SFSR_RD_subgrade_repair_Specs.doc

DOC document 269 KB Posted

Attached to
RECOVERY - South Fork Salmon River Road Subgrade Repair
Solicitation number
AG-82B1-S-09-0109
Issued by

About this file

J2 - Specs

View the file

Other files

File Type Posted
workschedule.pdf PDF
Amendment 001 —
SistersRepair_Final.pdf PDF
Amendment 001 —
Solicitation SF1442.pdf PDF
Main_SFSR_COVER_PAV_PATCH 1_7 —
Wage Determination.doc DOC document
fire precautions.doc DOC document
FS ARRA SIGN DETAILS 2apr09.pdf PDF
AG-82B1-S-09-0109.doc DOC document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

South Fork Salmon River Road Subgrade Repair Table of Contents

1Table of Contents

Preface 101 - Terms, Format, and Definitions

101.01 Meaning of Terms

101.03 Abbreviations.

101.04 Definitions.

102 - Bid, Award, and Execution of Contract 102 Bid, Award, and Execution of Contract 103 - Scope of Work Deletions 104 - Control of Work Deletions

104.06 Use of Roads by Contractor

105 - Control of Material

105.02 Material Sources.

105.02(a) Government-provided sources.

105.05 Use of Material Found in the Work.

106 - Acceptance of Work

106.07 Delete

109.02 Measurement Terms and Definitions. 11

107 - Legal relations and responsibility to the public………………

108 - Prosecution and progress . 14

109 - Measurement and payment . 15

155 - Schedules for Construction Contracts 156 - Public traffic … . . . ……………………………………………………………. .17 157 - Soil Erosion control . 20

171 - Weed and disease prevention . 22

201 - Clearing and grubbing . 24

203 - Removal of structures and obstructions.

204 - Excavation and embankment

251 - Riprap

251.01 Description

251.02 Material.

251.07 Acceptance

251.09 Payment.

253 - Gabions and revet mattresses

262 - Reinforced Soil Embankment 322 - Minor aggregate courses . 33 Table 262-1 Sampling and Testing Requirements 404 - Minor Hot Asphalt Concrete

404.02 Composition of Mix (Job-Mix Formula).

404.04 Weather Limitations.

404.06 Placing.

404.07 Compacting (a).

404.09 Acceptance.

Table 404-1. Sampling and Testing Requirements.

602 - Culverts and Drains

602.03 General.

635 - Temporary Traffic Control

635.03 General.

703 - Aggregate

703.05 Subbase, Base, Surface Course, and Screened Aggregate.

714 - Geotextile and Geocomposite Drain Material Tables 714-1 and 714-4.

714.03 Geogrids.

Table 714-7—Physical strength requirements for geogrids.

718 - Traffic Signing and Marking Material

Preface

Preface_wo_03_15_2004_m Delete all but the first paragraph and add the following:

The Forest Service, US Department of Agriculture has adopted FP-03 for construction of National Forest System Roads.

101 - Terms, Format, and Definitions

101.00_nat_us_07_25_2005

101.01_nat_us_01_22_2009

101.01 Meaning of Terms

Delete all references to the TAR (Transportation Acquisition Regulations) in the specifications.

101.03_nat_us_06_16_2006

101.03 Abbreviations.

Add the following to (a) Acronyms:

AFPA

MSHA

NIST

NESC

WCLIB

American Forest and Paper Association Mine Safety and Health Administration National Institute of Standards and Technology National Electrical Safety Code West Coast Lumber Inspection Bureau

Add the following to (b) SI symbols:

mp
Milepost
ppm
Part Per Million

101.04_nat_us_03_29_2007

101.04 Definitions.

Delete the following definitions and substitute the following:

Bid Schedule--The Schedule of Items.

Bridge--No definition.

Contractor--The individual or legal entity contracting with the Government for performance of prescribed work. In a timber sale contract, the contractor is the “purchaser”.

Culvert--No definition.

Right-of-Way--A general term denoting (1) the privilege to pass over land in some particular line (including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2) Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.

Add the following:

Adjustment in Contract Price--“Equitable adjustment,” as used in the Federal Acquisition Regulations, or “construction cost adjustment,” as used in the Timber Sale Contract, as applicable.

Change--“Change” means “change order” as used in the Federal Acquisition Regulations, or “design change” as used in the Timber Sale Contract.

Design Quantity--“Design quantity” is a Forest Service method of measurement from the FS-96 Forest Service Specifications for the Construction of Roads and Bridges. Under these FP specifications this term is replaced by the term “Contract Quantities”.

Forest Service--The United States of America, acting through the Forest Service, U.S. Department of Agriculture.

Neat Line--A line defining the proposed or specified limits of an excavation or structure.

Pioneer Road--Temporary construction access built along the route of the project.

Purchaser--The individual, partnership, joint venture, or corporation contracting with the Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.

Protected Streamcourse--A drainage shown on the plans or timber sale area map that requires designated mitigation measures.

Road Order--An order affecting and controlling traffic on roads under Forest Service jurisdiction. Road Orders are issued by a designated Forest Officer under the authorities of 36 CFR, part 260.

Schedule of Items--A schedule in the contract that contains a listing and description of construction items, quantities, units of measure, unit price, and amount.

Utilization Standards--The minimum size and percent soundness of trees described in the specifications to determine merchantable timber.

Add Figure 101-1—Illustration of road structure terms:

Figure 101-1—Illustration of road structure terms.

102 - Bid, Award, and Execution of Contract

102.00_nat_us_02_16_2005

102 Bid, Award, and Execution of Contract

Delete Section 102 in its entirety.

103 - Scope of Work

103.00_nat_us_02_16_2005

Deletions

Delete all but subsection 103.01 Intent of Contract.

104 - Control of Work

104.00_nat_us_06_16_2006

Deletions

Delete Sections 104.01, 104.02, and 104.04.

104.06_nat_us_02_17_2005

Add the following subsection:

104.06 Use of Roads by Contractor

The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to the limitations and authorizations designated in the Road Order(s) or described in the contract, when such use will not damage the roads or national forest resources, and when traffic can be accommodated safely.

105 - Control of Material

105.02_nat_us_01_18_2007

105.02 Material Sources.

105.02(a) Government-provided sources.

Add the following:

Comply with the requirements of 30 CFR 56, subparts B and H. Use all suitable material for aggregate regardless of size unless otherwise designated. When required, re-establish vegetation in disturbed areas according to section 625.

105.05_nat_us_05_12_2004

105.05 Use of Material Found in the Work.

Delete 105.05 (a) and (b) and the last sentence of the second paragraph and substitute the following:

Materials produced or processed from Government lands in excess of the quantities required for performance of this contract are the property of the Government. The Government is not obligated to make reimbursement for the cost of producing these materials.

106 - Acceptance of Work

106.07_nat_us_05_11_2004

106.07 Delete

Delete subsection 106.07.

107 - Legal Relations and Responsibility to the Public

107.05_nat_us_05_11_2004

107.05 Responsibility for Damage Claims.

Delete the entire subsection.

107.06_nat_us_06_16_2006

107.06 Contractor’s Responsibility for Work.

Delete the following from the first paragraph.

“except as provided in Subsection 106.07”.

107.09_nat_us_06_16_2006

107.09 Legal Relationship of the Parties.

Delete the entire subsection.

107.10_nat_us_06_16_2006

107.10 Environmental Protection.

Add the following:

Design and locate equipment repair shops, stationary refueling sites, or other facilities to minimize the potential and impacts of hazardous material spills on Government land.

Before beginning any work, submit a Hazardous Spill Plan. List actions to be taken in the event of a spill. Incorporate preventive measures to be taken, such as the location of mobile refueling facilities, storage and handling of hazardous materials, and similar information. The hazardous spill plan will describe how the contractor will comply with the following three methods to minimize fuel/oil leakage from construction equipment into the stream channel include the following:

i. All equipment used for instream work will be cleaned of external oil, grease, dirt and mud; and leaks repaired; prior to arriving at the project site. All equipment will be inspected by the Contracting Officer’s Representative before unloading at site. Any leaks or accumulations of grease will be corrected before entering streams or areas that drain directly to streams or wetlands.

ii. Equipment used for in-stream or riparian work (including chainsaws and other hand power tools) will be fueled and serviced in an established staging area (site-specifically recommended by CO). When not in use, vehicles will be stored in the designated staging area. The staging area should be in an area that will not deliver fuel, oil, etc. to streams.

iii. Oil-absorbing floating booms, and other equipment such as pads and absorbent “peanuts” appropriate for the size of the stream, will be available on-site during all phases of construction. For very small streams with few pools or slack water, booms may not be effective. More pads and straw bales to anchor booms may be necessary. Booms will be placed in a location that facilitates an immediate response to potential petroleum leakage.

Immediately notify the CO of all hazardous material spills. Provide a written narrative report form no later than 24 hours after the initial report and include the following:

· Description of the item spilled (including identity, quantity, manifest number, and other identifying information).

· Whether amount spilled is EPA or state reportable, and if so whether it was reported, and to whom. Federal and Idaho state regulations regarding spills will be followed: Any spills resulting in a detectable sheen on water shall be reported to the EPA National Response Center (1-800-424-8802). Any spills over 25 gallons will be reported to the IDEQ (1-800-632-800) (or Nevada equivalent), and cleanup will be initiated within 24 hours of the spill.

· Exact time and location of spill including a description of the area involved.

· Containment procedures.

· Summary of any communications the Contractor had with news media, Federal, state and local regulatory agencies and officials, or Forest Service officials.

· Description of clean-up procedures employed or to be employed at the site including final disposition and disposal location of spill residue.

When available provide copies of all spill related clean up and closure documentation and correspondence from regulatory agencies.

The Contractor is solely responsible for all spills or leaks that occur during the performance of this contract. Clean up spills or leaks to the satisfaction of the CO and in a manner that complies with Federal, state, and local laws and regulations.

108 - Prosecution and Progress

108.00_nat_us_02_16_2005

108 Delete.

Delete Section 108 in its entirety.

109 - Measurement and Payment

109.00_nat_us_02_17_2005

109 Deletions

Delete the following entire subsections:

109.06 Pricing of Adjustments.

109.07 Eliminated Work.

109.08 Progress Payments.

109.09 Final Payment.

109.02_nat_us_06_16_2006

109.02 Measurement Terms and Definitions.

(b) Contract quantity.

Add the following:

Contract quantities will be adjusted only when there are errors in the original design of 15% or more.

Change the following:

“(b) Cubic yard” to “(c) Cubic yard”.

Add the following definition:

(p) Thousand Board Feet (Mbf). 1,000 board feet based on nominal widths, thickness, and extreme usable length of each piece of lumber or timber actually incorporated in the job. For glued laminated timber, 1,000 board feet based on actual width, thickness, and length of each piece actually incorporated in the job.

155 - Schedules for Construction Contracts

155.00_nat_us_05_11_2004

155 Delete.

Delete Section 155 in its entirety.

156 - Public Traffic

156.00_nat_us_04_17_2007

Delete Section 156 in its entirety and replace with the following:

Description

156.01 This work consists of controlling and protecting public traffic adjacent to and within the project. This work also includes supplying and installing one ARRA Sign (American Recovery and Reinvestment Act) Material

156.02 Conform to the MUTCD and the following Sections and Subsections:

Construction sign panels

Retro-reflective sheeting

718.01

Temporary concrete barrier

Temporary plastic fence

710.11

Temporary traffic control devices

718.22

156.03 General.

Keep existing roads open to all traffic during road improvement work, and maintain them in a condition that will safely and adequately accommodate traffic. Delays may not exceed 4 hours at any one time followed by an open period of no less than the time necessary to let traffic pass. All work shall be performed between 7 :00 AM and 6:00 PM , Monday through Friday, unless otherwise authorized by the Contracting Officer. If alternate routes are closed by snow, delay times may need to be reduced.

Perform no work that interferes or conflicts with traffic or existing access to the roadway surface until a traffic control plan has been approved. Post construction signs and traffic control devices in conformance with MUTCD. All required signs will be in place and approved prior to beginning work on project.

If the Contractor agrees in writing to allow public traffic to use a new road being constructed prior to completion, it will be considered an existing road for traffic control purposes.

Do not construct detours outside of the clearing limits or use alternate route detours without the approval of the CO.

156.04 Temporary Traffic Control. Install and maintain temporary traffic control devices adjacent to and within the project as required by the approved traffic control plan and the MUTCD. Install and maintain traffic control devices as follows:

(a) Furnish and install traffic control devices before the start of construction operations. The Forest Service will provide two signs for the contractor to install at each end of the road. The signs are made of plywood, are approximately 4 feet by 8 feet and they are orange and black construction warning signs that say:

ROAD CONSTRUCTION

NEXT 30 MILES

EXPECT DELAYS

4 HOUR MAXIMUM

DETOUR LANDMARK

JOHNSON CREEK TO YELLOWPINE

(b) All detours outside of clearing limits will be approved in writing by the Contracting Officer as part of the traffic control plan.

(c) Install only those traffic control devices needed for each stage or phase.

(d) Relocate temporary traffic control devices as necessary.

(e) Remove devices that no longer apply to the existing conditions.

(f) Immediately replace any device that is lost, stolen, destroyed, or inoperative.

(g) Keep temporary traffic control devices clean.

(h) Remove all temporary traffic control devices upon contract completion or when approved.

(i) When required, use flaggers certified by the American Traffic Safety Services Association, the National Safety Council, the International Municipal Signal Association, a state agency, or other acceptable organization. Perform the work described under MUTCD Part 6. Use type III, VII, VIII, or IX retroreflective sheeting on flagger paddles. Do not use flags. Flaggers must wear high visibility safety apparel as required by MUTCD 6E.02.

(j) Maintain roadways and traffic control for public traffic during all periods when work is not in progress The ARRA sign shall say

PUTTING AMERICA

TO WORK

PROJECT FUNDED BY THE

AMERICAN RECOVERY

AND

REINVESTMENT ACT

The Forest Service Shield and the Recovery shield shall also be applied according to the attached layout details.

The specifications and layout details for the sign are attached to this solicitation, (see FS ARRA sign Details ) and the required size for this contract is for use on low speed roads, and for this project the outside dimensions shall be 42 inches by 27 inches.

Install the sign at the start of the project at the location approved by the COR.

156.06 Acceptance. Public traffic work will be evaluated under Subsection 106.02.

Measurement and Payment

156.07 Do not measure Public Traffic for payment. Compensation is made as an indirect payment.

157 - Soil Erosion Control

157.03_nat_us_02_24_2005

157.03 General

Delete the entire subsection and replace with the following:

Prior to the start of construction, submit a written plan that provides permanent and temporary erosion control measures to minimize erosion and sedimentation during and after construction. Do not begin work until the necessary controls for that particular phase of work have been implemented. Do not modify the type, size, or location of any control. Submit the erosion control plan proposal at least 14 days before operations begin to the Contracting Officer for approval.

Incorporate all permanent erosion control features into the project at the earliest practicable time, as outlined in the approved plan.

When erosion control measures are not functioning as intended, immediately take corrective action.

157.03_Forest_4_16_2009

The erosion control plan shall include all necessary measures to protect resources and government improvements. The plan shall include, but is not limited to the following:

1. The construction activities and sequence of implementation relating to specific erosion control measures.

2. The location and type of PERMANENT controls to be implemented during construction.

3. The location and type of TEMPORARY controls to be implemented during construction.

4. The location of each temporary stockpile site for the excavated material, and location of erosion control measures to prevent sediment from washing off of stockpile.

5. A supply of erosion control materials (e.g. silt fence, straw bales, and waddles) will be kept on hand to respond to sediment emergencies. Sterile straw or certified “weed free” straw will be used to prevent introduction of noxious weeds.

Add to the third paragraph:

Upon completion of construction at the site, the contractor shall remove all temporary dewatering materials and equipment from Government property. This includes items such as pumps, pipes and hoses and sandbags.

Add the following:

The Contractor shall adhere to the following practices:

a) In order to protect aquatic organisms, install screens on the intake of pumps with opening of 3/32 inch.

b) Construct the Dewatering and Sediment Control according to the Contractor’s approved plan.

c) Maintain the roads and stockpiles of material in a manner that prevents direct entry of sediment into the stream, by either preventing the erosion of sediments or collecting the sediments before it reaches the stream.

d) Construct permanent and temporary control features to intercept sediments. A settling basin will be constructed, or a portable one used, that is able to handle the volume of water anticipated, and that provides filtering capability. Dewatering of the excavation site, (of ground water from the excavation) will be done by pumping water to the settling basin and the basin shall be cleaned out when full of sediments. .

e) Any sanitation facilities established by the Contractor shall be located as designated by the CO.

f) All project operations will cease, except efforts to minimize storm or high flow erosion, under precipitation and high flow conditions that result in uncontrollable erosion in the construction area.

157.13 Maintenance and cleanup.

Delete the third paragraph and insert the following:

Erosion control materials such as hay bales, silt fences and waddles will be removed by a Forest Service hydrologist or soil scientist when the sites have revegetated.

171 - Weed and Disease Prevention

171.00_nat_us_03_30_2005

Description

171.01 This work consists of washing and treating construction equipment to remove seeds, plants, and plant fragments from the equipment before the equipment is used on National Forest System lands.

Material

171.02 Conform to the following Subsection:

Water

725.01

Construction Requirements

171.03 General . Notify the CO in writing at least 15 days before moving any construction equipment onto National Forest System lands. Construction equipment does not include cars, pickup trucks, and other vehicles that regularly travel between the construction site and areas outside of National Forest System lands.

Perform all work at a location designated on the plans or other locations approved in writing. Provide the CO with an opportunity to monitor the washing and inspection.

171.04 Equipment. Use a high pressure washing system.

For work on National Forest System lands, use a washing system that traps all wash water and either stores it for removal from National Forest System lands or recycles the water for continued use. If the equipment recycles the water, provide adequate filters for seed removal. Dispose of the filter material and removed seeds in an approved manner. Do not mix soaps, detergents, or other chemicals with the wash water.

For work at a commercial washing facility, use an approved facility.

171.05 Washing. Wash the sides, tops, and undercarriages of all construction equipment. Remove all seeds, plants, plant fragments, dirt, and debris from the construction equipment.

171.06 Inspection. Inspect the washed construction equipment, including the undercarriage, to ensure that the washing removed the dirt, debris, and seeds from the construction equipment. Rewash the construction equipment as necessary or as directed.

171.07 Acceptance. Weed prevention will be evaluated under Subsection 106.02.

Measurement

171.08 Do not measure weed prevention for payment.

Payment

171.09 Include all costs associated with the Section 171-Weed Prevention in the unit price for Section 151-Mobilization.

201 - Clearing and Grubbing

201.04_forest_ 07-_27_2009

201.01 Description

Delete the sentence and add the following:

This work consists of clearing and grubbing of the ditches designated on the Work Schedule and in the areas where the subdrain excavation will disturb vegetation.

201.04_nat_us_02_22_2005

201.02 Material

Delete the third sentence that references tree wound dressing.

201.03 General

Delete the last sentence that refers to tree wound dressing.

201.04 Clearing. (c)

Delete paragraph (c) and replace with the following:

(c) In areas outside the excavation, embankment, and slope rounding limits, cut stumps to within 12 inches or one-third of the stump diameter of the ground, whichever is higher, measured on the side adjacent to the highest ground. For timber sales, stump heights will meet the requirements of the Timber Sale contract.

201.04 Clearing.

Delete subsection (d) Add the following:

(e) Trim branches of remaining trees or shrubs to give a clear height of 14 feet above the roadbed unless otherwise indicated. Trim tree limbs as near flush with the trunk as practicable.

(f) Remove brush from log decks. Deck logs so that logs are piled parallel to one another; can be removed by standard log loading equipment; will not damage standing trees; will not interfere with drainage, and will not roll. Keep logs in log decks free of brush and soil.

201.06_forest 06_08_2005

201.06 Disposal.

Delete the section and add the following:

Dispose of limbs using 203.05 (e) windrowing construction slash.

Dispose of tree trunks and stumps and limbs using 203.05 (l) placing slash on construction slopes.

201.07 Acceptance

Delete the second and third sentences.

201.09 Payment:

Delete the section and add the following: Work under this item will be incidental to pay item 203, removal of structures and obstructions.

203 – Removal of Structures and Obstructions 203.05_nat_us_02_18_2005

203.01 Description

Add the following:

The existing corrugated metal pipe shall be removed and disposed of away from Forest land according to all applicable local, state and federal regulations and 203.05 (a). Temporary soil erosion control measures shall be in place prior to commencing. Excavation.

203.05 Disposing of Material.

Add the following:

(e) Windrowing Construction Slash. Place construction slash outside the roadway in neat, compacted windrows approximately parallel to and along the toeline of embankment slopes. Do not permit the top of the windrows to extend above subgrade. Use construction equipment to matt down all material in a windrow to form a compact and uniform pile. Construct breaks of at least 15 feet at least every 200 feet in a windrow. Do not place windrows against trees. Obtain approval for pioneer roads. A pioneer road may be constructed to provide an area for placement of windrows, provided the excavated material is kept within the clearing limits and does not adversely affect the road construction.

(l) Placing Slash on Embankment Slopes. Place construction slash on completed embankment slopes to reduce soil erosion. Place construction slash as flat as practicable on the completed slope. Do not place slash closer than 2 feet below subgrade. Priority for use of available slash is for: (1) through fills; (2) insides of curves; and (3) ditch relief outlets.

204 – Excavation and Embankment

204.01_forest_07-20-2009

203.02 Description

Delete and replace with the following:

This work consists of excavating roadway material to the lines, grades, and elevations shown on the drawings or designated in the Work Schedule This includes disposing of waste and shaping, compacting, and finishing roadway material prior to backfilling. Backfilling shall be according to Section 322.

204.06 Roadway Excavation

(a) General.

Add the following:

When roadway excavation is directly adjacent to waterways, the contractor shall use erosion control methods to keep excavated materials out of the waterways. Erosion control can include straw bales or waddles. Methods shall be submitted for approval prior to embankment work being performed.

Any excavation material deposited outside the roadway limits shall be retrieved by the Contractor as directed by the Contracting Officer.

204.14. Disposal of Unsuitable or Excess material.

Delete and replace with the following:

Dispose of unsuitable material at designated sites or legally off of the project.

Earthen material encountered during excavation, and roadway waste material, including concrete treated base and asphalt surfacing shall be removed and disposed of off of Forest Service system lands.

Measurement Add the following:

Excavation and disposal of Asphalt and cement treated base will be paid by the square feet of asphalt surfacing under pay item 203-03 and will include the cost to sawcut the asphalt surfacing and cement treated base, excavating the asphalt and cement treated base, and hauling and disposing of off the project.

Excavation and disposal of roadway earthen material will be paid by the cubic yard measured in place under pay item 204-16. The cubic yard measured in place is defined as the size of the hole excavated, but it does not include the volume occupied by the asphalt and the cement treated base.

251 - Riprap

251.00_01_us_10_11_2006

251.01 Description

Delete the first sentence and add the following:

This work consists of furnishing, hauling, and placing of riprap for bank protection, slope protection, drainage structures, erosion control, and other features shown on the plans.

251.02 Material.

Add the following:

When shown on the plans stone from the project site may be utilized.

251.07 Acceptance

Delete sampling and testing requirements of Table 251-1 and certification requirements of Subsection 106.03.

251.09 Payment.

Add the following:

The cost of excavation, embankment and haul required for placement of riprap is incidental to pay items listed in the bid schedule. No payment will be made under Item 251.

Section 253 – Gabions and Revet Mattresses

253.03_ Forest_ 07_20-2009

253.03 Construction Requirements

Add the following:

Install all gabions in accordance with the manufacturer’s recommendations. Stretch the gabions under tension to achieve proper alignment and minimize bulging.

262 - Reinforced Soil Embankment

262.00_forest_08_06_2009 Description

262.01 This work consists of constructing reinforced soil embankments by installing Geogrid.

Material

262.02 Conform to the following Subsections:

Geogrid, category 1,2,3,4,5,or 6
(Forest Service supplemental spec ) FSSS Table 714-7
Aggregate Subbase, Grading A
FSSS table 703-2

Construction Requirements

262.03 General. Before beginning work, submit a work plan for acceptance. Allow at least 3 days for acceptance. Include procedures for stretching and staking the geogrid.

Excavate according to Section 209. Grade the foundation for a width equal to the length of reinforcing elements plus 18 inches. Where the embankment is set on a rocky foundation, place 6 inches of aggregate subbase under the geogrid or reinforcing mesh. Dispose of unsuitable or excess excavation material according to Subsection 204.14.

The final limits and configuration of the excavation may vary, depending on the foundation materials encountered during excavation.

262.04 Reinforcing Elements. Place soil reinforcing elements at the specified elevation and alignment. Orient the reinforcing elements so that the maximum tensile strength available is in the direction of specified primary reinforcement.

Do not splice reinforcement elements in the primary direction. Overlap geogrids three ribs in the direction transverse to the primary direction, and attach with hog rings or other approved methods. Overlap reinforcing mesh one rib in the direction transverse to the primary direction.

Prevent wrinkle development or slippage of reinforcement elements during fill placement and spreading.

262.05 Backfilling. Install the base of the reinforced embankment within + 4 inches of the plan elevation or as directed by the CO. Backfill the geogrid with aggregate subbase grading A according to Subsection 209.10. Ensure that no voids exist below the geogrids or reinforcing mesh. Compact each layer according to Forest Service Supplemental Spec 322.05, compaction B. Do not use sheepsfoot rollers for compaction.

Do not damage or disturb the reinforcing elements. Do not operate equipment on the embankment with less than 6 inches of fill on top of the geogrid or reinforcing mesh. Correct all damaged, misaligned, or distorted reinforcing elements.

Backfill and compact behind the stabilized volume with structural backfill according to Subsection 209.10 and 209.11, method (b). At the end of each day's operation, slope the last lift of backfill away from the embankment face to direct surface runoff away from the face. Do not allow surface runoff from adjacent areas to enter the embankment construction area.

262.06 Embankment Slope Treatment. Treat the face of the reinforced slope for erosion control in according to Section 157.

262.07 Acceptance. Reinforcing elements will be evaluated under Subsections 106.02 and 106.03.

Construction of reinforced soil embankments and services will be evaluated under Subsections 106.02 and 106.04.

Aggregate subbase will be evaluated under Subsections 106.02 and 106.04. See Table FSSS 322-1 and 322-2 for sampling and testing requirements.

Measurement

262.08 Measure the items listed in the bid schedule according to Subsection 109.02 and the following.

Measure reinforcing elements by the square yard in place.

Measure aggregate subbase as specified in FSSS 322.

Payment

262.09 The accepted quantities, measured as provided in Subsection 109.02 and above, will be paid at the contract price per unit of measurement for the Section 262 pay item listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05.

262.01_nat_us_05_14_2004

Table 262-1 Sampling and Testing Requirements

Material or Product
Type of Acceptance (Subsection)
Characteristic
Test Methods Specifications
Sampling Frequency
Point of Sampling
Split Sample
Reporting Time
Backfill (704)
Measured and tested for conformance (106.04)
Classification
AASHTO M 145
One per soil type
Source of material
Yes
Before using in work
Gradation
AASHTO T 27 & AASHTO T 11
“
“
“
“
Moisture-Density
AASHTO T 180 Method D(1) or T99 Method C(1)
“
“
“
“
Compaction
AASHTO T 310 or other approved procedures
Minimum two per Lift
In-place
--
Before placing next layer

(1) Minimum of 5 points per proctor.

322 - Minor Aggregate Courses

322.00_nat_us_10_24_2007

Description

322.01 This work consists of constructing one or more courses of aggregate on a prepared surface. Work includes producing aggregate by grid rolling, screening, or crushing methods, or placing pit-run.

Subbase and base aggregate grading is designated as shown in FSSS Table 703-2 Material

322.02 Conform to the following Subsections:

Aggregate

703.05

Water

725.01

Construction Requirements

322.03 General. Prepare the surface on which the aggregate course is placed according to Section 204 or 303 as applicable.

Request approval of the roadbed in writing before placing aggregate.

Develop, haul, and apply water in accordance to Section 170.

Submit target values within the gradation ranges shown in Table 703-2 or 703-3 for the required grading. After reviewing the proposed target values the CO will determine the final values for the gradation and notify the Contractor in writing.

No quality requirements or gradation other than maximum size will be required for pit run and grid-rolled material. For grid rolling, use all suitable material that can be reduced to maximum size.

After processing on the road, remove all oversize material from the road and dispose of it as directed by the CO.

If the aggregate is produced and stockpiled before placement, handle and stockpiled according to Section 320. Establish stockpile sites at approved locations.

322.04 Mixing and Spreading. Mix the aggregate and adjust the moisture content to obtain a uniform mixture with a moisture content suitable for the specified compaction method. Spread and shape the mixture on the prepared surface in a uniform layer with no segregation of size, and to a loose depth that will provide the required compacted thickness.

Do not place in layers exceeding 6 inches in compacted thickness for aggregate base and surface courses or twice the maximum particle size for screened aggregate. When more than one layer is necessary, compact each layer according to Subsection 322.05 before placing the next layer. Route hauling and leveling equipment uniformly over the full width.

When placing aggregate over geotextile, place aggregate in a single lift to the full depth specified.

322.05 Compacting. Compact each layer full width. Roll from the sides to the center, parallel to the centerline of the road. Along curbs, headers, walls, and all places not accessible to the roller, compact the material with approved tampers or compactors.

Compact the aggregate using one of the following methods as specified:

Compaction A. Operating spreading and hauling equipment over the full width of the travelway.

Compaction B. Operate rollers and compact as specified in Subsection 204.11(a)(1).

Compaction C. Moisten or dry the aggregate to a uniform moisture content between 5 and 7 percent based on total dry weight of the mixture. Operate rollers and compact as specified in Subsection 204.11(a)(1).

Compaction D. Compact to a density of at least 95 percent of the maximum density, as determined by AASHTO T 99, method C or D.

Compaction E. Compact to a density of at least 96 percent of the maximum density, as determined by the Modified Marshall Hammer Compaction Method (available upon request from USDA Forest Service, Regional Materials Engineering Center, P.O. Box 7669, Missoula, MT 59807).

Compaction F. Compact to a density of at least 95 per-cent of the maximum density, as determined by AASHTO T 180, method C or D.

Compaction G. Compact to a density of at least 100 percent of the maximum density as determined by the Modified Marshall Hammer Compaction Method (available upon request from USDA Forest Service, Regional Materials Engineering Center, P.O. Box 7669, Missoula, MT 59807).

For all compaction methods, blade the surface of each layer during the compaction operations to remove irregularities and produce a smooth, even surface. When a density requirement is specified, determine the in place density and moisture content according to AASHTO T 310 or other approved test procedures.

322.06 Construction Tolerance. If grade finishing stakes are required, finish the surface to within ±0.10 feet from staked line and grade elevation.

If grade finishing stakes are not required, shape the surface to the required template and check the surface with a 10-foot straightedge. Defective areas are surface deviations in excess of 1/2 inch in 10 feet between any two contacts of the straightedge with the surface.

Correct all defective areas by loosening the material, adding or removing material, reshaping, and compacting.

Ensure that the compacted thickness is not consistently above or below the specified thickness. The maximum variation from the compacted specified thickness is ½ inch.

Ensure that the compacted width is not consistently above the specified width. The maximum variation from the specified width will not exceed +12 inches at any point.

322.07 Maintenance. Maintain the aggregate course to the correct line, grade, and cross‑section by blading, watering, rolling, or any combination thereof until placement of the next course. Correct all defects according to Subsection 322.06.

322.08 Acceptance. See Table 322-1 or Table 322-2 as applicable, for sampling and testing requirements.

Aggregate gradation and surface course plasticity index will be evaluated under Subsection 106.04. If the aggregate is obtained from a Government stockpile then the above characteristics will be evaluated under Subsection 106.02. Other aggregate quality properties will be evaluated under Subsections 106.02 and 106.04. Placement of aggregate courses will be evaluated under Subsections 106.02 and 106.04.

The allowable upper and lower aggregate gradation limits are the Target Value plus or minus the allowable deviations shown in Tables 703-2 and 703-3.

The allowable upper and lower Plasticity index limits for surface courses are stated in 703.05(b).

Preparation of the surface on which the aggregate course is placed will be evaluated under Section 204 or 303 as applicable.

Measurement

322.09 Measure the Section 322 items listed in the bid schedule according to Subsection 109.02 and the following as applicable.

322 09 forest_07_30_2009

Aggregate Base course will be paid by the ton under pay Item 322-01.

Aggregate Subbase course will be paid by the ton under Pay Item 322-05.

322.09_nat_us_10_24_2007

Measure thickness perpendicular to the grade of the travelway.

Measure width perpendicular to the centerline.

Payment

322.10 The accepted quantities will be paid at the contract price per unit of measurement for the Section 322 pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05.

Table 322-1

Sampling and Testing Requirements

Reporting Time
Before using

in work

“
“
“
48 hours

Split

Sample

Yes, when requested
“
“
“
Yes
Point of Sampling
Source of

material

“
“
“
From windrow or roadbed after processing or from approved crusher sampling device

Sampling

Frequency 1 per type & source of material

“
“
“
2 per day
Test Methods Specifications
AASHTO T 96
AASHTO T 104
AASHTO T 210
ASTM D 5821
AASHTO T 2
Category
—
—
—
—
—
Characteristic
LA abrasion (coarse)
Sodium sulfate soundness loss (coarse & fine)
Durability index (coarse & fine)
Fractured faces
Sample
Type of Acceptance (Subsection)
Measured and tested

for conformance

(106.04 & 105) Measured and tested for conformance

(106.04)

Material or Product
Aggregate source quality

703.05 Subbase, Base, and Surface courses

Table 322-1 (continued)

Sampling and Testing Requirements Reporting

Time

Before using in work
“
“
“
Before placing next layer
(1) Minimum of 5 points per proctor.

Split

Yes, when requested
“
“
“
—
Point of Sampling
Source of material
“
“
“
In-place

Sampling

1 per type and source of material
“
“
“
3 per day
Test Methods Specifications
AASHTO T 99 (1)
R-1 Marshall
AASHTO T 180(1)
R-1 Marshall
AASHTO T 310 or other approved procedures
Category
—
—
—
—
—
Characteristic
Moisture-density Method D
Moisture-density Method E
Moisture-density Method F
Moisture-density Method G
In-place density & moisture content
Type of Acceptance (Subsection)
Measured and tested

for conformance (106.04)

Material or Product
Subbase, Base, and Surface

Table 322-2

Sampling and Testing Requirements

Reporting Time
48 hours

Split

Yes

Point of Sampling
From windrow or roadbed after processing or from approved crusher sampling device

Sampling

2 per day

Test Methods Specifications
AASHTO T 2
Category
—
Characteristic
Sample
Type of Acceptance (Subsection)
Measured and tested

for conformance

(106.04 )

Material or Product
Screened Aggregate

404 - Minor Hot Asphalt Concrete

404.01 _forest_07_27_2009

404.01 Description

Delete the complete sentence, and add the following:

This work consists of paving sections of the South fork Salmon River road where subgrade work has occurred. This includes, but is not limited to, applying tack coat to edge joints of asphalt and applying tack coats to edges of concrete, supplying and placing and compacting the asphalt.

The cost to sawcut the existing asphalt surfacing and to sawcut the cement treated base , and to excavate the existing asphalt surfacing and cement treated base, and to haul and dispose the asphalt and cement treated base off of the project is included in Pay Item 203-03.

404.02_nat_us_06_09_2006

404.02 Composition of Mix (Job-Mix Formula).

Delete the second paragraph and replace with the following:

Submit a job-mix formula and supporting documentation, test results, and calculations for the material to be incorporated into the work. Include copies of laboratory test results and mix design data that demonstrate that the properties of the aggregate, additives, and mixture meet the current requirements and criteria of Federal or state agencies. Ensure that the job-mix formula was performed no more than one year prior to placing the hot asphalt concrete. After reviewing the Contractor’s proposed job-mix formula, the CO will determine the final values for the job-mix formula to be used and notify the Contractor in writing.

404.04_nat_us_03_02_2005

404.04 Weather Limitations.

Change 35o F to 45o F:

404.06_nat_us_03_02_2005

404.06 Placing.

Add the following:

Do not place asphalt until the CO has approved in writing the area where it will be placed.

Delete the last sentence and replace with the following:

Offset the longitudinal joint of one layer at least 6 inches from the joint in the layer immediately below. Make the longitudinal joint in the top layer along the centerline of two-lane roadways or at the lane lines of roadways with more than two lanes. Offset transverse joints in succeeding layers and in adjacent lanes at least 10 feet, where possible.

404.07_nat_us_03_02_2005

404.07 Compacting (a).

Delete and replace with the following:

(a) Roadway paving. Thoroughly and uniformly compact the surface a minimum of three passes with rollers that meet one of the following requirements:

(1) Steel-wheeled rollers, other than vibratory type, capable of exerting a force of not less than 1.5 ton/feet of width of the compression roll or rolls.

(2) Vibratory steel-wheel rollers with a minimum mass of 5 ton, equipped with amplitude and frequency controls, and designed to compact asphalt concrete.

(3) Pneumatic-tire rollers with smooth tread tires of equal size that provide a uniform compacting pressure for the full width of the roller and capable of exerting a ground pressure of at least 80 lbf/in2.

Perform initial compaction while the mixture is above 250 °F. Perform finish rolling with steel-wheel rollers and continue until no roller tracks remain.

404.09_nat_us_03_02_2005

404.09 Acceptance.

Add the following to the second paragraph:

See Table 404-1 for sampling and testing requirements.

Table 404-1. Delete and replace with the following:

Table 404-1. Sampling and Testing Requirements.

Material or Product
Type of Acceptance (Subsection)
Characteristic
Category
Sampling Methods Specifications
Sampling Frequency
Point of Sampling
Split Sample
Reporting Time
Asphalt Mixture (404.09)
-
-
-
AASHTO T 168
Three minimum per project and at least one per 500 Cubic yards
Roadway prior to compaction
yes
As soon as sampled

602 - Culverts and Drains

602.03_forest_09_04_2009

602.01 Description.

Add the following:

This work consists of removing the remains of burned out culverts and supplying and installing new culverts on the South Fork Salmon river Road.

This work also includes supplying and installing 4 inch plastic pipe, corrugated polyethylene drainage tubing.

602.03_nat_us_09_06_2005

602.03 General.

Delete the second paragraph and add the following:

Add the following:

The lengths and locations of the individual pipe are approximate. Do not order pipe until culvert locations are designated on the ground and a written list of the correct lengths is approved by the C.O.

Ensure that the final installed alignment of all pipe allows no reverse grades, and does not permit horizontal and vertical alignments to vary from a straight line drawn from center of inlet to center of outlet by more than 2 percent of pipe center length or 1.0 feet, whichever is less.

Clean and paint damaged coating caused by welding, field cutting, or handling in accordance with AASHTO M 36M and ASTM A 849.

Dispose of old culverts and waste debris according to FSSS 204.14.

635 - Temporary Traffic Control

635.03_nat_us_05_13_2004

635.03 General.

Add the following:

Install temporary traffic control signs to temporary posts or approved temporary sign mounts.

703 - Aggregate

703.05_nat_us_12_07_2006

Delete 703.05 and replace with the following:

703.05 Subbase, Base, Surface Course, and Screened Aggregate.

(a) Subbase or base aggregate. Furnish hard, durable particles or fragments of crushed stone, crushed slag, or crushed gravel conforming the following:

(1) Gradation

Table 703-2

(2) Liquid limit, AASHTO T 89

25 max.

(3) Plastic limit, AASHTO T 90

Nonplastic

(4) Los Angeles abrasion, AASHTO T 96

40% max.

(5) Sodium sulfate soundness loss (5 cycles), 12% max.

AASHTO T 104

(6) Durability index (coarse), AASHTO T 210

35 min.

(7) Durability index (fine), AASHTO T 210

35 min.

(8) Fractured faces, ASTM D 5821

50% min.

(9) Free from organic matter and lumps or balls of clay

Do not use material that breaks up when alternately frozen and thawed or wetted and dried.

Obtain the aggregate gradation by crushing, screening, and blending processes as necessary. Fine aggregate, material passing the No. 4 sieve, shall consist of natural or crushed sand and fine mineral particles.

Do not furnish material that contains asbestos fibers.

Delete Table 703-2 and replace with the following:

Table 703-2

Target Value Ranges for Subbase and Base Gradation

Percent by Mass Passing Designated Sieve (AASHTO T 27 and T 11)

Sieve Size
Grading Designation
A (Subbase)
B (Base)
3 inch
100
1 ½ inch
55-85

1 inch

¾ inch
10-35
86-100 (6)
½ inch
5-15

3/8 inch

51-82 (6)

No. 4
0-5
36-64 (6)

No. 40

12-26 (4)

No. 200

4.0 – 7.0 (3)

() The value in the parentheses is the allowable deviation (±from the target values.

714 - Geotextile and Geocomposite Drain Material

714.03_nat_us_02_25_2005

Tables 714-1 and 714-4.

Add the following note to both tables:

(4) Woven slit film will not be allowed.

Add the following:

714.03 Geogrids.

Furnish geogrids consisting of polymeric materials such as polypropylene, polyethylene, or polyester formed into a stable network of bars or straps fixed at their junctions such that the bars retain their relative position to each other.

Elevate and protect rolls with a waterproof cover if stored outdoors.

(a) Physical requirements. Furnish geogrid treated to resist ultraviolet degradation, and conforming to the physical strength requirements shown in table 714-7 according to ASTM D 4595 for the specified geogrid category. Strength values shown in table 714-7 represent minimum average roll values and are for the direction of primary reinforcement. Ensure that the aperture size for all geogrids is between ¾ to 3 inches.

(b) Evaluation procedures. Geogrids will be evaluated under Subsection 106.03. Furnish a certification and a sample of the geogrid.

Table 714-7—Physical strength requirements for geogrids.

Category
Minimum Ultimate Strength at Breakage (lbs/ft)
1
890
2
1985
3
2875
4
4110
5
5475
6
8215

718 - Traffic Signing and Marking Material

718.05_nat_us_02_25_2008

718.05 Aluminum Panels

Delete the third paragraph and replace with the following: