About this file

Specifications

View the file

Other files

File Type Posted
Map 8 - ColyerFarms.pdf PDF
Map 3- TowerRock.pdf PDF
Map 9 - DuryProperty.pdf PDF
Map 7 - Dial.pdf PDF
SF 1442 Cont _ 0359.docx DOCX document
Map 10- HSRD Vicinity.pdf PDF
Map 4 - GrapevineTrail.pdf PDF
Map 5- EderleProperty.pdf PDF
SF 1442 Cover Pg.pdf PDF
Experience Capability Statement 0359.doc DOC document
DBA.pdf PDF
Map 1 - Kaskaskia.pdf PDF
Map 6 - JohnsonCreek.pdf PDF
Map 2 - CampCadiz.pdf PDF
Map 11 - MBRD Vicinity.pdf PDF
Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOL NO: AG-4419-S-10-0359

UNIT: Shawnee National Forest PROJ NAME: Abandoned Several Wells

CIM-0900-4F-734-0908-01

SECTION 332100 - WATER SUPPLY WELLS

GENERAL

STATEMENT OF WORK: This project shall consist of filling and capping per State of Illinois code drilled wells identified in the Schedule of Items on the Shawnee National Forest. Contractor shall supply all manpower, equipment and supplies necessary for the work.

CODE REQUIREMENTS: All work on this project shall be in accordance with the current edition of the Illinois Water Well Construction Code, as well as any other State of Illinois regulation regarding capping and sealing of water wells.

DRILLING RECORDS: The Forest Service has no records regarding depth or subsurface conditions.

PERMITS, NOTIFICATIONS AND FORMS: Contractor is responsible for providing all permits necessary, providing any notification to state agencies and filling of all forms necessary to the state to certify the wells have been properly capped and sealed. Copies of all permits and forms shall be provided to the Government prior to submission of final payment.

PRODUCTS

REQUIREMENTS: All products used to cap and seal wells shall be as specified in the Current Illinois Water Well Construction Code.

EXECUTION

INSPECTION

Contractor shall visually inspect all work sites prior to starting work to assess access and site conditions that will affect the work. The Forest Service shall be responsible for marking well locations at each site. Global Positioning System (GPS) points for each well location shall be provided by the Forest Service.

SEALING AND CAPPING

Contractor shall notify the Contracting Officer’s Representative (COR) a minimum of 48 hours prior to beginning work.

SITE CLEANUP

Contractor shall be responsible for repairing all damage to the ground surface while accessing and capping wells. Surface shall be raked smooth and gravel or seed and mulch applied when necessary and as approved by the COR. Seed shall be a commercially available lawn mix.

REQUIRED SUBMITTALS

Contractor shall provide a photographic record on Compact Disc with a minimum of 3 pictures of each well capping; one prior to work beginning, one during capping and one after work is completed. A photo log shall be submitted to identify each photo.

Copies of all permits and forms obtained from and submitted to the state.

END OF SECTION 332100