NATIONAL FORESTS IN NORTH CAROLINA
BARTRAM TRAIL CONSTRUCTION FISH HAWK REROUTE # 4761
ENGINEER'S ESTIMATE
Project Name: National Forests in NC -Nantahala Ranger District Bartram Trail Construction Fish Hawk Reroute-#4761
| ITEM NO. |
| DESCRIPTION |
| METHOD OF |
MEASURE
| UNIT |
| Quantity |
| Unit Price |
| TOTALS |
| 15101 |
| Mobilization |
| LSQ |
| LS |
| 1.00 |
| 912, 915, 917, 984, 987, 988, 991, 981, 982, 983 |
| Trail Construction - including tread & drainage construction, out-sloping, installation & cleaning of grade dips, erosion control, clearing, brush-cutting, logging-out, danger tree removal |
| AQ |
| LF |
| 5280.0 |
BID OPTION # 1 -
Project Name: National Forests in NC -Nantahala Ranger District Bartram Trail Construction Fish Hawk Reroute-#4761
| ITEM NO. |
| DESCRIPTION |
| METHOD OF |
MEASURE
| UNIT |
| Quantity |
| Unit Price |
| TOTALS |
| 912, 915, 917, 984, 987, 988, 991, 981, 982, 983 |
| Trail Construction - including tread & drainage construction, out-sloping, installation & cleaning of grade dips, erosion control, clearing, brush-cutting, logging-out, danger tree removal |
| AQ |
| LF |
| 5280.0 |
| SUB-TOTAL FOR BID OPTION # 1 : |
| $ |
BID OPTION # 2 -
| Project Name: National Forests in NC -Nantahala Ranger District Bartram Trail Construction Fish Hawk Reroute-#4761 |
| Length (Miles) |
| 0.250 |
| ITEM NO. |
| DESCRIPTION |
| METHOD OF |
MEASURE
| UNIT |
| Quantity |
| Unit Price |
| TOTALS |
| 912, 915, 917, 984, 987, 988, 991, 981, 982, 983 |
| Trail Construction - including tread & drainage construction, out-sloping, installation & cleaning of grade dips, erosion control, clearing, brush-cutting, logging-out, danger tree removal |
| AQ |
| LF |
| 1320.0 |
| SUB-TOTAL FOR BID OPTION # 2 : |
| $ |
AG-4568-S-14-0073
BID OPTION # 3-
| Project Name: National Forests in NC -Nantahala Ranger District Bartram Trail Construction Fish Hawk Reroute-#4761 |
| Length (Miles) |
| 0.25 |
| ITEM NO. |
| DESCRIPTION |
| METHOD OF |
MEASURE
| UNIT |
| Quantity |
| Unit Price |
| TOTALS |
| 912, 915, 917, 984, 987, 988, 991, 981, 982, 983 |
| Trail Construction - including tread & drainage construction, out-sloping, installation & cleaning of grade dips, erosion control, clearing, brush-cutting, logging-out, danger tree removal |
| AC |
| LF |
| 1320.0 |
| SUB-TOTAL FOR BID OPTION # 3: |
| $ |
BID OPTION # 4-
| Project Name: National Forests in NC -Nantahala Ranger District Bartram Trail Construction Fish Hawk Reroute-#4761 |
| Length (Miles) |
| 0.25 |
| ITEM NO. |
| DESCRIPTION |
| METHOD OF |
MEASURE
| UNIT |
| Quantity |
| Unit Price |
| TOTALS |
| 912, 915, 917, 984, 987, 988, 991, 981, 982, 983 |
| Trail Construction - including tread & drainage construction, out-sloping, installation & cleaning of grade dips, erosion control, clearing, brush-cutting, logging-out, danger tree removal |
| AC |
| LF |
| 1320.0 |
| SUB-TOTAL FOR BID OPTION # 4: |
| $ |
BID OPTION # 5-
| Project Name: National Forests in NC -Nantahala Ranger District Bartram Trail Construction Fish Hawk Reroute-#4761 |
| Length (Miles) |
| 0.25 |
ITEM METHOD
NO. DESCRIPTION OF
MEASURE UNIT
Quantity Unit Price
TOTALS
| 912, 915, 917, 984, 987, 988, 991, 981, 982, 983 |
| Trail Construction - including tread & drainage construction, out-sloping, installation & cleaning of grade dips, erosion control, clearing, brush-cutting, logging-out, danger tree removal |
| AC |
| LF |
| 1320.0 |
SUB-TOTAL FOR BID OPTION # 5:
| SUB-TOTAL FOR BASE BID: |
| $ |
| SUB-TOTAL FOR BID OPTION # 1: |
| $ |
| SUB-TOTAL FOR BID OPTION # 2: |
| $ |
| SUB-TOTAL FOR BID OPTION # 3: |
| $ |
| SUB-TOTAL FOR BID OPTION # 4: |
| $ |
| SUB-TOTAL FOR BID OPTION # 5: |
| $ |
| TOTAL BID - BASE PLUS OPTIONS 1, 2, 3, 4 ,5 |
| $ |