Attachment 3 - Construction Specifications
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment_1.pdf | ||
| Att_4_-_Cushman_Road_WRP_0321_Construction_Plan.pdf | ||
| Att_5_SAM_Guide.docm | DOCM document | |
| Att_2_-_Davis_Bacon_WI15_dvb.mht | MHT file | |
| Att_1_-_Cushman_Road_WRP_Location_Map.pdf | ||
| Solicitation _Offer _and_Award-Standard_Form_1442 _Section_A.pdf | ||
| Solicitation_Sections_B_through_M.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USDA-NRCS-Wisconsin Section IV, Technical Guide 1-1 5/12
WISCONSIN CONSTRUCTION SPECIFICATION
1. Clearing
1. SCOPE
The work shall consist of the clearing and disposal of trees, snags, logs, brush, shrubs, stumps, and rubbish from the designated areas.
2. MARKING
The limits of the areas to be cleared will be marked by means of stakes, flags, tree markings, or other suitable methods. Trees to be left standing and uninjured will be designated by special markings placed on the trunks at a height of about 6 feet above the ground surface.
3. PROTECTION OF EXISTING VEGETATION
Trees and other woody vegetation designated to remain undisturbed shall be protected from damage throughout the entire construction period. Any damage resulting from the Contractor's operations or neglect shall be repaired by the Contractor.
Earthfill, stockpiling of materials, vehicular parking, and excessive foot or vehicular traffic shall not be allowed within the dripline of vegetation designated to remain in place. Vegetation damaged by any of these or similar actions shall be replaced with viable vegetation of the same species.
Any cuts, skins, scrapes, or bruises to the bark of the vegetation shall be carefully trimmed and local nursery accepted procedures used to seal damaged bark.
Any limbs or branches 0.5-inch or larger in diameter that are broken, severed, or otherwise seriously damaged during construction shall be cut off at the base of the damaged limb or branch flush with the adjacent limb or tree trunk.
All roots 1 inch or larger in diameter that are cut, broken, or otherwise severed during construction operations shall have the end smoothly cut perpendicular to the root. Roots exposed during excavation or other operations shall be covered with moist earth and/or backfilled as soon as possible to prevent them from drying.
4. CLEARING
Trees, brush, shrubs, stumps, and other woody growth shall be cleared to a height not exceeding 12 inches above the ground surface. Such growth may be cleared by cutting, pulling, grubbing, or other approved methods.
Trees shall be felled in such a manner as to avoid damage to trees that are to be left standing, existing structures, utilities, and with regard for the safety of persons.
When the designated areas to be cleared include borrow areas and/or areas upon which improvements are to be constructed, the required grubbing of stumps, roots, and other objectionable material in these areas shall be a part of this specification. The grubbing shall consist of the removal of all stumps, 5/12 1-2 roots of 1 inch in diameter or larger, buried logs, and other objectionable material to a minimum depth of 2 feet below a structure subgrade and 1 foot below an embankment foundation.
5. SITE EROSION CONTROL
Measures shall be installed, or the work performed in a manner that will minimize site erosion, and the production of sediment. Protective measures shall include but are not limited to diversions, waterways, seeding, mulching, sediment basins, and silt fences.
6. DISPOSAL
All materials cleared from the designated areas shall be burned or buried at approved locations or otherwise removed from the site. Buried materials shall be covered with a minimum of 2 feet of earthfill (including any topsoil added for seeding).
The Contractor is responsible for complying with all rules and regulations for disposal at locations away from the construction site or for the burning of cleared materials.
2-1 USDA-NRCS-Wisconsin
5/12
WISCONSIN CONSTRUCTION SPECIFICATION
2. Excavation
1. SCOPE
The work shall consist of the excavation of all materials necessary for the construction of the work.
2. USE OF EXCAVATED MATERIALS
To the extent that they are needed, all suitable materials removed from the specified excavations shall be used in the construction of the required earthfill. The suitability of materials for specific purposes will be determined by the Technician. The Contractor shall not waste or otherwise dispose of suitable excavated materials.
3. DISPOSAL OF WASTE MATERIALS
All surplus or unsuitable excavated materials will be designated as waste and shall be disposed of at the locations shown on the drawings or as approved by the Technician. Waste materials shall not be placed in wetlands.
Material placed in designated waste disposal areas shall be left in a neat and sightly condition and sloped to provide positive drainage. Compaction of the waste materials will not be required unless specified by the construction plans.
Waste material excavated from channels may be deposited in leveled spoilbanks or areas adjacent to the channel work (if permissible). The shape and slopes of the spoilbanks shall be indicated on the drawings or as approved by the Technician. Spoil piles shall be located a minimum of 12 feet from the top of the channel side slope.
Spoil piles or disposal areas shall be protected to minimize site erosion and the production of sediment. Protective measures may include but are not limited to diversions, seeding, mulching, sediment basins, and silt fences.
4. SPECIAL REQUIREMENTS FOR STRUCTURE AND TRENCH EXCAVATION
The required dimensions and side slopes of all structure and trench excavations shall be as shown on the drawings.
Excavation beyond the limits of the specified lines and grades shall be corrected by filling the resulting voids with approved compacted materials.
Excavation for the installation of pipes shall follow the practices contained in the Occupational Safety and Health Administration (OSHA) Subpart P, Excavation, of 29 CFR 1926.650, .651 and .652.
Side slopes shall be excavated or braced to safeguard the work and workers. When bracing or supporting is required, the width of the excavation shall be adjusted to allow for the space occupied by the sheeting, bracing, or other supporting installations. The Contractor shall furnish, place, and subsequently remove such supporting installations.
USDA-NRCS-Wisconsin 2-2
5/12
5. REMOVAL OF WATER
The Contractor shall construct and maintain all necessary cofferdams, channels, flumes, pumping equipment, and/or other temporary diversion and protective work for dewatering the various parts of the work. Foundations, cutoff trenches, and other parts of the work shall be maintained free from water as required for constructing each part of the work. After having served their purpose, all cofferdams and other temporary protective works shall be removed, or leveled to give a sightly appearance and so as not to interfere in any way with the operation, usefulness, or stability of the permanent structure.
6. BORROW EXCAVATION
When the quantities of suitable materials obtained from specified excavations are insufficient to construct the specified fill portions of the permanent works, additional materials shall be obtained from the designated borrow areas.
When shown on the drawings, sediment basins, terraces, diversions, or other measures shall be constructed to protect the borrow areas from erosion and retain sediment within the borrow area.
The upper six (6) inches shall be stripped from all borrow areas. This stripping shall be performed immediately prior to use of the borrow material to reduce the time the area is exposed to erosion. For large borrow areas, only a portion of the area should be stripped at a time. This material shall be redistributed over the area from which it came after borrow excavation is completed.
The extent of excavation and the selection of materials from the borrow area shall be as directed by the Technician. On completion of excavation, all borrow pits shall be left in a neat and sightly condition. All borrow areas shall be graded to blend with existing topography and sloped to prevent ponding and provide positive drainage.
7-1 5/12
WISCONSIN CONSTRUCTION SPECIFICATION
7. Mobilization and Demobilization
1.
The work consists of the mobilization and demobilization of the Contractor's forces and equipment necessary for performing the work required.
SCOPE
2.
Mobilization shall include:
EQUIPMENT AND MATERIAL
• All activities and associated costs for transportation of the Contractor's personnel, equipment, and operating supplies to the site;
• Establishment of offices, buildings, and other necessary general facilities for the Contractor's operations at the site
• Premiums paid for performance and payment bonds including coinsurance and reinsurance agreements as applicable
• Construction and maintenance of haul roads and equipment parking areas
• Other job related items
Demobilization shall include:
• All activities and costs for transportation of personnel, equipment, and supplies not utilized in the project from the site
• Disassembly, removal, and site cleanup of offices, buildings, and other facilities assembled on the site.
• Repair of access roads, temporary haul roads, and equipment parking areas leaving the project site in the same or better condition than at the start of the project.
• General cleanup and house keeping needed to restore a neat and orderly project site.
Access to the site, equipment parking, and staging areas are limited to that shown on the drawings or as approved by the technician.
4/22/2013 11:12 AM Project: Cushman Road WRP Material Specification
MATERIAL SPECIFICATION A
BIODEGRADABLE EXTENDED TERM EROSION CONTROL BLANKET
Description:
The extended-term double net erosion control blanket shall be a machine-produced mat of 70% agricultural straw and 30% coconut fiber with a functional longevity of up to 18 months.
(NOTE: functional longevity may vary depending upon climatic conditions, soil, geographical location, and elevation). The blanket shall be of consistent thickness with the straw and coconut evenly distributed over the entire area of the mat. The blanket shall be covered on the top and bottom sides with 100% biodegradable woven natural organic fiber netting. The netting shall consist of machine directional strands formed from two intertwined strands with cross directional strands interwoven through the twisted machine strands (commonly referred to as Leno weave) to form an approximate 0.50 x 1.0 (1.27 x 2.54 cm) mesh. The blanket shall be sewn together on 1.50 inch (3.81 cm) centers with degradable thread.
Material Content:
Matrix 70% Straw Fiber
30% Coconut Fiber
0.5 lbs/yd2
0.15 lbs/yd2
Netting Leno Woven 100% biodegradable jute
9.3 lb/1000 ft2
Thread Biodegradable
Material Properties:
Index Property Test Method Typical Thickness ASTM D6525 0.28 in Resiliency ETC Guidelines 86% Water Absorbency ASTM D1117 169% Mass/Unit Area ASTM6475 9.66 oz/yd2
Swell ECTC Guidelines 46% Smolder Resistance ECTC Guidelines Yes Stiffness ASTM D1388 0.42 oz-in Light Penetration ECTC Guidelines 14.1% Tensile Strength-MD ASTM D6818 164.4 lbs/ft Elongation-MD ASTM D6818 7.2%
Tensile Strength-TD ASTM D6818 226.8lbs/ft
Elongation-TD ASTM D6818 10.1%