Specifications.pdf

PDF 494 KB Posted

Attached to
Exigency Repairs to Watershed Site 107B, Navarro County, TX - EWP
Solicitation number
AG-7442-S-10-0059
Issued by

About this file

Specifications

View the file

Other files

File Type Posted
Long AbstractSite 107B.xlsx XLSX spreadsheet
RICHLAND CREEK 107B Layout.pdf PDF
Attachment 1 to Soliciation Site Showing.pdf PDF
Amendment 1.pdf PDF
F10-1357 Compaction.pdf PDF
Attachment 2Tech Note.pdf PDF
F10-1358 Compaction.pdf PDF
Richland Creek 107B SWPPP.pdf PDF
NEW VENDOR CODE FORM-2a1.xls XLS spreadsheet
Sheet 4.pdf PDF
Sheet 3.pdf PDF
Sheet 1.pdf PDF
AG-7442-S-10-0059.pdf PDF
SAFETY PROGRAM.doc DOC document
Sheet 2.pdf PDF
TX146_dvb.htm HTM file
Sheet 5.pdf PDF
Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(210-VI-NEH, May 2001) 2-1

Construction Specification 2—Clearing and Grubbing

1. Scope The work consists of clearing and grubbing and disposal of trees, snags, logs, brush, stumps, shrubs, and rubbish from the designated areas.

2. Protection of existing vegetation Trees and other vegetation designated to remain undisturbed shall be protected from damage throughout the duration of the construction period. Any damages resulting from the contractor's operations or neglect shall be repaired by the contractor.

Earthfill, stockpiling of materials, vehicular parking, and excessive foot or vehicular traffic shall not be allowed within the drip line of vegetation designated to remain in place. Vegetation damaged by any of these or similar actions shall be replaced with viable vegetation of the same species, similar condition, and like size unless otherwise approved by the contracting officer.

Any cuts, skins, scrapes, or bruises to the bark of the vegetation shall be carefully trimmed and local nursery accepted procedures used to seal damaged bark.

Any limbs or branches 0.5 inch or larger in diameter that are broken, severed, or otherwise seriously damaged during construction shall be cut off at the base of the damaged limb or branch flush with the adjacent limb or tree trunk. All roots 1-inch or larger in diameter that are cut, broken, or otherwise severed during construction operations shall have the end smoothly cut perpendicular to the root. Roots exposed during excavation or other operations shall be covered with moist earth or backfilled as soon as possible to prevent the roots from drying out.

3. Marking The limits of the area(s) to be cleared and grubbed will be marked by stakes, flags, tree markings, or other suitable methods. Trees to be left standing and uninjured will be designated by special markings placed on the trunk about 6 feet above the ground surface.

4. Clearing and grubbing All trees not marked for preservation and all snags, logs, brush, stumps, shrubs, rubbish, and similar materials shall be cleared from within the limits of the designated areas. Unless otherwise specified, all stumps, roots, and root clusters that have a diameter of 1 inch or larger shall be grubbed out to a depth of at least 2 feet below subgrade for concrete structures and 1 foot below the ground surface at embankment sites and other designated areas.

5. Disposal All materials cleared and grubbed from the designated areas shall be disposed of at locations shown on the drawings or in a manner specified in section 7. The contractor is responsible for complying with all local rules and regulations and the payment of any and all fees that may result from disposal at locations away from the project site.

6. Measurement and payment Method 1—For items of work for which specific units prices are established in the contract, the cleared and grubbed area is measured to the nearest 0.1 acre. Payment for clearing and grubbing is made for the total area within the designated limits at the contract unit price. Such payment will constitute full

AG-7442-S-10-0059

Watershed Site 107B, Navarro County, TX 1 of 49

(210-VI-NEH, May 2001) 2-2 compensation for all labor, equipment, tools, and all other items necessary and incidental to the completion of the work.

Method 2—For items of work for which specific unit prices are established in the contract, the length of the cleared and grubbed area is measured to the nearest full station (100 feet) along the line designated on the drawing or identified in the specifications. Payment for clearing and grubbing is made for the total length within the designated limits at the contract unit price. Such payment will constitute full compensation for all labor, equipment, tools, and all other items necessary and incidental to the completion of the work.

Method 3—For items of work for which specific unit prices are established in the contract, each tree, stump, and snag having a diameter of 4 inches or larger and each log having a diameter of 4 inches or larger and a length of 10 feet are measured before removal. The size of each tree and snag is determined by measuring its trunk at breast height above the natural ground surface. The size of each log is determined by measuring the butt and by measuring its length from butt to tip. The size of each stump is measured at the top. Diameter is determined by dividing the measured circumference by 3.14.

Payment for clearing and grubbing of each tree, stump, and snag having a diameter of 4 inches or larger and each log having a diameter of 4 inches or larger and a length of 10 feet or larger is made at the contract unit price for its size designation as determined by the following schedule:

Measured diameter Size designation

(in) (in)

4 to 8 6 8 to 12 10 12 to 24 18 24 to 36 30 36 to 60 48 Over 60 60

The sum of such payments shall constitute full compensation for clearing and grubbing (including the clearing and grubbing of smaller trees, stumps, snags, logs, brush, shrubs, and roots), applicable permits and associated fees, and rubbish removal. Such payment shall constitute full compensation for all labor, equipment, tools, and all other items necessary and incidental to the completion of the work.

Method 4—For items of work for which specific lump sum prices are established in the contract, payment for clearing and grubbing is made at the contract lump sum price. Such payment shall constitute full compensation for all labor, equipment, tools, and all other items necessary and incidental to the completion of the work.

All Methods—The following provisions apply to all methods of measurement and payment.

Compensation for any item of work described in the contract, but not listed in the bid schedule will be included in the payment for the item of work to which it is made subsidiary. Such items and the items to which they are made subsidiary are identified in section 7.

7. Items of work and construction details

Watershed Site 107B, Navarro County, TX 2 of 49

NRCS –07/26/2010 2-3

TX – RICHLAND 107B EWP

7. Items of work and construction details In Section 5, Disposal, all materials removed from the cleared and grubbed areas shall be burned or buried at areas designated or approved by the Contracting Officer.

Burning shall be accomplished at such times and manner as to minimize the annoyance or discomfort of the inhabitants of the area. Open burning shall be in accordance with state and local regulations.

Buried materials shall be buried at locations designated at the time of the showing of the site to prospective bidders. Buried material shall have a minimum earthfill cover of not less than 2 feet. The cover shall be placed in two lifts with each lift compacted by traversing the entire surface with one tread track of the material placement equipment.

The top lift shall be mounded at least 6 inches higher than the surrounding undisturbed area to prevent unsightly depressions after settlement. The finished surface of the disposal area shall be uniformly graded to prevent ponding of water.

All trees, snags, logs, brush, shrubs, stumps, and rubbish that are felled, detached, or otherwise dislocated in or near stream channels shall be disposed of as specified or removed to higher ground prior to the end of each workday. The Contractor is to take precaution, when temporarily stockpiling cleared and grubbed materials, to guard against such cleared and grubbed materials being floated or transported off the worksite by rainstorm runoff.

Items of work to be performed in conformance with this specification and the construction details therefore are:

a. Subsidiary Item, Clearing and Grubbing

(1) This item shall consist of all clearing and grubbing within the work limits required for construction of the works of improvement as shown on the drawings.

(2) The actual limits of required clearing and grubbing will be as designated or staked at the time of showing the site to prospective bidders.

(3) Upon completion of the clearing and grubbing operation, all areas which have been cleared and grubbed shall be dressed to be reasonably smooth by blading, dragging or floating. The entire area shall be reasonably free of abrupt mounds, dips and windrows to provide a clear area for construction staking.

(4) Separate payment will not be made for this item of work. Compensation for this item will be included in the payment for the bid item Excavation.

Watershed Site 107B, Navarro County, TX 3 of 49

(210-VI-NEH, January 2009) 5-1

Construction Specification 5—Pollution Control

1. Scope The work consists of installing measures or performing work to control erosion and minimize the production of sediment and other pollutants to water and air from construction activities.

2. Material All material furnished shall meet the requirements of the material specifications listed in section 8 of this specification.

3. Erosion and sediment control measures and works The measures and works shall include, but are not limited to, the following:

Staging of earthwork activities—The excavation and moving of soil materials shall be scheduled to minimize the size of areas disturbed and unprotected from erosion for the shortest reasonable time.

Seeding—Seeding to protect disturbed areas shall occur as soon as reasonably possible following completion of that earthwork activity.

Mulching—Mulching to provide temporary protection of the soil surface from erosion.

Diversions—Diversions to divert water from work areas and to collect water from work areas for treatment and safe disposition. They are temporary and shall be removed and the area restored to its near original condition when the diversions are no longer required or when permanent measures are installed.

Stream crossings—Culverts or bridges where equipment must cross streams. They are temporary and shall be removed and the area restored to its near original condition when the crossings are no longer required or when permanent measures are installed.

Sediment basins—Sediment basins collect, settle, and eliminate sediment from eroding areas from impacting properties and streams below the construction site(s). These basins are temporary and shall be removed and the area restored to its original condition when they are no longer required or when permanent measures are installed.

Sediment filters—Straw bale filters or geotextile sediment fences trap sediment from areas of limited runoff. Sediment filters shall be properly anchored to prevent erosion under or around them. These filters are temporary and shall be removed and the area restored to its original condition when they are no longer required or when permanent measures are installed.

Waterways—Waterways for the safe disposal of runoff from fields, diversions, and other structures or measures. These works are temporary and shall be removed and the area restored to its original condition when they are no longer required or when permanent measures are installed.

Other—Additional protection measures as specified in section 8 of this specification or required by Federal, State, or local government.

4. Chemical pollution The contractor shall provide watertight tanks or barrels or construct a sump sealed with plastic sheets to collect and temporarily contain chemical pollutants, such as drained lubricating or transmission fluids, grease, soaps, concrete mixer washwater, or asphalt, produced as a by-product of the construction

Watershed Site 107B, Navarro County, TX 4 of 49

(210-VI-NEH, January 2009) 5-2 activities. Pollutants shall be disposed of in accordance with appropriate State and Federal regulations. At the completion of the construction work, tanks, barrels, and sumps shall be removed and the area restored to its original condition as specified in section 8 of this specification. Sump removal shall be conducted without causing pollution.

Sanitary facilities, such as chemical toilets, or septic tanks shall not be located next to live streams, wells, or springs. They shall be located at a distance sufficient to prevent contamination of any water source. At the completion of construction activities, facilities shall be disposed of without causing pollution as specified in section 8 of this specification.

5. Air pollution The burning of brush or slash and the disposal of other materials shall adhere to state and local regulations.

Fire prevention measures shall be taken to prevent the start or spreading of wildfires that may result from project activities. Firebreaks or guards shall be constructed and maintained at locations shown on the drawings.

All public access or haul roads used by the contractor during construction of the project shall be sprinkled or otherwise treated to fully suppress dust. All dust control methods shall ensure safe construction operations at all times. If chemical dust suppressants are applied, the material shall be a commercially available product specifically designed for dust suppression and the application shall follow manufacturer's requirements and recommendations. A copy of the product data sheet and manufacturer's recommended application procedures shall be provided to the engineer 5 working days before the first application.

6. Maintenance, removal, and restoration All pollution control measures and temporary works shall be adequately maintained in a functional condition for the duration of the construction period. All temporary measures shall be removed and the site restored to near original condition.

7. Measurement and payment Method 1—For items of work for which specific unit prices are established in the contract, each item is measured to the nearest unit applicable. Payment for each item is made at the contract unit price for that item. For water or chemical suppressant items used for dust control for which items of work are established in section 8 of this specification, measurement for payment will not include water or chemical suppressants that are used inappropriately or excessive to need. Such payment will constitute full compensation for the completion of the work.

Method 2—For items of work for which lump sum prices are established in the contract, payment is made as the work proceeds and supported by invoices presented by the contractor that reflect actual costs. If the total of all progress payments is less than the lump sum contract price for this item, the balance remaining for this item will be included in the final contract payment. Payment of the lump sum contract price will constitute full compensation for completion of the work.

Method 3—For items of work for which lump sum prices are established in the contract, payment will be prorated and provided in equal amounts on each monthly progress payment estimate. The number of months used for prorating shall be the number estimated to complete the work as outlined in the contractor's approved construction schedule. The final month's prorate amount will be provided with the final contract payment. Payment as described will constitute full compensation for completion of the work.

Watershed Site 107B, Navarro County, TX 5 of 49

(210-VI-NEH, January 2009) 5-3

All Methods—The following provisions apply to all methods of measurement and payment.

Compensation for any item of work described in the contract, but not listed in the bid schedule is included in the payment for the item of work to which it is made subsidiary. Such items, and the items to which they are made subsidiary, are identified in section 8 of this specification.

8. Items of work and construction details

Watershed Site 107B, Navarro County, TX 6 of 49

NRCS –07/26/2010 5-4

8. Items of work and construction details

In Section 5, Air pollution, firebreaks or guards are not shown on the drawings.

The Contractor's written plan for pollution control shall be approved prior to the start of construction operations. Written plan shall at a minimum include proposed sequencing of operation to minimize duration and size of disturbed areas.

Items of work to be performed in conformance with this specification and the construction details therefore are:

a. Bid Item 1, Pollution Control

(1) This item shall consist of performing all work and furnishing all materials necessary to accomplish the work defined in Section 1 of this specification, including all works required to implement the Storm Water Pollution Prevention Plan, except sediment filters.

(2) In Section 7, Measurement and payment, Method 2 shall apply.

b. Bid Item 2, Sediment Filters

(1) This item shall consist of furnishing and installing sediment filters to the lengths and location designated by the Engineer. Maintenance of installed sediment filters shall be paid for under the bid item for Pollution Control.

(2) In Section 7, Measurement and Payment, Method 1 shall apply.

Watershed Site 107B, Navarro County, TX 7 of 49

(210-VI-NEH, May 2001 6-1

Construction Specification 6—Seeding, Sprigging, and Mulching

The work consists of preparing the area for treatment; furnishing and placing seed, sprigs, mulch, fertilizer, inoculant, lime, and other soil amendments; and anchoring mulch in designated areas as specified.

2. Material Seed—All seed shall conform to the current rules and regulations of the state where it is being used and shall be from the latest crop available. It shall meet or exceed the standard for purity and germination listed in section 7.

Seed shall be labeled in accordance with the state laws and the U.S. Department of Agriculture rules and regulations under the Federal Seed Act in effect on the date of invitations for bids. Bag tag figures are evidence of purity and germination. No seed will be accepted with a test date of more than 9 months before the delivery date to the site.

Seed that has become wet, moldy, or otherwise damaged in transit or storage will not be accepted. The percent of noxious weed seed allowable shall be as defined in the current State laws relating to agricultural seeds. Each type of seed shall be delivered in separate sealed containers and fully tagged unless exception is granted in writing by the contracting officer.

Fertilizer—Unless otherwise specified, the fertilizer shall be a commercial grade fertilizer. It shall meet the standard for grade and quality specified by State law. Where fertilizer is furnished from bulk storage, the contractor shall furnish a supplier's certification of analysis and weight. When required by the contract, a representative sample of the fertilizer shall be furnished to the contracting officer for chemical analysis.

Inoculants—The inoculant for treating legume seeds shall be a pure culture of nitrogen-fixing bacteria prepared specifically for the species and shall not be used later than the date indicated on the container or as otherwise specified. A mixing medium, as recommended by the manufacturer, shall be used to bond the inoculant to the seed. Two times the amount of the inoculant recommended by the manufacturer shall be used except four times the amount shall be used when seed is applied using a hydraulic seeder. Seed shall be sown within 24 hours of treatment and shall not remain in the hydraulic seeder longer than 4 hours.

Lime and other soil amendments—Lime shall consist of standard ground agriculture limestone, or approved equivalent. Standard ground agriculture limestone is defined as ground limestone meeting current requirements of the State Department of Agriculture. Other soil amendments shall meet quality criteria and application requirements specified in section 7.

Mulch tackifiers—Asphalt emulsion tackifiers shall conform to the requirements of ASTM D 977, Specification for Emulsified Asphalt. The emulsified asphalt may be rapid setting, medium setting, or slow setting. Nonasphaltic tackifiers required because of environmental considerations shall be as specified in section 7.

Straw mulch material—Straw mulch shall consist of wheat, barley, oat or rye straw, hay, grass cut from native grasses, or other plants as specified in section 7. The mulch material shall be air-dry, reasonably

Watershed Site 107B, Navarro County, TX 8 of 49

(210-VI-NEH, May 2001 6-2 light in color, and shall not be musty, moldy, caked, or otherwise of low quality. The use of mulch that contains noxious weeds is not permitted. The contractor shall provide a method satisfactory to the contracting officer for determining weight of mulch furnished.

Other mulch materials—Mulching materials, such as wood cellulose fiber mulch, mulch tackifiers, synthetic fiber mulch, netting, and mesh, are other mulching materials that may be required for specialized locations and conditions. These materials, when specified, must be accompanied by the manufacturer's recommendations for methods of application.

3. Seeding mixtures, sod, sprigs, and dates of planting The application rate per acre for seed mixtures, sprigs, or sod and date of seeding or planting shall be as shown on the plans or as specified in section 7.

4. Seedbed preparation and treatment Areas to be treated shall be dressed to a smooth, firm surface. On sites where equipment can operate on slopes safely, the seedbed shall be adequately loosened (4 to 6 inches deep) and smoothed. Depending on soil and moisture conditions, disking or cultipacking, or both, may be necessary to properly prepare a seedbed. Where equipment cannot operate safely, the seedbed shall be prepared by hand methods by scarifying to provide a roughened soil surface so that broadcast seed will remain in place.

If seeding is to be accomplished immediately following construction operations, seedbed preparation may not be required except on a compacted, polished, or freshly cut soil surface.

Rocks larger than 6 inches in diameter, trash, weeds, and other debris that will interfere with seeding or maintenance operations shall be removed or disposed of as specified in section 7.

Seedbed preparation shall be discontinued when soil moisture conditions are not suitable for the preparation of a satisfactory seedbed as determined by the contracting officer's technical representative

(COTR).

5. Seeding, sprigging, fertilizing, mulching, and stabilizing All seeding or sprigging operations shall be performed in such a manner that the seed or sprigs are applied in the specified quantities uniformly in the designated areas. The method and rate of seed application shall be as specified in section 7. Unless otherwise specified, seeding or sprigging shall be accomplished within 2 days after final grading is completed and approved.

Fertilizer, lime, and other soil amendments shall be applied as specified in section 7. When specified, the fertilizer and soil amendments shall be thoroughly incorporated into the soil immediately following surface application.

The rate, amount, and kind of mulching or mesh shall be as specified in section 7. Mulches shall be applied uniformly to the designated areas. They shall be applied to areas seeded not later than 2 working days after seeding has been performed. Straw mulch material shall be stabilized within 24 hours of application using a mulch crimper or equivalent anchoring tool or by a suitable tackifier. When the mulch crimper or equivalent anchoring tool is used, it shall have straight blades and be the type manufactured expressly for and capable of firmly punching the mulch into the soil. Where the equipment can be safely operated, it shall be operated on the contour. Hand methods shall be used where equipment cannot safely operate to perform the work required.

The tackifier shall be applied uniformly over the mulch material at the specified rate, or it shall be

Watershed Site 107B, Navarro County, TX 9 of 49

(210-VI-NEH, May 2001 6-3 injected into the mulch material as it is being applied. Mesh or netting stabilizing materials shall be applied smoothly, but loosely on the designated areas. The edges of these materials shall be buried or securely anchored using spikes or staples as specified in section 7.

The contractor shall maintain the mesh or netting areas until all work under the contract has been completed and accepted. Maintenance shall consist of the repair of areas damaged by water erosion, wind, fire, or other causes. Such areas shall be repaired to reestablish the intended condition and to the design lines and grades required by the contract. The areas shall be refertilized, reseeded, and remulched before the new application of the mesh or netting.

6. Measurement and payment Method 1—For items of work for which specific unit prices are established in the contract, each area treated is measured as specified in section 7 and the area calculated to the nearest 0.1 acre. Payment for treatment is made at the contract unit price for the designated treatment, which will constitute full compensation for completion of the work.

When specified as an item of work, mesh or netting is measured to the nearest square yard of surface area covered and accepted. Payment is made at the contract unit price and will constitute full compensation for completion of the work.

Method 2—For items of work for which specific lump sum prices are established in the contract, the quantity of work will not be measured for payment. Payment for this item is made at the contract lump sum price for the item and will constitute full compensation for the completion of the work.

Method 3—For items of work for which lump sum prices are established in the contract, payment is made as the work proceeds. Progress payments will be determined as specified in section 7. Payment of the lump sum contract price will constitute full compensation for completion of the work.

All Methods—The following provisions apply to all methods of measurement and payment.

Compensation for any item of work described in the contract, but not listed in the bid schedule is included in the payment for the item of work to which it is made subsidiary. Such items and the item(s) to which they are made subsidiary are identified in section 7.

7. Items of work and construction details

Watershed Site 107B, Navarro County, TX 10 of 49

NRCS –07/26/2010 6-4

7. Items of work and construction details

When working on slopes which are steeper than 3:1 horizontal to vertical, all rubber tire equipment on the slope will be held with truck or tractor and winch line with the truck or tractor operating along the crown of the embankment or other suitable flat surface. As an alternative, track (crawler) equipment with a low center of gravity may be used to perform work on slopes without a winch line requirement when operated in accordance with applicable OSHA requirements.

Items of work to be performed in conformance with this specification and the construction details therefore are:

a. Bid Item 3, Vegetation, Seeding

(1) This item shall consist of preparing the seedbed and furnishing and applying seed, hay mulch, tackifer and fertilizer to the designated areas as shown on the drawings.

(2) The grass seed shall be drilled or broadcast onto a firm, clean seedbed. Seed drilled shall be on the approximate contour. A grass seed drill equipped with depth control bands, grain drill with a grass seed attachment, or Brillion (type) seeder shall be used. The seed shall not be planted or covered deeper than ½ inch below the soil surface. The distance between rows shall not exceed 6 inches. Seed shall be distributed over the entire area at uniform rates. The areas shall be firmed before seeding and immediately following seeding with a cultipacker or corrugated packer roller weighing 180 to 190 pounds per foot of width. Only on areas not accessible to the drilling equipment, seed may be broadcast by hand. The hand seeded areas shall be hand raked and then firmed with a hand operated roller.

(3) Seed of high quality customarily sold in the trade is required. The seed must be in sound, clean bags with each bag containing a tag showing, among other things with respect to the contents of the bag, name of the seed, locality and year of harvest, and the percentage of purity and germination. Bag tag figures will be accepted for purity and germination and the seed will either be accepted or rejected by the designated representative on the basis of the bag tag test. Seeding rates are for “Pure Live Seed (PLS)” therefore, the percentage of purity as shown on the seed tag will determine the number of pounds of bulk material needed to obtain the required amount of pure live seed per acre.

(4) The seed mixture and application rate shall be:

(a) Common Bermuda grass, hulled (Cynodon dactylon) 4.6 lb. PLS per Acre

(b) Common Bermuda grass, unhulled (Cynodon dactylon) 6.0 lb. PLS per Acre

(c) Texhoka Buffalo grass burs (Buchloe dactyloides) 8.0 lb. PLS per Acre

(5) Fertilizer shall be of the pelleted form and shall be uniformly mixed. Prior to planting the grasses, fertilizer shall be applied and worked into the soil by disking with a weighted tandem disk to a depth of approximately 4 inches. No fertilizer shall be applied when the ground is excessively wet, frozen, or otherwise in an untillable condition. The rate of application of the fertilizer shall be thirty pounds of nitrogen (N), forty pounds of phosphorous (P) and no pounds of potassium (K) per acre).

Watershed Site 107B, Navarro County, TX 11 of 49

NRCS –07/26/2010 6-5

(6) In Section 5, straw mulch material shall consist of coastal bermudagrass or a native bluestem mix and the rate of application shall be 2-1/2 tons per acre. Mulches shall be stabilized by a nonasphaltic tackifier applied at a rate of 40 pounds per acre or by a mechanical crimper. The contractor shall submit the manufacturer’s product data and installation instructions for the tackifier to the Contracting Officer for approval of the product.

(7) In Section 6, Measurement and Payment, Method 1 will apply. Measurement for payment will be the surface area calculated to the nearest 0.1 acre.

b. Bid Item 4, Irrigation System

(1) This item shall consist of furnishing and installing a temporary sprinkler irrigation system as needed to irrigate the areas as designated in Section 7.a of this specification. The system shall be adequate to apply the volume of water and meet the application requirements specified in Sections 7.c (2) and 7.c (3) of this specification. The application of irrigation shall not cause runoff. The application shall be uniform ensuring that at any point the irrigated area shall be within 20 percent of the required application application.

(2) The contractor shall furnish all equipment, operators, maintenance, operating supplies, and materials needed to install the system. The contractor shall furnish in-line, propeller type water meter (s) with volumetric calibration. The meter(s) shall be installed so that all water applied for the irrigation of seeded grasses under the contract will be metered.

(3) Unless otherwise noted, the system shall be removed upon completion of the application of Irrigation.

(4) In Section 6, Measurement and Payment, Method 2 will apply.

c. Bid Item 4, Irrigation Water

(1) This item shall consist of applying irrigation water to the areas seeded. It shall include the cost of water and labor.

(2) The estimated application rate and schedule of irrigations will be as follows: 1st irrigation 2 acre-inches, 2nd, 3rd and 4th irrigations ½ acre inch at 2 days intervals and then twice a week for the next 4 weeks at ½ acre inch applications. Additional irrigation or adjustment in the application rates may be required as determined and approved by the Engineer until vegetation is established.

(3) Water for irrigation shall come from the reservoir. All areas will be irrigated with a sprinkler irrigation system. The total irrigation at any one time will be based on need as determined by the COTR. The water will be applied in a manner that:

Reasonable uniform distribution of required application will be obtained over the areas to be irrigated and excessive runoff or erosion will not occur. Adjustments in sprinkler spacing, nozzle sizes, pressures, or in the gross water applied shall be made when needed to accomplish the above objectives.

(4) Contract performance time will be increased to account for the time irrigation is performed.

(5) In Section 6, Measurement and Payment, Method 1 will apply. Measurement for payment will be 1000 gallon units and will be measured to the nearest 1000 gallons based on the applied volume determined from the readings of the in-line water meter(s).

Watershed Site 107B, Navarro County, TX 12 of 49

(210-VI-NEH, January 2009) 7-1

Construction Specification 7—Construction Surveys

1. Scope The work consists of performing all surveys, measurements, and computations required by this specification.

2. Equipment and material Equipment for construction surveys shall be of a quality and condition to provide the required accuracy.

The equipment shall be maintained in good working order and in proper adjustment at all times. Records of repairs, calibration tests, accuracy checks, and adjustments shall be maintained and be available for inspection by the engineer. Equipment shall be checked, tested, and adjusted as necessary in conformance with manufacturer's recommendations.

Material is field notebooks, stakes, templates, platforms, equipment, spikes, steel pins, tools, and all other items necessary to perform the work specified.

3. Quality of work All work shall follow recognized professional practice and the standards of the industry unless otherwise specified in section 9 of this specification. The work shall be performed to the accuracy and detail appropriate for the type of job. Notes, sketches, and other data shall be complete, recorded neatly, legible, reproducible and organized to facilitate ease in review and allow reproduction of copies for job documentation. Survey equipment that requires little or no manual recording of field data shall have survey information documented as outlined in section 9 of this specification.

All computations shall be mathematically correct and shall include information to identify the bid item, date, and who performed, checked, and approved the computations. Computations shall be legible, complete, and clearly document the source of all information used including assumptions and measurements collected.

If a computer program is used to perform the computations, the contractor shall provide the engineer with the software identification, vendor's name, version number, and other pertinent data before beginning survey activities. Computer generated computations shall show all input data including values assigned and assumptions made.

The elevations of permanent and temporary bench marks shall be determined and recorded to the nearest

0.01 foot. Differential leveling and transit traverses shall be of such precision that the error of vertical closure in feet shall not exceed plus or minus 0.1 times the square root of the traverse distance in miles.

Linear measurements shall be accurate to within 1 foot in 5,000 feet, unless otherwise specified in section 9 of this specification. The angular error of closure for transit traverses shall not exceed 1 minute times the square root of the number of angles turned.

The minimum requirements for placing slope stakes shall be at 100-foot stations for tangents, as little as 25 feet for sharp curves, breaks in the original ground surface and at any other intermediate stations necessary to ensure accurate location for construction layout and measurement. Slope stakes and cross sections shall be perpendicular to the centerline. Significant breaks in grade shall be determined for cross sections. Distances shall be measured horizontally and recorded to the nearest 0.1 foot. Side shots for interim construction stakes may be taken with a hand level.

Unless otherwise specified in section 9 of this specification, measurements for stationing and establishing the location of structures shall be made to the nearest 0.1 foot.

Elevations for concrete work, pipes, and mechanical equipment shall be determined and recorded to the nearest 0.01 foot. Elevations for earth work shall be determined and recorded to the nearest 0.1 foot.

Watershed Site 107B, Navarro County, TX 13 of 49

(210-VI-NEH, January 2009) 7-2

4. Primary control The baselines and bench marks for primary control, necessary to establish lines and grades needed for construction, are shown on the drawings and have been located on the job site.

These baselines and bench marks shall be used as the origin of all surveys, layouts, and measurements to establish construction lines and grades. The contractor shall take all necessary precautions to prevent the loss or damage of primary control points. Any stakes or control points lost or damaged by construction activity will be reestablished by the contractor or at contractor expense

5. Construction surveys Before work starts that requires contractor performed surveys, the contractor shall submit in writing for the engineer's review: the name, qualifications, and experience of the individuals to be assigned to the survey tasks.

Method 1—Contractor performed surveys shall include:

• checking and any supplemental or interim staking

• performing quantity surveys, measurements, and computations for progress payment

• other surveys as described in section 9 of this specification

Method 2—Contractor performed surveys shall consist of all work necessary for:

• establishing line and grade for all work

• setting slope stakes for all work

• checking and any supplemental or interim staking

• establishing final grade stakes

• performing quantity surveys, measurements, and computations for progress payment

• other surveys as described in section 9 of this specification

Method 3—Contractor performed surveys shall consist of all work necessary for:

• establishing line and grade for all work

• setting slope stakes for all work

• checking and any supplemental or interim staking

• establishing final grade stakes

• performing quantity surveys, measurements, and computations for progress payments

• performing original (initial) and final surveys for determinations of final quantities

• other surveys as described in section 9 of this specification.

6. Staking The construction staking required for the item shall be completed before work on any item starts.

Construction staking shall be completed as follows or as otherwise specified in section 9 of this specification:

Clearing and grubbing—The boundary of the area(s) to be cleared and grubbed shall be staked or flagged at a maximum interval of 200 feet, closer if needed, to clearly mark the limits of work. When contractor staking is the basis for determining the area for final payment, all boundary stakes will be reviewed by the engineer before start of this work item.

Excavation and fill—Slope stakes shall be placed at the intersection of the specified slopes and ground line. Slope stakes and the reference stakes for slopes shall be marked with the stationing, required cut or fill, slope ratio, and horizontal distance from the centerline or other control line. The minimum

Watershed Site 107B, Navarro County, TX 14 of 49

(210-VI-NEH, January 2009) 7-3 requirements for placing slope stakes is outlined in section 3, Quality of work.

Structures—Centerline and offset reference line stakes for location, alignment, and elevation shall be placed for all structures.

7. Records All survey data shall be recorded in fully identified standard hard-bound engineering survey field notebooks with consecutively numbered pages. All field notes and printed data shall include the purpose or description of the work, the date the work was performed, weather data, sketches, and the personnel who performed and checked the work. Electronically generated survey data and computations shall be bound, page numbered, and cross referenced in a bound field notebook containing the index for all survey activities. All work shall follow recognized professional practice.

The construction survey records shall be available at all times during the progress of the work for examination and use by the engineer and when requested, copies shall be made available. The original field notebooks and other records shall be provided to and become the property of the owner before final payment and acceptance of all work.

Complete documentation of computations and supporting data for progress payments shall be submitted to the engineer with each invoice for payment as specified in section 9 of the specification. When the contractor is required to conduct initial and final surveys as outlined in section 5, Construction Surveys, notes shall be provided as soon as possible after completion to the engineer for the purpose of determining final payment quantities.

8. Payment Method 1—For items of work for which lump sum prices are established in the contract, payment is made as the work proceeds, after presentation of correct and accurate invoices by the contractor showing related costs and evidence of the charges of suppliers, subcontractors, and others for supplies furnished and work performed. Invoices for the total amount of the contract price will not be accepted until all surveys are complete and required documentation has been determined complete. If the total of such payments is less than the lump sum contract price for this item, the unpaid balance will be included in the final contract payment. Payment of the lump sum contract price will constitute full compensation for completion of all work under the bid item.

Method 2—For items of work for which lump sum prices are established in the contract, payment is made as the work proceeds with progress payment amounts determined as a percentage of the total work planned as projected from the contractor's approved construction schedule. Payment of the lump sum contract price will constitute full compensation for completion of all work under this bid item.

All Methods—Payment will not be provided under this item for the purchase price of materials or equipment having a residual value.

Compensation for any item of work described in the contract, but not listed in the bid schedule will be included in the payment for the item of work to which it is made subsidiary. Such items and the item to which they are made subsidiary are identified in section 9 of this specification.

9. Items of work and construction details

Watershed Site 107B, Navarro County, TX 15 of 49

NRCS –07/26/2010 7-5

9. Items of work and construction details

In Section 5, Construction surveys, Method 2 shall apply.

In Section 8, Measurement and payment, Method 2 shall apply.

Items of work to be performed in conformance with this specification and the construction details therefore are:

a. Bid Item 6, Construction Surveys

(1) This item shall consist of performing all work required by Section 1 of this specification.

(2) All surveys shall proceed from benchmarks; reference points and/or stakes set or established by the Government. The benchmarks are shown on the drawings.

(3) Initial and final surveys for determinations of final quantities will be performed by the Government.

(4) The surveys conducted by the Contractor shall include, but not be limited to:

(a) Those required to check all excavation and earthfill slopes as work progresses to insure such slopes are maintained at those specified.

Earthfill slopes shall be checked at least each five feet of vertical interval and corrected to planned slope.

(b) Those required to check for depths of excavations and heights of earthfills.

(c) Those required to set “bluetops” for subgrades and for finished grades of all excavations, earthfills, and appurtenances to the works.

Watershed Site 107B, Navarro County, TX 16 of 49

(210-VI-NEH, May 2001) 8-1

Construction Specification 8—Mobilization and Demobilization

The work consists of the mobilization and demobilization of the contractor's forces and equipment necessary for performing the work required under the contract. It does not include mobilization and demobilization for specific items of work for which payment is provided elsewhere in the contract.

Mobilization will not be considered as work in fulfilling the contract requirements for commencement of work.

2. Equipment and material Mobilization shall include all activities and associated costs for transportation of contractor's personnel, equipment, and operating supplies to the site; establishment of offices, buildings, and other necessary general facilities for the contractor's operations at the site; premiums paid for performance and payment bonds including coinsurance and reinsurance agreements as applicable; and other items specified in section 4 of this specification.

Demobilization shall include all activities and costs for transportation of personnel, equipment, and supplies not required or included in the contract from the site; including the disassembly, removal, and site cleanup of offices, buildings, and other facilities assembled on the site specifically for this contract.

This work includes mobilization and demobilization required by the contract at the time of award. If additional mobilization and demobilization activities and costs are required during the performance of the contract as a result of changed, deleted, or added items of work for which the contractor is entitled to an adjustment in contract price, compensation for such costs will be included in the price adjustment for the item or items of work changed or added.

3. Payment Payment will be made as the work proceeds, after presentation of paid invoices or documentation of direct costs by the contractor showing specific mobilization and demobilization costs and supporting evidence of the charges of suppliers, subcontractors, and others. When the total of such payments is less than the lump sum contract price, the balance remaining will be included in the final contract payment.

Payment of the lump sum contract price for mobilization and demobilization will constitute full compensation for completion of the work.

Payment will not be made under this item for the purchase costs of materials having a residual value, the purchase costs of materials to be incorporated in the project, or the purchase costs of operating supplies.

4. Items of work and construction details

Watershed Site 107B, Navarro County, TX 17 of 49

NRCS –07/26/2010 8-2

4. Items of work and construction details

Items of work to be performed in conformance with this specification and the construction details therefore are:

a. Bid Item 7, Mobilization and Demobilization

(1) This item shall consist of performing all items of work for mobilization and demobilization as required by Sections 1 and 2 of this specification.

(2) The mobilization operation shall include but not be limited to the items in Section 2 of this specification and the following items of work:

(a) Access to the work area shall be designated at the showing of the site to prospective bidders. From the county road an access road shall be constructed and maintained by the Contractor. The access road shall be a minimum of 14 feet wide and be graded and smoothed to provide a surface which can be easily traversed by automobiles. The road shall be maintained in a smooth rut-free condition throughout the contract period.

(3) The demobilization operation shall include but not be limited to the following items of work:

(a) All debris, trash, tires, equipment, equipment parts, chains, cables, and other such items resulting from the construction operation shall be removed from the worksite and disposed of in an approved sanitary land fill of the Contractor's own choosing.

(b) All disturbed areas shall be bladed or smoothed to blend the area with the surrounding land surface. The bladed or smoothed surface shall be free of abrupt mounds, windrows, depressions or other irregularities that would prevent the safe operation of ordinary farm equipment thereon.

The finished surface shall prevent diversion of surface runoff and shall prevent standing or ponding water.

(c) All buildings, trailers, chain link fence, storage sheds, sanitary facilities and other such items shall be removed from the worksite when construction work is completed.

(d) All utilities shall be removed from the site as required by the owner of the utility after construction work is completed.

(e) The access road shall be bladed to be smooth and shall be left in a rut-free condition. If road base/rock is used on the access road it shall be removed after construction work is completed.

(4) The item of work subsidiary to this bid item is Traffic Control, as specified in Construction Specification 9.

Watershed Site 107B, Navarro County, TX 18 of 49

(210-VI-NEH, May 2001 9-1

Construction Specification 9—Traffic Control

Scope The work shall consist of establishing traffic control and maintaining safe, convenient use of public roads and rights-of-way.

6. Traffic and access The contractor's operations shall cause no unnecessary inconvenience to the public. The public rights-of-way shall be maintained at all times unless interruption is authorized by proper local authority. Contractor's authorized closing or detour plans shall be provided to the engineer for approval.

Safe and adequate access shall be provided and maintained to all public protection devices and to all critical utility control locations. Facility access shall be continuous and unobstructed unless otherwise approved.

7. Storage of equipment and material in public streets Construction materials and equipment shall not be stored or parked on public streets, roads, or highways. During any material or equipment loading or unloading activities that may temporarily interfere with traffic, an acceptable detour shall be provided for the duration of the activity. Any associated expense for this activity is the responsibility of the contractor.

Excavated material, including suitable material that is intended for adjacent trench backfill or other earth backfill as specified in section 5 of this specification, shall not be stored on public streets, roads, or highways that remain in service for the public. Any waiver of this requirement must be obtained from the proper local authority and approved by the engineer.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .