- RECOVERY: Construct 25 miles of non-motorized trails in Chattooga and Walker counties, GA
- Solicitation number
- AG-4419-S-10-0604
About this file
Wage Determination Chattooga County GA
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SOW.docx | DOCX document | |
| Clauses.docx | DOCX document | |
| Permit Info.docx | DOCX document | |
| Project Map.pdf | ||
| Wage -Walker Co.pdf | ||
| SF 1442.pdf | ||
| Design Parameters.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
General Decision Number: GA100319 03/12/2010 GA319
Superseded General Decision Number: GA20080319
State: Georgia
Construction Type: Highway
Counties: Chattooga and Elbert Counties in Georgia.
HIGHWAY CONSTRUCTION PROJECTS
Modification Number Publication Date
0 03/12/2010
SUGA2009-015 05/22/2009
Rates Fringes
CARPENTER (Form Work Only).......$ 12.02 2.55
CEMENT MASON/CONCRETE FINISHER...$ 12.03 0.00
LABORER: Common or General......$ 9.25 1.57
LABORER: Flagger................$ 8.43 1.39
LABORER: Pipelayer..............$ 8.50 0.00
OPERATOR: Asphalt Paver.........$ 14.50 0.86
OPERATOR: Backhoe/Excavator.....$ 12.06 0.00
OPERATOR: Blade/Grader..........$ 13.90 1.40
OPERATOR: Bulldozer.............$ 13.48 1.67
OPERATOR: Crane.................$ 15.56 3.95
OPERATOR: Mechanic..............$ 15.78 1.13
OPERATOR: Sweeper...............$ 13.20 1.40
OPERATOR: Roller.................$ 11.86 1.34
TRUCK DRIVER.....................$ 12.36 1.40
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29 CFR 5.5(a)(1)(ii)).
3/30/2010http://www.wdol.gov/wdol/scafiles/davisbacon/GA319.dvb
In the listing above, the "SU" designation means that rates listed under the identifier do not reflect collectively bargained wage and fringe benefit rates. Other designations indicate unions whose rates have been determined to be prevailing.
WAGE DETERMINATION APPEALS PROCESS
1.) Has there been an initial decision in the matter? This can be:
* an existing published wage determination
* a survey underlying a wage determination
* a Wage and Hour Division letter setting forth a position on a wage determination matter
* a conformance (additional classification and rate) ruling
On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.) and
3.) should be followed.
With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of
Construction
Wage Determinations. Write to:
Branch of Construction Wage Determinations
Wage and Hour Division
U.S. Department of Labor
200 Constitution Avenue, N.W.
Washington, DC 20210
2.) If the answer to the question in 1.) is yes, then an interested party
(those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR
Part 7).
Write to:
Wage and Hour Administrator
U.S. Department of Labor
The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board
(formerly the
Wage Appeals Board). Write to:
Administrative Review Board
U.S. Department of Labor
4.) All decisions by the Administrative Review Board are final.
END OF GENERAL DECISION