AG-4568-S-16-0019
NFNC Nantahala Ranger District Standing Indian Campground Restroom Remodel
Bid Schedule Standing Indian Campground - Loop #5 Bath-house Renovation
BASE BID ITEMS: Tsali Campground
*Pay Item Description Quantity Unit Unit Price Amount
| 1. | MOBILIZATION | 1 | LS | $_________ |
| (Not to exceed 5% of Base bid) | | | |
2. DEMOLITION
| A. | Selective Building Demolition | 1 | LS | $_________ |
| per Drawings including disposal | | | |
| B. | Concrete Apron Demolition & | 1 | LS | $_________ |
| re-grading incl. ABC stone | | | |
| base placement | | | |
3. CONCRETE WORK:
| A. | Patching of interior | 1 | LS | $________ |
| Concrete floors | | | |
| B. | Construction of 6” thk. | 138 | SF | $_________ | $________ |
| Reinf. Concrete sidewalk incl. | | | | |
| turndowns and anchorage to bldg. | | | | |
4. BUILDING REPAIRS:
| A. | Construction of 8” width | 137 | SF | $_________ | $ |
| Block Partition walls and | | | | |
| Plumbing Chase walls | | | | |
| Installation of 4” thk. | 14 | EA | $_________ | $ |
| Block caps | | | | |
| B. | Installation of new | 5 | EA | $ | $ |
| Alum. Block vents | | | | |
| C. | Installation of new metal doors | 3 | EA | $ | $ |
| Incl. hardware | | | | |
| D. | Installation of Gable Ends | 80 | SF | $_________ | $ |
| Screens w/ S.Steel Expanded Metal | | | | |
| E. | Installation of Hardi-Panel | 1 | LS | $ |
| On Soffits, Gable Ends & Ceilings | | | |
| F. | Installation of 5/4x10 | 1 | LS | $ |
| Miratec Fascia Boards | | | |
| G. | Installation of 6x6 Porcelain | 266 | SF | $ | $ |
| Floor Tiles & 3x3 Mosaic | | | | |
| Porcelain Showers and Drain Tiles | | | | |
| Installation of 6x12 Porcelain | 112 | LF | $ | $ |
| Cove Base Tiles | | | | |
| Installation of 6x6 Porcelain | 278 | SF | $ | $ |
| Wall Tiles | | | | |
| H. | Installation of solid plastic | 1 | LS | $ |
| Toilet Compartments & Shower Doors | | | |
| I. | Construction of P.Tank and | 1 | LS | $ |
| Water Heaters Wooden Shelves | | | |
5. PLUMBING REPAIRS:
A. Water Supply Rough Plumbing
| Copper piping incl. shut-off and | 1 | LS | | $ |
| | | Drain valves | |
| B. | Waste and Vent Rough Plumbing | 1 | LS | $ |
| Sch. 40 PVC | | | |
| C. | Installation of Floor and Shower | 4 | EA | $ | $ |
| Drains | | | | |
| D. | Installation of 119 gal. fiberglass | 1 | EA | $ | $ |
| Pressure Tank | | | | |
| E. | Installation of Specified | 1 | EA | $ | $ |
| Booster Pump incl. pressure switch | | | | |
| F. | Installation of specified | 2 | EA | $ | $ |
| Water Heaters | | | | |
| G. | Installation of Shower Controls | 2 | EA | $ | $ |
| Incl. TMV, Push button Valve | | | | |
| and shower head | | | | |
| H. | Installation of Wall Hung | 2 | EA | $ | $ |
| Lavatories incl. Faucet | | | | |
| I. | Installation of Wall Hung | 2 | EA | $ | $ |
| Flush Valve Commodes incl. | | | | |
| Carrier, Flush Valve & Seat | | | | |
| J. | Installation of Floor Mounted | 2 | EA | $ | $ |
| Flush Valve Commode incl. | | | | |
| Flush Valve & Seat | | | | |
| K. | Installation of Bathroom | 1 | LS | $ |
| Accessories incl. Mirrors, | | | |
| Grab Bars & Clothes Hooks, etc. | | | |
6. ELECTRICAL REPAIRS:
A. Installation of 125 Amp Load 1 LS $ Center incl. branch breakers and grounding/bonding
| B. | Installation of type A | 5 | EA | $ | $ |
| Light Fixtures incl. conduit | | | | |
| & wiring from Load Center | | | | |
| C. | Installation of type B | 1 | EA | $ | $ |
| Light Fixtures incl. conduit | | | | |
| & wiring from Load Center | | | | |
| D. | Installation of specified | 2 | EA | $ | $ |
| Hand Dryers incl. conduit | | | | |
| & wiring from Load Center | | | | |
| E. | Installation of Wall Mtd. | 3 | EA | $ | $ |
| Quartz Infrared heaters incl. | | | | |
| conduit & wiring from Load Center | | | | |
| F. | Host Site Electrical Pedestal | 1 | EA | $ | $ |
| Per detail sheet 10 of drawings | | | | |
7. ROOFING REPAIRS:
A. Removal of existing shingles 9.5 SQ $_________ $ (pull all nails)
| B. | Removal of (4) roof skylights | 1 | LS | $ |
| including patching opening | | | |
| C. | Cutting of Rafter Tails and | 1 | LS | $ |
| Installation of 2x8 sub-fascia | | | |
| D. | Installation of 30# roofing felt | 1 | LS | $ |
| and Drip Edge | | | |
| E. | Installation of GAF Timberline | 9 | SQ | $ | $ |
| Lifetime Shingles – Weatherwood Color | | | | |
| F. | Installation of Roof Ridge Vent | 20 | LF | $ | $ |
| and TimberTex Ridge caps | | | | |
Total Bid Price $___________
* Any other item of work shown on the drawings or required by the specifications shall be considered incidental to the bid items shown, and no additional payment will be made.
Attachment 00