Request for Proposal Construction (Design & Build Construction)
Shoal Creek Pine Glen Bridge Project Cleburne County, Alabama
Solicitation No.: AG-4419-S-10-0627
Project No.: CIM-0801-33R
NAICS CODE: 237310
Proposal Due Date: May 26, 2010 Time: 2:00 PM (EST)
TABLE OF CONTENTS
1. INSTRUCTIONS
1.1. General Description of Work
1.2. What Must Be Included with Proposal Submission
1.3. Schedule of Proposal Activities
1.5. Questions
1.6. Proposal Sealing
1.7. Basis for Proposal Evaluation
1.8 Pre-Proposal Meetings
1.9. Letter of Acknowledgment – Attachment A
1.10 Contact Information
SF1442 – Solicitation (page 1 of 4) SF1442 – Solicitation (page 2 of 4) SF1442 – Solicitation (page 3 of 4) SF1442 – Solicitation (page 4of 4)
PART I—THE SCHEDULE
SCHEDULE OF ITEMS
SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
SECTION D--PACKAGING AND MARKING
SECTION E--INSPECTION AND ACCEPTANCE
SECTION F--DELIVERIES OR PERFORMANCE
52.219-3 Notice of Total HUBZone Set-Aside (Jan 1999)
52.228-15 Performance and Payment Bonds—Construction
PART III--LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS
SECTION J--LIST OF ATTACHMENTS
FAR 52.223-1 Biobased Product Certification (DEC 2007)
SECTION L--INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS OR
RESPONDENTS
52.204-11 American Recovery and Reinvestment Act—Reporting
Requirements (MAR 2009)
52.215-2 Audit and Records—Negotiation (Mar 2009) – ALT I (Mar 2009)
52.225-21 Required Use of American Iron, Steel, and Other Manufactured Goods— Buy American Act—Construction Materials
52.225-22 Notice of Required Use of American Iron, Steel, and Other Manufactured Goods—Buy American Act—Construction Materials
52.225-23 Required Use of American Iron, Steel, and Other Manufactured Goods— Buy American Act—Construction Materials Under Trade Agreements
52.225-24 Notice of Required Use of American Iron, Steel, and Other Manufactured Goods—Buy American Act—Construction Materials Under Trade Agreements.
Attachment A Attachment B – Wage Determination Statement
1. INSTRUCTIONS
This Request for Proposal (RFP) is issued by USDA Forest Service – EROC East, 1720 Peachtree St., NW, Suite 700, Atlanta, GA 30309, hereinafter referred to as FS, to obtain the services of one General "Prime" Contractor (GC), also referred to as Offeror or Contractor, who shall be singularly responsible to satisfy the terms of the resulting contract. The contract is for Shoal Creek Pine Glen Bridge Project in accordance with the scope of work, design drawings, specifications and contract requirements included herein.
The contract will be a Firm-Fixed-Priced. The contractor for this contract will be competitively chosen using Source Selection procedures as described within this RFP. FS will evaluate all responses using the criteria stated herein. This is a Best Value Selection, therefore, FS may award, should it determine it to be in its best interest, to other than the lowest priced offeror, and other than the highest technically rated offeror. The award will be made on a best value basis considering factors such as past performance, experience, capability, capacity, price and overall cost to the Government. Past performance of similar type of work will be considered as an evaluation factor.
This is a competitive RFP for HUBZone Entities ONLY.
This section contains the specific information and instructions needed to prepare a proposal submission for this anticipated award.
1.1. General Description of Work
The GC will provide all labor, materials, equipment, and supervision for the Shoal Creek Bridge Replacement Project in accordance with the specifications and drawing contained herein.
1.2. What Must Be Included with Proposal Submission
In order to properly evaluate proposal received it should include, at minimum, the following:
Cover Should reference this Request for Proposal number and include:
Dunn & Bradstreet Number ______________________________ Tax ID Number ____________________ Email Address ____________________ Note: This information must match the information in the Central Contractor Registration (CCR) website.
Price Proposal
• Price proposal shall be submitted under separate cover and include at minimum:
• Full breakout of labor and materials anticipated.
• Completed Schedule of Items attached in Section B.
• Completed SF1442.
Price proposals shall include all fees and charges.
Other than price
1. Construction Capability
Provide Offeror shall provide a listing of current inventory of construction equipment.
2. Technical Capability
Provide listing the work experience of lead and secondary personnel, as well as primary subcontractors designated to work on project design, construction, and quality control. Contractor shall provide Firm’s standard terms and conditions including any limitations to liability. The Contractor must employ professional personnel to perform the work required under this Statement of Work. Personnel used must possess at least two years of drainage/hydraulic and/or site development design experience with current knowledge of Design/Construction Best Management Practices. The professional conducting the preconstruction work required under this Statement of Work must be a registered Professional Engineer with appropriate engineering and environmental qualifications.
3. Experience.
4. Provide a listing with contact information for all projects from within the last three years. If a project was less than successfully completed list a brief summary of lessons learned. Listing shall describe project scope, location, initial and final price, date and identify a customer point of contact for each project.
5. Past Performance
6. Provide at least 3 written references to substantiate past performance with contact information from within the last three years.
7.
B. Phase II
8. Conceptual Design
9. Provide a design narrative with information addressing the work described in the
RFP for each site. In addition, a proposed layout of operations and Type-Size- Location drawings, and schedule is required. Failure to submit a written narrative or to address any of the evaluation factors will result in the firm not being considered.
10. Price analysis
Provide a breakdown of project cost by site for each of the following: 1. Planning & Design, and 2. Construction.
Financial- Proposal shall provide verification of financial status of the company, credit information.
1.3. Schedule of Proposal Activities
Submission:
Proposals for the RFP shall be received at the following location:
Attention:
Cassandra Carey, Contracting Officer 1720 Peachtree St., NW Suite 700 Atlanta, GA 30309
RFP submissions must be delivered complete by 2:00 PM, EST on May 26, 2010 to the above address.
Proposal received after the 2:00 PM EST on May 26, 2010 will not be considered and will be returned unopened.
Quantity: The Offeror shall submit three (3) copies of all proposals
1.4. Location of Work
Work is to be performed for the Pine Glen Bridge Project, Montgomery, Alabama.
1.5. Questions
Questions: All questions concerning proposal submissions shall be directed to the Contracting Officer, Cassandra Carey at cncarey@fs.fed.us, the Contract Specialist Myron Carr at mhcarr@fs.fed.us and the Contracting Officers Representative (COR) erikadavis@fs.fed.us via email only.
The subject line shall read: Questions RFP # AG-4419-S-10-0627
THE LAST DAY TO SUBMIT QUESTIONS IS: May 21, 2010 at 4:00pm EST
1.6. Proposal Sealing
The contents of each proposal submission are to be placed in sealed envelopes or other sealed enclosure and identified with Offeror’s Name, Project Name, submission material title/heading, Dunns Number , RFP number, and the time/date delivery requirement.
1.7. Basis for Proposal Evaluation
The Government will award a contract resulting from this solicitation to the responsible offeror whose offer conforming to the solicitation will be most advantageous to the Government in accordance with best value criteria.
1.8 Pre-Proposal Meetings
May 19, 2010 10:30 am Shoal Creek Ranger District
(334) 241-8108
1.9. Letter of Acknowledgment – Attachment A
Please complete the attached letter of acknowledgment and forward to the Contracting Officer at cncarey@fs.fed.us by May 10, 2010 to verify your intention to place a proposal.
1.10 Contact Information
All proposal submissions shall include a valid email contact address.
SF1442 – Solicitation (page 1 of 4)
SF1442 – Solicitation (page 2 of 4)
SF1442 – Solicitation (page 3 of 4)
SF1442 – Solicitation (page 4of 4)
PART I—THE SCHEDULE
SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS
SCHEDULE OF ITEMS
Design-Build Construction Contract
CIM-0801-33R
NF AL Sub-project – Shoal Creek RD Pine Glen Bridge
No. Description Unit Qty Total
1 Planning: LS 1 $
Contractor shall provide all labor, materials, testing, equipment, and supplies to perform the following, to include but not limited to: Site investigation, H&H, Structure Alternatives, Construction Limits, Permitting, Project Mgmt., etc.
2 Preliminary Design LS 1 $ Contractor shall provide all labor, materials, testing, equipment, and supplies to perform the following, to include but not limited to: Survey, Foundation Analysis, Preliminary Quantities & Cost Estimate, Structure Outline, Initial Sheets, Traffic Control Plan, etc.
3 Final Design LS 1 $ Contractor shall provide all labor, materials, testing, equipment, and supplies to perform the following, to include but not limited to: Structure Computation, Final sheets, Special Provisions, Submittal Summary, Schedule, EE, Erosion Control Plan, etc.
4 Load Rating LS 1 $ In accordance with SOW 5 Construction LS 1 $
Contractor shall provide all labor, materials, testing, equipment, and supplies to construct Pine Glen Bridge according to approved design.
TOTAL $
Notes: Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed-Price Construction Contracts, shall not be in addition to the contract price. Include bond payments under Bid Item No. 2 Pre-construction. Payment will be made on actual work performed as described in FP-03 109.01 unless otherwise noted.
All efforts required by Request for Proposal are incidental to the above bid items and no additional payments will be made.
SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
Scope of Work
American Recovery and Reinvestment Act
Package for ARRA Contract Actions
CIM-0801-33R
NF AL Sub-project – Shoal Creek RD Pine Glen Bridge
USDA-Forest Service National Forests in Alabama Shoal Creek Ranger District
Heflin, Alabama
Miera C. Nagy, Forest Supervisor
Kim Bittle, District Ranger Jay Edwards, ARRA Coordinator
Contact: Erika L. Davis
USDA, FOREST SERVICE (R-8)
NATIONAL FORESTS IN ALABAMA
PINE GLEN BRIDGE 500-8.0
ROAD BRIDGE DESIGN & CONSTRUCTION: STATEMENT OF WORK
A. DESCRIPTION OF WORK
1. Complete Design Package for Replacement of Pine Glen Bridge 500-8.0 in accordance to Forest Service Handbook guidelines except when deviations are part of the specific task order, contract or agreement, or when approved by the Forest Engineer.
2. The Shoal Creek contains certain aquatic species identified and listed as threatened and endangered (T&E) and/or considered sensitive. A biological evaluation (BE) of the area of potential impact has been performed in accordance to the National Environmental Policy Act (NEPA) requirements and standard practices. The area of potential impact encompasses the general area around the existing bridge including road, approaches, stream banks, and the stream, in addition to the area downstream from the existing bridge to the area of the proposed new bridge, and any vicinity areas that will be impacted by construction and activities.
3. Mitigation measures as identified in the BE would minimize impact to these aquatic species. These measures shall be listed and implemented in the general notes, remarks drawing sheet, and supplemental specification of the bridge design package.
4. Construction of approved bridge design.
5. Provide As-Builts upon completion of construction.
B. EXISTING BRIDGE
1. The road bridge over Shoal Creek on Forest Service Road 500 at Pine Glen was constructed in the 1940’s. This bridge is a 2- span reinforced concrete slab, 13 ft wide (out-out) deck, 32 ft long, with concrete wingwalls and approaches to the bridge deck.
The existing bridge has a design load rating of H10. The Pinhoti National Scenic Hiking Trail also uses the bridge as a means of crossing over Shoal Creek. EXISTING BRIDGE
DEMOLITION IS NOT INCLUDED IN THIS WORK.
C. LOCATION OF NEW BRIDGE
1. The new bridge will be located within a corridor that extends from the centerline of the existing bridge, 150 feet downstream and 300 feet upstream. The new bridge location requires the design for the relocation of new segment of road on both approaches to the new bridge and provide access to Pine Glen Campground from new road segment.
Contractor must coordinate with the Forest Engineer for a field visit. A vicinity map (GIS) that shows general location of existing bridge will be available to contractor.
D. INFORMATION TO BE PROVIDED TO CONTRACTOR
Services to be provided or coordinated by U.S. Forest Service include the following:
a. USGS Topographical Map of location and vicinity map.
b. Bridge Design Requirements (8 pages document)
c. Design Drawings: Information Requirements and Standards (4 pages document)
d. Photographs of the existing structure.
e. USFS will provide a bridge type, and location.
f. Biological Evaluation (BE) of the area of potential impact.
E. INFORMATION TO BE PROVIDED BY CONTRACTOR
1. Services to be provided and/or coordinated by CONTRACTOR include the following:
a. Road bridge site Topographic Survey
b. Subsurface Exploration and Geotechnical Report stamped by a licensed engineer.
c. Hydrologic and Hydraulic Analysis of the site.
d. Specifications – Design all structures in accordance with AASHTO, subject to the modifications and additions contained herein. Use AASHTO material specifications if they exist; only use ASTM, FEDSPEC, MILSPEC, etc. if there is no appropriate AASHTO material specification.
e. Bridge design in accordance to Bridge Design Requirements (8 pages document)
f. Design Drawings: Information Requirements and Standards (4 pages document)
g. Calculations - Perform all design calculations by a qualified (qualified meaning having a minimum 3 years of bridge design experience) registered Professional Engineer or by a qualified engineer working under the supervision of a qualified Professional Engineer. Perform a thorough independent check of all calculations (not merely a math check) and affix the professional seal (non-Federal Government engineers only) and signature of the responsible engineer on the final set of calculations. Submit two copies of the design calculations to the Forest Engineer for review and retention.
Submit design calculations that are legible and fully annotated to facilitate review.
Explain formulae and terms and cite all references.
h. Complete Design Load Rating for new bridge in accordance with the applicable portions of the AASHTO.
F. GENERAL
1. In general, the design shall meet the requirements in Forest Service Handbook (FSH 7709.56) and AASHTO’s “Standard Specifications for Highway Bridges”, current edition.
G. DESIRED BRIDGE STRUCTURE: (See Bridge Design Requirements)
1. A truss structure is recommended with guardrails that follow the natural contour of the road for elevation and includes approach guardrails per ALDOT standards (with flared end treatments on both ends of the structure). Bridge railings shall conform to FSH Chapters 4 and 7. Bridge shall accommodate pedestrian traffic.
2. The proposed bridge structure will have a design load of HS-20-44.
H. DESIGN PACKAGE INCLUDES:
1. Span Length alternatives: economical span length
2. Complete set of 24” X 36”plans. (Copies as needed for interim comments may be 11”X17” (scaled appropriately, not just reduced). Plans should be done in AutoCAD 2006 or newer. Refer to Design Drawings: Information Requirements and Standards
3. Set of specifications to include the FP-03 “Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects”, Forest Service Supplemental Specifications as required, and Alabama DOT specifications for local materials.
4. Engineer’s Estimate of Costs.
5. Calculation of Contract Days; time frames for construction need to fall within the March to October months due to hunting season.
6. Inventory and operating ratings for the designed bridge with calculations. (separate this cost out as an alternative)
7. Electronic CD copy of the final approved set of plans, specifications, cost estimate, and construction schedule.
I. INCLUDED IN THE PLANS WILL BE AT LEAST THE FOLLOWING COMPONENTS:
1. Title Sheet
2. Quantities table and any general notes.
3. Plan and profile sheets; construction limits will be shown on plan view.
4. Site alignment data: sheet showing the general layout of the bridge, road and channel
5. Site Plan/Roadway sheet showing Temporary Bench Marks (TBMs), contours, bridge and channel location
6. Substructure Layout
7. All detail sheets necessary
8. Railing Details
9. Boring Log
10. Traffic Control Plan – NFSR 500 must be open to all traffic during construction and the necessary distance from existing bridge site and both ways per MUTCD guidelines. Plan would include appropriate signage for closure from all directions at points where detours are available. All signs and installations will meet MUTCD standards.
11. Erosion Control Plan and Details
J. SCHEDULE:
CALENDAR DAYS ACTION
0 Contract Award (NTP Signed)
7 Contractor Submits Schedule & Required Documents
30 Contractor Submits 30% Design Package
51 Forest Service Reviews and Returns Comments on 30% Design
61 Contractor Submits USACE/ADEM Completed Permit Application (as necessary) to Forest Service
75 Contractor Submits Final Design Package
89 Forest Service Reviews and Returns Comments on Final Design
106 Contractor Submits Final Design Package with Revisions
126 Forest Service Approves Final Design for Construction
130 Construction Begins
250 Construction Completed
260 Construction As-Built Submitted to Forest Service
260 TOTAL CONTRACT PERFORMANCE PERIOD
K. Source Selection Criteria
1. Phase One. Contractor shall submit a complete proposal, by date specified, providing the following information on the SF-330 form:
a. Construction Capability. Offeror shall provide a listing of current inventory of construction equipment.
b. Technical Capability. Offeror shall demonstrate by listing the work experience of lead and secondary personnel, as well as primary subcontractors designated to work on project design, construction, and quality control. Contractor shall provide Firm’s standard terms and conditions including any limitations to liability. The Contractor must employ professional personnel to perform the work required under this Statement of Work. Personnel used must possess at least three years of bridge design experience with current knowledge of Design/Construction Best Management Practices. The professional conducting the preconstruction work required under this Statement of Work must be a registered Professional Engineer in the State of Alabama with appropriate engineering and environmental qualifications. Preference will be given to teams with previous design-build construction experience.
c. Experience. The Offeror shall provide a listing with contact information for all projects from within the last three years. If a project was less than successfully completed list a brief summary of lessons learned. Listing shall describe project scope, location, initial and final price, date and identify a customer point of contact for each project.
d. Past Performance. The offeror should provide at least 3 written references to substantiate past performance with contact information from within the last three years.
2. Phase Two. Contractor shall submit a complete proposal, by date specified, providing the following information:
a. Conceptual Design. A design narrative must be submitted with information addressing the work described in the Statement of Work to include a summary of findings from preliminary site investigation. In addition, a proposed layout of operations and Type-Size-Location drawings, and schedule is required. Failure to submit a written narrative or to address any of the evaluation factors will result in the firm not being considered.
b. Price analysis. Offeror shall submit a breakdown of project cost according to the Schedule of Items.
NATIONAL FORESTS IN ALABAMA, ENGINEERING UNIT
A. GENERAL
1. Design - Complete Design Package for Replacement of Pine Glen Bridge 500-8.0 in accordance to Forest Service Handbook guidelines except when deviations are part of the specific task order, contract or agreement, or when approved in writing by the Forest Engineer. Contractor is responsible for aquiring all required permits to complete construction.
2. Abbreviations/Definitions
AASHTO - American Association of State Highway and Transportation Officials' Standard Specifications for Highway Bridges, 17th Edition. AASHTO LRFD Bridge Design Specifications, US, 3rd edition, is also permissible.
� Back Wall - What many bridge engineers call "end diaphragm" or "end wall".
� Diaphragm - What many bridge engineers call "intermediate diaphragm."
� Full Size Drawing: ANSI "D" size (22" x 34" cut sheet).
� Half Size Drawing, Check Print, & Final Drawing: ANSI "B" size (11" x 17" cut sheet).
� Multi-Beam Bridge - As defined by AASHTO.
� Client Address: National Forests in Alabama, Engineering Unit - Forest Service, 2946 Chestnut Street, Alabama 36107. Phone 334-241-8174; FAX 334-241-8101.
3. Specifications – Design all structures in accordance with AASHTO, subject to the modifications and additions contained herein. Use AASHTO material specifications if they exist; only use ASTM, FEDSPEC, MILSPEC, etc. if there is no appropriate AASHTO material specification.
4. Calculations - Perform all design calculations by a qualified (qualified meaning having a minimum 3 years of bridge design experience) registered Professional Engineer or by a qualified engineer working under the supervision of a qualified Professional Engineer.
Perform a thorough independent checks of all calculations (not merely a math check) and affix the professional seal (non-Federal Government engineers only) and signature of the responsible engineer on the final set of calculations. Submit two copy of the design calculations to the Forest Engineer for review and retention. Submit design calculations that are legible and fully annotated to facilitate review. Explain formulae and terms and cite all references.
5. Bridge Width – Use bridge widths that are consistent with design criteria, standards, and elements established for the transportation facility. Except when stated otherwise by the Forest Engineer, use the following roadway (curb-to-curb) width on Pine Glen bridge:
Single-lane Pine Glen Bridge: Use 18 feet as the minimum clear distance between curbs or railings. Use widths in excess of 32 feet only to accommodate curve widening, off-highway vehicles, pedestrian traffic and minor deviations (up to 2 feet) resulting from using standard modular structural units.
6. Drainage - On all road bridges, promote drainage by providing a minimum 1 percent crown, a minimum 1 percent gradient, or by superelevating the bridge, as appropriate.
7. Bridge Gradient - For all road bridges with concrete curbs, a minimum 1 percent grade from one end to the other is required to facilitate drainage off the bridge, unless otherwise specified. Grades in excess of 5 percent need to be carefully designed to ensure adequate clearance between the superstructure and substructure and to ensure that excessive gradient does not represent a hazard to users. Contact the Forest Engineer before using a grade greater than 5 percent.
B. SITE SURVEY AND SITE PLAN DEVELOPMENT
Prior to any design and a required by the specific task order, perform a site survey that records existing groundlines at a potential bridge site. Apply the following guidance to the survey and to the site plan, which documents the results of the survey:
1. Survey the site so that results are displayed in English units, with the drawing unit = 1” (inch). Note the date of the survey on ALL documents that display data from the site survey.
2. Survey the stream a minimum of 150 feet downstream and 300 feet upstream from the centerline of the existing bridge, or 5 bridge lengths above and below the proposed bridge location.
3. Location of the new bridge requires roadway re-alignment that maintains access to Pine Glen Campground. Coordinate with the Forest Engineer to ensure that an adequate area is selected for the topographic survey. Additional areas may need to be surveyed to establish temporary crossings for use during construction, as well.
4. Establish control points/reference points to be used during construction of the bridge that are outside the construction area, yet reasonably visible from the proposed alignment and work site. Clearly identify the location and nature of the control point on the site survey and final contract plans.
5. Establish a minimum of two permanent bench marks at location that would be used as control points during construction and be left in place for future reference. Assume local coordinates (x,y,elev.) to a the first permanent benchmark.
6. Show 1’-0” contour intervals and label every 5-foot contour on the site plan.
7. Display information accurately in 3D format. Do not reduce to 2D by setting elevation to “0.”
C. HYDROLOGY AND HYDRAULICS
Design the Pine Glen Bridge structure to pass a 100-year frequency flood with a minimum clearance of 5 feet between high water and the lowest point on the bottom of the superstructure, unless otherwise specified. Other clearance heights/freeboard will be specified, when needed. Refer any problems to the Forest Engineer for resolution.
Prior to design, perform a hydrologic and hydraulic analysis of the site. The goal of any hydrologic and hydraulic analysis at a site is to determine how the flow of water at the site will pass through the proposed structure, whether this can be accomplished without future blockage of the channel and/or waterway under the structure.
1. Adequately survey the stream, including profiles and cross-sections, to generate sufficient information to perform a HEC-RAS analysis of the stream at the bridge site.
Note the date of the survey on ALL documents. Note and survey grade control locations such as: steps, bedrock, logs, or rock clusters. Provide description labels identifying these features.
2. Identify the following: floodplain terraces and floodplain shape details, aggraded areas—gravel bars, islands, etc., degraded areas—scour pools, degraded channels, etc., bank erosion, bedrock locations, and the existing culvert (if applicable)—especially mark and survey the culvert invert locations for use as references points in the contract.
3. Visually observe any apparent high water elevations in the field.
4. In the field, visually establish a reasonable bank full width. The bank full width is defined as the width of the water surface, measured normal to the stream, at a normal flood level (Q2). Establish the bank full width at several locations, both upstream and downstream, so that a representative average bank full width is developed. Ensure that sites where bank full width is measured are outside the influence of any current structures, such as culverts.
5. Visually observe stream velocities at the site at the time of the visit.
6. Determine the Q2 and Q100 flows for the site using USGS Regression equations, stream gages, or any other pertinent or more applicable methods, including specific Forest analyses.
7. Determine a bank full width for site using HEC-RAS. Compare it to the visually observed bank full width. Establish a recommended bank full width to be used for the design of the stream cross-section at the bridge site.
8. Using HEC-RAS, determine a water surface profile and flow depth for the Q100 flow.
Confirm calculated flow depth with any observed high water marks at the site.
9. During analysis use a final stream cross-section used that emulates the natural stream bottom i.e. slightly curved/banked vs. a flat bottom across the stream width. Show several cross-sections along the surveyed length that typify the basic channel shape.
10. Include the following on other notes and sketches, as appropriate:
a. Existing bedforms—physical description, size of particles
b. Steps – spacing between, configurations, particle sizes
c. Reference reach location and description
d. Bank material composition description
e. Locations of utilities—overhead and underground
D. DESIGN SUBMITTALS
1. All design submittals shall meet the following requirements:
a. Investigate alternatives that are feasible on the basis of constructability and economics for the site. Use criteria identified in the specific Task Order for the contract.
b. Submit a design drawing and report (2 copies of each) sufficient to indicate type and geometry of structure proposed, including both superstructure and substructure elements. Include an engineering cost estimate for the proposed structure. Include all information outlined in SOW, section G.1.
c. Include any assumptions or findings used in the preliminary design on both the drawing and in the report. This information may include hydrologic and hydraulic results and results of geotechnical investigation such as assumed bearing capacities and/or pile depths.
2. Preliminary Design (30% completion) shall include:
a. This work consists of the investigation and preliminary design of two bridge alternatives to assist in selecting the structure for final design.
b. Submit preliminary designs on half-size sheets (ANSI B Size) using paper media. As a minimum, include the following items for each alternate, with items 1) – 5) for each alternate on one sheet.
1) Plan and elevation views of each alternate; plan view to be shown on topographic map of site.
2) Typical cross-section of each distinct superstructure type showing deck, and bridge rail configuration, with major dimensions.
3) Configuration, elevations and major dimensions of all substructures.
4) Hydraulic analysis for each distinct bridge type for Q100. Show elevation of Q100 on elevation view.
5) Preliminary quantities and cost estimate for each alternate, using existing Forest Service construction specification methods of measurement and pay items where feasible.
6) Summary of relative advantages and disadvantages associated with each alternate.
7) Recommendation of alternate for final design, with supporting reasons.
8) CAD disk for each design submittal in AutoCAD™ format (release 2006 or newer).
9) Also include the information called for below under "Intermediate Design" for each alternative, when intermediate design is identified as a separate part of the work.
3. Intermediate Design (60% completion)
a. When design drawings for each bridge are at the stage where major elements may be identified, submit intermediate design drawings for review (half size black line prints on paper). One marked up set will be returned, showing any desired changes. Include the following minimum details on the drawings:
1) General layout sheet with plan and elevation view showing ground profile;
beginning and end of bridge stations; bridge width; skew; elevations of deck, footings, and/or pile caps; elevation of design high water (Q100); and the type and extent of riprap or other bank protection.
2) Typical bridge cross section with size and location of major elements identified; roadway width; and type of bridge rail system.
3) Elevation of substructure components with major elements sized; pier and abutment types, location and orientation shown.
4) Preliminary quantities and cost estimate for each alternate, using existing Forest Service construction specification methods of measurement and pay items where feasible.
4. Final Design - When designs are complete, submit the following:
a. When design drawings for the bridge are complete, submit final design drawings for review (half size black line prints on paper). One marked up set will be returned, showing any desired changes.
b. After making required changes, submit one complete set of original half size design drawings on paper and the CD’s for the AutoCAD™ drafted design drawings. Should changes to any AutoCAD™ drafted sheets be required after submission of the disks, the original disk will be held by the Forest Engineer until receipt of the corrected disk, when the original disk will be returned, if requested.
c. Submit one copy of the design and quantity calculations with the final design drawings.
d. Submit one copy of any necessary Special Project Specifications with the final design drawings, but only after contacting the Forest Engineer to verify the necessity. Submit an electronic copy of the Special Project Specification in MS- Word© format.
E. Submit one copy of the Construction Cost Estimate (as opposed to just construction quantities) and Construction Time Estimate with the final design drawings.
F. DESIGN - SUPERSTRUCTURE
1. Loading - Unless stated otherwise, base design upon AASHTO HS 20-44 live loading increased 25 percent "HS 25". For bridges designed using AASHTO LRFD Specifications, use HL93 as the live load.
2. Allowable Stresses – Design structures in accordance with AASHTO allowable stresses. Tubular members and their connections shall be designed per the AISC “Hollow Structural Sections Connections Manual” latest edition.
3. Wearing Surface – Minimum of 1/2 inch wearing surface as per bridge deck design.
4. Minimum Concrete Strengths -
a. The minimum design strength for non-air entrained concrete is 5500 psi at 28 days.
b. Call out all other concrete, except Seal concrete, as Class A(AE) and require a minimum 28 day design strength of 3,500 psi (Forest Service specifications call for 5 percent air in all Class A(AE) concrete).
5. Minimum Deck Thickness – Design a minimum deck thickness of 6-1/2 inches, which includes a 1/2 inch wearing surface.
6. Truss Design
a. Design upstream and downstream truss for a given span length to be identical.
b. Open truss bridges shall be designed per AASHTO section 10.16.12 and by a professional engineer experienced in pony truss bridge design and top chord stability criteria utilizing elastic lateral restraints.
c. Specify AASHTO allowable steel and concrete stresses at transfer of prestress force and under design live, but design for the minimum concrete strengths given in Section F.4. As a minimum, check truss stresses against the allowable stresses at midspan, and centerline of bearing.
d. All vertical truss members shall be perpendicular to the bottom chord of the truss after the bridge is erected and dead loads applied.
e. Shop drawings shall be prepared and reviewed by the designer and submitted to the owner for approval. The contractor shall be responsible for verification of all field dimensions prior to bridge fabrication..
7. Camber, and Dead Load Deflection Diagram - Include predicted camber and calculated deflection due to superimposed dead load in the design of all multi-span bridges; and single-span bridges having cast-in-place decks. Show these values on the drawings in a diagrammatic and tabular form for the tenth points of all spans. Base camber calculations upon an assumed age of 8 weeks.
8. Final Deck Elevation Diagram – For all bridges, provide a tabular diagram on the drawings which shows the design final deck surface elevations. Compute these final deck surface elevations for the same points as in #7 above, plus tenth points along each edge of deck and roadway centerline. Also compute final deck surface elevations at each end of the deck at all corners, roadway centerline, and line centerline. The connection of the floor beam to a pony truss system shall not be solely into the side of a tubular bottom chord without the use of additional stiffeners.
9. Concrete Curbs, Parapets and Curb End Blocks – Require concrete curbs to be cast at the precasting facility before being shipped. Construct concrete curbs, parapets and curb end blocks of air entrained 3500 psi Class A(AE) concrete.
10. Drains – Design drains to carry water off the superstructure considering the geometry of the structure, the site location and the expected weather conditions. Normally, place drains so that water discharges onto the riprap above the Q100 flow elevation. Drain designs should minimize plugging.
11. Deck Guard Angles – Use galvanized deck guard angles across the roadway portion of the concrete bridge deck at each end of the deck and at all deck joints. For prestressed concrete slabs, incorporate the deck guard angle into slab during casting.
As necessary, incorporate the deck guard angle into the back wall at the roadfill edge of the back wall.
12. Bearing Pads:
a. Design 60 durometer chloroprene (neoprene) bearing pads for each truss end, with a minimum thickness of 1/2 inch. Furnish one piece pads unless the design requires the pads to be laminated. Do not allow field punching of the pads to fit around any connections extending from the cap to the truss. Use joint filler material or expanded polystyrene under the back walls and above the cap, plus under the truss where there is no bearing pad, to seal the opening against earth and moisture. Pads are required even when beveled steel bearing plates are used.
b. Design bearing pads following AASHTO, using Load Group I (plus IB if spars are the rare design load), for the anticipated extreme temperature range of the trusss at the bridge site.
13. Reinforcing Steel - Use Grade 60 reinforcing steel.
G. DESIGN - SUBSTRUCTURE
1. Load Groups – Design substructures for Load Groups I, IB (if a spar is the rare design load), II, and III. For Load Group III, include loads caused by shear resistance in the bearing pads when the concrete is at its anticipated low temperature for the bridge site.
2. Seismic Considerations – Design all substructures and the connections between substructure and superstructure in conformance with the current AASHTO seismic design guidelines. For the normal single-span bridge this means ensuring adequate width of bearing seats and adequate strength of connections between trusses and substructures. In addition, normally build "earthquake blocks" into the tops of substructure caps at both ends of all spans. Use the seismic acceleration coefficient that would be used by the state bridge design section for the state in which the structure is to be located.
4. Load Ratings for New Bridge Designs
a. Complete design load ratings for new bridge in accordance with the applicable portions of the AASHTO. Submit with original final design drawings.
b. In the reports, include the completed rating forms followed by computations to support the ratings.
c. State that the report is based upon the assumption that the bridge(s) is in new condition and constructed in accordance with Pine Glen Bridge Replacement Drawing(s) (specify applicable drawings).
d. Provide two (2) copies of bridge load ratings for final bridge design, with set being individually bound and bearing the name, seal, and date of both rater and checker.
NATIONAL FORESTS IN ALABAMA, ENGINEERING UNIT
H. GENERAL
Note: Display the seal and signature of the responsible Engineer on all drawing sheets.
Also show the following data, neatly grouped, on the general layout sheet: date, name and signature of organization's designer, checker and approver; as well as the organization's title (and logo if desired).
� Full Size Drawing: ANSI "D" size (22" x 34" cut sheet).
� Half Size Drawing, Check Print, & Final Drawing: ANSI "B" size (11" x 17" cut sheet).
I. DRAWINGS - GENERAL LAYOUT AND FOUNDATION
1. General Layout
a. General Notes: Use the standard General Layout Sheet Notes, edited for the particular job.
b. Plan View: Show the following information in the Plan View of the bridge.
1) Stationing (increasing from left to right on the drawing) and elevation of beginning and end of bridge (BOB and EOB) on roadway centerline. When a wearing surface is present, note if the elevation is to the top of the wearing surface or to the top of the superstructure unit, to avoid confusion.
2) Add coordinates table (N,E,Z) for BOB and EOB, TBM, C/L Alignment and any other feature to assist in project staking.
3) Railing information not given on the standard railing sheets. This includes the specific alternate desired, when several are permitted (type finish -painted, galvanized, weathering steel; type approach rail end anchorage and end piece), variations from what is shown on the standard rail sheets (post spacing, bends in rail, different lengths of rail), distance from the first bridge rail and first approach guardrail posts from the ends of the bridge, etc. Label and dimension curved railing thoroughly to avoid fabrication errors, since railing shop drawings are normally not called for in contracts. Also show rail post spacing used as well as the rail pay length.
4) Skew the bridge as designed and laid out for. Normally only use standard skews such as 0, 15, and 30 degrees. For other skews, or skews in excess of 30 degrees, consult with the Forest Engineer before proceeding with the design.
5) Overall dimension of the bridge out-to-out as well as a dimension showing the span length.
6) Roadway width and lane widths/shoulder width, as appropriate.
7) Centerline roadway, centerline structure, and the offsets to chords of the roadway at BOB and EOB when a straight bridge is laid out on a curved roadway (as is normally the case). Label each of the above on the drawing.
c. Elevation View: Show the following information in the Elevation View of the bridge
1) Profile of the bridge projected from the right side of the bridge down into an elevation view. Show a simple bar graph near the detail with elevations marked at either 5 foot or 10 foot intervals and labeled “Elevations in Feet.”
2) The Q100 flow elevation and flow volume. Also list the minimum vertical clearance between the lowest portion of the superstructure and the Q100 predicted flow height in the General Note on Hydrology and Hydraulics.
3) The minimum bank full width.
4) Riprap size class, typical slopes, blanket thickness, elevation at top of riprap, bankfull width behind which riprap should be placed, and any other required dimension; also show cut-off trenches and keys. If the skew of the bridge exceeds 15 degrees, show an additional riprap detail normal to the stream centerline.
5) Gradient on the bridge.
6) The substructure type to be used at each abutment and an indication of required design bearing capacities for spread footings or design pile capacities and factor of safety for piling abutments. Include the word “design” in the capacity labels to avoid confusion with “ultimate” capacities.
For pile abutments, also show the minimum pile penetration required for scour (maximum pile tip elevation) as well as the anticipated pile tip for achieving design capacity. If pile shoes/rock tips are required, call out the specific part or approved equal. Label the abutments as “Abutment 1” and “Abutment 2.”
d. Drawing index: Normally, place the index to the immediate left of the title block on the first sheet and list each sheet (by drawing number, sheet number and sheet title) that comprises the structure’s complete drawing package, including any standard drawings to be used.
e. Diagram of any non-HS (non ML) design loading, such as mobile spars.
f. North arrow.
g. Signature Block: Include the following on the first sheet:
Reviewed By: (Designer of Record) Recommended By:
Forest Engineer:
District Ranger:
Staff Officer:
Forest Supervisor:
Approved By:
Regional Forester:
2. Foundation Information - Present the following information on the drawings
a. Statement of the visual classification of streambed materials, unless this information is not available (normally included in the Foundation Information section of the General Layout Sheet Notes).
b. Drilled hole, seismic, or dug pit log data, to include (normally placed on the Foundation Sheet):
1) Hole nomenclature
2) Date drilled
3) Elevations and descriptions of all soil and rock units
4) Elevation of water table (or lack thereof)
5) Results of standard penetration tests, when this information is available
6) Percent recovery, when this information is available
c. Piling, shaft or footing locations are normally shown on the Foundation Sheet, tied to contours and stationing. Centerlines of substructures are normally shown here, with stationing, to assist in structure layout in the field.
d. North arrow.
J. DRAWINGS - SUPERSTRUCTURE
1. Show and dimension all bent bars. Bar lists are not normally necessary.
2. When applicable to the type superstructure, include:
a. Camber, and Dead Load Deflection Diagram
b. Final Deck Elevation Diagram
c. Deck Joint Details
3. Truss Sheet(s):
a. Include all information needed by the truss fabricator to build the basic truss on the truss sheet(s), except reference may be made to the written specifications.
Needed information includes:
1) Truss lifting loop locations, any other tubular member locations, bearing pads, reinforcing steel embedded both in the the curb or parapet, and concrete surface finish.
2) Truss elevation view showing the total structure at midspan, at connection points, and at centerline of bearing or at the end of the truss.
3) Identify anchor, suspended, and canteliver spans and overall lengths.
4) Truss panel dimensions and details.
b. Elastomeric bearing pad details are normally shown on the truss sheets.
c. Use the standard Prefabricated Truss Notes on the truss sheet, edited for the specific truss(es) and job. Include the following specific requirements:
1) Specify the following:
a) height of truss on centers.
b) compression and tension members.
c) mild reinforcing steel grades
d) initial and final stress losses used in the design.
e) field weld locations, type, and limitations
2) Refer to the specification for the allowable fabrication tolerances.
3) State where and how the trusses are to be supported during transport to the job and require lifting cables to make an angle greater than 45 degrees with the top of the truss.
5) State the anticipated truss camber at 8 weeks of age.
K. DRAWINGS - SUBSTRUCTURE
1. Show and dimension all bent bars. Bar lists are not normally necessary.
2. Give elevations to assist in construction, such as bottom of footings, top of caps (include any steps), tops of endwalls and wingwalls.
3. Call out required and permissible horizontal construction joints.
4. State if elevation views are looking ahead or back on station, etc. and specify the fill and stream sides of vertical elements when helpful to avoid confusion in construction.
5. Show bearing details, except normally elastomeric bearing pad details are placed on the truss sheets. Include details on any grout pad to be used under bearing pads on bridges with excessive grades; show a detailed view that identifies the anticipated clearance between the bottom of the truss and the top of the cap/bearing seat.
Final Checklist – Highway Bridge Supporting Information for Plans, Specifications, and Estimate
Forest:
Ranger District:
Designed By:
Checked By:
Project Name:
Date:
I. Project Supporting Documentation:
Yes A. Letter requesting Regional approval B. Plan sheets C. Specifications and special provisions D. Engineer’s cost estimate E. Project schedule F. Design analysis G. Project engineering report H. Endorsement for compliance to aquatic and terrestrial organism passage
II. Plan Sheets:
Yes N/A
A. Cover Drawing
1. Title of project, Region, Forest, District
2. Index to drawings
3. Vicinity map and project location
a. Arrows and distance to major cities, highway numbers and road names
4. Signature block - Forest Supervisor, Regional Engineer, P.E. Checker
B. Plan and Profile Drawings
1. Plan view – Existing and finish topography, new structure outline
a. Construction limits, right-of-way, limits of work area, staging area
b. Removal of existing structure, disposal area
c. Environmental considerations, silt fences, containment areas
d. Riprap, ditches, cut and fill slopes, and signing
e. Centerline and geometrics of roadway, horizontal curve criteria, and superelevation ..
f. Guard rail layout, beginning and ending of bridge and roadway
g. Bench marks, coordinates, elevation control, and north arrow
h. Utilities and utilities ownership
i. Final signing, pavement markings, seeding
2. Profile – New structure and centerline of roadway
a. Elevations and stationing for roadway, subgrade, foundation
b. Vertical curve criteria
3. Detour – Plan and profile
a. Typical cross section and limits
b. Signing
4. Borrow and disposal areas
a. Haul routes and distances
b. Gates and traffic control
SOL NO: AG-4419-S-10-0627
RECOVERY – Shoal Creek Pine Glen Bridge Project
C. Civil Detail Drawings
1. Typical roadway section and limits
a. Pavement structure agrees with design analysis, prime and tack coat
b. Dimensions for pavement, shoulder, ditch, cut and fill slopes
2. Riprap section, class of riprap, membrane, toe detail D. Substructure Drawings
1. Plan and elevation views, dimensions, identified materials
2. Control and construction joints with details
3. Reinforcement location, mark number, size of bar
4. blockouts, connection details, anchors
5. Drainage when applicable
6. Reinforcement table, mark number, size, bends, weight, quantity
7. Piling layout and test piling locations
8. Earth abutments, wingwalls, type of finish
E. Superstructure Sheet
1. Plan and elevation views
a. Dimensions, reference station, identified materials, type of finish
b. Cross sections and details with reference to drawing
2. Control and construction joints with details
3. Reinforcement location, mark number, size of bar
4. Lifting points, blockouts, diaphragms, connection details, anchors, drainage
5. Connections, terminal sections, and anchors for railing system
6. Reinforcement table, mark number, size, bends, weight, quantity
F. Railing System
1. Plan and elevation views, dimensions, layout, height requirements, and offsets
a. Identified materials, end treatments, anchors
b. Reference to crash tested criteria and use of other’s drawings
2. Control and construction joints…