This revised Construction Specification Page 254-3 will replace the original.

View the file

Other files

File Type Posted
AG-6215-S-09-0010 Amendment 2 —
Revised Drawings for Big Caney 37.pdf PDF
Sheets 2 - 16 of 16 for Site 37.pdf PDF
Soliciation_Packet.doc DOC document
Sheets 2 - 9 of 9 for Site 36-A.pdf PDF
Construction Specifications.pdf PDF
SF-1442.pdf PDF
Wage Rates.htm HTM file
Sheet 1 of 9 for Site 36-A.pdf PDF
Sheet 1 of 16 for Site 37.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NRCS – March 2009, Revised July 2009 254-3 KS –Big Caney Watershed District EWP, FRD 37

7. Items of work and construction details Items of work to be performed in conformance with this specification and the construction details are:

Bid Item 2 - Earthfill, Auxiliary Spillway Repair

(1) This item shall consist of the construction of the machine-compacted fill required to replace and/or restore the material eroded from the auxiliary spillways. The completed work shall conform to the lines and grades of the auxiliary spillways as shown on the drawings.

(2) Fill material will be obtained on-site from the locations as shown on the plans.

Material deposited from the eroded areas may be recovered and used as fill within one foot of the finished surface. As allowable, recovered material shall be used first before proceeding to the designated borrow area. Rock larger than 6 inches will be allowed if compaction can be accomplished and does not hinder construction operations.

(3) Compaction shall be accomplished by two passes entirely over each 9-inch lift of fill material below the topsoil and over each 12-inch lift of topsoil by the machine hauling or pushing the fill material. Foundation surfaces shall be scarified a minimum of 4 inches deep prior to placement of fill material. Vertical foundation surfaces shall be worked down adequately prior to placement of fill to ensure proper bonding with the fill material.

(4) For items of work for which specific lump sum prices are established in the contract, the quantity of earthfill will not be measured for payment. Payment for earthfill will be made at the contract lump sum price and will constitute full compensation for all labor, equipment, tools, and all other items necessary and incidental to the completion of the work.

(5) Payment will constitute compensation for the following related subsidiary items:

(a) Pollution Control Measures - Construction Specification 251

(b) Clearing and Grubbing - Construction Specification 252

(c) Excavation, Borrow - Construction Specification 255