Text version
CIM-0900-7F-168-0910-03 Michigan Toilet Buildings Hiawatha National Forest West Unit
Request for Proposal
Construction
(Repair and Alteration)
MICHIGAN TOILET FACILITY & STORAGE
BUILDING REPLACEMENT PROJECT
HIAWATHA NATIONAL FOREST-
ESCANABA, MICHIGAN
Solicitation No.: AG-4419-S-10-0439
Project No.: CIM-0900-7F-168-0910-02
CIM-0900-7F-168-0910-03
NAICS CODE: 238910
Proposal Due Date: April 15, 2010
Time: 2:00 PM (EST)
TABLE OF CONTENTS
1. INSTRUCTIONS
1.1. General Description of Work
1.3. Schedule of Proposal Activities
1.5. Questions
1.6. Proposal Sealing
1.7. Basis for Proposal Evaluation
1.8. Letter of Acknowledgment – Attachment A
1.9 Pre-Proposal Meetings
1.10 Contact Information
SF1442 – Solicitation (page 1 of 4) SF1442 – Solicitation (page 2 of 4) SF1442 – Solicitation (page 3 of 4) SF1442 – Solicitation (page 4 of 4)
PART I—THE SCHEDULE
SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
SECTION D--PACKAGING AND MARKING
SECTION E--INSPECTION AND ACCEPTANCE
SECTION F--DELIVERIES OR PERFORMANCE
SECTION G--CONTRACT ADMINISTRATION DATA
PART II--CONTRACT CLAUSES
PART III--LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS
SECTION J--LIST OF ATTACHMENTS
Attachment A - Statement of Knowledgement
Attachment B- Wage DeterminationPART IV--REPRESENTATIONS AND
INSTRUCTIONS
PART IV--REPRESENTATIONS AND INSTRUCTIONS
FAR 52.223-1 Biobased Product Certification (DEC 2007)
SECTION L--INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS OR
RESPONDENTS
52.204-11 American Recovery and Reinvestment Act—Reporting
Requirements (MAR 2009)
52.215-2 Audit and Records—Negotiation (Mar 2009) – ALT I (Mar 2009)
52.225-21 Required Use of American Iron, Steel, and Other Manufactured Goods—
Buy American Act—Construction Materials
52.225-22 Notice of Required Use of American Iron, Steel, and Other Manufactured
Goods—Buy American Act—Construction Materials
52.225-23 Required Use of American Iron, Steel, and Other Manufactured Goods—
Buy American Act—Construction Materials Under Trade Agreements
52.225-24 Notice of Required Use of American Iron, Steel, and Other Manufactured
Goods—Buy American Act—Construction Materials Under Trade Agreements
SECTION M--EVALUATION FACTORS FOR AWARD
Attachment A Attachment B
1. INSTRUCTIONS
This Request for Proposal (RFP) is issued by USDA Forest Service – EROC East, 1720 Peachtree St., NW, Suite 700, Atlanta, GA 30309, hereinafter referred to as FS, to obtain the services of one General "Prime" Contractor (GC), and also referred to as Offeror or Contractor, who shall be singularly responsible to satisfy the terms of the resulting contract. The contract is for Michigan Toilet Replacement at the Hiawatha National Forest in accordance with the scope of work, design drawings, specifications and contract requirements included herein.
The contract will be a Firm-Fixed-Priced. The contractor for this contract will be competitively chosen using Source Selection procedures as described within this RFP. FS will evaluate all responses using the criteria stated herein. This is a Best Value Selection, therefore, FS may award, should it determine it to be in its best interest, to other than the lowest priced offeror, and other than the highest technically rated offeror.
This RFP is set aside for Small Business Entities ONLY.
This section contains the specific information and instructions needed to prepare a proposal submission for this anticipated award.
1.1. General Description of Work
The GC will provide all labor, materials, equipment, and supervision for the Toilet Facilities and restoration of the areas at the Hiawatha National Forest in accordance with the specifications and drawing contained herein.
1.2. What Must Be Included with Proposal Submission
In order to properly evaluate proposal received it should include, at minimum, the following:
Cover
Should reference this Request for Proposal number and include:
Dunn & Bradstreet Number ______________________________ Tax ID Number ________________________________________ Email Address _________________________________________ Note: This information must match the information in the Central Contractor Registration (CCR) website.
Price Proposal
• Price proposal shall be submitted under separate cover and include at minimum:
• Full breakout of labor and materials anticipated.
• Completed Schedule of Items attached in Section I.
• Completed SF1442.
Price proposals shall include all fees and charges.
Other than price
1. Past Performance:
Provide two references of most recent projects completed that are similar to this project in scope and size. Please provide the name of the firm, address, telephone number and point of contact.
2. Technical Capability:
Provide an on-site personnel flowchart and list of specific proposed equipment to be used (make, model, HP, etc.)
3. Quality Control/Safety:
Provide a description planned compliance with the various codes, quality control plan and safety plan
Financial- Proposal shall provide verification of financial status of the company
1.3. Schedule of Proposal Activities
Submission:
Proposals for the RFP shall be received at the following location:
Attention:
Cassandra Carey, Contracting Officer 1720 Peachtree St., NW Suite 700 Atlanta, GA 30309
RFP submissions must be delivered complete by 2:00 PM, EST on April 15, 2010 to the above address.
Proposal received after the 2:00 PM EST on April 15, 2010 will not be considered and will be returned unopened.
Quantity: The Offeror shall submit two (2) copies of all proposals
1.4. Location of Work
Work is to be performed in Alger, Chippewa , Delta, Mackinaw and Schoolcraft Counties of the Hiawatha National Forest, Michigan.
1.5. Questions
Questions: All questions concerning proposal submissions shall be directed to the Contracting Officer, Cassandra Carey at cncarey@fs.fed.us, the Contract Specialist JoAnn Doughty at jdoughty@fs.fed.us and the Contracting Officers Representative (COR) kguillard@fs.fed.us, ggardner@fs.fed.us via email only.
Questions RFP # AG-4419-S-10-0439
THE LAST DAY TO SUBMIT QUESTIONS IS: April 8, 2010 at 4:00pm EST
1.6. Proposal Sealing
The contents of each proposal submission are to be placed in sealed envelopes or other sealed enclosure and identified with Offeror’s Name, Project Name, submission material title/heading, Dunns Number , RFP number, and the time/date delivery requirement.
1.7. Basis for Proposal Evaluation
The Government will award a contract resulting from this solicitation to the responsible offeror whose offer conforming to the solicitation will be most advantageous to the Government in accordance with best value criteria provided in Section M of this document.
1.8. Letter of Acknowledgment – Attachment A
Please complete the attached letter of acknowledgment and forward to the Contracting Officer at cncarey@fs.fed.us by March 29, 2010 to verify your intention to place a proposal.
1.9 Pre-Proposal Meetings
None
1.10 Contact Information
All proposal submissions shall include a valid email contact address.
SF1442 – Solicitation (page 1 of 4)
SF1442 – Solicitation (page 2 of 4)
SF1442 – Solicitation (page 3 of 4)
SF1442 – Solicitation (page 4 of 4)
PART I—THE SCHEDULE
SECTION B-- Michigan Toilet Buildings Hiawatha National Forest West Unit
SCHEDULE OF ITEMS
Item Description Quantity
Unit of
Measure Bid Price Total
1 Vault Pumping (single) 10 Each
2 Vault Pumping (double) 7 Each
3 Toilet Demolition (single) 10 Each
4 Toilet Demolition (double) 7 Each
Site Work, topsoil, seed and mulch 17 LS
6 Concrete 3500 SF
7 Mobilization 1 Each
8 Aggregate Pathway 50 LF
Total
SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
STATEMENT OF WORK
1. PROJECT TITLE: Munising and Rapid River/Manistique Building Demolition
2. GENERAL PROJECT DESCRIPTION: Demolition and site work of 10 single and 7 double existing toilet buildings.
3. PROJECT SITES: The buildings are located on the West Unit of the Hiawatha National Forest at 8 recreation sites: Lake Superior Boat Launch (1 double) , AuTrain Lake Campground ( 6 singles), Pete’s Lake Campground ( 2 singles, 2 doubles), Widewaters Campground ( 1 double), Bay Furnace Campground (2 doubles) , Flowing Well Campground (1 double), Pine Marten Run Trailhead (1 single), and Bay de Noc Grand Island Middle Trailhead (1 single).
4. SCOPE OF WORK: The Contractor shall provide all plant, labor, equipment, materials, supplies and supervision required to clear, demolish and dispose of toilet buildings including site restoration at recreation sites located in the Hiawatha National Forest.
This project includes, but is not limited to, the following work:
A. Demolition and disposal of entire buildings including vaults.
B. Removal of stumps.
C. Restoration of areas disturbed as a result of the demolition.
5. PERIOD OF PERFORMANCE: Work on this project needs to be closely coordinated with the placement of new toilets tentatively scheduled to be installed in May and beginning of June, 2010.
WEST UNIT
TOILET BUILDING DEMOLITION AND SITE PREPARATION
HIAWATHA NATIONAL FOREST
INDEX TO SPECIFICATIONS
DIVISION 1 - GENERAL REQUIREMENTS
01025 GENERAL REQUIREMENTS
DIVISION 2 - SITEWORK
02050 DEMOLITION
02930 TOPSOIL AND SEEDING
DIVISION 2 CONCRETE
SECTION 03300 - CAST-IN-PLACE CONCRETE
DIVISION 4- DIVISION 16
Not Used
01025-1
SECTION 01025
GENERAL REQUIREMENTS
PART 1 GENERAL
1.1 Site Visit: It is highly recommended that the contractor visit the work site to verify all dimensions and thoroughly familiarize themselves with existing conditions prior to submission of bid.
1.2 Applicable Codes: All work in this contract shall be done in accordance with National Fire Protection Association (NFPA), OSHA-Occupational Safety and Health Act (July 1989 and subsequent updates), ANSI B 20.1 1992, 40 CFR EPA (1996) Environmental Protection Agency, and all local safety and fire regulations.
1.3 Contracting Authority: All references made to the Contracting Officer shall include and be applicable to the Contracting Officer's Representative (COR)/ Government Inspector. Authorization to make changes to the Contract remains with the Contracting Officer. Unless otherwise specified, all requests from the contractor and all approvals by the Contracting Officer shall be in writing.
1.4 Permits: The Contractor is responsible for securing any necessary permits to accomplish the work.
1.5 Verification of Dimensions: The Contractor shall be responsible for the coordination and proper relation of their work to the site conditions and will familiarize themselves with all details of the work and working conditions. The Contractor shall verify all dimensions in the field, and will advise the Contracting Officer in writing of any discrepancy before performing any work.
1.6 Coordination of Work: It shall be the Contractor's responsibility to conduct all phases of their work in connection with this contract in such a manner as to assure a minimum of interference with Government activities in the area.
Provisions shall be made by the Contractor and approved by the Contracting Officer to avoid interferences with the free passage into and out of adjoining and adjacent areas not involved in the contracted work. Contractor shall work in phases, limit areas of work, adjust times of work, or provide alternate access routes if necessary to allow for traffic flow in critical areas or heavy use times.
1.7 Traffic Control: The Contractor shall provide signs, barricades, personnel or other forms of traffic control as necessary to safely direct or restrict the flow of traffic around or through their area of work at all times and in accordance with the Manual on Uniform Traffic Control Devices.
1.8 Detours and Alternate Routes: Detour routes shall be made of existing roads with signs and barricades set up by the Contractor to direct traffic around
01025-2 the areas of work. Where detours cannot be made using existing roads, the Contractor shall restrict work areas to one lane of the road while maintaining the other lane open to traffic. The Contractor shall provide flag persons to control two way traffic where roadways are limited to one lane.
1.9 Existing Structures and Equipment: All existing structures and equipment not to be demolished shall be protected from damage. Structures or equipment damaged by the Contractor shall be repaired or replaced to match the preexisting condition.
1.10 Utilities not Shown: If the Contractor encounters, within the construction limits of the entire project, utilities not shown on the plans and not visible as to the date of this contract and such utilities will interfere with construction operations, the Contractor shall immediately notify the Contracting Officer’s Representative as to the necessity for removal or relocation. Verbal notification shall be confirmed in writing.
1.11 Fire Prevention: Cutting or welding will be permitted only in areas that are or have been made fire safe. Where possible, all combustibles shall be located at least 35 feet horizontally from the work site. Where such location is impracticable, combustibles shall be protected with flameproof covers or otherwise shielded with metal guards or curtains. Edges of covers shall be tight to prevent sparks from going under them. This precaution is also important at overlaps where several covers are used to protect a large pile. Other fire prevention precautions shall be in accordance with the latest National Fire Codes.
The contractor shall have a type "A" (water) fire extinguisher and an additional worker to watch for hot slag contacting combustible materials during all cutting or welding operations.
1.12 Site Cleanliness: The contractor shall maintain a clean and hazard free work site. Cleanup shall be daily or more often as necessary to maintain a clean and hazard free work site.
1.13 Safety: The Contractor shall comply with all State and Federal OSHA regulations and the United States Department of Agriculture “Health and Safety Code Handbook” FSH 6709.11. The Contractor and all personnel under the Contractor’s direction shall wear hardhats in compliance with the “Health and Safety Code Handbook” pg. 20-13, work boots, shirts, and long pants.
PART 2 PRODUCTS
(Not Applicable)
PART 3 EXECUTION
(Not Applicable)
01025-3
END OF SECTION
02050-1
SECTION 02050
DEMOLITION
PART 1 GENERAL
1.1 GENERAL REQUIREMENTS
The Contractor is responsible for the demolition and disposal of each building in its entirety. Rubbish and debris shall be removed from Government property daily, unless otherwise directed, to avoid accumulation at the demolition site.
Materials that cannot be removed daily shall be stored in areas specified by the Contracting Officer.
1.2 DUST CONTROL
The amount of dust resulting from demolition shall be controlled to prevent the spread of dust to occupied portions of the construction site and to avoid creation of safety hazards or nuisance in the surrounding area.
1.3 PROTECTION
1.3.1 Protection of Personnel
A. During the demolition work the Contractor shall continuously evaluate the condition of the structure and take necessary measures take to protect all personnel working in and around the demolition site.
1.3.2 Protection of Existing Property.
The Contractor shall coordinate work of this section with all other work and shall construct and maintain shoring, bracing, and supports as required. The Contractor shall ensure that structural elements are not, overloaded and shall be responsible for increasing structural supports or adding new supports as may be required as a result of any cutting, removal, or demolition work performed under this contract.
1.5.3 Protection of Trees
Trees within the project site which might be damaged during the work under this contract shall be protected from damage. If damaged, they shall be replaced in kind or as approved by the Contracting Officer.
1.5.4 Environmental Protection
The work shall comply with the applicable environmental requirements.
1.6 BURNING
02050-2
The use of burning at the project site for the disposal of refuse and debris will not be permitted.
1.7 THE USE OF EXPLOSIVES
Use of explosives will not be permitted.
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION
3.1 VAULTS
The Contractor shall be responsible for pumping all vaults by a licensed septic company prior to demolition.
Toilet buildings to be completely removed, as indicated in the attachments, are to have the entire vault removed (including the bottom of the vault).
When in-place disposal of the vault is allowed the contractor may bury the concrete after he has verified that the vault is pumped clean, applied lime to bottom of vault and the vault has been broken down with holes punched through the bottom so that water cannot sit in the remaining structure. The vault may not have any portion remaining within 12” of final grade.
3.2 CLEAN UP
Debris and rubbish shall be removed from the building site daily. Debris shall be removed and transported in a manner that prevents spillage on streets or adjacent areas. All loads shall be covered and any additional local regulations regarding hauling and disposal shall apply.
3.3 DISPOSITION OF MATERIALS
A. The Contractor is responsible for the disposal of all materials and debris associated with the demolition work. Disposal shall be made in accordance with all local and federal disposal regulations.
B. Material Salvaged by the Contractor: Material salvaged by the Contractor shall be stored as approved by the Contracting Officer and shall be removed from Government property before completion of the project. Material salvaged for the Contractor shall not be sold on the site.
C. Items Salvaged for the Government: None
02050-3
D. Recycling: All concrete shall be recycled to the extent practical.
E. Disposal: Demolished material shall be disposed of in an approved landfill located off Federal property. Contractor shall provide a weight ticket to the Government of all material sent to a landfill.
3.5 RESTORATION
All areas disturbed by demolition shall be leveled and graded. Disturbed areas are to be graded to match surrounding contours. All vaults are to be filled with clean sand fill and compacted to fill voids to within 4” of finish grade.
These areas shall be restored with topsoil and seed in accordance with specification section 02930 Topsoil and Seeding unless otherwise noted
3.6 TEMORARY TOILET FACILITIES
In the event there is lag time between demolition of old toilet buildings and vaults and installation of new toilet buildings and vaults, contractor is required to provide temporary toilet facilities where no toilet facilities are available.
02050-3
02930
TOPSOIL AND SEEDING
PART 1 GENERAL
1.1 WORK INCLUDED
A. Provide topsoil and seeding to replace surfaces that are excavated or damaged during construction.
1.2 SUBMITTALS
A. None
PART 2 PRODUCTS
2.1 TOPSOIL
A. General: Topsoil shall be either the existing topsoil from grass areas to be excavated during this project, or imported topsoil from a commercial source. Imported topsoil shall be used to make up the difference between the required topsoil quantity and the quantity of topsoil salvaged from this project. All topsoil shall be free of sod, gravel, clay, stumps, roots, debris, objects larger than ¼" inch in diameter, toxic materials, and any material which is harmful to the growth of grass. The pH range shall be 5.4 to 7.0.
B. Existing topsoil: The existing topsoil, if used for new grass areas, shall be stripped, stockpiled, and maintained separate from the underlying soil. For bidding purposes, the bidder shall assume that the pH of the existing topsoil meets this specification.
C. Imported topsoil: Imported topsoil shall be obtained from well-drained areas, shall contain no trash or foreign material and shall be of ¼" inch particle size or less.
2.2 FERTILIZER
A. Fertilizer shall be commercial grade, free flowing, and of uniform composition.
B. Fertilizer shall be proportioned by weight as follows: 12% nitrogen, 12% phosphorous, and 12% potassium.
2.3 GRASS SEED
A. Seed shall be perennial ryegrass.
2.4 MULCH
A. Mulch shall be straw or excelsior applied at a rate of 2 tons per acre. Hay is not permitted.
PART 3 EXECUTION
3.1 TOPSOIL PLACEMENT AND GRADING
A. Spread the topsoil to minimum depth of 4 inches. Topsoil shall be smoothly graded to eliminate any deviations greater than 2 inches in 4 feet and to eliminate tracks from vehicles, pedestrians and animals.
02050-4
B. Grade the topsoil to ensure drainage.
3.2 FERTILIZING
A. Apply fertilizer at the rate of 650 pounds per acre.
3.3 SEEDING
A. Broadcast seeding:
1. Apply grass seed with a broadcast spreader.
2. Apply one half of the seed in one directions, then apply the remainder at a right angle to the first application.
3. The total applied quantity of grass seed shall be 4 pounds per 1000 sq ft.
4. Rake the area to cover the grass seed.
B. Hydroseeding:
1. Hydroseeding may be used as an alternative to broadcast seeding and will include the 12-12-12 fertilizer.
3.4 MULCH
A. Apply straw to a depth of 1/8 inch. This is not necessary if hydroseeding.
02050-5
SECTION 03300 - CAST-IN-PLACE CONCRETE
PART 1 - GENERAL
1.1 SECTION REQUIREMENTS
A. Submittals: Product Data concrete mix designs and laboratory test reports.
B. Comply with ASTM C 94; ACI 301, "Specification for Structural Concrete"; ACI 117, "Specifications for Tolerances for Concrete Construction and Materials"; and CRSI's "Manual of Standard Practice" and as here in modified.
PART 2 - PRODUCTS
2.1 MATERIALS
A. Plain Steel Wire: ASTM A 82, as drawn.
B. Portland Cement: ASTM C 150, Type I or II.
C. Fly Ash: ASTM C 618, Type C or F.
D. Aggregates: ASTM C 33, uniformly graded.
E. Joint-Filler Strips: ASTM D 1751, cellulosic fiber, or ASTM D 1752, cork.
F. Repair Topping: Factory-packaged, portland or blended hydraulic cement-based, polymer-modified, self-leveling traffic-bearing topping with minimum 28-day compressive strength of 5700 psi (39 MPa).
2.2 MIXES
A. Proportion normal-weight concrete mixes to provide the following properties:
1. Compressive Strength shall not be less than 4000 psi (27.6 MPa) at 28 days for any sample.
2. Slump Limit: 4 inches (100 mm) at point of placement.
3. Air Content: 5.5 to 7.0 percent for concrete exposed to freezing and thawing, 2 to 4 percent elsewhere.
PART 3 - EXECUTION
3.1 CONCRETING
A. Construct formwork and maintain tolerances and surface irregularities within ACI 117 limits of Class A for concrete exposed to view and Class C for other concrete surfaces.
B. Accurately position, support, and secure reinforcement.
02050-6
C. Install construction, isolation, and contraction joints where indicated. Install full-depth joint-filler strips at isolation joints. Control joints shall be installed within 12 hours of placement.
D. Place concrete in a continuous operation and consolidate using mechanical vibrating equipment.
E. Protect concrete from physical damage, premature drying, and reduced strength due to hot or cold weather during mixing, placing, and curing.
F. Formed Surface Finish: Smooth-formed finish for concrete exposed to view, coated, or covered by waterproofing or other direct-applied material; rough-formed finish elsewhere.
G. Slab Finishes: Nonslip-broom finish to exterior concrete platforms, steps, and ramps.
H. Begin curing concrete slabs after finishing. Keep concrete continuously moist for at least seven days Contractor shall perform field tests and to submit test reports.
I. Protect concrete from damage. Repair surface defects in formed concrete and slabs.
END OF SECTION 03300
Vault Toilet Disposal and Site Work
Contractor shall provide all materials, equipment and labor to decommission/dispose of vault toilet building and vaults and perform site work as described.
This work is being done in preparation for the installation of new prefabricated toilet buildings by CXT Corporation.
Installation of new toilet buildings is anticipated between May 15 and June 15, 2010.
All buildings are located in campgrounds, picnic areas, or trailheads on the West side of the Hiawatha National Forest. (See Attached Map) Due to the short turn around after work can begin in the spring it is critical that the contractor demonstrates to the Forest Service that they can plan site work and toilet disposal in conjunction with the Forest Service and the installer. The FS will know exact dates of installs and where they will start by early spring of
Ideally the contractor will be able to coordinate with the installer to stay “a step ahead” to limit need for protective fencing and flooding at excavation. If any excavation that will not have a new toilet installed the same day needs to have the hole filled to grade with backfill material. Any material needed for this will be the responsibility of the contractor.
Structure Decommissioning
The contractor shall have all vaults pumped by a licensed septic pumper at the contractor’s expense. Upon completion of this pumping the contractor shall physically secure (e.g. screw the doors shut) the building so that no further use occurs after pumping. It will be the contractors responsibility to re-pump the vault if it is not empty on the day of disposal therefore it is important to schedule pumping to be done as near to the time of removal as possible.
All buildings will become property of the contractor and shall be removed from government property. Unless specifically stated differently in the description of work for each site the vault shall also become the property of the
02050-7 contractor and removed from government property. When in-place disposal of the vault is allowed the contractor may bury the concrete after they have verified that the vault is pumped clean, applied lime to bottom of vault and the vault has been broken down with holes punched through the bottom so that water cannot sit in the remaining structure. The vault may not have any portion remaining within 12” of final grade.
All sites shall be free of debris and shall be graded leveled in preparation for toilet building and vault placement by prefabricated building contractor. Contractor is responsible for back filling in demolished or removed vaults with sand or other approved fill material.
Crushed Aggregate for Pathways
Where specified, provide aggregate for pathways after toilet building installation. Pathways shall be compacted aggregate 4 foot wide and 6 inches deep. Specification for aggregate is as follows:
3/8" 100% No.4 78-83 No.8 52-61 No.16 38-42 No.30 23-31 No.50 17-24 No.100 12-17
No.200 7-11
Aggregate meeting the above specified aggregate is commercially available from Bichler Sand and Gravel, Escanaba, MI
Temporary Toilet Facilities
In the event there is more than 2 days lag time between demolition of old toilet buildings and vaults and installation of new toilet buildings and vaults, contractor is required to provide temporary toilet facilities where no toilet facilities are available.
02050-8
Munising Ranger District
Lake Superior Boat Launch (T47NR21WS25)
Site is located approximately 3.5 miles West of Au Train MI.
• Remove one double toilet building. Vault may be buried at site.
• Construct two 4 feet wide by 35 feet long aggregate pathways from new toilet building to road.
• Topsoil, seed and mulch disturbed area around new toilet building and old toilet site.
Note: this site will not have a new toilet installed. Work may be done after new toilet installation.
Au Train Lake Campground (T46NR20WS8)
Site is located approximately 4 miles South of Au Train MI.
Preparation work
• Near Campsite #10. Remove two single toilet buildings and concrete pads adjacent to site campsite #10. Vaults and pads may be buried at site. Obliterate two 30 foot aggregate pathways. Level site and topsoil, seed and mulch. (Note: this site will not have a new toilet installed. Work may be done after new toilet installation.)
• Campsite #16 (new toilet location). Cut 12, trees (8 inches or less) and grub stumps. Remove logs, brush and stumps from site. Place and level approximately 20 CY sand fill.
• Near Campsite #25. Remove two single toilet buildings and concrete pads. Vaults and pads may be buried at site. Cut seven trees (8 inches or less) and grub stumps. Remove logs and stumps from site. Scatter brush in user developed pathways as directed by COR. Level site. (Note: this site will not have a new toilet installed. Work may be done after new toilet installation.)
• Near Campsite #29. Remove two single toilet buildings and concrete pads adjacent to site campsite #29. Vaults and pads may be buried at site. Obliterate aggregate pathways. Level site and topsoil, seed and mulch. (Note: this site will not have a new toilet installed. Work may be done after new toilet installation.)
Finish Work
• Campsite #16. Construct 15 foot x 5 foot concrete landing at new toilet. Construct 125 foot by 4 foot concrete pathway from landing to road Topsoil, seed and mulch disturbed areas.
• Near Campsite #25. Construct 15 foot x 5 foot concrete landing at new toilet. Construct 100 foot by 4 foot concrete pathway from landing to road. Topsoil, seed and mulch disturbed areas.
Pete’s Lake Campground/Day Use Area (T44NR18WS07)
Site is located approximately10 miles South of Wetmore, MI.
• Near Campsite #4. Remove two single toilet buildings, concrete pads, and wood curbing adjacent to site campsite #4. Vaults and pads may be buried at site. Cut three trees and grub stumps. Brush small group of saplings. Remove trees, stumps and brush. Provide sand fill and level site.
• Near Campsite #26. Remove double toilet building, concrete pad, vault and 25 feet of asphalt pathway. Cut five trees and grub stumps. Remove trees, stumps and brush.
02050-9
• Day Use Area. Remove double toilet building (closest to parking lot) , concrete pad, vault. Cut four trees and grub stumps. Remove trees, stumps and brush.
Finish work
• Near Campsite #4. Construct 15 foot x 5 foot concrete landing at new toilet. Construct 100 foot by 4 foot concrete pathway from landing to road. Topsoil, seed and mulch disturbed areas.
• Near Campsite #26. Construct 15 foot x 5 foot concrete landing at new toilet. Construct75 foot by 4 foot concrete pathway from landing to road. Topsoil, seed and mulch disturbed areas.
• Day Use Area. Construct 15 foot x 5 foot concrete landing at new toilet. Construct 100 foot by 4 foot concrete pathway from landing to road. Topsoil, seed and mulch disturbed areas
Widewater Campground (T44NR19WS12)
Site is located approximately11 miles South of Wetmore, MI.
• Near Campground Entrance. Remove double toilet and concrete pad. Vaults and pad may be buried at site. Level site and topsoil, seed and mulch. (Note: this site will not have a new toilet installed.
Work may be done after new toilet installation.)
• Between Campsites #7 and #8. Level site for new toilet installation. Minor pruning of branches required to accommodate new building.
• Between Campsites #7 and #8. Construct 15 foot x 5 foot concrete landing at new toilet. Construct 75 foot by 4 foot concrete pathway from landing to road. Scarify campsite #8. Topsoil, seed and mulch disturbed areas.
Bay Furnace Campground/Day Use Area (T47NR19WS29)
Site is located in Christmas, MI.
• Near Campsite #37. Remove double toilet, concrete pad, vaults and 15 foot asphalt pathway. Cut five trees and grub stumps. Remove trees, stumps and brush. Minor clearing of saplings at back of site. Level site.
• Day Use Area. Remove double toilet, concrete pad, vaults and 50 foot asphalt pathway. Cut several small trees and grub stumps. Remove trees, stumps and brush.
• Near Campsite #37. Construct 15 foot x 5 foot concrete landing at new toilet. Construct 75 foot by 4 foot concrete pathway from landing to road. Topsoil, seed and mulch disturbed areas.
• Day Use Area. Construct 15 foot x 5 foot concrete landing at new toilet. Construct 75 foot by 4 foot concrete pathway from landing to road. Topsoil, seed and mulch disturbed areas.
02050-10
Rapid River/Manistique Ranger District
Flowing Well Campground (T41NR19WS20)
Site is located approximately3miles North of Nahma Junction, MI.
• Near Campsite #6. Remove double toilet, 40 foot asphalt pathway. Vault may be buried at site.
Topsoil, seed and mulch. (Note: this site will not have a new toilet installed. Work may be done after new toilet installation.)
• Campsite #6. Flush cut five trees. Stumps may remain in place. Level site in preparation for installation of new toilet building.
• Campsite #6. Construct 15 foot x 5 foot concrete landing at new toilet. Construct 15 foot by 4 foot aggregate pathway from toilet building to road. Topsoil, seed and mulch disturbed areas.
Pine Marten Run Trailhead (T44NR18WS35)
Site is located approximately 6 miles East of Forest Highway 13 on Delta County Road 440.
• Trailhead . Remove single toilet. Vaults may be buried at site. (Note: this site will not have a new toilet installed. Work may be done after new toilet installation.)
• Trailhead (new toilet location). No clearing required. Strip and stockpile topsoil at new toilet location.
• Trailhead (new toilet location). After new toilet installation spread stockpiled topsoil. Seed and
Bay de Noc-GI Trailhead (T43NR20WS5) Site is located approximately 20 miles North of Rapid River MI on Delta County Road 509, near intersection with Delta County Road 440. (Note: No work may occur Thursday through Tuesday of Memorial Day weekend.)
• Trailhead . Remove single toilet. Vaults may be buried at site. (Note: this site will not have a new toilet installed. Work may be done after new toilet installation.)
• Trailhead (new toilet location). No clearing required. Strip and stockpile topsoil at new toilet location.
• Trailhead (new toilet location). After new toilet installation spread stockpiled topsoil. Seed and
02050-11
02050-12
AGAR 452.211-72 Statement of Work/Specifications (FEB 1988)
The Contractor shall furnish the necessary personnel, material, equipment, services and facilities (except as otherwise specified), to perform the Statement of Work/Specifications.
AGAR 452.211-73 Attachments to Statement of Work/Specifications (FEB 1988)
The attachments to the Statement of Work/Specifications listed in Section J are hereby made part of this solicitation and any resultant contract.
02050-13
SECTION D--PACKAGING AND MARKING
{For this Solicitation, there are NO clauses in this Section}
02050-14
SECTION E--INSPECTION AND ACCEPTANCE
FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.arnet.gov/far/
FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES
52.246-12 Inspection of Construction (AUG 1996)
02050-15
SECTION F--DELIVERIES OR PERFORMANCE
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.arnet.gov/far/
52.242-14 Suspension of Work (APR 1984)
FAR 52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 45 calendar days. The time stated for completion shall include final cleanup of the premises.
AGAR 452.236-75 Maximum Workweek – Construction Schedule (NOV 1996)
Within 10 calendar days after receipt of a written request from the Contracting Officer, the Contractor must submit the following information in writing for approval:
(a) A schedule as required by FAR clause 52.236-15, Schedules for Construction Contracts, and
(b) The hours (including the daily starting and stopping times) and days of the week the Contractor proposed to carry out the work.
The maximum workweek that will be approved is 40 hours.
02050-16
SECTION G--CONTRACT ADMINISTRATION DATA
SECTION H--SPECIAL CONTRACT REQUIREMENTS
02050-17
PART II--CONTRACT CLAUSES
SECTION I--CONTRACT CLAUSES
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
www.arnet.gov/far/ www.usda.gov/procurement/policy/agar.html
52.202-1 Definitions (JUL 2004) 52.203-3 Gratuities (APR 1984) 52.203-5 Covenant Against Contingent Fees (APR 1984) 52.203-6 Restrictions on Subcontractor Sales to the Government (SEP 2006) 52.203-7 Anti-Kickback Procedures (JUL 1995) 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity (JAN 1997) 52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (JAN 1997) 52.203-12 Limitation on Payments to Influence Certain Federal Transactions (SEP 2007) 52.204-4 Printed or Copied Double-Sided on Recycled Paper (AUG 2000) 52.204-9 Protecting the Government's Interest when Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (MAY 2008) 52.211-18 Variation in Estimated Quantity (APR 1984) 52.215-2 Audit and Records -- Negotiation (JUN 1999) 52.219-6 Notice of Total Small Business Set-Aside (JUNE 2003) 52.219-8 Utilization of Small Business Concerns (MAY 2004) 52.219-14 Limitations on Subcontracting (DEC 1996) ) 52.222-3 Convict Labor (JUN 2003) 52.222-4 Contract Work Hours and Safety Standards Act -- Overtime Compensation (JUL 2005) 52.222-6 Davis-Bacon Act (JUL 2005) 52.222-7 Withholding of Funds (FEB 1988) 52.222-8 Payrolls and Basic Records (FEB 1988) 52.222-9 Apprentices and Trainees (JUL 2005) 52.222-10 Compliance with Copeland Act Requirements (FEB 1988) 52.222-11 Subcontracts (Labor Standards) (JUL 2005) 52.222-12 Contract Termination - Debarment (FEB 1988) 52.222-13 Compliance with Davis-Bacon and Related Act Regulations (FEB 1988) 52.222-14 Disputes Concerning Labor Standards (FEB 1988) 52.222-15 Certification of Eligibility (FEB 1988) 52.222-21 Prohibition of Segregated Facilities (FEB 1999) 52.222-26 Equal Opportunity (MAR 2007) 52.222-27 Affirmative Action Compliance Requirements for Construction (FEB 1999) 52.222-35 Equal Opportunity for Special Disabled Veterans, Veterans of the Vietnam Era, and other Eligible
Veterans (SEP 2006) 52.222-36 Affirmative Action for Workers with Disabilities (JUN 1998)
02050-18
52.222-37 Employment Reports on Special Disabled Veterans, Veterans of the Vietnam Era, and other Eligible Veterans (SEP 2006)
52.222-50 Combating Trafficking in Persons (SEP 2007) 52.223-5 Pollution Prevention and Right-to-Know Information (AUG 2003) 52.223-6 Drug-Free Workplace (MAY 2001) 52.223-14 Toxic Chemical Release Reporting (AUG 2003) 52.223-15 Energy Efficiency in Energy-Consuming Products (DEC 2007) 52.225-13 Restrictions on Certain Foreign Purchases (JUN 2008) 52.227-1 Authorization and Consent (DEC 2007) 52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement (DEC 2007) 52.227-4 Patent Indemnity -- Construction Contracts (DEC 2007) 52.228-2 Additional Bond Security (OCT 1997) 52.228-11 Pledges of Assets (FEB 1992) 52.228-12 Prospective Subcontractor Requests for Bonds (OCT 1995) 52.228-14 Irrevocable Letter of Credit (DEC 1999) 52.228-15 Performance and Payment Bonds – Construction (NOV 2006) 52.229-3 Federal, State, and Local Taxes (APR 2003) 52.232-5 Payments Under Fixed-Price Construction Contracts (SEP 2002) 52.232-17 Interest (OCT 2008) 52.232-23 Assignment of Claims (JAN 1986) 52.232-27 Prompt Payment for Construction Contracts (OCT 2008) 52.232-33 Payment by Electronic Funds Transfer – Central Contractor Registration (OCT 2003) 52.233-1 Disputes (JULY 2002) 52.233-3 Protest After Award (AUG 1996) 52.233-4 Applicable Law for Breach of Contract Claim (OCT 2004) 52.236-2 Differing Site Conditions (APR 1984) 52.236-3 Site Investigation and Conditions Affecting the Work (APR 1984) 52.236-5 Material and Workmanship (APR 1984) 52.236-6 Superintendence by The Contractor (APR 1984) 52.236-7 Permits and Responsibilities (NOV 1991) 52.236-8 Other Contracts (APR 1984) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements (APR 1984) 52.236-10 Operations and Storage Areas (APR 1984) 52.236-11 Use and Possession Prior to Completion (APR 1984) 52.236-12 Cleaning Up (APR 1984) 52.236-13 Accident Prevention (NOV 1991)
Alternate I (NOV 1991) 52.236-15 Schedules for Construction Contracts (APR 1984)
Alternate I (APR 1984) 52.236-17 Layout of Work (APR 1984) 52.236-21 Specifications and Drawings for Construction (FEB 1997)
Alternate II (APR 1984) 52.236-26 Preconstruction Conference (FEB 1995) 52.242-13 Bankruptcy (JUL 1995) 52.243-4 Changes (AUG 1987) 52.244-6 Subcontracts for Commercial Items (MAR 2009) 52.245-1 Property Records (JUN 2007) 52.246-21 Warranty of Construction (MAR 1994) 52.248-3 Value Engineering – Construction (SEP 2006) 52.249-2 Termination for Convenience of the Government (Fixed-Price) (MAY 2004)--Alternate I (SEP
1996)
02050-19
52.249-10 Default (Fixed-Price Construction) (APR 1984) 52.253-1 Computer Generated Forms (JAN 1991)
AGRICULTURE ACQUISITION REGULATION (48 CFR CHAPTER 4) CLAUSES
452.232-70 Reimbursement for Bond Premiums – Fixed-Price Construction Contracts (NOV 1996) 452.236-71 Prohibition Against the Use of Lead-Paint (NOV 1996) 452.236-72 Use of Premises (NOV 1996) 452.236-73 Archeological or Historic Sites (FEB 1988) 452.236-74 Control of Erosion, Sedimentation and Pollution (NOV 1996) 452.236-76 Samples and Certificates (FEB 1988) 452.236-77 Emergency Response (NOV 1996)
52.204-7 Central Contractor Registration (APR 2008)
(a) Definitions. As used in this clause—
“Central Contractor Registration (CCR) database” means the primary Government repository for Contractor information required for the conduct of business with the Government.
“Data Universal Numbering System (DUNS) number” means the 9-digit number assigned by Dun and Bradstreet, Inc. (D&B) to identify unique business entities.
“Data Universal Numbering System+4 (DUNS+4) number” means the DUNS number means the number assigned by D&B plus a 4-character suffix that may be assigned by a business concern. (D&B has no affiliation with this 4-character suffix.) This 4-character suffix may be assigned at the discretion of the business concern to establish additional CCR records for identifying alternative Electronic Funds Transfer (EFT) accounts (see the FAR at Subpart 32.11) for the same concern.
“Registered in the CCR database” means that—
(1) The Contractor has entered all mandatory information, including the DUNS number or the DUNS+4 number, into the CCR database; and
(2) The Government has validated all mandatory data fields, to include validation of the Taxpayer Identification Number (TIN) with the Internal Revenue Service (IRS), and has marked the record “Active”. The Contractor will be required to provide consent for TIN validation to the Government as a part of the CCR registration process.
(b) (1) By submission of an offer, the offeror acknowledges the requirement that a prospective awardee shall be registered in the CCR database prior to award, during performance, and through final payment of any contract, basic agreement, basic ordering agreement, or blanket purchasing agreement resulting from this solicitation.
(2) The offeror shall enter, in the block with its name and address on the cover page of its offer, the annotation “DUNS” or “DUNS+4” followed by the DUNS or DUNS+4 number that identifies the offeror’s name and address exactly as stated in the offer. The DUNS number will be used by the Contracting Officer to verify that the offeror is registered in the CCR database.
(c) If the offeror does not have a DUNS number, it should contact Dun and Bradstreet directly to obtain one.
(1) An offeror may obtain a DUNS number—
02050-20
(i) Via the internet at http://fedgov.dnb.com/webform or if the offeror does not have internet access, it may call Dun and Bradstreet at 1-866-705-5711 if located within the United States;
or
(ii) If located outside the United States, by contacting the local Dun and Bradstreet office. The offeror should indicate that it is an offeror for a U.S. Government contract when contacting the local Dun and Bradstreet office.
(2) The offeror should be prepared to provide the following information:
(i) Company legal business name.
(ii) Tradestyle, doing business, or other name by which your entity is commonly recognized.
(iii) Company physical street address, city, state and Zip Code.
(iv) Company mailing address, city, state and Zip Code (if separate from physical).
(v) Company telephone number.
(vi) Date the company was started.
(vii) Number of employees at your location.
(viii) Chief executive officer/key manager.
(ix) Line of business (industry).
(x) Company Headquarters name and address (reporting relationship within your entity).
(d) If the Offeror does not become registered in the CCR database in the time prescribed by the Contracting Officer, the Contracting Officer will proceed to award to the next otherwise successful registered Offeror.
(e) Processing time, which normally takes 48 hours, should be taken into consideration when registering. Offerors who are not registered should consider applying for registration immediately upon receipt of this solicitation.
(f) The Contractor is responsible for the accuracy and completeness of the data within the CCR database, and for any liability resulting from the Government’s reliance on inaccurate or incomplete data. To remain registered in the CCR database after the initial registration, the Contractor is required to review and update on an annual basis from the date of initial registration or subsequent updates its information in the CCR database to ensure it is current, accurate and complete. Updating information in the CCR does not alter the terms and conditions of this contract and is not a substitute for a properly executed contractual document.
(g) (1) (i) If a Contractor has legally changed its business name, “doing business as” name, or division name (whichever is shown on the contract), or has transferred the assets used in performing the contract, but has not completed the necessary requirements regarding novation and change-of-name agreements in Subpart 42.12, the Contractor shall provide the responsible Contracting Officer a minimum of one business day’s written notification of its intention to:
(A) Change the name in the CCR database;
02050-21
(B) Comply with the requirements of Subpart 42.12 of the FAR;
(C) Agree in writing to the timeline and procedures specified by the responsible Contracting Officer. The Contractor must provide with the notification sufficient documentation to support the legally changed name.
(ii) If the Contractor fails to comply with the requirements of paragraph (g)(1)(i) of this clause, or fails to perform the agreement at paragraph (g)(1)(i)(C) of this clause, and, in the absence of a properly executed novation or change-of-name agreement, the CCR information that shows the Contractor to be other than the Contractor indicated in the contract will be considered to be incorrect information within the meaning of the “Suspension of Payment” paragraph of the electronic funds transfer (EFT) clause of this contract.
(2) The Contractor shall not change the name or address for EFT payments or manual payments, as appropriate, in the CCR record to reflect an assignee for the purpose of assignment of claims (see FAR Subpart 32.8, Assignment of Claims). Assignees shall be separately registered in the CCR database. Information provided to the Contractor’s CCR record that indicates payments, including those made by EFT, to an ultimate recipient other than that Contractor will be considered to be incorrect information within the meaning of the “Suspension of payment” paragraph of the EFT clause of this contract.
(h) Offerors and Contractors may obtain information on registration and annual confirmation requirements via the Internet at http://www.ccr.gov or by calling 1-888-227-2423, or 269-961-5757.
52.222-39 Notification Of Employee Rights Concerning Payment Of Union Dues Or Fees (Dec 2004)
(a) Definition. As used in this clause-
"United States" means the 50 States, the District of Columbia, Puerto Rico, the Northern Mariana Islands, American Samoa, Guam, the U.S. Virgin Islands, and Wake Island.
(b) Except as provided in paragraph (e) of this clause, during the term of this contract, the Contractor shall post a notice, in the form of a poster, informing employees of their rights concerning union membership and payment of union dues and fees, in conspicuous places in and about all its plants and offices, including all places where notices to employees are customarily posted. The notice shall include the following information (except that the information pertaining to National Labor Relations Board shall not be included in notices posted in the plants or offices of carriers subject to the Railway Labor Act, as amended (45 U.S.C. 151-188)).
Notice to Employees
Under Federal law, employees cannot be required to join a union or maintain membership in a union in order to retain their jobs. Under certain conditions, the law permits a union and an employer to enter into a union-security agreement requiring employees to pay uniform periodic dues and initiation fees. However, employees who are not union members can object to the use of their payments for certain purposes and can only be required to pay their share of union costs relating to collective bargaining, contract administration, and grievance adjustment.
If you do not want to pay that portion of dues or fees used to support activities not related to collective bargaining, contract administration, or grievance adjustment, you are entitled to an appropriate reduction in your payment. If you believe that you have been required to pay dues or fees used in part to support activities not related to collective bargaining, contract administration, or grievance adjustment, you may be entitled to a refund and to an appropriate…