S-0084 ATTACHMENT NO. 2.doc

DOC document 171 KB Posted

Attached to
RECOVERY - ROAD RECONDITIONING. Black Betty Road Decommissioning
Solicitation number
AG-82B1-S-09-0084
Issued by

About this file

Attachment No. 2 Specifications

View the file

Other files

File Type Posted
S-0084 Specs..docx DOCX document
Attachment A-1 S-0084.docx DOCX document
SF30 AMEND 1.pdf PDF
MTSCA76-1342.pdf PDF
S-0084 COVER.pdf PDF
S-0084 DRAWINGS.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

IPNF SPECIAL PROJECT SPECIFICATION

Black Betty Rehab Section 101 - Abbreviations

101.02 Delete in its entirety and substitute the following:

Pay Items & Pay Units And

AC

Acre

AL.

Aluminum

ASP

Asphalt

AVAIL

Available

BARR

Barrier

BKN

Broken

BST

Bituminous Surface Treatment

CATTLEGD

Cattle guard

CLEAR (CLG)

Clearing

CLEAR/GRUB

Clearing & Grubbing

CMP

Corrugated Metal Pipe

COMP

Compaction

CONC

Concrete

CONST

Construction (Construct)

CTD

Coated (Coating)

CUSH

Cushion

CY (CU YD)

Cubic Yard

CY MI (CYM)

Cubic Yard Mile

DIA

Diameter

DL

Double Lane

DWGS

Drawings

EA

Each

EMB

Embankment

EXC

Excavation F&I Furnish & Install

FDN

Foundation

FT

Foot (Feet)

FUNC

Function

GAL

Gallon

GR.

Grade

GRUB

Grubbing

HDPE

High Density Polyethylene

HOR

Horizontal

HR

Hour

HT

Height I Install

IN

Inches

INCL

Including (Includes)

IND

Individual

JCT

Junction L Logs

LBS

Pounds

LDG

Loading

LF (LIN FT

Linear (lineal) Foot

LS

Lump Sum

LT

Left

MAT'L

Material M Metal

MAX

Maximum

MBF

One Thousand Feet Board Measure

MGALS

One Thousand Gallons

MHD

Method

MI

Mile

MIN

Minimum

MISC

Miscellaneous

MP

Mile Post

MSF

One Thousand Square Feet

OTBC

Open Top Box Culvert P M Placement Method

PVC

Polyvinyl chloride

RD

Road

RECOND

Reconditioning

RECONST

Reconstruction (Reconstruct)

REFL

Reflectorized

RT

Right

STMP (STP)

Stump(s)

SB

Self Balance

SEC

Section

SF

Square Foot (Feet)

SL

Single Lane

SLD

Solid

ST

Slash Treatment

STA

Station (100 Feet)

STA YD

Station Yard

STL

Steel

STR (STRUC)

Structural

SY (SQ YD)

Square Yard

SZ

Size T&L Tops & Limbs

TBR

Timber

TH

Thickness

TM

Ton Mile

TO

Turnout

TOL

Turnout Left

TOR

Turnout right

TRS

Trees

UOT

Utilization of timber

VERT

Vertical W Width W/ With W/O Without

X-SEC

Cross Section

YD

Yard

F04 - SPS 101 – 1 (2/3/09)

SPECIAL PROJECT SPECIFICATION

Section 102 - Definitions

Add the following:

"Noxious Weeds or Weeds. Any exotic plant species established or that may be introduced in the State which may render land unfit for agriculture, forestry, livestock, wildlife, or other beneficial uses and which is designated by the State's Department of Agriculture, or by the County's weed management district, or by other appropriate agencies having jurisdiction, or as listed on the current "All States Noxious Weed List".

Shop Drawings. Incidental design sheets and/or drawings, which the Contractor is required to submit to the Contracting Officer. Shop drawings shall conform to the contract requirements, but they are not part of the contract drawings. They may be drawings, diagrams, schedules, performance charts, brochures, and similar data prepared by the Contractor, subcontractor, manufacturer, suppliers, or distributors that illustrate how specific portions of the work are to be fabricated or installed.

Weed Management District. A weed management district is any area of land identified for one of the following: a project or job site, a County, two or more Counties, or a National Forest.

De-compaction. De-compaction is the process of mechanically loosening the surface layer or layers of a road. De-compaction may be performed by any means that loosens the soil to a condition similar to natural soil conditions. After de-compaction the surface should be left in a roughened condition free of any furrows that may concentrate or channel water.”

SPS 102 - 1 (2/3/09)

SPECIAL PROJECT SPECIFICATION

Black Betty Rehab Section 103 – Intent of Contract

Replace the second sentence with the following:

“Unless otherwise provided, the contractor shall furnish all labor, materials, equipment, tools, transportation, and supplies, and shall perform all work as indicated in the drawings and specifications, and in accordance with provisions of the contract.”

SPS 103 - 1 (2/3/09)

SPECIAL PROJECT SPECIFICATION

Black Betty Rehab Section 104 – Maintenance for Traffic 104.01 Roads to be

Delete the first two paragraphs and replace with the following:

Constructed

"All roads shall be closed during project work in accordance with the sign plan.

Prior to the Contractor shutting down any operations, the Contractor shall take such precautions as may be necessary to prevent damage to the project, such as approaches, crossings or intersections; and shall make provisions for normal drainage and minimization of erosion.

CONSTRUCTION SIGNING

The contractor shall provide, erect, and maintain all necessary barricades, suitable and sufficient signs, and other traffic control devices in accordance with the latest edition of the Manual on Uniform Traffic Control Devices (MUTCD). The contractor shall take necessary precautions for the protection of the work and safety of the public. Access roads closed to traffic for safety and to protect the work shall be protected by effective barricades and signs."

PAYMENT

104.03

Basis

"Payment for construction signing and traffic control under this section shall be considered subsidiary to Pay Item 601 Mobilization, and no separate payment will be made."

SPS 104 - 1 (2/3/09)

IPNF SPECIAL PROJECT SPECIFICATION

Black Betty Rehab Section 106 - Measurement & Payment 106.03 Units of Under "(a) Cubic Yard," add the following:

Measurement "(4) Material, Compacted in Place. The measurement computed using measurements of material in the compacted state on the project. Statistically random measurements of length, depth, and width for computation of quantities shall be made when Actual Quantities are shown in the SCHEDULE OF ITEMS."

106.04 Methods of Add the following:

Measurement "The Variation of Quantity Clause does not apply to items paid for on a Designed Quantity (DQ) or Lump Sum Quantity (LSQ) basis."

F04 - SPS 106 - 1 (2/3/09)

SPECIAL PROJECT SPECIFICATION

Black Betty Rehab Section 202 - Removal of Structures and Obstructions

DESCRIPTION

202.01

Work

“Remove a bridge located at the junction of Forest Roads 409 and 965 and a gate at the junction of Forest Road 409 and 962.”

CONSTRUCTION

202.03 Add to this section:

Removal of Bridges, "Upon removal all metal culverts and treated wood from log culverts Culverts, &

(including geotextile fabric), bridge, and gate shall become the property of Other Structures the contractor and shall be removed from National Forest System lands and disposed of in accordance with Federal, State and local laws.

Non-treated woody debris from the removal of log culverts and open top culverts shall be treated as clearing debris and disposed of as SHOWN ON THE DRAWINGS.”

202.04

Delete in entirety.

Removal of Pipe, Other than Culverts

PAYMENT

202.06

Delete in entirety and substitute the following:

“Removal and disposal of drainage structures is incidental to Pay Items listed under 210 as shown in the SCHEDULE OF ITEMS and no separate payment shall be made.”

SPS 202 - 1 (2/3/09)

SPECIAL PROJECT SPECIFICATION

Black Betty Rehab Section 204 - Soil Erosion & Water Pollution Control

DESCRIPTION

204.01

Delete in entirety and substitute the following:

Work "This work consists of special temporary and/or permanent construction measures as SHOWN ON THE DRAWINGS and/or listed in this specification to control soil erosion and water pollution. Such measures may include (but are not limited to) filter windrows, slash blankets, brush barriers, drainage devices, earth berms, earthen water bars, sediment basins, aggregate base/surfacing, rock ditches, riprap, seeding, mulching, and/or straw bales.

This work shall also include special construction methods SHOWN ON THE DRAWINGS to control erosion."

MATERIALS

204.02

Delete the 2nd paragraph and substitute the following:

Requirements "All other materials shall meet commercial grade standards and shall be approved by the Contracting Officer before being incorporated into the project."

CONSTRUCTION

204.03

Delete the 2nd paragraph and substitute the following:

Performance "Erosion control measures shall be incorporated into the project at the earliest practicable time as outlined in the approved schedule"

"Install sediment basins on the downstream side of each stream channel crossing where water occurs AS SHOWN ON THE DRAWINGS.”

SPS 204 - 1 (2/3/09)

SPECIAL PROJECT SPECIFICATION

MEASUREMENT

204.04

Add the following to the first paragraph:

Method

"Items not shown in the SCHEDULE OF ITEMS will not be measured."

204.05

Delete in entirety and substitute the following:

“Erosion control work required under this specification and not shown in the SCHEDULE OF ITEMS shall be incidental to Pay Items listed under 210 as shown Table 1 and no separate payment shall be made.”

Table 1

SECTION
DURATION
DESCRIPTION OF WORK
TIMING OF CONSTRUCTION

Incidental to

Temporary
Sediment basins. Made of noxious weed free straw or grass hay.
Prior to restoration of stream channels where water occurs.

Incidental to 210

Permanent
Water bars
As specified in Section 210

Incidental to 210

Permanent
Seeding
As specified in Section 625

Incidental to 210

Permanent
Full road re-contour
As specified in Section 210

SPS 204 - 2 (2/3/09)

Black Betty Rehab Delete the standard specification “Section 210-Obliteration of Abandoned Roadways” and substitute the following:

Section 210 - Rehabilitation of Abandoned Roadways

DESCRIPTION

210.01 Rehabilitation of roadways includes but is not limited to restoring stream crossings, Work removing ditch relief culverts, full road re-contour, and seeding and mulching disturbed areas. Restore stream crossings by removing fill and drainage structures and installing gradient control structures. This work includes excavation of stream crossings without drainage structures such as springs, seeps, and headwater swales. Identified work is an estimate and it shall be the responsibility of the contractor to determine actual work for each road to meet specifications outlined in the contract.

CONSTRUCTION

210.02

Begin work at the road terminus and progress towards the permanent road closure.

Work may begin at either end if more than one road junction exists. Where roads are overgrown with brush and small regeneration, equipment shall be operated over brush without grubbing, scarifying or otherwise destroying the established root system of the road way except at designated work sites and to maintain a service road for safe passage. Repair existing mass wasting sites to allow heavy equipment access. All drainage structures/appurtenances shall be removed, dismantled and disposed of in accordance with Section 202.

Vegetation in the existing roadway, windfall and/or concentrations of woody debris, frozen soil, ice and snow shall not be incorporated into the excavated material. It may be placed above the road, on finished slopes or hauled to the designated disposal area. After rehabilitation work is completed scatter large boulders, stumps, dead logs, and/or clearing debris on the finished surface AS SHOWN ON THE DRAWINGS.

210.03

Full road re-contour consists of de-compacting the cut slope half of the road

Full Road way to a depth of 30 inches, excavating fill from the fill slope, and embanking on Re-contour the cut slope half of the road way. Contour fill to match the adjacent natural side slopes.

A 200 foot long representative test strip designated by the Contracting Officer shall be de-compacted to determine the adequacy of de-compaction in the upper layer of for each road way within the same width, depth, soil and surface parameters as designated by the Contracting Officer. The Contracting Officer may approve other methods of de-compaction.

SPS 210 - 1 (2/3/09)

SPECIAL PROJECT SPECIFICATION

Black Betty Rehab Close designated roads by fully re-contouring the road AS SHOWN ON THE DRAWINGS. Re-contour a 200 foot section of road within 0.1 mile of milepost

0.0 with a hill slope greater than or equal to 70 percent, or in a location determined by the Contracting Officer.

210.04

All streams, including springs, seeps and headwater swales shall be restored to Stream Channel natural ground slope. Do not place excavated material against a weeping cut bank, Restoration spring or in ponded water, allow for proper drainage. Prior to restoration, install a sediment basin in the stream where water is present AS SHOWN ON THE DRAWINGS. The sediment basin can be eliminated with approval of the Contracting Officer.

Perform stream channel restoration AS SHOWN ON THE DRAWINGS. Prior to restoration, install a sediment basin in the stream channel where surface water is present AS SHOWN ON THE DRAWINGS. The sediment basin can be eliminated with approval of the Contracting Officer. De-compact one half of the roadway nearest the cut slope to a depth of 30” before placing road fill excavated from the stream channel.

Removal of any drainage structures shall be in accordance with Section 202. Adjacent road ways shall be re-contoured to approximate adjacent side slopes. Use logs, rock, or rootwads to install gradient control structures. Trees near the stream channel may be used for gradient control and shall be designated by the Contracting Officer. These trees may require felling or bucking into the proper lengths. Rock can be used for gradient control if conserved from adjacent excavation.

Category I - Typical stream crossing in this category will have a fill length measured from the edge of the road shoulder to the downhill toe of fill of less than 15 feet, may or may not require a drainage structure to be removed, and shall require three gradient control structures to be installed. General difficulty level is low.

Category II - Typical stream crossing in this category will have a fill length measured from the edge of the road shoulder to the downhill toe of fill of greater than 15 feet and less than 25 feet, may or may not require a drainage structure to be removed, and shall require four gradient control structures to be installed. General difficulty level is low to moderate.

Category III - Typical stream crossing in this category will have a fill length measured from the edge of the road shoulder to the downhill toe of fill of greater than 25 feet and less than 40 feet, may or may not require a drainage structure to be removed, and shall require five gradient control structures to be installed. General difficulty level is moderate.

SPS 210 - 2 (2/3/09)

SPECIAL PROJECT SPECIFICATION

Black Betty Rehab Category IV - Typical stream crossing in this category will have a fill length measured from the edge of the road shoulder to the downhill toe of fill of greater than 40 feet and less than 60 feet, may or may not require a drainage structure to be removed, and requires six gradient control structures to be installed. General difficulty level is moderate to high.

Category V - Typical stream crossing in this category will have a fill length measured from the edge of the road shoulder to the downhill toe of fill of greater than 60 feet and less than 80 feet, may or may not require a drainage structure to be removed, and requires seven gradient control structures to be installed. General difficulty level is high.

Category VI - Typical stream crossing in this category will have a fill length measured from the edge of the road shoulder to the downhill toe of fill of greater than 80 feet, may or may not require a drainage structure to be removed, and requires eight gradient control structures to be installed. General difficulty level is high.

210.05

Ditch relief culverts shall consist of the removal of culverts other than those Ditch Relief found at stream crossings. The removal of drainage structures shall be in accordance Culverts with Section 202. The remaining trench shall remain connected to the inside ditch and shall be out sloped to provide drainage.

210.06

Seed and mulch all disturbed areas except where surface water exists in Seeding, accordance with Section 625. After stream channel restoration is complete, break & Mulching open grass hay or straw bales and uniformly scatter on slopes of the newly restored stream channel in loose layers no more than 6 inches thick.

210.07

The method of measurement as described in Section 106, will be designated in the SCHEDULE OF ITEMS. Distances are measured along the road way centerline to the nearest 0.1 mile prior to treatment. Drainage structures (culverts) shall be the number of complete structures measured from inlet to outlet.

210.08

The following items shall be incidental to Pay Items listed under 210 as shown in the

SCHEDULE OF ITEMS and no separate payment shall be made.

SPS 210 - 3 (2/3/09)

(a) Full road re-contour.

(b) Stream channel restoration.

(c) Sediment basins

(d) Gradient control structures

(e) Drainage relief for springs, weeping cut banks, and pond water.

(f) Ditch relief culvert removal.

(g) Seeding & mulching.

The accepted quantities will be paid for at the contract unit price for each

Pay Item shown in the SCHEDULE OF ITEMS.

Payment will be made under:

Pay Item

Pay Unit

210(01) Decommission, Road 962

L.S.

210(02) Decommission, Road 965

SPS 210 - 4 (2/3/09)

Section 601 - Mobilization

DESCRIPTION

601.01 Add the following to this section:

"Preparatory work shall include cleaning of all equipment before entering National

Forest System Lands. The contractor is required to clean all construction equipment prior to entering National Forest System Lands. This cleaning shall remove all dirt, plant parts, and material that may carry noxious weed seeds into the area. Only construction equipment inspected by the Contracting Officer will be allowed to operate within

National Forest System Lands. All subsequent move-ins of equipment shall be treated the same as the initial move-in. Truck beds and dump boxes hauling to the project site must also be cleaned prior to entering the work area.

Prior to initial move-in, the Contractor shall make all construction equipment available for inspection by the Contracting Officer at an agreed upon location. The Contractor shall provide the Contracting Officer at least 24 hours advance notification when equipment is ready for inspection.”

SPS 601 - 1 (2/3/09)

SPECIAL PROJECT SPECIFICATION

Black Betty Rehab Section 619 – Riprap

DESCRIPTION

619.01

“This work includes locally obtaining, excavation and placing of rock for the gradient control AS SHOWN ON THE DRAWINGS.”

RIPRAP

CLASS

STONE

WEIGHT

IN LBS

% SMALLER THAN THE GIVEN
1. 2. & 3. EQUIVALENT CUBIC SIZE

INCHES

BETWEEN

EQUIVALENT

CUBIC SIZE

MM

REMARKS

<---weight Size------------------------------------------------------>

VI
400

1.Size developed from weight using specific gravity of 2.71 and unit weight of 169 LBS/cubic ft. and then rounded to nearest inch.

2.To determine weight of non cubic rocks - use the following formula:

X=WxDxLx .0978 LBS/Cubic Inch

X = Stone Weight (LBS) W = Width D = Depth L = Length Example:

20"x14"x11"x.0978=301lbs

619.21

“Obtaining, excavation and placing of rock for the gradient control is incidental to Pay Items listed under 210 as shown in the SCHEDULE OF ITEMS and no separate payment shall be made.”

SPS 619 - 1 (2/3/09)

SPECIAL PROJECT SPECIFICATION

Black Betty Rehab Section 625 - Seeding & Mulching

DESCRIPTION

625.01 Delete in entirety and substitute the following:

“This work shall consist of preparing seedbeds and furnishing and placing required seed. Straw and grass hay bale sediment basins are used for mulch upon completion of stream channel restoration.”

625.03

Add the following:

Seeding Seasons

“Time of application shall be as specified below:

During the Months marked with an 'X' below:

JAN
FEB
MAR
APR
MAY
JUNE
JULY
AUG
SEPT
OCT
NOV
DEC
x
x
x
x
x

Should climatic conditions permit, application may be performed outside the months marked above upon written approval by the Contracting Officer.”

625.05

The following is added:

Application

Methods for Seed, “The kinds of seed to be furnished and the amounts to be applied in terms of Fertilizer, pure live seed (PLS) shall be as follows for all channel restoration sites and shall

& Limestone be referred to as Standard Moist Site Mix.

Standard Moist Site Mix

SPECIES
PLS LBS/AC
Slender wheatgrass "Pryor" or "Revenue" (Elymus trachycaulus, subspecies trachycaulus)
3.0
Sheep fescue "Durar" (Festuca ovina)
5.0
Mountain brome "Bromar" (Bromus marginatus)
5.0
Annual rye (Lolium multiflorum)
4.0
*Alsike clover (Trifolium hybridum)
2.0
TOTAL
19.0

SPS 625 - 1 (2/3/09)

Black Betty Rehab

Acceptable substitutes:

Blue wildrye "Arlington" or "Elkton" (Elymus glaucus) @ 3 PLS LBS/AC for slender wheatgrass.

Streambank wheatgrass "Sodar" @ 3 PLS LBS/AC for slender wheatgrass.

* Streambank wheatgrass "Sodar" @ 1 PLS LBS/AC for Alsike clover if treating weeds with herbicides or if use of Alsike clover would conflict with other resource values.

The kinds of seed to be furnished and the amounts to be applied in terms of pure live seed shall be as follows for all road and other highly disturbed sites and shall be referred to as the Standard Dry Site Mix.

Standard Dry Site Mix

SPECIES
PLS LBS/AC
Slender wheatgrass "Pryor" or "Revenue" (Elymus trachycaulu,s subspecies trachycaulus)
6.0
Sheep fescue "Durar" (Festuca ovina)
5.0
Streambank wheatgrass "Sodar" (Elymus lanceolatus, subspecies psammophilus)
3.0
Annual rye (Lolium multiflorum)
2.0
Canby bluegrass "Canbar" (Poa canbyi)
4.0
TOTAL
20.0

Acceptable substitutes:

Big bluegrass "Sherman" (Poa ampla) @ 4 PLS LBS/AC for Canby bluegrass.

Pounds of seed to be furnished per acre shall be obtained by dividing the pounds of pure live seed required per acre by the product of the percent purity and percent germination.

Pounds of seed per acre to be furnished shall be obtained by dividing the pounds of pure live seed (PLS) per acre required by the product of the percent purity times the germination rate:

PLS LBS/acre = pounds commercial seed per acre purity x germination

Example:

5 PLS LBS/acre_____ = 6.54 pounds of commercial seed per acre

0.9 x 0.85

(where purity = 90% and germination = 85%)

Apply seed by the Dry Method.”

SPS 625 - 2 (2/3/09)

SPECIAL PROJECT SPECIFICATION

625.06

Application of

Mulch

“After stream channel restoration is completed break open straw or grass hay bales and uniformly scatter on slopes of newly restored stream channel in loose layers no more than 6 inches thick. Mulching shall not be done in the presence of surface water. Apply mulch by the Dry Method.”

625.08

Delete in entirety.

Installation of

Netting & Erosion

Control Blankets

625.11

“Seeding and mulching shall be incidental to Pay Items listed under 210 as shown in the SCHEDULE OF ITEMS and no separate payment shall be made.”

SPS 625 - 3 (2/3/09)

SPECIAL PROJECT SPECIFICATION

Black Betty Rehab

Section 637 - Equipment Rental

DESCRIPTION

637.01

"Equipment Rental work under this project shall be utilized for additional project work not included and described on the Work Site List or included in the SCHEDULE OF ITEMS."

EQUIPMENT

637.03 Items of

Add the following to paragraph (j):

Equipment

Hydraulic Excavator

(1) 150 SAE Net horsepower.

(2) Tracked, crawler type.

(3) No fluid leaks, machine will near stream.

(4) Bucket must be equipped with hydraulic "thumb", claw style with teeth capable of grasping material.

(5) Hook or Eye on backside of bucket to allow attachment of chain or cable.

Bucket capacity minimum 1.75 yards3.

(6) Hydraulically Operated.

(7) Equipped with a frame mounted hook/eye to accommodate attachment of a cable, chain or choker.

(8) Minimum digging depth of 25 feet.

(9) 1995 model or newer.

*Or similar type of equipment accepted by the Contracting Officer.

SPS 637 - 1 (2/3/09)

637.04

Delete this susbsection in entirety.

Moving of

Equipment

637.07

Replace the first sentence in the second paragraph:

Quantities will include the actual hours, to the nearest quarter hour.

637.08

"Pay Item

637(12) Hydraulic Excavator . . . . . . . . . . . . . . . . . . . .HR”

SPS 637 - 2 (2/3/09)

Section 651 – Stream Enhancement Structures

DESCRIPTION

651.01 This work shall consist of hauling and installing cover logs. Erosion control measures shall be taken according to Section 204-Soil Erosion & Water Pollution Control.

651.02

The Contractor will be required to move equipment and/or materials to the

Access work sites. The Contractor is responsible to keep damage to existing vegetation minimal. The contractor shall remove any debris from any vehicle road used in the project area and repair any vehicle road used in the project area to its original condition if damaged by the contractor during contract time.

651.03 Install 20 cover logs at the bridge removal site AS SHOWN ON THE

DRAWINGS. Evenly distribute 10 cover logs amongst restored channel sites on Forest Road 965. The remaining 60 logs are to be used for gradient control on roads 962 and 965.

651.04

Embankment shall be placed in maximum layers of one foot using a hydraulic

Embankment excavator, removing large voids by tamping the entire surface of each layer of the

Placing embankment with the excavator bucket or another method approved by the

Method Contracting Officer. Where material containing a large amount of rock is used to construct embankments, a solid embankment shall be provided by working rocks and fines in with the larger rocks to fill the voids. Excess material generated from stream enhancement structure installation shall be spread over the adjacent undisturbed floodplain in loose layers no more than 6 inches in depth.

MEASUREMENT

651.05

The method of measurement as described in Section 106 will be DESIGNATED Method in the SCHEDULE OF ITEMS.

PAYMENT

651.06 Hauling and installation of cover logs is incidental to Pay Items listed under

651 as shown in the SCHEDULE OF ITEMS and no separate payment shall be made.

Payment will be made under:

Pay Item

651(04) Cover Log

SPS 651 - 1 (2/3/09)

REGIONAL SPECIAL PROJECT SPECIFICATION

Black Betty Rehab Section 713 - Roadside Improvement Materials 713.04

Replace the first paragraph with the following paragraph:

Seed “The kinds of grass, legumes and cover crop seed furnished shall be those stipulated in the SPECIAL PROJECT SPECIFICATIONS. All seed shall meet the requirements of Federal Specification-JJJ-S-181, which shall be amended as follows:

All seed purchased shall be certified to be free of noxious weed seeds from weeds listed on the current "All States Noxious Weeds List".

Replace the second paragraph with the following paragraph:

“Seed shall be furnished separately or in mixture in standard containers with (1) seed name; (2) lot number; (3) net weight; (4) percentages of purity and of germination (in case of legumes, percentage of germination to include hard seed); and (5) percentage of maximum weed seed content clearly marked for each kind of seed. The contractor shall furnish the Contracting Officer duplicate signed copies of a statement certifying that each lot of seed has been tested by a certified seed analyst. This statement shall include (1) name and address of laboratory, (2) date of test, (3) lot number for each kind of seed, and (4) results of tests as to name, percentages of purity and of germination, and percentage of weed content for each kind of seed furnished, and, in case of a mixture, the proportions of each kind of seed. Laboratory testing for noxious weeds shall be conducted prior to seed mixing. Only after a finding and documentation in writing of no weeds on the current "All States Noxious Weeds List" will the seed be accepted and used. Legume seed shall be inoculated with approved cultures in accordance with the instructions of the manufacturer. Seed analysis labels attached to the bags shall be provided to the Contracting Officer.”

R01-85 SPS 713 - 1 (4/96)

File details come from the government source that posted it. Updated .