Pre-bid_notes.docx
DOCX document 12 KB Posted
- Solicitation number
- AG-55N9-S-17-0013
About this file
meeting notes and attendees. this is not an amendment and does not need to be acknowledged as part of your quote.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RoadLogs.pdf | ||
| Maps.pdf | ||
| CombinedSynopsisSolicitationCommServices_rdmtce.docx | DOCX document | |
| SCAWageDetermination.pdf | ||
| DrawingsSpecifications.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
WAYNE NATIONAL FOREST
PRE-BID MEETING FOR IRONTON DISTRICT F.S. ROAD MAINTENENCE LAWRENCE COUNTY, OHIO.
AG55N9-S-17-0013. MAY 7, 2017 @ 10:30.
| COMPANY | REPRESENTATIVE | PHONE # | |||||
| Taylor Excavating | Chelsea | taylorexcavating5507@yahoo.com | 740-645-3654 | ||||
| Southern 52 | Chuck Edwards | eddozerman@g.mail | 740-377-3311 | ||||
| USFS | Mike Grebeck |
We went to all six (6) of the sites and discussed each item.
Question: If there is a problem with the time of delivery of stone to the work site and if the trucker can’t tail gate, how will it be rectified? Can contractors haul it themselves? Answer: NO. The Gov’t will address this concern with the quarry and the contractor both prior to the award and if it arises, in the process of performing the project.