AG-7103-S-10-0013 Amend 0001.pdf
PDF 861 KB Posted
- Attached to
- RECOVERY TAS::12 1073::TAS Repair of Concrete Pipe, Poteau River Site 4, Scott County, Arkansas
- Solicitation number
- AG-7103-S-10-0013
About this file
Amendment 0001
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bid Results.pdf | ||
| Att 2 - Drawings.pdf | ||
| AG-7103-S-10-0013.pdf | ||
| Att 3 - NRCS Safety.pdf | ||
| Att 1 - Specs.pdf | ||
| Att 4 - AR201.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE PAGE OF PAGES
J 1 2
2. AMENDMENT/MODIFICATION NO.
3. EFFECTIVE DATE
2010 JUN 04
4. REQUISITION/PURCHASE REQ. NO.
5. PROJECT NO. (If applicable)
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE USDA – NRCS – Arkansas State Office 700 West Capitol Avenue, Room 3416 Little Rock, AR 72201
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State, and ZIP Code)
9A. AMENDMENT OF SOLICITATION NO.
AG-7103-S-10-0013
9B. DATED (See Item 11
2010 MAY 15
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (See Item 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
_X___ The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers _____ is extended, __X__ is not extended. Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods: (a) By completing Items 8 and 15, and returning _____ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not _ is required to sign this document and return the original to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible).
RECOVERY – PRINCIPAL SPILLWAY CONDUIT REPAIR, POTEAU RIVER SITE 4, SCOTT COUNTY, ARKANSAS
A. Section H, Page 12 of 123 – Add the following clause reference after the last line:
“H.15 452.236-72 Use of Premises B. Section H, Page 18 of 123 – Delete this page and replace with the attached Page 18 of 123, annotated
“Attachment 1”, which adds Clause 452.236-72, Use of Premises.
(continued next page)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA
BY
(Signature of Contracting Officer)
16C. DATE SIGNED
NSN 7540-01-152-8070 STANDARD FORM 30 (REV. 10-83)
PREVIOUS EDITION UNUSABLE 30-105 Prescribed by GSA
FAR (48 CFR) 53.243
Solicitation No. AG-7103-S-10-0013 Amendment No. 0001
C. Section I, Page 20 of 123 – Add the following clause reference after the last line:
“I.89 452.228-71 Insurance Coverage”
D. Section I, Page 107 of 123 – Delete this page and replace with the attached Page 107 of 123, annotated “Attachment 2”, which adds Clause 452.228-71, Insurance Coverage.
E. Section L, Page 113 of 123 – Add the following clause reference after the last line:
“L.23 452.228-70 Alternative Forms of Security”
F. Section L, Page 122 of 123 – Delete this page and replace with the attached Page 122 of 123, annotated “Attachment 3”, which adds Clause 452.228-70, Alternative Forms of Security.
G. Section J, List of Documents, Exhibits and Other Attachments, Page 108 of 123, End of Second Line – Change the number of pages for Attachment 2, maps and Drawings from 6 to 8.
H. Attachment 2, Maps and Drawings, Page 6 – Insert the attached Pages 7 and 8, annotated “Attachment 4” after Page 6.
President’s Day Memorial Day Independence Day Labor Day Columbus Day Veterans Day Thanksgiving Day Christmas Day
(End of Clause)
H.15 452.236-72 .USE OF PREMISES (NOV 1996)
(a) Before any camp, quarry, borrow pit, storage, detour, or bypass site, other than shown on the drawings, is opened or operated on USDA land or lands administered by the USDA, the Contractor shall obtain written permission from the Contracting Officer. A camp is interpreted to include a campsite or trailer parking area of any employee working on the project for the Contractor.
(b) Unless excepted elsewhere in the contract, the Contractor shall (i) provide and maintain sanitation facilities for the work force at the site and (ii) dispose of solid waste in accordance with applicable Federal, State and local regulations. (End of Clause)
(End of clause)
H.15
AG-7103-S-10-013 Page 18 of 123 Amendment 0001, Attachment 1
(3) The agreed price for, or the proceeds of sale of, materials, supplies, or other things acquired by the Contractor or sold under the provisions of this clause and not recovered by or credited to the Government.
(l) If the termination is partial, the Contractor may file a proposal with the Contracting Officer for an equitable adjustment of the price(s) of the continued portion of the contract. The Contracting Officer shall make any equitable adjustment agreed upon. Any proposal by the Contractor for an equitable adjustment under this clause shall be requested within 90 days from the effective date of termination unless extended in writing by the Contracting Officer.
(m)(1) The Government may, under the terms and conditions it prescribes, make partial payments and payments against costs incurred by the Contractor for the terminated portion of the contract, if the Contracting Officer believes the total of these payments will not exceed the amount to which the Contractor will be entitled.
(2) If the total payments exceed the amount finally determined to be due, the Contractor shall repay the excess to the Government upon demand, together with interest computed at the rate established by the Secretary of the Treasury under 50 U.S.C. App. 1215(b)(2). Interest shall be computed for the period from the date the excess payment is received by the Contractor to the date the excess is repaid. Interest shall not be charged on any excess payment due to a reduction in the Contractor's termination settlement proposal because of retention or other disposition of termination inventory until 10 days after the date of the retention or disposition, or a later date determined by the Contracting Officer because of the circumstances.
(n) Unless otherwise provided in this contract or by statute, the Contractor shall maintain all records and documents relating to the terminated portion of this contract for 3 years after final settlement. This includes all books and other evidence bearing on the Contractor's costs and expenses under this contract. The Contractor shall make these records and documents available to the Government, at the Contractor's office, at all reasonable times, without any direct charge. If approved by the Contracting Officer, photographs, microphotographs, or other authentic reproductions may be maintained instead of original records and documents.
(End of clause)
89. 52.253-1 Computer Generated Forms. (JAN 1991)
(a) Any data required to be submitted on a Standard or Optional Form prescribed by the Federal Acquisition Regulation (FAR) may be submitted on a computer generated version of the form, provided there is no change to the name, content, or sequence of the data elements on the form, and provided the form carries the Standard or Optional Form number and edition date.
(b) Unless prohibited by agency regulations, any data required to be submitted on an agency unique form prescribed by an agency supplement to the FAR may be submitted on a computer generated version of the form provided there is no change to the name, content, or sequence of the data elements on the form and provided the form carries the agency form number and edition date.
(c) If the Contractor submits a computer generated version of a form that is different than the required form, then the rights and obligations of the parties will be determined based on the content of the required form.
(End of clause)
90. 452.228-71 Insurance Coverage (Nov 1996)
Pursuant to FAR clause 52.228-5, Insurance-Work on a Government Installation, the Contractor will be required to present evidence to show, as a minimum, the amounts of insurance coverage indicated below: (a) Workers Compensation and Employer's Liability. The Contractor is required to comply with applicable Federal and State workers' compensation and occupational disease statutes. If occupational diseases are not compensable under those statutes, they shall be covered under the employer's liability section of the insurance policy, except when contract operations are so commingled with a Contractor's commercial operations that it would not be practical to require this coverage. Employer's liability coverage of at least $100,000 shall be required, except in States with exclusive or monopolistic funds that do not permit worker's compensation to be written by private carriers. (b) General Liability. The Contractor shall have bodily injury liability insurance coverage written on a comprehensive form of policy of at least $500,000 per occurrence (c) Automobile Liability. The Contractor shall have automobile liability insurance written on a comprehensive form of policy. The policy shall provide for bodily injury and property damage liability covering the operation of all automobiles used in connection with performing the contract. Policies covering automobiles operated in the United States shall provide coverage of at least $200,000 per person and 500,000 per occurrence for bodily injury and $20,000 per occurrence for property damage or loss. (d) Aircraft Public and Passenger Liability. When aircraft are used in connection with performing the contract, the Contractor shall have aircraft public and passenger liability insurance. Coverage shall be at least $200,000 per person and $500,000 per occurrence for bodily injury, other than passenger injury. Coverage for passenger injury shall be at least $200,000 multiplied by the number of seats or passengers, whichever is greater.
(End of Clause)
AG-7103-S-10-013 Page 107 of 123 Amendment 0001, Attachment 2 offeror's financial agent is not directly on-line to the Fedwire and, therefore, not the receiver of the wire transfer payment.
(End of provision)
L.20 52.233-2 Service of Protest. (SEP 2006)
(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from:
Janet I. Holmes, Contracting Officer
USDA – NRCS
Federal Building, Room 5202 700 West Capitol Avenue Little Rock, Arkansas 72201
(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.
(End of provision)
L.21 52.236-27 Site Visit (Construction). (FEB 1995) - Alternate I (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) An organized site visit has been scheduled for May 26, 2010, at 10:00 a.m. We will meet at the Poteau River Conservation District and then proceed to the work site.
Name: Stanley Mathis Location: Poteau River Conservation District 87 Pine Street Waldron, Arkansas 72958-0242 Telephone: 479-637-3633 (End of provision)
L.22 452.204-70 Inquiries. (FEB 1988)
Inquiries and all correspondence concerning this solicitation should be submitted in writing to the Contracting Officer.
Offerors should contact only the Contracting Officer issuing the solicitation about any aspect of this requirement prior to contract award.
(End of provision)
L.23 452.228-70 Alternative Forms of Security (Nov 1996)
If furnished as security, money orders, drafts, cashiers checks, or certified checks shall be drawn payable to:
USDA, Natural Resources Conservation Service
(End of Provision)
AG-7103-S-10-013 Page 122 of 123 Amendment 0001, Attachment 3
AG-7103-S-10-0013 Page 7 of 8 Attachment 2 Amendment 0001, Attachment 4
AG-7103-S-10-0013 Page 8 of 8 Attachment 2 Amendment 0001, Attachment 4
File details come from the government source that posted it. Updated .