J1 Work specifications

View the file

Other files

File Type Posted
Amendment 1.rtf RTF text file
SF18 Contractor to complete and return.rtf RTF text file
J2- ATV Trail Brushing Maps.pdf PDF
AG-4419-S-10-0665.rtf RTF text file
J3 - SCA Wage Determination.doc DOC document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Forest Service Supplemental Specifications ATV & Snowmobile Trail Brushing

AAP # CIM-0909-11T-469-0909-02

Superior National Forest St. Louis County, Lake Counties, Minnesota Table of Contents

1Table of Contents

Preface 101 - Terms, Format, and Definitions

101.01 Meaning of Terms

101.03 Abbreviations.

101.04 Definitions.

102 - Bid, Award, and Execution of Contract 102 Bid, Award, and Execution of Contract 103 - Scope of Work Deletions 104 - Control of Work Deletions

104.06 Use of Roads by Contractor

105 - Control of Material

105.02 Material Sources.

105.02(a) Government-provided sources.

105.05 Use of Material Found in the Work.

106 - Acceptance of Work

106.07 Delete

107 - Legal Relations and Responsibility to the Public

107.05 Responsibility for Damage Claims.

107.06 Contractor’s Responsibility for Work.

107.09 Legal Relationship of the Parties.

107.10 Environmental Protection.

108 - Prosecution and Progress 108 Delete.

109 - Measurement and Payment 109 Deletions

109.02 Measurement Terms and Definitions.

155 - Schedules for Construction Contracts 155 Delete.

156 - Public Traffic 201 - Clearing and Grubbing

201.01 Description

201.02 Material:

201.06 Disposal.

203 - Removal of Structures and Obstructions

203.01 Description.

203.05 Disposing of Material.

635 - Temporary Traffic Control

635.03 General.

718 - Traffic Signing and Marking Material

718.05 Aluminum Panels

Preface

Preface_wo_03_15_2004_m Delete all but the first paragraph and add the following:

The Forest Service, US Department of Agriculture has adopted FP-03 “Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects” for construction of National Forest System Roads. The referenced standard specifications are fully applicable to this project unless modified herein by these Supplemental Specifications.

101 - Terms, Format, and Definitions

101.00_nat_us_07_25_2005

101.01_nat_us_01_22_2009

101.01 Meaning of Terms

Delete all references to the TAR (Transportation Acquisition Regulations) in the specifications.

101.03_nat_us_06_16_2006

101.03 Abbreviations.

Add the following to (a) Acronyms:

AFPA

MSHA

NIST

NESC

WCLIB

American Forest and Paper Association Mine Safety and Health Administration National Institute of Standards and Technology National Electrical Safety Code West Coast Lumber Inspection Bureau

Add the following to (b) SI symbols:

mp
Milepost
ppm
Part Per Million

101.04_nat_us_03_29_2007

101.04 Definitions.

Delete the following definitions and substitute the following:

Bid Schedule--The Schedule of Items.

Bridge--No definition.

Contractor--The individual or legal entity contracting with the Government for performance of prescribed work. In a timber sale contract, the contractor is the “purchaser”.

Culvert--No definition.

Right-of-Way--A general term denoting (1) the privilege to pass over land in some particular line (including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2) Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.

Add the following:

Adjustment in Contract Price--“Equitable adjustment,” as used in the Federal Acquisition Regulations, or “construction cost adjustment,” as used in the Timber Sale Contract, as applicable.

Change--“Change” means “change order” as used in the Federal Acquisition Regulations, or “design change” as used in the Timber Sale Contract.

Design Quantity--“Design quantity” is a Forest Service method of measurement from the FS-96 Forest Service Specifications for the Construction of Roads and Bridges. Under these FP specifications this term is replaced by the term “Contract Quantities”.

Forest Service--The United States of America, acting through the Forest Service, U.S. Department of Agriculture.

Neat Line--A line defining the proposed or specified limits of an excavation or structure.

Pioneer Road--Temporary construction access built along the route of the project.

Purchaser--The individual, partnership, joint venture, or corporation contracting with the Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.

Protected Streamcourse--A drainage shown on the plans or timber sale area map that requires designated mitigation measures.

Road Order--An order affecting and controlling traffic on roads under Forest Service jurisdiction. Road Orders are issued by a designated Forest Officer under the authorities of 36 CFR, part 260.

Schedule of Items--A schedule in the contract that contains a listing and description of construction items, quantities, units of measure, unit price, and amount.

Utilization Standards--The minimum size and percent soundness of trees described in the specifications to determine merchantable timber.

102 - Bid, Award, and Execution of Contract

102.00_nat_us_02_16_2005

102 Bid, Award, and Execution of Contract

Delete Section 102 in its entirety.

103 - Scope of Work

103.00_nat_us_02_16_2005

Deletions

Delete all but subsection 103.01 Intent of Contract.

104 - Control of Work

104.00_nat_us_06_16_2006

Deletions

Delete Sections 104.01, 104.02, and 104.04.

104.06_nat_us_02_17_2005

Add the following subsection:

104.06 Use of Roads by Contractor

The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to the limitations and authorizations designated in the Road Order(s) or described in the contract, when such use will not damage the roads or national forest resources, and when traffic can be accommodated safely.

105 - Control of Material

105.02_nat_us_01_18_2007

105.02 Material Sources.

105.02 delete 105.05_nat_us_05_12_2004

105.05 Use of Material Found in the Work.

Delete 105.05 (a) and (b) and the last sentence of the second paragraph and substitute the following:

Materials produced or processed from Government lands in excess of the quantities required for performance of this contract are the property of the Government. The Government is not obligated to make reimbursement for the cost of producing these materials.

106 - Acceptance of Work

106.07_nat_us_05_11_2004

106.07 Delete

Delete subsection 106.07.

107 - Legal Relations and Responsibility to the Public

107.05_nat_us_05_11_2004

107.05 Responsibility for Damage Claims.

Delete the entire subsection.

107.06_nat_us_06_16_2006

107.06 Contractor’s Responsibility for Work.

Delete the following from the first paragraph.

“except as provided in Subsection 106.07”.

107.09_nat_us_06_16_2006

107.09 Legal Relationship of the Parties.

Delete the entire subsection.

107.10_nat_us_06_16_2006

107.10 Environmental Protection.

Add the following:

Design and locate equipment repair shops, stationary refueling sites, or other facilities to minimize the potential and impacts of hazardous material spills on Government land.

Before beginning any work, submit a Hazardous Spill Plan. List actions to be taken in the event of a spill. Incorporate preventive measures to be taken, such as the location of mobile refueling facilities, storage and handling of hazardous materials, and similar information. Immediately notify the CO of all hazardous material spills. Provide a written narrative report form no later than 24 hours after the initial report and include the following:

· Description of the item spilled (including identity, quantity, manifest number, and other identifying information).

· Whether amount spilled is EPA or state reportable, and if so whether it was reported, and to whom.

· Exact time and location of spill including a description of the area involved.

· Containment procedures.

· Summary of any communications the Contractor had with news media, Federal, state and local regulatory agencies and officials, or Forest Service officials.

· Description of clean-up procedures employed or to be employed at the site including final disposition and disposal location of spill residue.

When available provide copies of all spill related clean up and closure documentation and correspondence from regulatory agencies.

The Contractor is solely responsible for all spills or leaks that occur during the performance of this contract. Clean up spills or leaks to the satisfaction of the CO and in a manner that complies with Federal, state, and local laws and regulations.

108 - Prosecution and Progress

108.00_nat_us_02_16_2005

108 Delete.

Delete Section 108 in its entirety.

109 - Measurement and Payment

109.00_nat_us_02_17_2005

109 Deletions

Delete the following entire subsections:

109.06 Pricing of Adjustments.

109.07 Eliminated Work.

109.08 Progress Payments.

109.09 Final Payment.

109.02_nat_us_06_16_2006

109.02 Measurement Terms and Definitions.

(b) Contract quantity.

Add the following:

Contract quantities will be adjusted only when there are errors in the original design of 15% or more.

155 - Schedules for Construction Contracts

155.00_nat_us_05_11_2004

155 Delete.

Delete Section 155 in its entirety.

156 - Public Traffic

156.00_nat_us_04_17_2007

Delete Section 156 in its entirety and replace with the following:

Description

156.01 This work consists of controlling and protecting public traffic adjacent to and within the project.

Material

156.02 Conform to the MUTCD and the following Sections and Subsections:

Construction sign panels

Retro-reflective sheeting

718.01

Temporary concrete barrier

Temporary plastic fence

710.11

Temporary traffic control devices

718.22

156.03 General. Unless otherwise provided for in Table 156-1, keep existing roads open to all traffic during road improvement work, and maintain them in a condition that will adequately accommodate traffic. Delays may not exceed 5 minutes at any one time followed by an open period of no less than 10 minutes.

Perform no work that interferes or conflicts with traffic or existing access to the roadway surface until a traffic control plan has been approved. Post construction signs and traffic control devices in conformance with MUTCD. All required signs will be in place and approved prior to beginning work on project.

If the Contractor agrees in writing to allow public traffic to use a new road being constructed prior to completion, it will be considered an existing road for traffic control purposes.

156.04 Temporary Traffic Control. Install and maintain temporary traffic control devices adjacent to and within the project as required by the approved traffic control plan and the MUTCD. Install and maintain traffic control devices as follows:

(a) Furnish and install traffic control devices before the start of construction operations.

(b) All detours outside of clearing limits will be approved in writing by the Contracting Officer as part of the traffic control plan.

(c) Install only those traffic control devices needed for each stage or phase.

(d) Relocate temporary traffic control devices as necessary.

(e) Remove devices that no longer apply to the existing conditions.

(f) Immediately replace any device that is lost, stolen, destroyed, or inoperative.

(g) Keep temporary traffic control devices clean.

(h) Remove all temporary traffic control devices upon contract completion or when approved.

(i) When required, use flaggers certified by the American Traffic Safety Services Association, the National Safety Council, the International Municipal Signal Association, a state agency, or other acceptable organization. Perform the work described under MUTCD Part 6. Use type III, VII, VIII, or IX retroreflective sheeting on flagger paddles. Do not use flags. Flaggers must wear high visibility safety apparel as required by MUTCD 6E.02.

156.05 Acceptance. Public traffic work will be evaluated under Subsection 106.02.

Measurement and Payment

156.06 Do not measure Public Traffic for payment. Compensation is made as an indirect payment.

201 - Clearing and Grubbing

201.00_nat_us_08_05_2009

201.01 Description

Replace with the following:

This work consists of: Cutting and masticate all grass, brush, and trees up to 3 inches in diameter along both sides of the specified trail.

201.04_nat_us_02_22_2005

201.02 Material:

Delete Tree wound dressing material reference.

201.03 General.

Delete the first and last sentence of the paragraph.

201.04 Clearing.

Delete the section in its entirety and replace with the following:

201.04 Clearing and Roadside Brushing.

Within the clearing limits, brush, downed timber and other vegetation as follows:

This work consists of: Cutting and masticate all grass, brush, and trees up to 3 inches in diameter along both sides of the specified trail. Vegetation shall be cut to within 6 inches of the ground surface or as close as commercially possible to the surface of an uncuttable obstacle such as rock. Exact specifics of trail brushing will vary due to trail width and terrain. Contractor and COR will agree on these specifics. Typical cutting widths will vary between six and eight feet. Limbing to a height of 10 feet as measured from the center of the trail, will also be required.

Contractor shall be responsible for removing cut limbs and branches from trail after completion of brushing if it has not been completely masticated.

Many sections of the trail have not been brushed before so there is not a defined edge.

The Contractor must plan on slower operations than on road brushing due to more obstacles. All brush and limbs that meet these specifications shall be removed to provide a clear travel way.

The contractor shall furnish all labor, equipment, supervision, transportation, operating supplies, and incidentals necessary to perform machine roadside brushing on roads specified herein, in compliance with the terms, specifications, conditions, and provisions. Brushing equipment shall be either wheeled or track and shall meet general commercial industry standards. Hand work shall be required when cutting and limbing individual trees and disposing of brush and slash. The equipment used to perform this work shall meet safety standards and shall be in good mechanical condition.

201.01_nat_us_02_18_2005

201.05 Grubbing.

Delete this section in its entirety.

201.04_nat_us_03_03_2005

201.06 Disposal.

203 - Removal of Structures and Obstructions

203.01_nat_us_02_25_2005

203.01 Description.

Delete and replace with the following:

This work consists of disposing of slash, tops and limbs, brush and woody debris.

203.05_nat_us_02_18_2005

203.05 Disposing of Material.

Add the following:

(e) Chipping or Grinding. Use an approved chipping machine to grind slash and woody debris. Deposit chips or ground woody material on embankment slopes or outside the roadway to a loose depth less than 6 inches. Chips or ground woody material will not be permitted within the traveled roadway.

635 - Temporary Traffic Control

635.03_nat_us_05_13_2004

635.03 General.

Add the following:

Install temporary traffic control signs to temporary posts or approved temporary sign mounts.

718 - Traffic Signing and Marking Material

718.05_nat_us_08_05_2009

718.05 Aluminum Panels

Delete the third paragraph and replace with the following:

Clean, degrease and properly prepare the panels according to methods recommended by the sheeting manufacturer. Conversion coatings will conform to ASTM B-921 or ASTM B-449.