- RECOVERY: TRAIL REALIGNMENT AND REPAIRS AND RESURFACE PARKING LOT, SHAWNEE NATIONAL FOREST
- Solicitation number
- AG-4419-S-10-0569
About this file
Specifications
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SF 1442.pdf | ||
| Experience_Capability Statement.doc | DOC document | |
| DBA_WD.pdf | ||
| LM CHIP_SEAL General Notes.pdf | ||
| LM SITE LOCATION.pdf | ||
| SF 1442 Cont_0569.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CIM-0900-14F-30-0908-02
DESCRIPTION/SPECIFICATIONS/WORK STATEMENT
SCOPE OF CONTRACT: Resurface Parking Lots and Access Drive at the, Lincoln Douglas Debate Site. Oil and Chip surface replacement on the Mississippi Bluffs Ranger District at the Jonesboro Ranger Station located in Jonesboro, Illinois. Contractor shall provide all expertise, labor, supervision, services, equipment, tools, supplies, permits, licenses, transportation, and incidentals necessary to perform road repair and surfacing.
ESTIMATED QUANTITIES:
Area of Parking and Access Drive: __2400_SY______
Total Area for this job is: __2400_SY______
The U.S. Department of Transportation Federal Highway Administration (FHWA) Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects FP-03 (U.S.
Customary Units) is the governing Specification document for this contract. FHWA Specification document can be ordered from Superintendent of Documents, U.S. Government Printing Office, Washington D.C. 20402, or downloaded from the following website at http://www.wfl.fha.dot.gov/design/specs/fp03.htm. In case of conflict with any part, or parts, of said Specifications, the said Special Project Specifications shall take precedence and shall govern. Specification changes shall be made as follows:
SPECIAL CONTRACT REQUIREMENTS
DIVISION 100-GENERAL REQUIREMENTS
Section 101-Terms, Format, and Definitions
101.04 Definitions. Delete the following definitions and substitute the following:
Contractor. The individual or legal entity contracting with the Government for performance of prescribed work. As used in specifications and drawings for specified roads (Timber Sale Contracts), “Contractor” is “purchaser.”
Station. (1) A measure of distance used for highways and railroads equal to 100 feet. (English) or (1) A measure of distance used for highways and railroads equal to 1 kilometer (metric). (2) A precise location along a survey line.
101.04 Definitions. Add the following:
Best Management Practice. A series of water quality protection practices and procedures approved or certified by the State water quality agency under the provisions of sections 319 and 402 of the Clean Water Act, as amended.
Change. “Change” means “change order” as used in the Federal Acquisition Regulations.
Forest Service. The United States of America, acting through the Forest Service, U.S.
Department of Agriculture.
Section 107-LEGAL RELATIONS AND RESPONSIBILITY OF THE PUBLIC
107.08 Sanitation, Health, and Safety.
Add the Following:
References: In addition to publications referenced in the Contract and FAR 52.236-13, the following Code of Federal Regulations (CFR) publications designate and define hazardous materials and conditions, and establish procedures for handling these materials and conditions.
29 CFR, Part 1910: Occupational Safety and Health Administration (OSHA) General Industry and Health Standards.
29 CFR, Part 1926: OSHA Construction Industry Standards.
40 CFR, Part 61: National Emission Standards for Hazardous Air Pollutants.
40 CFR, Part 261: Environmental Protection Agency (EPA) Characteristics of Hazardous Waste.
40 CFR, Part 761, EPA Polychlorinated Biphenyls (PCBs), Manufacturing, Processing, Distribution in Commerce and Use Prohibitions.
Acquisition of Publications: Referenced CFR publications may be purchased from the Superintendent of Documents, U.S. Government Printing Office, Washington, D.C. 20402.
Prior to commencing construction, representatives of the Contractor, including the Superintendent, shall meet with the Government to review the Contract's safety and health requirements. The Contractor's safety and health program shall be reviewed, and implementation of safety and health provisions pertinent to the Work shall be discussed.
Contractor Responsibility: The Contractor shall assume full responsibility and liability for compliance with all applicable codes, standards and regulations pertaining to the health and safety of personnel during execution of the Work. The Contractor shall have written safety and health programs in compliance with 29 CFR Parts 1910 and 1926.
Safety and Health Programs: The Contractor shall submit, for approval, copies of the project safety and health programs, as applicable to the work scope, or required as a result of the safety meeting, including but not necessarily limited to the following:
Occupational Noise Exposure.
Fall Protection.
Personnel Protective Equipment.
Control of Hazardous Energy.
Electrical Safety Related Work Practices.
Lead.
Respirator Protection.
Confined spaces.
Special facilities, devices, equipment and similar items used by the Contractor in execution of the Work shall comply with 29 CFR Part 1910, Subpart I and other applicable regulations.
In accordance with FAR 52.236-13, when the Contractor is notified by the Government, of non-compliance with safety or health provisions of the Contract, the Contractor shall immediately, correct the unsafe or unhealthy condition. In accordance with FAR 52.236-14 if the Contractor fails to comply promptly, all or part of the Work will be stopped by Government notice. The Contractor shall not be allowed any extension of time or compensation for damages in connection with a work stoppage for unsafe or unhealthy conditions.
The Contract shall take all necessary precautions to prevent injury to the public, occupants, or damage to property of others.
Dispose of solid, liquid and gaseous contaminants in accordance with local codes, laws, ordinances and regulations.
Comply with applicable federal, state and local noise control laws, ordinances and regulations, including but not limited to 29 CFR 1910.95 and 29 CFR 1926.52.
107.11-Protection of Forests, Parks, and Public Lands
Add the following paragraph:
Contractor shall inform and educate the supervisor(s) on the job and each individual worker that any snake encountered must not be killed or harmed. The timber rattlesnake is legally protected under the Illinois Endangered Species Protection Act, and a violation is a Class A misdemeanor.
(Class A misdemeanors carry a fine of up to $1,000 and up to 364 days in jail.) Contractor is to notify the CO of any timber rattlesnake sighting.
DIVISION 150-PROJECT REQUIREMENTS
Section 156-PUBLIC TRAFFIC
156.03-Accommodating Traffic During Work
Replace Section with the follow:
Areas receiving chipseal shall be closed to traffic during the period that work is being performed and 24 hours following. Maintain the surface and limit traffic in accordance with contract specifications. Work shall be performed between 8:00 a.m. on Monday to 12:00 noon on Friday and left in a condition acceptable to recreation traffic the remainder of the week. No work shall be performed on weekends and Holidays (including the day before and the day after). Damage to areas not completed by the Contractor shall be repaired to its original condition at the Contractor’s expense.
The Contracting Officer’s Representative (COR) shall be notified in writing a minimum of ten days prior to starting the chipseal work.
DIVISION 300-AGGREGATE COURSES
Section 301-Untreated Aggregate Courses
Delete subsection 301.01 in its entirety and replace with the following:
301.01 Furnish, haul, and place a 2” IL. CA-10 aggregate base or surface course on the reconditioned base areas of the travel way.
Delete subsection 301.03 in its entirety and replace with the following:
301.03 General. Prepare the surface on which the aggregate course is placed according to Section 303 as applicable.
Delete subsection 301.05 in its entirety and replace with the following:
301.05 Compacting. Compact the aggregate using the following method as specified in the
SCHEDULE OF ITEMS:
Compaction B. Moisten or dry the aggregate to uniform moisture content suitable for compaction. Use equipment capable of obtaining compaction requirements. The compacting units may be of any type, provided that they are capable of compacting each lift of material as specified and that meet the minimum requirements as follows:
a) Steel-wheel rollers, other than the vibratory type, shall be capable of exerting a force of not less than 2970 lbs./ft. of width of the compression roll or rolls.
b) Vibratory steel-wheel rollers shall have a minimum weight of 5 tons. The compactor shall be equipped with amplitude and frequency controls, and specifically designed to compact the material on which it is used.
c) Pneumatic-tire rollers shall have smooth tread tires of equal size that will provide a uniform compacting pressure for the full width of the roller and capable of exerting a ground pressure of al least 11,500 lbs./sq.ft.
Section 303-Road Reconditioning
303.01-Work
Replace the paragraph with the following:
Recondition existing travel way. Scarify, shape and compact the existing travel way. Repair washouts, pot holes and otherwise damaged travel way whether gravel or paved.
Add the following:
Recondition and / or restore the road surface of parking area to adequately drain.
303.08-Pulverizing
Replace Section with the following:
Blade and shape the existing travel way to remove surface irregularities. Maintain the existing cross slope or crown. Establish a blading pattern that will retain the surfacing on the roadbed and provide a thorough mixing of the materials within the completed travel way width. Scarify and shape the travel way’s existing bituminous (chip seal) surface and pulverize until all lumps are reduced to a maximum size of 3 inches. The pulverized material shall be shaped and incorporated into the travel way.
Berms of materials at the edge of the travel way shall be removed and IL CA-10 placed adjacent to edge of roadway as shown on the typical section after completion of chipseal.
The scarified area shall be shaped to match the existing travel way template and provide for a 2 inch depth of CA-10 aggregate surfacing over the entire area. The joint where the scarified area meets the existing bituminous surface shall be cut to its full depth so as to tie in the new work with the existing bituminous surface.
DIVISION 400-ASPHALT PAVEMENT AND SURFACE TREATMENT
Section 409-Asphalt Surface Treatment
409.15 Payment
Pay Item Description Pay Unit 409(01) Removal of existing Oil and Chip, Surface blading and installation of double Oil and Chip surface LS
DIVISION 600- INCIDENTIAL CONSTRUCTION
Section 615—Sidewalks, Drives Pads, and Paved Medians
Delete entire section and replace with the following:
615.01 Description of Work
The work shall consist of removal and disposal of approximately 5,280 Lf. of existing asphalt pavement and sub base material. Construction of an ADA accessible trail having a clear tread width of not less than 60 inches, utilizing a crushed aggregate pavement which includes: trail realignment, clearing and grubbing; excavation and embankment; removing slough and berms;
filling ruts and holes; reshaping back slopes; slope rounding; constructing lead out ditches;
providing a finished trail subgrade tread, an aggregate base course, ADA compliant surface course and trail edging.
615.02 General Construction
Vegetative Removal - Systemic herbicide shall be applied, as per manufacturer's instructions, to all weeds and grasses within trail alignment to ensure that they be removed/killed completely before any construction on top of existing trail.
Subgrade Preparation - Prior to placing any pavement, shape, fill, grade, and compact the subgrade, to ninety-five percent (95%) Standard Proctor Density. The base shall be four inches (4") of compacted CA-6 crushed stone base on a dry natural or compacted subgrade. Where excavation to the finished grade elevation results in sub grade of unsuitable soil, the unsuitable material shall be removed and replaced with approved materials. Approved material for backfilling shall be aggregate base course, or other material approved by the Contracting Officer
(CO).
Placing Crushed Aggregate - Place the crushed aggregate on prepared subgrade, and rake smooth using a steel fine rake to desired grade and cross section. Place, to avoid segregation, in one layer of four inches (4”) maximum thickness. Do not apply deeper than four inches (4”) in one lift.
Backfilling - Backfill excavation to trail edge with scraper spoils, using backfill to hold edge of crusher fines in place.
Compaction - Immediately compact aggregate into smooth, firm surface with self-propelled, vibratory roller of sufficient weight. Maintain proper moisture content per proctor submitted by the Contractor. Rolling shall continue until all material is firmly locked and keyed together. The appearance and surface shall be uniform smooth with all ridges, waves, ruts, holes, and dips removed. Surface shall not vary more than one-half inch (½”) when measured with a ten foot (10’) straight edge applied parallel to the centerline. Correct any variation by loosening, reshaping, and re-rolling. When finished, compacted trail shall be a minimum of four inches (4”) deep in all locations.
In any areas where there are underground pipes, use extreme caution when compacting trail to protect pipe. Discuss alternative compaction methods with the Contracting Officers Representative (COR) prior to execution for approval if pipe hazard is anticipated.
Finishing - At completion of surfacing, remove excess spoils from along trail edge and deposit on site as directed by Contracting Officers Representative (COR).
Rake along all trail edges to ensure finished appearance and positive drainage away from trail.
Inspection - Finished surface shall be smooth, uniform, and solid. Dried, compacted pavement material shall be firm all the way through with no spongy areas. Loose material shall not be present on the surface.
Unconsolidated areas shall be dug out, and replaced with new crushed screenings with a high proportion of fines meeting the grading requirements. Patched areas then shall be wetted thoroughly and rolled smooth. Patching shall be completed prior to any pavement smoothing required.
Significant irregularities shall be smoothed out prior to final acceptance of work. Smoothing shall be accomplished by rewetting/saturating rough areas thoroughly, and rolling the trail with a heavy roller (1,000 - 1,500 pounds powered walk-behind or small rider). Wackers are not acceptable.
Final thickness of completed pavement shall not vary more than ½ inch from dimension indicated. Measurements shall be taken by means of test holes taken at random locations in the finished trail surface. Correct any variations in the thickness beyond the allowable ½ inch by repeating the installation.
615.03 Submittals
Submit four (4) copies of each of the following:
Crushed Aggregate Pavement
a. Submit sieve analysis of material to ensure it meets grading requirements.
b. Submit sample of crushed aggregate screenings for approval, one-half (½) cubic foot.
c. Sieve analysis of crushed aggregate screenings shall be approved in writing by the Contracting Officer (CO) prior to delivery of any material to the project site.
Prepare a sample finished pavement section of each pavement type. Sample section shall be full width of pavement, with length equal to three (3) times the width. The Contracting Officer (CO) prior to final placement of the entire paving shall approve sample pavement section in writing.
Delivery, Storage, and Handling
Protect all materials from damage during delivery and storage.
Product Conditions
Use lightweight hauling equipment. Exercise care in using equipment, avoiding damage to existing structures.
Review installation procedures and coordinate aggregate paving work with other work affects.
All hard surface paving, including concrete walks and asphalt paving must be completed prior to installation of aggregate paving.
Cold Weather:
1. Do not use frozen materials or materials mixed or coated with ice or frost.
2. Do not build on frozen work or wet, saturated or muddy subgrade.
Protect partially or fully completed paving against damage from any traffic when work is in progress, curing, maturing, and settling until substantial competition. Any barricade constructed must still be accessible by emergency and fire equipment during and after installation.
Protect adjacent work and surfaces from damage during porous unit paving installation.
615.04 Materials
Crusher Fines Screenings - Clean, hard, durable particles or fragments of ¼ inch minus select brown/gray crushed granite or local available compatible material. Fines shall be evenly mixed throughout the aggregate. When produced from gravel, fifty percent (50%) by weight, of the material retained on a Number four (4) sieve shall have one fractured face.
The portion retained on the Number four (4) sieve shall have a maximum percentage of wear of fifty (50) at five hundred (500) revolutions as determined by AASHTO T96-77
The portion passing a Number forty (40) sieve shall have a maximum liquid limit of twenty-five
(25) and a maximum plasticity index of seven (7), as determined by AASHTO T89-81, respectively.
The crushed aggregate screenings shall be free from clay lumps, organic matter, and deleterious material.
Grading requirements are as follows:
Percentage of Weight Passing a Square Mesh Sieve AASHTO T11-82 and T27-82
Sieve Designation
Percent Passing
Sieve Designation
Passing
3/8 inch 100 No. 30 40 - 50 No. 4 95 - 100 No. 50 25 - 35 No. 8 75 - 80 No. 100 20 - 25 No. 16 55 - 65 No. 200 5 - 15
615.05 Payment
Pay Item Description Pay Unit 615(01) Removal and disposal of approximately 5,280 Lf. LS of existing asphalt pavement and sub base material.
Construction of an ADA accessible trail having a clear tread width of not less than 60 inches, utilizing a crushed aggregate pavement.
DIVISION 700-MATERIALS
Section 702-Bituminous Material
702.03-Emulsified Asphalt
f. High Float Emulsion: high float emulsion shall meet the requirements listed in the following table:
HIGH FLOAT EMULSION
Medium Setting
TEST HFE-150
Viscosity, Saybolt Furol at 50°C,sec 50+(and pumpable)
Sieve Test (850µm)(No.20), retained on sieve, percent
0.10-
Settlement, percent∗ 5-
Storage Stability test, 1 day• 1-
Distillation test: Residue from distillation test to
260°C, percent Oil distillate, by volume percent
65+ 7-
Characteristics of residue from distillation Test to
260°C, Penetration at 25°C, 100g, 5sec
150-300
Coating test (all grades) 3 minutes, stone coated thoroughly
Float test at 60°C, sec 1200+
∗∗∗∗The test requirement for settlement may be waived when the emulsified asphalt is used in less than five days time; or the purchaser may require that the settlement test be run from the time the sample is received until it is used, if the elapsed time is less than five days.
••••The 24 hour (one-day) storage stability test may be used instead of the five day settlement test.
HFE-150, in general, is used for the following:
� Bituminous surface treatment � Coarse graded aggregate mixes � Machine mix surfaces, open graded aggregate mixes
702.04-Application Temperatures
Add the following to Table 702.1
Temperature Range (minimum-maximum)
Type and Grade of Asphalt Spraying Temperatures Mixing Temperatures High Float Emulsion
HFE-150 60-70 -
Section 703-Aggregate
703.05-Subbase, Base, and Surface Course Aggregate
CA10 and CA16 aggregate shall meet the requirements of the State of Illinois “Standard Specifications for Road and Bridge Construction Adopted January 1, 2002”, as shown on the Drawings and in the Schedule of Items.
703.10-Asphalt Surface Treatment Aggregate
CA10 and CA16 aggregate shall meet the requirements of the State of Illinois “Standard Specifications for Road and Bridge Construction Adopted January 1, 2002”, as shown on the Drawings and in the Schedule of Items.