_1_Loon_Rapids_Road_Specifications.doc
DOC document 232 KB Posted
- Attached to
- CN - Loon Rapids Road Reconstruction Project Federal contract opportunity
- Solicitation number
- AG-569R-S-14-0010
About this file
Attachment 1 - Specifications
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| _2_Loon_Rapids_Road_Drawings.pdf | ||
| AG-569R-S-14-0010.pdf | ||
| _4_Experience_Questionnaire.doc | DOC document | |
| _3_Wage_Determination_WI10_dvb.mht | MHT file |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ENGINEERING SCHEDULE OF ITEMS
FR 2297 Reconstruction , Loon Rapids Road, Project # R-814 Lakewood / Laona Ranger District
Chequamegon-Nicolet National Forest
Oconto County, Wisconsin
ITEM
NO.
DESCRIPTION
PAY
UNIT
EST.
QTY.
UNIT
PRICE
TOTAL
PRICE
15101 Mobilization
(to include washing of equipment)
| Lump Sum |
| 1 |
| 15702 |
| Silt Fence |
| Foot |
| 300 |
| 25101 |
| Placed Rip-Rap – Type = Fractured Face Quarry Stone (size shall conform to Class 3 Standard Rip Rap) |
| Cubic Yard |
| 25 |
| 30308 |
| Roadway Reconditioning – Re-shape exist. Road Bed to 2% In-Slope |
| Square Yard |
| 1,700 |
| 40301 |
| 3” Hot Asphaltic Concrete Pavement Type E0.3 |
(placed in two 1-1/2” layers)
| Square Yard |
| 1,700 |
| 60201 |
| Re-inforced Concrete Pipe – 18” Round |
| Foot |
| 128 |
| 60401 |
| Precast Re-inforced Concrete Manhole – 4’ Inside Diameter |
| Foot |
| 16 |
| 60905 |
| 4” Hot Asphaltic Concrete Curb |
| Foot |
| 925 |
| 62503 |
| Seeding, and Mulching, Dry Method |
| Lump Sum |
| 1.00 |
| 63501 |
| Temporary Traffic Control |
| Lump Sum |
| 1.00 |
TOTAL = _____________
STANDARD SPECIFICATIONS FOR CONSTRUCTION OF ROADS AND BRIDGES ON FEDERAL HIGHWAY PROJECTS --- FP – 03 ----, SPECIFICATION LIST
FR 2297 Loon Rapids Rd., Project # R-814
Road Number
| 101 |
| Terms, Format, and Definitions |
| 102 |
| Bid, Award, and Execution of Contract |
| 103 |
| Scope of Work |
| 104 |
| Control of Work |
| * |
| * |
| 105 |
| Control of Materials |
| * |
| 106 |
| Acceptance of Work |
| * |
| 107 |
| Legal Relations |
| * |
| 108 |
| Prosecution and Progress |
| * |
| 109 |
| Measutement and Payment |
| * |
| 155 |
| Schedules for Construction Contracts |
| * |
| 156 |
| Public Traffic |
| * |
| 157 |
| Soil Erosion Control |
| * |
| 251 |
| Rip-Rap |
| * |
| 303 |
| Roadway Reconditioning |
| * |
| 403 |
| Hot Mix Asphalt Concrete Pavement |
| * |
| 602 |
| Culverts and Drains |
| * |
| 609 |
| Hot Asphaltic Concrete Curb – 4” |
| * |
| 625 |
| Turf Establishment |
| * |
| 635 |
| Temporary Traffic Control |
| * |
Preface
Delete all but the first paragraph and add the following:
The Forest Service, US Department of Agriculture has adopted FP-03 for construction of National Forest System Roads.
101 - Terms, Format, and Definitions
101.01 Meaning of Terms
Delete all references to the TAR (Transportation Acquisition Regulations) in the specifications.
101.01 Meaning of Terms
Delete all references to the FAR (Federal Acquisition Regulations) in the specifications.
101.03 Abbreviations.
Add the following to (a) Acronyms:
Add the following to (b) SI symbols:
101.04 Definitions.
Delete the following definitions and substitute the following:
Bid Schedule--The Schedule of Items.
Bridge--No definition.
Contractor--The individual or legal entity contracting with the Government for performance of prescribed work. In a timber sale contract, the contractor is the “purchaser”.
Culvert--No definition.
Right-of-Way--A general term denoting (1) the privilege to pass over land in some particular line (including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2) Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.
Add the following:
Adjustment in Contract Price--“Equitable adjustment,” as used in the Federal Acquisition Regulations, or “construction cost adjustment,” as used in the Timber Sale Contract, as applicable.
Change--“Change” means “change order” as used in the Federal Acquisition Regulations, or “design change” as used in the Timber Sale Contract.
Design Quantity--“Design quantity” is a Forest Service method of measurement from the FS-96 Forest Service Specifications for the Construction of Roads and Bridges. Under these FP specifications this term is replaced by the term “Contract Quantities”.
Forest Service--The United States of America, acting through the Forest Service, U.S. Department of Agriculture.
Neat Line--A line defining the proposed or specified limits of an excavation or structure.
Pioneer Road--Temporary construction access built along the route of the project.
Purchaser--The individual, partnership, joint venture, or corporation contracting with the Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.
Protected Streamcourse--A drainage shown on the plans or timber sale area map that requires designated mitigation measures.
Road Order--An order affecting and controlling traffic on roads under Forest Service jurisdiction. Road Orders are issued by a designated Forest Officer under the authorities of 36 CFR, part 260.
Schedule of Items--A schedule in the contract that contains a listing and description of construction items, quantities, units of measure, unit price, and amount.
Utilization Standards--The minimum size and percent soundness of trees described in the specifications to determine merchantable timber.
Add Figure 101-1—Illustration of road structure terms:
Figure 101-1—Illustration of road structure terms.
102 - Bid, Award, and Execution of Contract
Delete Section 102 in its entirety.
103 - Scope of Work
Delete all but subsection 103.01 Intent of Contract.
104 - Control of Work
Delete Sections 104.01, 104.02, and 104.04.
Add the following subsection:
104.06 Use of Roads by Contractor
The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to the limitations and authorizations designated in the Road Order(s) or described in the contract, when such use will not damage the roads or national forest resources, and when traffic can be accommodated safely.
105 - Control of Material
105.02 Material Sources.
105.02(a) Government-provided sources.
Add the following:
Comply with the requirements of 30 CFR 56, subparts B and H. Use all suitable material for aggregate regardless of size unless otherwise designated. When required, re-establish vegetation in disturbed areas according to section 625.
105.02(a) Government Provided Sources.
(a) Government-provided sources. Add the following:
Government-provided sources for this project are identified as follows:
(1) Government-provided mandatory sources.
Obtain material for use as (borrow/riprap/boulders/etc.) and in the production of aggregates under Sections (301/401/411/etc.) from (Material Source Number or name).
(2) Government-provided optional sources.
Material for use as (borrow/riprap/boulders/etc.) and in the production of aggregates under Sections (301/401/411/etc.) may be obtained from (Material Source Number or name).
105.05 Use of Material Found in the Work.
Delete 105.05 (a) and (b) and the last sentence of the second paragraph and substitute the following:
Materials produced or processed from Government lands in excess of the quantities required for performance of this contract are the property of the Government. The Government is not obligated to make reimbursement for the cost of producing these materials.
106 - Acceptance of Work
106.01 Conformity with Contract Requirements.
Delete Subsection 106.01 and substitute the following:
Follow the requirements of FAR Clause 52.246-12 Inspection of Construction.
References to standard test methods of AASHTO, ASTM, GSA, and other recognized standard authorities refer to the methods in effect on the date of solicitation for bids.
Perform all work to the lines, grades, cross-sections, dimensions, and processes or material requirements shown on the plans or specified in the contract.
Incorporate manufactured materials into the work according to the manufacturer’s recommendations or to these specifications, whichever is more strict.
Plan dimensions and contract specification values are the values to be strived for and complied with as the design values from which any deviations are allowed. Perform work and provide material that is uniform in character and reasonably close to the prescribed value or within the specified tolerance range. The purpose of a tolerance range is to accommodate occasional minor variations from the median zone that are unavoidable for practical reasons.
When standard manufactured items are specified (such as fence, wire, plates, rolled shapes, pipe conduits, etc., that are identified by gauge, unit mass, section dimensions, etc.), the identification will be considered to be nominal masses or dimensions. Unless specific contract tolerances are noted, established manufacturing tolerances will be accepted.
The Government may inspect, sample, or test all work at any time before final acceptance of the project. When the Government tests work, copies of test reports are furnished to the Contractor upon request. Government tests may or may not be performed at the work site. If Contractor testing and inspection is verified by the Government, the Contractor’s results may be used by the Government to evaluate work for acceptance. Do not rely on the availability of Government test results for process control.
Acceptable work conforming to the contract will be paid for at the contract unit bid price. Four methods of determining conformity and accepting work are described in Subsections 106.02 to 106.05 inclusive. The primary method of acceptance is specified in each Section of work. However, work may be rejected at any time it is found by any of the methods not to comply with the contract.
Remove and replace work that does not conform to the contract, or to prevailing industry standards where no specific contract requirements are noted, at no cost to the Government.
(a) Disputing Government test results. If the accuracy of Government test results is disputed, promptly inform the CO. If the dispute is unresolved after reasonable steps are taken to resolve the dispute, further evaluation may be obtained by written request. Include a narrative describing the dispute and a proposed resolution protocol that addresses the following:
(1) Sampling method;
(2) Number of samples;
(3) Sample transport;
(4) Test procedures;
(5) Testing laboratories;
(6) Reporting;
(7) Estimated time and costs; and
(8) Validation process.
If the evaluation requires additional sampling or testing be performed, mutually agree with the Government on witnessing procedures and on sampling and testing by a third party laboratory. Use a third party laboratory accredited by the AASHTO accreditation program. Provide proof of the laboratory’s accreditation for the test procedures to be used. Do not use the same laboratory that produced the disputed Government test results or that produced the test results used as a basis for the dispute.
The CO will review the proposed resolution protocol and may modify it before final approval and execution.
The Government will use the approved resolution protocol test results to determine the validity of the disputed testing. If the Government test results are validated, the Contractor will be responsible for all costs associated with developing and performing the resolution protocol. If the Government test results are not validated, the Government will be responsible for all costs associated with developing and performing the resolution protocol. If the validity of the Government test results cannot be determined, the Contractor and Government will equally share all costs associated with developing and carrying out the resolution protocol.
(b) Alternatives to removing and replacing non-conforming work. As an alternative to removal and replacement, the Contractor may submit a written request to:
(1) Have the work accepted at a reduced price; or
(2) Be given permission to perform corrective measures to bring the work into conformity.
The request must contain supporting rationale and documentation. Include references or data justifying the proposal based on an evaluation of test results, effect on service life, value of material or work, quality, aesthetics, and other tangible engineering basis. The CO will determine disposition of the nonconforming work.
106.07 Delete
Delete subsection 106.07.
107 - Legal Relations and Responsibility to the Public
107.05 Responsibility for Damage Claims.
Delete the entire subsection.
107.06 Contractor’s Responsibility for Work.
Delete the following from the first paragraph.
“except as provided in Subsection 106.07”.
107.09 Legal Relationship of the Parties.
Delete the entire subsection.
107.10 Environmental Protection.
Add the following:
Design and locate equipment repair shops, stationary refueling sites, or other facilities to minimize the potential and impacts of hazardous material spills on Government land.
Before beginning any work, submit a Hazardous Spill Plan. List actions to be taken in the event of a spill. Incorporate preventive measures to be taken, such as the location of mobile refueling facilities, storage and handling of hazardous materials, and similar information. Immediately notify the CO of all hazardous material spills. Provide a written narrative report form no later than 24 hours after the initial report and include the following:
· Description of the item spilled (including identity, quantity, manifest number, and other identifying information).
· Whether amount spilled is EPA or state reportable, and if so whether it was reported, and to whom.
· Exact time and location of spill including a description of the area involved.
· Containment procedures.
· Summary of any communications the Contractor had with news media, Federal, state and local regulatory agencies and officials, or Forest Service officials.
· Description of clean-up procedures employed or to be employed at the site including final disposition and disposal location of spill residue.
When available provide copies of all spill related clean up and closure documentation and correspondence from regulatory agencies.
The Contractor is solely responsible for all spills or leaks that occur during the performance of this contract. Clean up spills or leaks to the satisfaction of the CO and in a manner that complies with Federal, state, and local laws and regulations.
108 - Prosecution and Progress
108 Delete.
Delete Section 108 in its entirety.
109 - Measurement and Payment
109 Deletions
Delete the following entire subsections:
109.06 Pricing of Adjustments.
109.07 Eliminated Work.
109.08 Progress Payments.
109.09 Final Payment.
109.02 Measurement Terms and Definitions.
(b) Contract quantity.
Add the following:
Contract quantities will be adjusted only when there are errors in the original design of 15% or more.
Change the following:
“(b) Cubic yard” to “(c) Cubic yard”.
Add the following definition:
(p) Thousand Board Feet (Mbf). 1,000 board feet based on nominal widths, thickness, and extreme usable length of each piece of lumber or timber actually incorporated in the job. For glued laminated timber, 1,000 board feet based on actual width, thickness, and length of each piece actually incorporated in the job.
151 - Mobilization
Delete Section 151 in its entirety and replace with the following.
Description
151.01 This work consists of moving personnel, equipment, material, and incidentals to the project and performing all work necessary before beginning work at the project site; obtaining of permits, insurance, and bonds. This work also includes washing and treating construction equipment and vehicles necessary for equipment transport to remove seeds, plants, and plant fragments before the equipment is used on Forest Service lands, according to the requirements within.
Construction Requirements Wash the sides, tops, and undercarriages of all construction equipment. Remove all seeds, plants, plant fragments, dirt, and debris from the construction equipment. Only equipment inspected by the Forest Service will be allowed to operate within the project area. All subsequent move-ins of equipment to the project area will be treated in the same manner as the initial move-in. This requirement does not apply to cars, pickup trucks, and other vehicles that regularly travel between the construction site and areas off the National Forest.
Equipment will be considered free of soil, seed, and other such debris when a visual inspection does not disclose such material. Disassembly of equipment, components or the need for specialized inspection tools is not required.
Notify the CO in writing at least 72 hours before moving any construction equipment onto the national forest. Notification will include an agreed upon location where the equipment will be available for inspection by the Forest Service. Inspection will be required after every cleaning.
Use methods of cleaning and locations for cleaning approved by the CO.
For work at a commercial washing facility, use an approved facility.
New infestations of noxious weeds of concern to Forest Service and identified by either Contractor or Forest Service, in the Project Area or on the haul route, will be promptly reported to the other party. Contractor and Forest Service will agree on treatment methods to reduce or stop the spread of noxious weeds when new infestations are found. A current list of noxious weeds of concern to Forest Service is available at each Forest Service office.
Measurement
151.02 Clean equipment prior to moving onto this project. The initial cleaning will not be included in the measurement for payment. Payment for cleaning will only be made if subsequent cleanings are ordered by the CO. Measurement shall be on an “each” basis, meaning one complete cleaning of all equipment required for this contract. Subsequent cleanings necessitated by the Contractor’s actions but not directed by the CO will not be included in the measurement for payment.
Measure mobilization according to Subsection 109.02.
Payment
151.03 The accepted quantity, measured as provided in Subsection 109.02, will be paid at the contract price per unit of measurement for the Section 151 pay item shown in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05.
Progress payments for mobilization lump sum will be paid as follows:
(a) If applicable, bond premiums will be reimbursed according to FAR Clause 52.232-5 Payments Under Fixed-Price Construction Contracts, after receipt of the evidence of payment.
(b) When 5 percent of the original contract amount is earned from other bid items, 50 percent of the mobilization item, or 5 percent of the original contract amount, whichever is less, will be paid.
(c) When 10 percent of the original contract amount is earned from other bid items, 100 percent of the mobilization item, or 10 percent of the original contract amount, whichever is less, will be paid.
(d) Any portion of the mobilization item in excess of 10 percent of the original contract amount will be paid after final acceptance.
Include all costs associated with the initial cleaning of equipment in the unit bid price for Mobilization. Cleaning for subsequent move-ins will not be paid for unless after a suspension ordered by the CO.
155 - Schedules for Construction Contracts
155 Delete.
Delete Section 155 in its entirety.
156 - Public Traffic
156.03 Accommodating Traffic During Work.
Delete the following from the last paragraph:
according to Subsection 106.07(b)
156.08 Traffic and Safety Supervisor.
Delete this subsection in its entirety.
157 - Soil Erosion Control
157.03 General
Delete the entire subsection and replace with the following:
Prior to the start of construction, submit a written plan that provides permanent and temporary erosion control measures to minimize erosion and sedimentation during and after construction. Do not begin work until the necessary controls for that particular phase of work have been implemented. Do not modify the type, size, or location of any control. An alternate erosion control plan with all necessary permits may be submitted 30 days before intended use.
Incorporate all permanent erosion control features into the project at the earliest practicable time, as outlined in the approved plan.
When erosion control measures are not functioning as intended, immediately take corrective action.
208 - Structure Excavation and Backfill for Selected Major Structures
208.04 General.
Add the following to the end of the second sentence of the third paragraph:
"... to the CO a minimum of 5 days prior to beginning excavation work."
Add the following to the end of the third sentence of the third paragraph:
"...to the CO a minimum of 15 days prior to installation."
208.09 Foundation Preparation.
Add the following after the first paragraph:
The foundation elevation is defined as the bottom of footings, for spread footing placement; the bottom of the pile cap, for construction of pile foundations; and the toe of the wall, for construction of retaining walls, except wingwalls at bridges.
Replace all material from any over-excavation below the designated footing elevation with concrete, compacted gravel, or foundation fill at the direction of the CO.
When boulders or irregular, fractured, or seamed bedrock precludes excavation to the designated footing elevation without further loosening of previously solid material, the CO may order removal of such loose material and allow payment for concrete, gravel, or structural backfill that is required to restore foundation material to the designated elevation
208.13 Measurement.
Add the following to the second paragraph:
(f) Material excavated to construct end walls or wing walls which lie outside the excavation limits specified above.
Add the following paragraph:
Foundation over-excavation and the resulting replacement material will not be measured for payment unless the CO determines the over-excavation was unavoidable because of the nature of the material.
209 - Structure Excavation and Backfill
Section 209A. —Structure Excavation and Backfill for Selected Minor Structures Description
209A.01 This work consists of excavating, preparing foundations, backfilling, and subsequent removal of safety features for the construction of selected structures with or without a geo-grid reinforcing mesh and welded wire facing.
Material
209A.02 Conform to the following Subsections:
Crushed Aggregate 703.06
Backfill Material 704.03
Structural backfill 704.04
Geotextile type I-D 714.01
Geogrids, Category 1, 2, 3, 4, 5 or 6 714.03
Welded wire form 720.01(b)
Construction Requirements
209A.03 Preparation for Structure Excavation. Clear the area of vegetation and obstructions according to Sections 201 and 203.
209A.04 General. Excavate trenches or foundation pits to a width and length that allows room for work. When excavation is complete obtain written approval of the foundation. Ensure the foundation is firm with uniform density throughout its length and width. Foundation Elevation is described as the elevation at the bottom of any bedding for installing the structure.
Where necessary to blast rock, blast according to Section 205.
Follow OSHA safety regulations (29 CFR, Part 1926, Subpart P, Excavation) for sloping the sides of excavations, using shoring and bracing, and for using other safety features. When sides of excavations are sloped for safety considerations, provide one copy of the design that demonstrates conformity with OSHA regulations. Where support systems, shield systems, or other protective systems are to be used, design the shoring according to Section 562 and submit working drawings and construction details according to Subsection 104.03.
Remove safety features when no longer necessary. Remove shoring and bracing to at least 2 feet below the surface of the finished ground.
Saw cut or mill existing pavements or concrete structures adjacent to the area to be excavated that are designated to remain.
Do not deposit excavated material in or near a waterway. Do not stockpile excavated material or allow equipment closer than 2 feet from the edge of the excavation.
Dispose minor amounts of unsuitable or excess material on exposed slopes prior to seeding, or at designated sites or legally off the project. If approved, suitable excavated material may be used as backfill material or structural backfill.
Remove all water as necessary to perform work.
Survey minor structures according to Subsection 152.03 (e) and (i), and verify the limits of the structure. Survey and establish controls within + 0.16 feet. Grade the foundation for a width equal to the length of the bottom geo-grid layer.
209A.05 Foundation Preparation. Excavate any unsuitable material below foundation grade, and replace it with suitable backfill material. Place backfill material in horizontal layers that, when compacted, do not exceed 6 inches in depth. Compact each layer according to Subsection 210.07.
Compact the foundation prior to placing backfill in Subsection 210.06
209A.06 Backfill. Place leveling course with crushed aggregate on the foundation grade when required. Backfill with structural backfill material. Place backfill in horizontal layers that do not exceed 6 inches in compacted thickness. Compact each layer according to Subsection 210.07.
Bring structural backfill up evenly on all sides of the structure as appropriate. Extend each layer to the limits of the excavation or to natural ground.
Ensure when placing the geotextile or geo-grid layers that there are no voids below the layer. When placing geotextiles overlap the geotextile a minimum of one foot. When placing geo-grid overlap the joints a minimum of three feet. Do not operate equipment directly on top of or damage the welded wire form facing, geotextile, or geo-grid elements. Place the geotextile and geo-grid smooth and free of wrinkles or folds. Correct all damaged, misaligned, or distorted structure elements. Repair all damage to galvanized coating before installation.
Do not deviate from the design batter of the welded wire form by more than 1 inch per 10 feet of structure height.
209A.07 Compacting. Determine optimum moisture content and maximum density according to AASHTO T 99, method C. Adjust the moisture content of the backfill material to a moisture content suitable for compaction.
Compact material placed in all layers to at least 95 percent of the maximum density. Determine the in place density and moisture content according to AASHTO T 310 or other approved test procedures.
Do not apply density requirements as measured by AASHTO T 310 to material that is incapable of being tested or compacted to maximum values determined by AASHTO T 99. For these materials, fill the voids around the rock in each layer with earth or other fine material. Compact each layer, full width, until there is no visible evidence of further consolidation, with a vibratory steel wheeled roller with a mass of at least 8 tons.
In places not accessible to the rollers compact with alternative equipment to obtain the required compaction requirements.
209A.08 Acceptance. See Table 210-1 for sampling and testing requirements.
Clearing and removal of obstructions will be evaluated under Sections 201 and 203.
Survey work will be evaluated under Subsection 106.02 and 106.04.
Material for the backfill material and structural backfill will be evaluated under Subsections 106.02 and 106.04.
Structure excavation and backfill work will be evaluated under Subsections 106.02 and 106.04.
Shoring and bracing will be evaluated under Subsections 106.02 and 106.04.
Welded wire forms, geotextiles, and geogrids will be evaluated under Subsection 106.02 and 106.03.
Placement of welded wire forms, geotextiles, and geogrids will be evaluated under Subsection 106.02 and 106.04.
Measurement
209A.09 Measure the Section 210 items listed in the bid schedule according to Subsection 109.02 and the following.
Measure structural excavation by the cubic yard in its original position according to Subsections 204.16 (a) (1) and (2). Do not include the following volumes in structure excavation:
(a) Any material included within the staked limits of the excavation, such as contiguous channel changes and ditches, for which measurement is covered under other sections; or
(b) Material rehandled, except when the contract specifically requires excavation after embankment placement.
Measure backfill material and structural backfill by the cubic yard in place for the volume placed according to Subsection 204.16 (c).
Measure geotextile by the horizontal and vertical dimensions.
Payment
209A.10 The accepted quantities measured as provided in Subsection 109.02 and above, will be paid at the contract price per unit of measurement for the Section 210 pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05.
Payment for structure excavation, shoring, and bracing will be full compensation for excavation to a depth of 6 feet below the lowest elevation shown on the plans for each minor structure. When the excavation exceeds 6 feet, either the Contractor or the CO may request an equitable price adjustment for the depth in excess of 6 feet.
209.10 Backfill.
(a) General.
Add the following:
Replace any pipe that is distorted by more than 5 percent of nominal dimensions, or that is ruptured or broken.
Do not place or backfill pipe that meets any of the following conditions until the excavation and foundation have been approved in writing by the CO:
· Embankment height greater than 6 feet at subgrade centerline.
· Installation in a protected stream course.
· Round pipe with a diameter of 48 inches or greater.
· Pipe arches with a span of 50 inches or greater.
· Any box culvert or structure other than pipe culverts.
(b) Pipe culverts.
(1) Pipe culverts with compacted backfill.
Add the following:
Excavate an area on each side of the pipe as needed to effectively achieve compaction requirements. Backfill without damaging or displacing the pipe. Complete backfilling of the trench with suitable material.
209.11 Compacting.
Delete the subsection and add the following:
Compact backfill using designated compaction method A, B, or C:
Method A. Ensure that backfill density exceeds the density of the surrounding embankment.
Method B. Adjust the moisture content of the backfill material to a moisture content suitable for compaction. Compact each layer using appropriate compaction equipment until visual displacement ceases. For compaction under sections 252, 254, 255, 257, 258 and 262 compact with a vibratory steel wheeled roller with a mass of at least 8 tons.
Method C. Determine optimum moisture content and maximum density according to AASHTO T 99 method C. Adjust the moisture content of the backfill material to a moisture content suitable for compaction. Compact material placed in all layers to at least 95 percent of the maximum density. Determine the in place density and moisture content according to AASHTO T 310 or other approved test procedures.
Table 209-1 Sampling and Testing Requirements
Add the following:
(2) Compaction methods (A) and (B) do not require AASHTO T-99 or T-310 test methods for foundation fill.
251 - Riprap
251.03 General.
Add the following:
Place riprap under or adjacent to structures before placing prefabricated superstructure units or constructing superstructure falsework unless otherwise approved by the CO.
251.08 Measurement.
Add the following:
Payment for excavation and embankment required for placement of riprap is indirectly included in the pay item for riprap.
403 - Hot Asphalt Concrete Pavement
403.06 Surface Preparation.
Add the following:
Prelevel dips, depressions, sags, excessive or nonexistent crown, or other surface irregularities with hot asphalt concrete according to Section 404. Spread and compact the hot asphalt concrete in layers parallel to the grade line not exceeding 2 inches in compacted depth.
403.16 Pavement Smoothness.
Delete the heading and replace with the following:
Pavement Smoothness and Surface Tolerance
Add the following:
The maximum variation from the compacted width is 3 inches and the average width of 4 or measurements for any ½ mile of road segment is the specified width.
The maximum variation from the compacted specified thickness is ¼ inch and the average thickness of 4 measurements for any ½ mile of road segment is the specified thickness
403.17 Acceptance.
Modify Table 403-1 Sampling, Testing, and Acceptance Requirements as follows:
In the sampling frequency column for the characteristics: gradation, asphalt content, and compaction, add the following:
but no fewer than a minimum of 1 per shift.
Add the following:
Table 403-1—Acceptance Sampling and Testing Requirements.
| Material or Product |
| Type of Acceptance (Subsection) |
| Characteristic |
| Category |
| Test Methods Specifications |
| Sampling Frequency |
| Point of Sampling |
| Split Sample |
| Reporting Time |
| Pavement Width |
| Measured and tested conformance (Subsection 106.04) |
| Width |
| - |
| - |
| 4 per each 0.5 mile |
| Pavement after compaction |
| - |
| 4 Hours |
| Pavement Thickness |
| Measured and tested conformance (Subsection 106.04) |
| Thickness |
| - |
| - |
| 4 per each 0.5 mile |
| Pavement after compaction |
| - |
| 4 Hours |
602 – Culverts and Drains
602.03 General.
Add the following:
Ensure that the final installed alignment of all pipe allows no reverse grades, and does not permit horizontal and vertical alignments to vary from a straight line drawn from center of inlet to center of outlet by more than 2 percent of pipe center length or 1.0 feet, whichever is less.
625 - Turf Establishment
625.03 General.
Delete the first subsection and add the following:
Apply turf establishment to finished slopes between April 15 and September 15. Do not seed during windy weather or when the ground is excessively wet, frozen, snow covered, extremely dry, cloddy, hard pan, or is otherwise un-tillable.
Seed Mixtures shall consist of the following:
Purple Prairie Clover --- (Dalea Petalostemum Purpurea) --- 4% Blackeyed Susan --- (Rudbeckia Hirta) --- 1% Big Bluestem --- (Andropogon Gerardi) --- 10% Sideoats Grama --- (Bouteloua Curtipendula) --- 20% Canada Wildrye --- (Elymus Canadensis) --- 35% Annual Ryegrass --- (Lolium Multiflorum) --- 10% Little Bluestem --- (Schizachyrium Andropogon Scoparium) --- 10% Indiangrass --- (Sorgastrum Nutans) --- 10%
Seeding Rates:
20 pounds of seed mixture per acre.
625.05 Watering.
Delete the entire subsection
625.06 Fertilizing.
Delete the entire subsection
625.07 Seeding. (a) Dry method.
Remove the last sentence “Lightly compact the seedbed within 24 hours after seeding.”
625.08 Mulching.
Add after the first sentence:
“Mulching shall include furnishing and placing required straw mulch to newly disturbed soil”
Mulch material shall be applied uniformly. If applied by mechanical means, wheel ruts and any re-compaction of the surfaces will be returned to their previous condition and mulch re-applied at the contractor’s expense.
635 - Temporary Traffic Control
635.03 General.
Add the following:
Install temporary traffic control signs to temporary posts or approved temporary sign mounts.
PAGE
_1299580650.doc
AFPA
MSHA
NIST
NESC
WCLIB
American Forest and Paper Association Mine Safety and Health Administration National Institute of Standards and Technology National Electrical Safety Code West Coast Lumber Inspection Bureau
_1299580678.doc mp
Milepost ppm
Part Per Million