Ratcliff_Dam_-_Supplemental_Specifications.sealed2.pdf
PDF 2 MB Posted
- Attached to
- Ratcliff Lake Recreation Area Spillway Repair
- Solicitation number
- AG-7DF5-S-17-0006
About this file
Supplemental Specifications
View the file
Other files
| File | Type | Posted |
|---|---|---|
| AG-7DF5-S-17-0006_1.pdf | ||
| Wage_Determination.pdf | ||
| AG-7DF5-S-17-0006.pdf | ||
| Plans_For_Construction_170814.pdf | ||
| CONTRACTORS_FINANCIAL_INFORMATION_SHEET.pdf | ||
| Scope_of_Work.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Specifications 100% Construction Documents Submittal
Project AG-43ZP-C-17-0001 A&E Services to Design Repairs to Ratcliff Dam for National
Forests & Grasslands in Texas
Lufkin, Texas
O’BrienEngineering, Inc.
Hydraulics – Hydrology – Civil Engineering
August 14, 2017 jmcclure Josh Seal - Hor i
Ratcliff Dam Supplemental Specifications FP-03
Table of Contents
Ratcliff Dam Supplemental Specifications FP-03 ........................................................................... i
Table of Contents ............................................................................................................................. i
Preface
101 - Terms, Format, and Definitions
101.01 Meaning of Terms
101.03 Abbreviations
101.04 Definitions
102 - Bid, Award, and Execution of Contract
102 Bid, Award, and Execution of Contract
103 - Scope of Work
Deletions
104 - Control of Work
Deletions
104.03 Specifications and Drawings
104.06 Use of Roads by Contractor
105 - Control of Material
105.02 Material Sources
105.02(a) Government-provided sources
105.02(b) Contractor-provided sources
105.05 Use of Material Found in the Work
106 - Acceptance of Work
106.01 Conformity with Contract Requirements
106.07 Delete
107 - Legal Relations and Responsibility to the Public
Deletions
107.06 Contractor’s Responsibility for Work
107.10 Environmental Protection
ii
107.11 Protection of Forests, Parks, and Public Lands:
108 - Prosecution and Progress
108 Delete
109 - Measurement and Payment
Deletions
109.02 Measurement Terms and Definitions
152 - Construction Survey and Staking
152.01(c) Material
152.02 General
152.03 Survey and Staking Requirements
152.03 (l) Miscellaneous Survey and Staking
Table 152-1 Tolerances for reestablishing P-line, traverse, and elevations
Table 152-2 Cross section and slope stake tolerances
153 - Contractor Quality Control
153.01 Description
153.02 Contractor Quality Control Plan
153.05 Acceptance
155 - Schedules for Construction Contracts
155 Delete
156 - Public Traffic
156.01 Description
156.02 Material
156.03 General
156.04 Temporary Traffic Control
156.05 Temporary Closures
156.06 Acceptance
157 - Soil Erosion Control
157.03 General
170 - Develop Water Supply and Watering
171 - Weed and Disease Prevention
201 – Clearing and Grubbing iii
201.01 Description
201.04 Clearing
203 – Removal of Structures and Obstructions
203.03 Salvaging Material
203.05 Disposing of Material
204 – Excavation and Embankment
204.01 Description
205 – Rock Blasting
205 Delete
206 – Reserved
206 Spillway Area Grading and Fill
206.01 Embankment Fill for Dams and Areas Outside of the Roadway Prism
206.02 Structural Backfill for Dams
206.03 Drainage Aggregate for Dams
208 – Structure Excavation And Backfill For Selected Major Structures
208.04 General
208.06 Cofferdams
208.08 Dewatering
211 – Roadway Obliteration
211 Delete
212 – Linear Grading
212.04 Grading Tolerance
214 – Geocell/Cellular Confinement System
214.04 Quality Assurance and Control
214.05 Installation
214.06 Acceptance
252 – Special Rock Embankment And Rock Buttress
252 Delete
253 – Gabions and Revet Mattresses
Deletions
253.01 Description
iv
253.04 Delivery and Storage
253.05 Handling
253.06 Shop Drawings
253.07 Representative Samples
253.08 Documentation of Testing
253.09 Foundation Preparation
253.10 Installation of Cellular Concrete Mattresses
253.11 Finishing
253.12 Revet Mattresses
253.13 Acceptance
253.14 Measurement
253.15 Payment
254 – Crib Walls
254 Delete
255 – Mechanically Stabilized Earth Walls
255 Delete
256 – Permanent Ground Anchors
256 Delete
257 – Alternate Retaining Walls
257 Delete
258 – Reinforced Concrete Retaining Walls
258.06 Backfilling
258.06 Backfilling
259 – Soil Nail Retaining Walls
259 Delete
260 – Rock Bolts
260 Delete
261 – Rock Dowels
261 Delete
302 – Treated Aggregate Courses
302 Delete v
303 – Road Reconditioning
303 Delete
309 – Emulsified Asphalt-Treated Base Course
309 Delete
324 - Minor Aggregate, Commercial Source
401 – Asphalt Pavements and Surface Treatments
401 Delete
402 – Hot Asphalt Concrete Pavement by Hveem or Marshall Mix Design Method
402 Delete
403 – Hot Asphalt Concrete Pavement
403 Delete
404 – Minor Hot Asphalt Concrete
404 Delete
405 – Open Graded Asphalt Friction Course
405 Delete
408 – Cold Recycled Asphalt Base Course
408 Delete
409 – Asphalt Surface Treatment
409 Delete
410 – Slurry Seal
410 Delete
411 – Asphalt Prime Coat
411 Delete
412 – Asphalt Tack Coat
412 Delete
413 – Asphalt Pavement Milling
413 Delete
414 – Asphalt Pavement Crack and Joint Sealing
414 Delete
415 – Paving Geotextiles
415 Delete vi
416 – Continuous Cold Recycled Asphalt Base Course
416 Delete
417 – Minor Cold Asphalt Mix
417 Delete
501 – Rigid Pavement
501 Delete
502 – Rigid Pavement Restoration
502 Delete
551 – Driven Piles
551 Delete
553 – Prestressed Concrete
553 Delete
555 – Steel Structures
555 Delete
556 – Bridge Railing
556 Delete
557 – Timber Structures
557 Delete
558 – Dampproofing
558 Delete
559 – Waterproofing
559 Delete
560 – Removal of Concrete by Hydrodemolition
560 Delete
563 – Painting
563 Delete
564 – Bearing Devices
564 Delete
565 – Drilled Shafts
565 Delete
566 – Shotcrete vii
566 Delete
602 – Culverts and Drains
602 Delete
603 – Structural Plate Structures
603 Delete
604 – Manholes, Inlets, and Catch Basins
604 Delete
606 – Corrugated Metal Spillways
606 Delete
607 – Cleaning, Reconditioning, and Repairing Existing Drainage Structures
607 Delete
608 – Paved Waterways
608.10 Acceptance
609 – Curb and Gutter
609 Delete
610 – Horizontal Drains
610 Delete
613– Simulated Stone Masonry Surface
613 Delete
615 – Sidewalks, Drive Pads, and Paved Medians
615 Delete
617 – Guardrail
617 Delete
619 – Fences, Gates, and Cattle Guards
619 Delete
625 - Turf Establishment
625.07 Seeding
633 – Permanent Traffic Control
633 Delete
634 – Permanent Pavement Markings
634 Delete viii
635 - Temporary Traffic Control
635.03 General
636 – Signal, Lighting, and Electrical Systems
636 Delete
637 – Facilities and Services
637 Delete
702 – Asphalt Material
702 Delete
703 – Aggregate
Deletions
703.06 Crushed Aggregate
703.09 Reserved
704 – Soil
704.13 Spillway Embankment Fill
704.14 Clay core
704.15 Structural Backfill for Wingwalls
705 - Rock
705.02 Riprap Rock
707 – Metal Pipe
707 Delete
708 – Paint
708 Delete
709 - Reinforcing Steel and Wire Rope
709.01 Reinforcing Steel
709.02 Wire Rope Or Wire Cable
709.03 Prestressing Steel
710 – Fence and Guardrail
710 Delete
714 – Geotextile And Geocomposite Drain Material
714.01(a) Physical Requirements
Tables 714-1 and 714-4 ix
714.03 Geogrids
Table 714-7—Physical strength requirements for geogrids
715 – Piling
715 Delete
716 – Material For Timber Structures
716 Delete
718 – Traffic Signing And Marking Material
718 Delete
720 – Structural Wall And Stabilized Embankment Material
720.01 Mechanically Stabilized Earth Wall Material
720.02 Gabion and Revetment Mattress Material
720.03 Metal Bin Type Crib Walls
721 – Electrical And Illumination Material
721 Delete
Preface
Delete all but the first paragraph and add the following:
The Forest Service, US Department of Agriculture has adopted FP-03 for construction of National Forest System Roads.
101 - Terms, Format, and Definitions
101.01 Meaning of Terms
Delete all references to the TAR (Transportation Acquisition Regulations) in the specifications.
101.03 Abbreviations.
Add the following to (a) Acronyms:
AFPA
MSHA
NIST
NESC
WCLIB
American Forest and Paper Association Mine Safety and Health Administration National Institute of Standards and Technology National Electrical Safety Code West Coast Lumber Inspection Bureau
Add the following to (b) SI symbols:
mp Milepost ppm Part Per Million
101.04 Definitions.
Delete the following definitions and substitute the following:
Bid Schedule--The Schedule of Items.
Bridge--No definition.
Contractor--The individual or legal entity contracting with the Government for performance of prescribed work. In a timber sale contract, the contractor is the “purchaser”.
Culvert--No definition.
Right-of-Way--A general term denoting (1) the privilege to pass over land in some particular line (including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2) Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.
Add the following:
Adjustment in Contract Price--“Equitable adjustment,” as used in the Federal Acquisition Regulations, or “construction cost adjustment,” as used in the Timber Sale Contract, as applicable.
http://www.nist.gov/
Change--“Change” means “change order” as used in the Federal Acquisition Regulations, or “design change” as used in the Timber Sale Contract.
Design Quantity--“Design quantity” is a Forest Service method of measurement from the FS-96 Forest Service Specifications for the Construction of Roads and Bridges. Under these FP specifications this term is replaced by the term “Contract Quantities”.
Forest Service--The United States of America, acting through the Forest Service, U.S.
Department of Agriculture.
Neat Line--A line defining the proposed or specified limits of an excavation or structure.
Pioneer Road--Temporary construction access built along the route of the project.
Purchaser--The individual, partnership, joint venture, or corporation contracting with the Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.
Protected Streamcourse--A drainage shown on the plans or timber sale area map that requires designated mitigation measures.
Road Order--An order affecting and controlling traffic on roads under Forest Service jurisdiction. Road Orders are issued by a designated Forest Officer under the authorities of 36 CFR, part 260.
Schedule of Items--A schedule in the contract that contains a listing and description of construction items, quantities, units of measure, unit price, and amount.
Utilization Standards--The minimum size and percent soundness of trees described in the specifications to determine merchantable timber.
Add Figure 101-1—Illustration of road structure terms:
Figure 101-1—Illustration of road structure terms.
102 - Bid, Award, and Execution of Contract
102 Bid, Award, and Execution of Contract
Delete Section 102 in its entirety.
103 - Scope of Work
Deletions
Delete all but subsection 103.01 Intent of Contract.
104 - Control of Work
Delete Sections 104.01, 104.02, and 104.04.
104.03 Specifications and Drawings.
Add the following:
(c) As-Built-Plans. Furnish one set of as built plans. The Government will provide one set of contract plans to be used exclusively for recording the as-built details of the project. Use red pencil or red ink to record the information on the as-built plans.
Note all additions or revisions to the location, character, and dimensions of the prescribed work shown on the contract plans. Line out all details shown that are not applicable to the completed work. Check off details shown that were incorporated into the completed work without change.
Retain the plans at the project site and, as work progresses, continually update them to reflect the as-built details. Upon request, make the plans available to the CO to review for compliance with these specifications.
Show the following types of changes on the as-built plans:
(1) Typical section(s)
(a) Revisions in dimensions
(b) Revisions in materials
(2) Plan and profile
• Revisions to the alignment
• Changes in the construction limits
• Revisions in location, type, and grade of road approaches
• Location and type of utilities
• Location, size, and type of underdrains
• Skew of culverts
• Channel changes
• Location of monuments and permanent references
• Elevations for all aerial and underground crossings of utilities
• Location, length, and type of fencing
• Revisions to grades, elevations, and stationing of intersection PIs
• Equations
• Culvert diameter, length, type, and stationing. On culvert extensions, indicate the length of the existing pipe and the length of the extension.
• Location, length, stationing, and type of retaining walls
• Location, length, stationing, and end treatment of guardrail
(3) Bridge
(a) Stationing of bridge ends
(b) Revisions to footing and seal elevations
(c) Pile length, size, type, and tip elevation
(d) Any changes in plan or dimensions including any major changes in reinforcing
(4) Miscellaneous
(a) Revisions to parking areas or turnouts
(b) Final location, type and length of curbs, sidewalks, etc.
Furnish the as-built working plans to the CO before the final inspection. Correct all details found during the final inspection that are not shown on the as-built plans and return to the CO within 5 days.
Add the following subsection:
104.06 Use of Roads by Contractor
The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to the limitations and authorizations designated in the Road Order(s) or described in the contract, when such use will not damage the roads or national forest resources, and when traffic can be accommodated safely.
105 - Control of Material
105.02 Material Sources.
105.02(a) Government-provided sources.
Add the following:
Comply with the requirements of 30 CFR 56, subparts B and H. Use all suitable material for aggregate regardless of size unless otherwise designated. When required, re-establish vegetation in disturbed areas according to section 625.
Government-provided sources for this project are identified as follows:
(1) Government-provided mandatory sources.
Obtain material for use as N/A and in the production of aggregates under Sections (301/401/411/etc.) from N/A.
Haul & Waste unsuitable excess excavation material at Nearby Areas Designated by the COR
(2) Government-provided optional sources.
Material for use as N/A and in the production of aggregates under Sections (301/401/411/etc.)
may be obtained from N/A.
105.02(b) Contractor-provided sources.
All material (e.g., soil, gravel, sand, borrow, aggregate, etc.) transported onto National Forest System land or incorporated into the work will be weed-free. The Contracting Officer may request Written Documentation of methods used to determine the weed-free status of any and all materials furnished by the contractor. Contractor-provided expertise and methods to establish weed-free status must be appropriate for the weeds of concern in the local area. The following applies to this contract:
OPTION 1: LIST PROJECT-SPECIFIC WEEDS OR APPROPRIATE WEED LIST. YOU
MAY INCLUDE ACCEPTABLE METHODS TO ESTABLISH “WEED-FREE” AS
APPLICABLE TO YOUR PROJECT. DO THIS IN CONJUNCTION WITH YOUR UNIT
WEED SPECIALIST.
Weeds specific to this project: There are no Noxious Weeds or Invasive Species known to be common to the Project area.
Weeds & methods specific to this project:
Weed species or applicable weed list
Method
None N/A
OPTION 2: REPLACE CONTRACTOR-DOCUMENTED DETERMINATION WITH
FOREST SERVICE APPROVAL OF SOURCES BASED ON INSPECTIONBY A FS WEED
SPECIALIST – MAKE SURE THIS IS COORDINATED WITH YOUR UNIT WEED
SPECIALISTS. USE OF THIS OPTION COMMITS FOREST SERVICE RESOURCES.
A Forest Service weed specialist will inspect proposed sources to determine weed-free status.
Provide the Contracting Officer Written Notification of Proposed Material Sources __21___ Days prior to use. Written approval of the specific source will be provided to the contractor. If weed species are present in the proposed source, appropriate mitigation measures may allow conditional use of the source as required by the Contracting Officer.
105.05 Use of Material Found in the Work.
Delete 105.05 (a) and (b) and the last sentence of the second paragraph and substitute the following:
Materials produced or processed from Government lands in excess of the quantities required for performance of this contract are the property of the Government. The Government is not obligated to make reimbursement for the cost of producing these materials.
106 - Acceptance of Work
106.01 Conformity with Contract Requirements.
Delete Subsection 106.01 and substitute the following:
Follow the requirements of FAR Clause 52.246-12 Inspection of Construction.
References to standard test methods of AASHTO, ASTM, GSA, and other recognized standard authorities refer to the methods in effect on the date of solicitation for bids.
Perform all work to the lines, grades, cross-sections, dimensions, and processes or material requirements shown on the plans or specified in the contract.
Incorporate manufactured materials into the work according to the manufacturer’s recommendations or to these specifications, whichever is more strict.
Plan dimensions and contract specification values are the values to be strived for and complied with as the design values from which any deviations are allowed. Perform work and provide material that is uniform in character and reasonably close to the prescribed value or within the specified tolerance range. The purpose of a tolerance range is to accommodate occasional minor variations from the median zone that are unavoidable for practical reasons.
When standard manufactured items are specified (such as fence, wire, plates, rolled shapes, pipe conduits, etc., that are identified by gauge, unit mass, section dimensions, etc.), the identification will be considered to be nominal masses or dimensions. Unless specific contract tolerances are noted, established manufacturing tolerances will be accepted.
The Government may inspect, sample, or test all work at any time before final acceptance of the project. When the Government tests work, copies of test reports are furnished to the Contractor upon request. Government tests may or may not be performed at the work site. If Contractor testing and inspection is verified by the Government, the Contractor’s results may be used by the Government to evaluate work for acceptance. Do not rely on the availability of Government test results for process control.
Acceptable work conforming to the contract will be paid for at the contract unit bid price. Four methods of determining conformity and accepting work are described in Subsections 106.02 to
106.05 inclusive. The primary method of acceptance is specified in each Section of work. However, work may be rejected at any time it is found by any of the methods not to comply with the contract.
Remove and replace work that does not conform to the contract, or to prevailing industry standards where no specific contract requirements are noted, at no cost to the Government.
(a) Disputing Government test results. If the accuracy of Government test results is disputed, promptly inform the CO. If the dispute is unresolved after reasonable steps are taken to resolve the dispute, further evaluation may be obtained by written request. Include a narrative describing the dispute and a proposed resolution protocol that addresses the following:
(1) Sampling method;
(2) Number of samples;
(3) Sample transport;
(4) Test procedures;
(5) Testing laboratories;
(6) Reporting;
(7) Estimated time and costs; and
(8) Validation process.
If the evaluation requires additional sampling or testing be performed, mutually agree with the Government on witnessing procedures and on sampling and testing by a third-party laboratory. Use a third-party laboratory accredited by the AASHTO accreditation program.
Provide proof of the laboratory’s accreditation for the test procedures to be used. Do not use the same laboratory that produced the disputed Government test results or that produced the test results used as a basis for the dispute.
The CO will review the proposed resolution protocol and may modify it before final approval and execution.
The Government will use the approved resolution protocol test results to determine the validity of the disputed testing. If the Government test results are validated, the Contractor will be responsible for all costs associated with developing and performing the resolution protocol. If the Government test results are not validated, the Government will be responsible for all costs associated with developing and performing the resolution protocol.
If the validity of the Government test results cannot be determined, the Contractor and Government will equally share all costs associated with developing and carrying out the resolution protocol.
(b) Alternatives to removing and replacing non-conforming work. As an alternative to removal and replacement, the Contractor may submit a written request to:
(1) Have the work accepted at a reduced price; or
(2) Be given permission to perform corrective measures to bring the work into conformity.
The request must contain supporting rationale and documentation. Include references or data justifying the proposal based on an evaluation of test results, effect on service life, value of material or work, quality, aesthetics, and other tangible engineering basis. The CO will determine disposition of the nonconforming work.
106.07 Delete
Delete subsection 106.07.
107 - Legal Relations and Responsibility to the Public
Delete subsections 107.05 and 107.09.
107.06 Contractor’s Responsibility for Work.
Delete the following from the first paragraph.
“except as provided in Subsection 106.07”.
107.10 Environmental Protection.
Add the following:
Design and locate equipment repair shops, stationary refueling sites, or other facilities to minimize the potential and impacts of hazardous material spills on Government land.
Before beginning any work, submit a Hazardous Spill Plan. List actions to be taken in the event of a spill. Incorporate preventive measures to be taken, such as the location of mobile refueling facilities, storage and handling of hazardous materials, and similar information. Immediately notify the CO of all hazardous material spills. Provide a written narrative report form no later than 24 hours after the initial report and include the following:
• Description of the item spilled (including identity, quantity, manifest number, and other identifying information).
• Whether amount spilled is EPA or state reportable, and if so whether it was reported, and to whom.
• Exact time and location of spill including a description of the area involved.
• Containment procedures.
• Summary of any communications the Contractor had with news media, Federal, state and local regulatory agencies and officials, or Forest Service officials.
• Description of clean-up procedures employed or to be employed at the site including final disposition and disposal location of spill residue.
When available provide copies of all spill related clean up and closure documentation and correspondence from regulatory agencies.
The Contractor is solely responsible for all spills or leaks that occur during the performance of this contract. Clean up spills or leaks to the satisfaction of the CO and in a manner that complies with Federal, state, and local laws and regulations.
107.11 Protection of Forests, Parks, and Public Lands:
Before starting any operations on the project, the Contractor shall prepare & submit a Project Fire Plan, for review and approval by the Contracting Officer, providing for the prevention and control of fires in the project area. The Contractor shall certify compliance with all Federal and State fire protection and suppression requirements, before beginning operations during the fire period and closed season. Required Tools and Equipment shall be kept currently in serviceable condition and immediately available for initial attack on fires.
108 - Prosecution and Progress
108 Delete.
Delete Section 108 in its entirety.
109 - Measurement and Payment
Delete the following entire subsections:
109.06 Pricing of Adjustments.
109.07 Eliminated Work.
109.08 Progress Payments.
109.09 Final Payment.
109.02 Measurement Terms and Definitions.
(b) Contract quantity.
Add the following:
Contract quantities will be adjusted only when there are errors in the original design of 15% or more.
Change the following:
“(b) Cubic yard” to “(c) Cubic yard”.
Add the following definition:
(p) Thousand Board Feet (Mbf). 1,000 board feet based on nominal widths, thickness, and extreme usable length of each piece of lumber or timber actually incorporated in the job. For glued laminated timber, 1,000 board feet based on actual width, thickness, and length of each piece actually incorporated in the job.
152 - Construction Survey and Staking
152.01(c) Material.
Add the following:
Use required stake dimensions and materials. Pre-paint the top 2 inches of all stakes and lath, or mark them with plastic flagging. Use designated colors for paint or flagging. Mark all stakes with a stake pencil that leaves a legible imprint, or with waterproof ink.
Do not use aerosol spray paints.
Use moisture-resistant paper for survey notes. Keep notes in books with covers that will protect the contents and retain the pages in numerical sequence.
152.02 General.
Delete the first two sentences.
Add the following:
When indicated on the plans, a preliminary survey line has been established on the ground. The project location line is established by offsets from this preliminary line.
Delete second sentence in second paragraph and replace with the following:
Reestablish missing reference, control lines, or stakes as necessary to control subsequent construction staking operations
152.03 Survey and Staking Requirements.
(b) Roadway cross-sections.
Replace the first two sentences with the following:
Take roadway cross-sections normal to centerline. When the centerline curve radius is less than or equal to 200 feet, take cross-sections at a maximum centerline spacing of 25 feet. When the centerline curve radius is greater than 200 feet take cross-sections at a maximum centerline spacing of 80 feet.
c) Slope Stakes & References:
Replace section with the following:
Slope stakes and references. When required, locate slope stakes on designated portions of the road. Locate the slope stake catch points and use them to establish clearing limits and slope stake references.
Mark slope stakes with the station, the amount of cut or fill, the horizontal distance to centerline, and the slope ratios.
Place slope reference stakes at least 10 feet outside the clearing limit and mark with the offset distance to the slope stake. Place sight stakes when required.
Prior to clearing and grubbing operations, move the slope stake outside the clearing limit to the slope reference stake. After clearing and grubbing and before excavation, reset the slope stakes in their original position.
Use the designated method to establish the slope stake catchpoint.
• Method I—Computed Method. Use the template information shown in the plans or other Government-provided data to calculate the actual location of the catchpoint. The slope stake “catchpoint distance” provided may be used as a trial location to initiate slope staking. Recatch slope stakes on any section that does not match the staking report within the tolerances established in Table 152-2.
• Method II—Catchpoint Measurement Method. Determine the location of slope stake catchpoints by measuring the catchpoint distances shown in the plans or other Government-provided data.
(d) Clearing and grubbing limits.
Add the following:
Establish clearing limits on each side of the location line by measuring the required horizontal or slope distances shown in the stake notes. Mark the clearing limits with flagging or tags on trees to be left standing, or on lath. Make markings intervisible, and no more than 90 feet apart.
After establishing clearing limits, move the location line stake outside the clearing limits for station identification purposes, and mark it with horizontal distance to location line.
(e) Centerline reestablishment.
Replace with the following:
Reestablish centerline from instrument control points. The maximum spacing between centerline points is 25 feet when the centerline curve radius is less than or equal to 200 feet. When the centerline curve radius is greater than 200 feet, the maximum distance between centerline points is 80 feet.
(g) Culverts.
Replace subsection with the following:
Set culvert reference stakes at all culvert locations. Set a culvert reference stake on the centerline of the culvert 10 feet from each end or beyond the clearing limit, whichever is greater. Record the following on culvert reference stakes:
(1) Diameter, actual field measured length, and type of culvert.
(2) The vertical and horizontal distance from the reference stake to the invert at the ends of the culvert.
(3) Station of actual point where culvert intersects centerline.
When required, stake headwall for culverts by setting a hub with a guard stake on each side of the culvert on line with the face of the headwall. Perform this work after clearing is completed.
152.03 (l) Miscellaneous Survey and Staking.
(11) Drain Dips
(12) Erosion Control Measures
Replace Table 152-1 with the following two tables:
Table 152-1 Tolerances for reestablishing P-line, traverse, and elevations.
Precision
Class
Minimum Position Closure Angular Accuracy (±)
L-Line Tangent Control Pointsa
Vertical Closureb
A (Bridges)
1/10,000 2 sets, direct/reverse 10 second rejection limit
N/A
0.02 ft or 0.02ft/1000ftc
B 1/5,000 2 sets, direct/reverse 20 second rejection limit
0.1 ft
0.02 ft or 0.02ft/1000ftc
C 1/1,000 1 set, direct/reverse 1 minute rejection limit
0.2 ft 0.5ft/1000ftc
D 1/300 Foresight and backsight; 15 minute rejection limitc
0.4 ft 1.0ft/1000ftc
E 1/100 Foresight and backsight; 30 minute rejection limitc
0.8 ft 1.0ft/1000ftc
a. Accuracy of offset measurement.
b. Determine vertical closures at intervals not to exceed 2000 ft as measured along centerline.
c. Use greater value.
Table 152-2 Cross section and slope stake tolerances.
Item Tolerances
A B C D E
Allowable deviation of cross-section line projection from a true perpendicular to tangents, a true bisector of angle points, or a true radius of curves
(±)2o (±)3o (±)3o (±)5o (±)5o
Take cross-sections topography measurements so that variations in ground from a straight line connecting the cross-section points will not exceed
0.5 ft 1.0 ft 2.0 ft 2.0 ft 3.0 ft
Horizontal and vertical accuracy for cross-sections, in feet or percentage of horizontal distance measured from traverse line, whichever is greater.
0.1 ft or 0.4%
0.15 ft or 0.6%
0.2 ft or 1.0%
0.2 ft or 1.0%
0.3 ft or 1.0%
Horizontal and vertical accuracy for slope stake, slope stake references, and clearing limits. In feet or percentage of horizontal distance measured from centerline or reference stake, whichever is greater.
Slope reference stakes and slope stakes. 0.1 ft or 0.4%
0.15 ft or 0.6%
0.2 ft or 1.0%
0.2 ft or 1.0%
0.3 ft or 1.0%
Clearing limits 1.0 ft 1.0 ft 1.0 ft 1.5 ft 2.5 ft
153 - Contractor Quality Control
153.01 Description.
Add the following:
The quality-control services of inspections, tests, and related actions, including reports shall be performed by Contractor, by independent agencies, and by governing authorities. They do not include contract enforcement activities performed by the Contracting Officer. The quality of all project work shall be the responsibility of the Contractor. All Sampling & Testing Services shall be performed by and be the responsibility of an independent currently certified testing laboratory, the cost of which shall be borne by the Contractor.
153.02 Contractor Quality Control Plan.
Add the following:
Sampling & Testing methods shall be according to Section 154. Submit written proposals for approval of alternate AASHTO or State approved test methods. Alternate methods may be allowed based on documented equivalence to the specified method.
Add the following:
If Contractor Quality Control Plan requires any revisions or corrections, the Contractor shall resubmit the updated plan within 10 Days. The Government reserves the right to require changes in the Contractor Quality Control Plan during the contract period as necessary to obtain the quality specified. No change in the approved Contractor Quality Control Plan may be made without written concurrence by the Contracting Officer.
Inspect and test all work often enough to ensure that the quality of materials, workmanship, construction, finish, and functional performance is in compliance with applicable specifications and drawings. Quality Control Daily Reports shall be completed by the Quality Control Supervisor. Test reports shall be completed by person performing the test. The Contracting Officer may designate locations of tests.
Sampling, Testing, and Certification requirements and frequency for specific items shall be as specified in the drawings and specification. Refer to Table 153-1 as a summary of the required sampling, testing, and certification for the project - the table is to assist the Contractor, but may not be all inclusive – additional submittals may be required by the specific specification section:
TABLE 153-1 SUBMITTAL SCHEDULE
SPEC.
SECTION SECTION TITLE SUB-
SECTION REQUIRED SUBMITTAL
104 Control of Work 104.03 As-Built Plans 105 Control of Material 105.02 (b) Contractor Provided Sources
107 Legal Relations & Responsibility to the Public 107.10 Hazardous Spill Plan
107 Legal Relations & Responsibility to the Public 107.11 Project Fire Plan
152 Construction Survey and Staking 152.02 Survey and Construction
Staking Notes
153 Contractor Quality Control 153.02 Contractor Quality Control Plan
153 Contractor Quality Control 153.04 Testing and Inspection Records
154 Contractor Sampling and Testing 154.04 Record of Test Results
156 Public Traffic 156.03 Traffic Control and Safety Plan
157 Soil Erosion Control 157.03 Erosion Prevention and Control Measures Plan
157 Soil Erosion Control 157.03 Alternate Erosion Prevention and Control Measures Plan
171 Weed and Disease Prevention 171.03 Equipment Schedule for Noxious Weed Inspection
Structure Excavation and
Backfill for Selected Major Structures
208.04 Approval of the Character and
Suitability of Foundation Material
Structure Excavation and
Backfill for Selected Major Structures
208.04 Copy of Excavation Design
Conforming to OSHA Regulations
Structure Excavation and
Backfill for Selected Major Structures
208.04 Shoring Work Drawings and
Construction Details
Structure Excavation and
Backfill for Selected Major Structures
208.06 Cofferdam Work Drawings
209 Structure Excavation and Backfill 209.11 Compaction Test Results
213 Subgrade Stabilitation 213.03 Subgrade Stabilization Mix Design
253 Gabions and Revet Mattresses 253.03 Installation Drawings
253 Gabions and Revet Mattresses 253.06 Shop Drawings for the Layout and Details of the Cellular Concrete Mats
253 Gabions and Revet Mattresses 253.07
Product Literature and Representative Samples of the Cellular Concrete Mattresses, Cables, Fittings, Anchors, and
Filter Fabric
253 Gabions and Revet Mattresses 253.07 Manufacturer's Certification of the Revetment System and Components
253 Gabions and Revet Mattresses 253.08 Hydraulic Performance Test Results
258 Reinforcing Concrete Walls 258.03 Forms and Falsework Drawings
258 Reinforcing Concrete Walls 258.04 Order Lists and Bending Diagrams for Reinforcing
Steel
301 Untreated Aggregate Courses 301.03
Proposed Target Values for the Appropriate Sieve Sizes along with a Representative 300- Pound Sample
304 Aggregate Stabilization 304.03 Mix Design
324 Minor Aggregate, Commercial Source 324.03
Roadbed Approval and Aggregate Gradation
Submittals
324 Minor Aggregate, Commercial Source 324.05 Compaction Test Results
552 Structural Concrete 552.03 Concrete Mix Design 552 Structural Concrete 552.09 Quality Control Plan of Mix
552 Structural Concrete 552.10
Detailed Plan for Producing, Transporting, Placing, Protecting, Curing and
Temperature Monitoring of Concrete During Cold Weather
554 Reinforcing Steel 554.03 Concrete Reinforcing Steel
Order Lists & Bending Diagrams
602 Culverts and Drains 602.03 Fabricator’s Certification 614 Lean Concrete Backfill 614.03 Composition of Mix
622 Rental Equipment 622.02 Model and Serial Number of Each Piece fo Equipment
623 General Labor 623.02 Daily Record of Hours
Worked and Certified Copies of Payroll
625 Turf Establishment 625.07 Seed Mix and Certification
703 Crushed Aggregate 703.6 Flex base compliance with TxDOT Standards
704 Soil 704.03 (a) Gradation Submittal for
Backfill Material-Item 209 & Pay Item 602
714 Geotextile and Geocomposite Drain Material 714.03 (b) Certification and Product
Sample
153.05 Acceptance.
If the Contractor Quality Control Plan and Quality Control Daily Inspection Reports are not submitted as specified, the Contracting Officer may retain all payments until such time a plan is submitted, approved, and implemented with all noted deficiencies corrected.
155 - Schedules for Construction Contracts
155 Delete.
Delete Section 155 in its entirety.
156 - Public Traffic
Delete Section 156 in its entirety and replace with the following:
156.01 Description. This work consists of controlling and protecting public traffic adjacent to and within the project.
156.02 Material. Conform to the MUTCD and the following Sections and Subsections:
Construction sign panels 633 Retro-reflective sheeting 718.01 Temporary concrete barrier 618 Temporary plastic fence 710.11 Temporary traffic control devices 718.22
156.03 General. Unless otherwise provided for in Table 156-1, keep existing roads open to all traffic during road improvement work, and maintain them in a condition that will adequately accommodate traffic. Delays may not exceed 20 minutes at any one time followed by an open period of no less than 10 minutes.
Perform no work that interferes or conflicts with traffic or existing access to the roadway surface until a submitted Traffic Control & Safety Plan has been reviewed and approved by the Contracting Officer. Post construction signs and traffic control devices in conformance with MUTCD. All required signs will be in place and approved prior to beginning work on project.
If the Contractor agrees in writing to allow public traffic to use a new road being constructed prior to completion, it will be considered an existing road for traffic control purposes.
156.04 Temporary Traffic Control. Install and maintain temporary traffic control devices adjacent to and within the project as required by the Approved Traffic Control & Safety Plan and the MUTCD. Do not construct detours outside of the clearing limits or use alternate route detours without the approval of the CO. Install and maintain traffic control devices as follows:
(a) Furnish and install traffic control devices before the start of construction operations.
(b) All detours outside of clearing limits will be approved in writing by the Contracting
Officer as part of the traffic control & safety plan.
(c) Install only those traffic control devices needed for each stage or phase.
(d) Relocate temporary traffic control devices as necessary.
(e) Remove devices that no longer apply to the existing conditions.
(f) Immediately replace any device that is lost, stolen, destroyed, or inoperative.
(g) Keep temporary traffic control devices clean.
(h) Remove all temporary traffic control devices upon contract completion or when approved.
(i) When required, use flaggers certified by the American Traffic Safety Services Association, the National Safety Council, the International Municipal Signal Association, a state agency, or other acceptable organization. Perform the work described under MUTCD Part 6. Use type III, VII, VIII, or IX retroreflective sheeting on flagger paddles. Do not use flags. Flaggers must wear high visibility safety apparel as required by MUTCD 6E.02.
156.05 Temporary Closures. Road segments may be closed as shown in Table 156-1. The maximum consecutive days of closure shall be followed by a minimum number of consecutive days open to traffic as shown. Maintain traffic control devices during closure period(s).
Appropriate barricades and signs will be erected and maintained as shown in the Traffic Control & Safety Plan or as otherwise designated.
Prior to closing roads during construction, give Written Notice to the Contracting Officer at least 21 Days in advance.
Table 156-1 Temporary Road Closures
Road
Number From
Terminus To
Terminus Maximum
Consecutive Days of Closure
Minimum Consecutive Days Open
All Project Roads
As Shown on Project
Vicinity Map
As Shown on Project
Vicinity Map
3 Roads Open to Traffic, Unless an Approved
Scheduled Closure is in Effect.
(a) Contractor will coordinate with the Government, to inform Affected State &
County Agencies and Private Land Owners within the Closed Area prior to closing road. There will be NO ROAD CLOSURES allowed on the weekends.
156.06 Acceptance. Public traffic work will be evaluated under Subsection 106.02.
156.06 Measure Traffic Control under Section 635.
157 - Soil Erosion Control
157.03 General
Delete the entire subsection and replace with the following:
Prior to the start of construction, submit a written Erosion Prevention & Control Measures Plan, that provides permanent and temporary erosion control measures to minimize erosion and sedimentation during and after construction. Do not begin work until the necessary controls for that particular phase of work have been implemented. Do not modify the type, size, or location of any control. An alternate erosion prevention & control measures plan with all necessary permits may be submitted 30 days before intended use.
Incorporate all permanent erosion control features into the project at the earliest practicable time, as outlined in the approved plan.
When erosion control measures are not functioning as intended, immediately take corrective action.
170 - Develop Water Supply and Watering
Add the following section:
Description
170.01 Description. This work consists of developing an acceptable water supply, furnishing, hauling, and applying water.
Materials
170.02 Materials. Conform to the following subsection.
Water 725.01.
Construction Requirements
170.03 Development of Supply & Access. Develop water supplies and access to the water supplies as required. Use designated water sources or other approved water sources. Before using non-designated water sources, obtain all necessary permissions, water rights, and permits.
170.04 Equipment. Provide mobile watering equipment with watertight tanks of known capacity. Provide for positive control of water application from the driver’s position.
170.05 Application. Apply water uniformly without ponding or washing.
170.06 Acceptance. Developing water supplies and watering will be evaluated under Subsections 106.02 and 106.04.
Measurement
170.07 Measurement. Measure the Section 170 items listed in the bid schedule according to Subsection 109.02.
Payment
170.08 Payment. The accepted quantities will be paid at the contract price per unit of measurement for the Section 170 pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05.
171 - Weed and Disease Prevention
Add the following section:
Description
171.01 Description. This work consists of washing and treating construction equipment to remove seeds, plants, and plant fragments from the equipment for inspection by the Government, before the equipment is used on National Forest System lands.
Material
171.02 Material. Conform to the following Subsection:
Water 725.01
Construction Requirements
171.03 General. Notify the CO in writing at least 15 Days, to schedule an inspection, before moving any construction equipment onto National Forest System lands. Construction equipment does not include cars, pickup trucks, and other vehicles that regularly travel between the construction site and areas outside of National Forest System lands.
Perform all work at a location designated on the plans or other locations approved in writing.
Provide the CO with an opportunity to monitor the washing and inspection.
171.04 Equipment. Use a high pressure washing system.
For work on National Forest System lands, use a washing system that traps all wash water and either stores it for removal from National Forest System lands or recycles the water for continued use. If the equipment recycles the water, provide adequate filters for seed removal. Dispose of the filter material and removed seeds in an approved manner. Do not mix soaps, detergents, or other chemicals with the wash water.
For work at a commercial washing facility, use an approved facility.
171.05 Washing. Wash the sides, tops, and undercarriages of all construction equipment.
Remove all seeds, plants, plant fragments, dirt, and debris from the construction equipment.
171.06 Inspection. Inspect the washed construction equipment, including the undercarriage, to ensure that the washing removed the dirt, debris, and seeds from the construction equipment.
Rewash the construction equipment as necessary or as directed.
171.07 Acceptance. Weed prevention will be evaluated under Subsection 106.02.
Measurement
171.08 Measurement. Do not measure weed prevention for payment.
Payment
171.09 Payment. Include all costs associated with the Section 171-Weed Prevention in the unit price for Section 151-Mobilization.
201 – Clearing and Grubbing
201.01 Description
Replace with the following:
This work consists of clearing and grubbing within clearing limits and other designated areas.
201.04 Clearing
Add the following:
When marked in advance, remove dead trees over 6 inches in diameter measured at 12 inches above the ground that lean toward the road or dam embankment and are tall enough to reach the roadbed or dam embankment.
Delete paragraph (b) and replace with the following:
(b) Remove trees greater than four inches with root balls. Within the limits of grubbing, buried material such as logs, stumps, roots of downed trees that are greater than one (1) inch in diameter, matter roots, rubbish, and foreign debris shall be grubbed and removed to a minimum depth of twenty-four (24) inches below existing or proposed finished grades, whichever is lower. Backfill root ball hole and other voids with dam embankment material per.
Delete paragraph (c) and replace with the following:
(c) In areas outside the excavation, embankment, and slope rounding limits, cut stumps to within 12 inches or one-third of the stump diameter of the ground, whichever is higher, measured on the side adjacent to the highest ground.
Delete subsection (d) and replace with the following:
(d) Trim tree branches that extend over the road surface and shoulders to attain a clear height of 14 feet. If required, remove other branches to present a balanced appearance.
Trim according to accepted tree surgery practices.
(e) Trim tree branches that extend over the road surface and shoulders to attain a clear height of 14 feet. If required, remove other branches to present a balanced appearance.
Trim according to accepted tree surgery practices.
(f) Remove branches over dam embankment.
203 – Removal of Structures and Obstructions
203.03 Salvaging Material
Add the following:
Salvage grouted riprap per the plans.
203.05 Disposing of Material
Delete subsections (b) Burn, (c) Bury, and (d) Hazardous material.
(e) Windrowing Construction Slash. Place construction slash outside the roadway in neat, compacted windrows approximately parallel to and along the toeline of embankment slopes. Do not permit the top of the windrows to extend above subgrade. Use construction equipment to matt down all material in a windrow to form a compact and uniform pile. Construct breaks of at least 15 feet at least every 200 feet in a windrow. Do not place windrows against trees. Obtain approval for pioneer roads. A pioneer road may be constructed to provide an area for placement of windrows, provided the excavated material is kept within the clearing limits and does not adversely affect the road construction.
(f) Scattering. Scatter construction slash outside the clearing limits without damaging trees.
Limb all logs. Place logs and stumps away from trees, positioned so they will not roll, and are not on top of one another. Limb and scatter other construction slash to reduce slash concentrations.
(g) Chipping or Grinding. Use an approved chipping machine to grind slash and stumps greater than 3 inches in diameter and longer than 3 feet. Deposit chips or ground woody material on embankment slopes or outside the roadway to a loose depth less than 6 inches. Minor amounts of chips or ground woody material may be permitted within the roadway if they are thoroughly mixed with soil and do not form a layer.
(h) Debris Mat. Use tree limbs, tops, cull logs, split stumps, wood chunks, and other debris to form a mat upon which construction equipment is operated. Place stumps upside down and blend stumps into the mat.
(i) Decking Firewood Material. Remove brush from decks. Limb and deck logs that do not meet Utilization Standards according to Subsection 201.04 as directed by the CO. Cut logs to lengths less than 30 feet. Ensure that logs stacks are stable and free of brush and soil.
(j) Removal to designated locations. Remove construction slash to designated locations.
(k) Piling. Pile construction slash in designated areas. Place and construct piles so that if the piles are burned, the burning will not damage remaining trees. Keep piles free of dirt from stumps. Cut unmerchantable logs into lengths of less than 20 feet.
(l) Placing Slash on Embankment Slopes. Place construction slash on completed embankment slopes to reduce soil erosion. Place construction slash as flat as practicable on the completed slope. Do not place slash closer than 2 feet below subgrade. Priority for use of available slash is for: (1) through fills; (2) insides of curves; and (3) ditch relief outlets.
(m) Hydrological Sensitive Placement. Where required use this method in combination with other designated methods to dispose of material to reduce erosion and to aid in re-vegetation:
1. Place windrow segments on contours, wrap in type I geotextile.
2. Place logs as log erosion barriers on contours. Place logs so that 80% of their length is on the ground surface.
3. Scatter slash on bare or disturbed areas within or outside the clearing limits as directed.
4. Scatter chips or ground woody material on bare or disturbed areas within or outside the clearing limits as directed.
Place stumps in swales or on sites to form planting pockets. Place windrow segments on contours, wrap in type I geotextile.
204 – Excavation and Embankment
204.01 Description
Add the following:
This section only applies to the roadway embankment and should not be used for the dam embankment or other related grading.
205 – Rock Blasting
205 Delete
Delete Section 205 in its…