Section B - Schedule of Items Rev 1.doc

DOC document 33 KB Posted

Attached to
RECOVERY* Shelter/Roof Replacement - Pisgah National Forest, North Carolina
Solicitation number
AG-4419-S-10-0438
Issued by

About this file

Section B - Schedule of Items Rev 1

View the file

Other files

File Type Posted
Attachment 1 - Specifications Rev 1.pdf PDF
Exhibit 1 - Drawings Rev 1.pdf PDF
SF30 Amendment 1.pdf PDF
Sign In Sheet.pdf PDF
Attachment 1 - Specifications.pdf PDF
Section B - Schedule of Items.pdf PDF
Exhibit 1 - Drawings.pdf PDF
Sec C thru M - Solicitation.doc DOC document
Section A - SF1442.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BID SCHEDULE

PINK BEDS PICNIC SHELTER

REVISED 4/27/2010

Pay Item Description Quantity Method of Unit Unit Price Amount

Measurement

1.

MOBILIZATION

1 LSQ LS $_________

2.

ENTRANCE SHELTER CONSTRUCTION

1. Existing Roof Demolition 1 DQ LS $_________ (Dispose of off NFsNC land)

2. Timber Framing Replacements 1 DQ LS (see drawings for components)

3. Red Cedar Shakes 5.0 DQ SQ $_________ $_________

(Includes Ice Shield &

Cedar Breather)

4. 2x6 rough sawn sheeting

5.0 DQ SQ $________ $________

(match existing)

5. Stain Entire Structure

LS

Sherwin Williams –

SW3007 Lodge Brown Or equal

(includes prep. work)

TOTAL BASE BID $__________________

LARGE (LOWER) PICNIC SHELTER - OPTION ITEMS

6. Roof Demolition

LSQ LS

(Dispose of off NFsNC land)

7. Red Cedar Shakes 11 DQ SQ $_________ $_________ (Includes Ice Shield &

Cedar Breather)

C.

8. Timber Framing Replacements 1 DQ LS

(see drawings for components)

9. 2x6 T&G PT (0.6) Sheeting 11 DQ SQ $________ $________

10. Remove and re-grout cracked 2 DQ LS Foundation columns.

11. Stain Entire Structure

Sherwin Williams –

SW3007 Lodge Brown Or equal

(includes prep. work)

TOTAL BID $______________

* Any other item of work shown on the drawings or required by the specifications shall be considered incidental to the bid items shown, and no additional payment will be made. Bidders must provide prices on all base bid items and alternates/optional items to be considered for award. One award will be made from this solicitation.