also include the nine-digit zip code and congressional district if applicable.

(xi) Names and total compensation of each of the subcontractor's five most highly compensated officers, for the calendar year in which the subcontract is awarded if--

(A) In the subcontractor's preceding fiscal year, the subcontractor received--

(l) 80 percent or more of its annual gross revenues in Federal contracts (and subcontracts), loans, grants (and subgrants), and cooperative agreements; and

(2) $25,000,000 or more in annual gross revenues from Federal contracts (and subcontracts), loans, grants (and subgrants), and cooperative agreements; and

(B) The public does not have access to information about the compensation of the senior executives through periodic reports filed under section 13(a) or 15(d) of the Securities Exchange Act of 1934 (15 U.S.C. 78m(a), 78o(d)) or section 6104 of the Internal Revenue Code of 1986.

52.209-5 -- Certification Regarding Responsibility Matters. (Dec 2008)

(a)

(1) The Offeror certifies, to the best of its knowledge and belief, that --

(i) The Offeror and/or any of its Principals --

(A) Are [_] are not [_] presently debarred, suspended, proposed for debarment, or declared ineligible for the award of contracts by any Federal agency;

(B) Have [_] have not [_], within a three-year period preceding this offer, been convicted of or had a civil judgment rendered against them for: commission of fraud or a criminal offense in connection with obtaining, attempting to obtain, or performing a public (Federal, state, or local) contract or subcontract; violation of Federal or state antitrust statutes relating to the submission of offers; or commission of embezzlement, theft, forgery, bribery, falsification or destruction of records, making false statements, tax evasion, violating Federal criminal tax laws, or receiving stolen property; and

(C) Are [_] are not [_] presently indicted for, or otherwise criminally or civilly charged by a governmental entity with, commission of any of the offenses enumerated in paragraph (a)(1)(i)(B) of this provision; and

(D) Have [_], have not [_], within a three-year period preceding this offer, been notified of any delinquent Federal taxes in an amount that exceeds $3,000 for which the liability remains unsatisfied.

(1) Federal taxes are considered delinquent if both of the following criteria apply:

(i) The tax liability is finally determined. The liability is finally determined if it has been assessed. A liability is not finally determined if there is a pending administrative or judicial challenge. In the case of a judicial challenge to the liability, the liability is not finally determined until all judicial appeal rights have been exhausted.

(ii) The taxpayer is delinquent in making payment. A taxpayer is delinquent if the taxpayer has failed to pay the tax liability when full payment was due and required. A taxpayer is not delinquent in cases where enforced collection action is precluded.

(2) Examples.

(i) The taxpayer has received a statutory notice of deficiency, under I.R.C. §6212, which entitles the taxpayer to seek Tax Court review of a proposed tax deficiency. This is not a delinquent tax because it is not a final tax liability. Should the taxpayer seek Tax Court review, this will not be a final tax liability until the taxpayer has exercised all judicial appeal rights.

(ii) The IRS has filed a notice of Federal tax lien with respect to an assessed tax liability, and the taxpayer has been issued a notice under I.R.C. §6320 entitling the taxpayer to request a hearing with the IRS Office of Appeals contesting the lien filing, and to further appeal to the Tax Court if the IRS determines to sustain the lien filing. In the course of the hearing, the taxpayer is entitled to contest the underlying tax liability because the taxpayer has had no prior opportunity to contest the liability. This is not a delinquent tax because it is not a final tax liability.

Should the taxpayer seek tax court review, this will not be a final tax liability until the taxpayer has exercised all judicial appeal rights.

(iii) The taxpayer has entered into an installment agreement pursuant to I.R.C. §6159. The taxpayer is making timely payments and is in full compliance with the agreement terms. The taxpayer is not delinquent because the taxpayer is not currently required to make full payment.

(iv) The taxpayer has filed for bankruptcy protection.

The taxpayer is not delinquent because enforced collection action is stayed under 11 U.S.C. 362 (the Bankruptcy Code).

(ii) The Offeror has [[_] has not [_], within a three-year period preceding this offer, had one or more contracts terminated for default by any Federal agency.

(2) “Principal,” for the purposes of this certification, means an officer; director; owner;

partner; or a person having primary management or supervisory responsibilities within a business entity (e.g., general manager; plant manager; head of a subsidiary, division, or business segment, and similar positions).

This Certification Concerns a Matter Within the Jurisdiction of an Agency of the United States and the Making of a False, Fictitious, or Fraudulent Certification May Render the Maker Subject to Prosecution Under Section 1001, Title 18, United States Code.

(b) The Offeror shall provide immediate written notice to the Contracting Officer if, at any time prior to contract award, the Offeror learns that its certification was erroneous when submitted or has become erroneous by reason of changed circumstances.

(c) A certification that any of the items in paragraph (a) of this provision exists will not necessarily result in withholding of an award under this solicitation. However, the certification will be considered in connection with a determination of the Offeror’s responsibility. Failure of the Offeror to furnish a certification or provide such additional information as requested by the Contracting Officer may render the Offeror nonresponsible.

(d) Nothing contained in the foregoing shall be construed to require establishment of a system of records in order to render, in good faith, the certification required by paragraph (a) of this provision. The knowledge and information of an Offeror is not required to exceed that which is normally possessed by a prudent person in the ordinary course of business dealings.

(e) The certification in paragraph (a) of this provision is a material representation of fact upon which reliance was placed when making award. If it is later determined that the Offeror knowingly rendered an erroneous certification, in addition to other remedies available to the Government, the Contracting Officer may terminate the contract resulting from this solicitation for default.

(End of Provision)

52.209-6 Protecting the Government's Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment. (SEP 2006)

52.215-2 Audit and Records - Negotiation. (MAR 2009)

52.215-2 -- Audit and Records – Negotiation. Alternate I (Mar 2009)

52.215-8 -- Order of Precedence -- Uniform Contract Format (Oct 1997)

52.215-14 -- Integrity of Unit Prices. (Oct 1997)

52.219-6 Notice of Total Small Business Set-Aside. (JUN 2003)

52.219-14 Limitations on Subcontracting. (DEC 1996)

52.219-28 Post-Award Small Business Program Rerepresentation. (APR 2009)

(a) Definitions. As used in this clause -

Long-term contract means a contract of more than five years in duration, including options.

However, the term does not include contracts that exceed five years in duration because the period of performance has been extended for a cumulative period not to exceed six months under the clause at 52.217-8, Option to Extend Services, or other appropriate authority.

Small business concern means a concern, including its affiliates, that is independently owned and operated, not dominant in the field of operation in which it is bidding on Government contracts, and qualified as a small business under the criteria in 13 CFR part 121 and the size standard in paragraph (c) of this clause. Such a concern is ""not dominant in its field of operation'' when it does not exercise a controlling or major influence on a national basis in a kind of business activity in which a number of business concerns are primarily engaged. In determining whether dominance exists, consideration shall be given to all appropriate factors, including volume of business, number of employees, financial resources, competitive status or position, ownership or control of materials, processes, patents, license agreements, facilities, sales territory, and nature of business activity.

(b) If the Contractor represented that it was a small business concern prior to award of this contract, the Contractor shall rerepresent its size status according to paragraph (e) of this clause or, if applicable, paragraph (g) of this clause, upon the occurrence of any of the following:

(1) Within 30 days after execution of a novation agreement or within 30 days after modification of the contract to include this clause, if the novation agreement was executed prior to inclusion of this clause in the contract.

(2) Within 30 days after a merger or acquisition that does not require a novation or within 30 days after modification of the contract to include this clause, if the merger or acquisition occurred prior to inclusion of this clause in the contract.

(3) For long-term contracts -

(i) Within 60 to 120 days prior to the end of the fifth year of the contract; and

(ii) Within 60 to 120 days prior to the date specified in the contract for exercising any option thereafter.

(c) The Contractor shall rerepresent its size status in accordance with the size standard in effect at the time of this rerepresentation that corresponds to the North American Industry Classification System (NAICS) code assigned to this contract. The small business size standard corresponding to this NAICS code can be found at http://www.sba.gov/ services/contractingopportunities/ sizestandardstopics/.

(d) The small business size standard for a Contractor providing a product which it does not manufacture itself, for a contract other than a construction or service contract, is 500 employees.

(e) Except as provided in paragraph (g) of this clause, the Contractor shall make the rerepresentation required by paragraph (b) of this clause by validating or updating all its representations in the Online Representations and Certifications Application and its data in the Central Contractor Registration, as necessary, to ensure that they reflect the Contractor's current status. The Contractor shall notify the contracting office in writing within the timeframes specified in paragraph (b) of this clause that the data have been validated or updated, and provide the date of the validation or update.

(f) If the Contractor represented that it was other than…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .