RECOVERY ACT: Beaver Pond Dam Design/Build on the White Mountain National Forest. Grafton County, New Hampshire
Solicitation number
AG-4419-S-10-0073
Issued by

About this file

Specs

View the file

Other files

File Type Posted
Clauses.doc DOC document
Clauses.doc DOC document
CIM-0900-1F-107-0922-02_DamReconstruction-BeaverPond_ExhA-SiteMap.pdf PDF
Solicitation.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BEAVER POND DAM RECONSTRUCTION

CIM-0900-1F-107-0922-02

American Recovery & Reinvestment Act Project

USDA Forest Service - Eastern Region - White Mountain National Forest

Scope of Work for Design-Build Services

I. General A. Introduction

The White Mountain National Forest requests engineering and construction services for the reconstruction of the Beaver Pond dam as described below.

The Design-Builder shall provide all equipment, supplies, personnel, supervision, materials, quality control, and incidentals for the complete survey, geotechnical investigation, design, fabrication, and construction of the work described.

B. Description of Work

i. The project includes reconstruction of the earthen dam and replacing the spillway and outlet (drain) structure.

ii. The design shall restore the dam to approximate the pre-existing facility, including a new concrete spillway and a new outlet structure to regulate the water level of the pond.

C. Location

The project is located on the White Mountain National Forest, Pemigewasset Ranger District, Town of Woodstock, Grafton County, New Hampshire at Kinsman Notch on the west side of NH-112 approximately 4 miles northwest of the junction of NH-112 and NH-118. See Exhibit A.

D. Pre-Bid Tour

A pre-bid tour is planned as shown below.

i. Location: At Site.

ii. Date & Time: Tuesday, December 8, 2009 at 10:00AM.

E. Utilities

i. No known utilities are located within the work area, but the Design-Builder is urged to investigate any possible utility locations and shall preserve or replace any utilities damaged by the Contractor’s actions.

ii. There is no Government sanitation, water, electrical or housing services available. The Design-Builder shall make its own arrangements for temporary facilities. Temporary campsites may be approved, upon request of the contractor at least 14 days prior to planned use.

F. Government Project Leader

For additional information contact J. Sylvester at the White Mountain National Forest Engineering Office at the Saco Ranger Station 603.447.5448,ext. 135, or mobile 603.455.9939.

II. Technical Requirements A. Scope

The Design-Builder shall prepare a final design package for the complete construction project.

B. Safety Plan

The Design-Builder shall prepare and adhere to a construction safety plan. The safety plan shall indicate safe procedures, emergency response actions and communications strategy.

Conduct safety meetings at least once weekly during construction to inform personnel of relevant issues encountered at the site. Document meeting attendance and provide notes to the Forest Service.

C. Final design packages shall be prepared in U.S. Customary Units consisting of the following subsections. The final submittal shall include two complete hard copy sets and one complete electronic set on CD-Rom. Hard copy sets shall be individually bound.

i. Construction Plans

a) Final plans shall be provided on 11" x 17" (B size) sheets with the standard White Mountain National Forest title block (to be provided). One drawing set shall be on 4-mil double matte polyester film and one set on paper.

b) Plans shall indicate design standards or limitations stated by the Design Engineer, such as but not limited to, Structural Criteria, Timber Grades, Steel Grades, Concrete Strength, Compaction, etc.

c) Electronic plans shall be AutoCAD 2008 compatible, free of external references and fully functional.

ii. Specifications

a) Governing specifications shall be the USDA Forest Service Eastern Region Dam Specifications (to be provided).

b) Any Supplemental Specifications required and included shall reference the appropriate sections in the standard specifications.

c) Final specifications shall be formatted for 8.5”x 11” sheets and shall be Microsoft Word 2007 compatible and fully functional.

iii. Schedule of Items

a) The Schedule shall depict the units and quantities of work.

b) Item numbers shall be consistent with the Specifications.

c) Electronic Schedule of Items shall be Word 2007 compatible and fully functional.

iv. Cost Estimate

a) Cost shall depict a good-faith opinion of probable costs of the work for each pay item.

b) Pay Item numbers shall be consistent with the Schedule and the Specifications.

c) Electronic Cost Estimate shall be Excel 2007 compatible and be fully functional.

v. Permit application forms and supplemental reports and data.

a) Any and all Federal, State, and Local permits and fees required for the construction activities shall be the responsibility of the Design-Builder.

b) The Design-Builder shall obtain all necessary permits with enough lead time so not to cause delay of construction activities.

c) All reports, data, etc. effecting or related to the design or construction shall be submitted to the Forest Service D. Design packages shall be prepared by, or under the supervision of a professional engineer licensed by the state of New Hampshire. The professional engineer shall affix their stamp and signature upon all approved final design package submittals.

E. All design and construction shall be in accordance with applicable Federal, State, and local laws and regulations.

F. Subsurface exploration shall be the responsibility of the Design-Builder, and be commensurate with complexity of the project and proposed construction. Any resulting geotechnical report shall be submitted to the Forest Service.

G. A traffic control plan shall be prepared by the Design-Builder, with all temporary and permanent signing conforming to the Manual of Uniform Traffic Control Devices (MUTCD).

i. Closure of the entire work site will be allowed during construction.

ii. Closure of the existing parking area will be allowed during construction and the normal work week. Beginning at 3:00 PM on Fridays, a portion of the parking area (50%+/-) shall be made available for use to forest visitors for the weekend and any included legal holidays.

iii. Reflect in the traffic control plan closure locations and schedule.

H. The Design-Builder shall prepare an erosion control plan which will minimize movement of construction sediment from the project site, which will meet all State of New Hampshire, Department of Natural Resources and Army Corps of Engineers requirements. Construction shall be consistent with “Best Management Practices for Erosion and Sedimentation Control”

I. Construction shall not occur within the wetted perimeter of live streams during the months of October through April annually, without prior approval.

J. Design recommendations shall consider economic viability of the project. Design and construction shall incorporate standard products and procedures where practical to minimize project complexity and cost.

K. The Design-Builder shall prepare recommendations of design exceptions in writing for approval where conditions require deviation from design standards.

L. The Design-Builder shall be responsible for quality control of all phases of the Contract, including necessary supervision, inspection, sampling, testing and reporting.

III. Structure Requirements

A. Design of the dam and associated structures shall be in accordance with the most current versions of Forest Service Manual 7500 – Water Storage and Transmission and Forest Service Handbook 7509.11 – Dams Management Handbook.

Manuals and Handbooks noted above can be located at the following website http://www.fs.fed.us/im/directives/.

B. Dam height shall provide adequate freeboard to contain a 100-year flood without over-topping, or if necessary and feasible, provide an emergency spillway.

C. The elevation of the concrete spillway shall be set to maintain the permanent pool elevation of the lake that meets all the requirements of the engineering and wildlife staffs of the White Mountain National Forest D. The dimensions of the concrete spillway, and any auxiliary spillways that are included in the design, shall be adequate to meet the standards as specified in 7524.31 – Spillway sizing standards. This section of the manual specifies that the spillway(s) shall be sized to safely pass the design inflow of a 100-year storm.

E. Spillway shall be reinforced concrete, with no manual or mechanical means of controlling water levels and shall be easily maintained.

F. Outlet structure or drain shall provide a manually operated mechanical means for operation, shall be easily accessible, require minimal maintenance, and be protected (locked) from access and operation by others. If a gate valve system is used, a rising stem is required. Any operators that are necessary to manipulate the drain system shall also be provided.

G. The existing dam Hazard Classification is ‘LOW’ and the Administrative Classification is ‘D’. No change is anticipated or expected for either the Hazard or Administrative classification.

IV. Deliverables A. The approximate schedule shown in Table 1 shall be followed to meet a construction completion date of September 01, 2011. The delivery schedule is dependent upon date of the Notice to Proceed and may be adjusted by the Forest Service as approved.

B. The Forest Service will provide review comments at each submittal stage. The Design-Builder shall participate in conference calls or office meetings with the Forest Service to discuss and find resolution to comments to the satisfaction of the Forest Service. The Design-Builder shall annotate and provide a written response to each comment, documenting the agreed to resolution.

C. Initial site visit shall be with the design engineers, and/or principal engineer, and the designated construction superintendent.

D. Surveys shall be suitable for establishing limits of construction, control of work, and construction estimates.

i. The entire survey set shall be tied to known benchmarks of existing geodetic surveys, if and/or where practicable.

ii. Submit survey data electronically in ASCII format (tab or comma delimited) to the Forest Service with the final design submittals.

E. 35% Design review, including at minimum:

i. Surveys and topographic information.

ii. Hydrological Data

iii. Geotechnical Investigation.

iv. Preliminary Erosion Control Plan.

v. Preliminary Layouts with Plans, Profiles, Cross-Sections, and Calculations.

vi. Preliminary Cost Estimates.

vii. Preliminary Specification List.

F. 95% Design review, including at minimum:

i. Title Sheets.

ii. General Notes/Quantities Sheets.

iii. Typical Section Sheets.

iv. Plan/Profile Sheets and Design Calculations.

v. Erosion Control Plan Sheets.

vi. Traffic Control Plan Sheets.

vii. Boring Log Sheets.

viii. Miscellaneous Detail Sheets.

ix. Draft Final Cost Estimate - including itemized lists of pay items and quantities.

x. Draft Final Specifications - specifications shall be provided in final typed form using Forest Service Specifications.

xi. Permit Application forms completed and submitted.

G. 100% Final Design with professional engineer’s stamp and signature. The final design shall address all previous reviews and comments and permit conditions. See Section II-C for final submittal requirements.

H. Dam design reports including structural evaluations, geotechnical and hydraulic analysis, stamped and signed by the engineer.

I. Fabrication Drawings shall be prepared by material suppliers for approval by the Forest Service prior to construction.

J. Material supplier certifications shall be furnished to the Government during construction in accordance with the applicable specifications, including but not limited to the following certificates:

i. Concrete Mix Design.

ii. Steel Mill Reports and Hardware Certification.

iii. Piping and valves certification.

iv. Aggregate Gradation.

Table 1 – Delivery Schedule

Deliverable
Due Date
Notice to Proceed
04/01/2010
35% Review
06/01/2010
95% Review
08/01/2010
100% Final Design, Reports, and Permits
11/01/2010
Fabrication Drawings
04/01/2011
Commence Construction
05/01/2011
Performance Completion
09/01/2011

V. Material Requirements A. Design-Builder shall perform the necessary testing and quality control to ensure materials incorporated into the project meet the requirements.

B. All materials used in the construction or incorporated in the final product shall be free of asbestos.

C. All material shall be new, of top quality, durable, and from sources approved by the Government.

D. Related components shall be compatible with final product in-place.

E. Structural components shall meet the grade rating requirements, or better than, shown in the plans.

F. Timber, if any, shall be pressure treated in accordance with applicable standards, suitable for aquatic environments.

G. Concrete shall be minimum 4,000-psi and of an approved mix design.

H. Exposed steel components and hardware shall be stainless steel where practicable.

VI. Construction Requirements

A. Construction shall be in accordance with the accepted and approved design, specifications, and drawings, as expanded, amended and approved by the Contracting Officer.

B. Construction work week shall be limited to 5:00 AM Monday through 3:00 PM Friday. No work on weekends or legal holidays shall be permitted without prior approval of the Forest Service. A portion of the parking area shall be made available for use to forest visitors on weekends.

C. Construction shall not begin before approval of fabrication submittals and construction permits and shall proceed diligently until completion. Contractor shall perform the work in a safe and conscientious manner.

D. Prior to the start of any on site construction activities, the Design-Build contractor shall hold a preconstruction meeting near the vicinity of the project. The meeting schedule and location shall be coordinated and approved by the Government. As a minimum the Design-Builder shall discuss the following items.

i. Identify the full time construction superintendent.

ii. Safety officer and general safety provisions

iii. Identification of the Design-Builder’s testing and sampling firm.

iv. Review of regulatory permits.

v. Review of the construction schedule.

vi. Review of the submittal log.

vii. Sub-contractors, if any

viii. Certified payrolls

ix. Construction staging.

x. Traffic control.

xi. Review of key items in the plans and specifications.

xii. Erosion control methodologies.

xiii. Additional items necessary for project coordination.

E. Throughout the course of the Project, the Design-Build contractor shall hold progress meetings at least every two weeks unless more frequent meeting are required by the Contracting Officer. A progress meeting shall be held prior to submission of any invoice for payment of construction costs. As a minimum, the following items shall be discussed.

i. Review of the project schedule.

ii. Review of the submittal log and submittals in general.

iii. Review of the upcoming work.

iv. Discussion of upcoming progress payment.

v. Certified payrolls

vi. Additional items necessary for project coordination.

F. Design-Builder shall be responsible for construction and quality control including establishing temporary benchmarks, construction surveying and staking, inspection, and necessary sampling and testing.

G. Design-Builder shall construct the project according to the approved Plans and Specifications.

H. Design-Builder shall furnish and install “American Recovery and Reinvestment Act” Project Funding Source Sign Assembly prior to commencing construction. See sign details, required sign sizes are highlighted.

I. Construction equipment and vehicles used off-highway shall be washed clean of excess debris and shall be free of soil, plant parts, and weed seeds and shall be inspected and approved by the Forest Service prior to use on the project.

J. Construction shall incorporate the approved erosion control plan.

K. Unless designated for salvage, removed structures and obstructions become the property of the Design-Builder and shall be disposed legally off National Forest System Land.

L. As-Built drawings shall be retained onsite during construction and updated as necessary to reflect changes in conditions or work. Mark such changes in red on the drawings. Submit one set of approved as-built drawings to the Government upon completion of work.

M. The Forest Service will inspect the work at anytime for the benefit of the Government and may reject any work or material found not in compliance with contract requirements.

VII. Measurement and Payment A. The method of measurement for determining final payment for each pay item shall be based on Lump Sum Quantities. See the Schedule of Items.

i. Do not measure directly.

ii. The bid amount is complete payment for all work described in the contract necessary to complete the work for that item.

iii. Progress payment may be made based on a percentage of work completed and approved.

iv. Progress payment does not imply acceptance.

B. The completed and accepted design will be paid for at the contract lump sum price, which will be full compensation for the survey, design, detailing, subsurface exploration, and reporting required to prepare the approved final design.

C. The completed and accepted construction will be paid for at the contract lump sum price, which will be full compensation for the work required in accordance with the approved plans, schedule of items, specifications and requirements.

Schedule of Items for Design-Build Services

BEAVER POND DAM RECONSTRUCTION

Item
Description
Unit of Measure
Quantity
Unit Price
Total
1
Beaver Pond Dam Design
Lump Sum
1
2
Beaver Pond Dam Construction
Lump Sum
1

Total Price

Evaluation Factors for Award VIII. Award Determination Award will be made to that offeror whose proposal is (1) technically acceptable and (2) technical/cost relationship is the most advantageous to the Government. Evaluation factors other than price, when combined, are approximately equal to price in the award decision. The critical factor in making any cost/technical trade-off is not the spread between the technical ratings, but rather, the significance of that difference. The significance of the spread of ratings will be determined on the basis of what the difference might mean in terms of the performance and what it would cost the Government to take advantage of it. Award may not necessarily be made for technical capabilities that would appear to exceed those needed for the successful performance of the work. The Government reserves the right to make cost/technical trade-offs that are in the best interest of and advantageous to the Government.

Award may be made without further discussions. Offers should be submitted initially on the most favorable terms, from a price and technical standpoint, which the Contractor can submit to the Government. The Government may, after evaluation of the proposals, conduct further oral or written discussions as appropriate, with all offerors whose proposals are within the competitive range. Failure to provide all information requested by the RFP may render the proposal as unacceptable.

IX. Evaluation Factors

Technical

Technical proposals will be evaluated and rated by a Technical Evaluation Panel who may have access to the price proposals. Proposals shall be prepared in accordance with the technical proposals preparation instructions. Proposals shall reflect a technical understanding of, and approach to, the project. Proposals shall be as complete as practical, yet concise. Any proposals greater the 20 pages in length will only be evaluated based on the first 20 pages.

The followings factors will be used in the technical evaluation process, listed in no certain order as all are of equal importance.

1. Past Experience The Prime Contractor’s past dam design and construction experiences shall be shown on similar projects completed over the past five years. Experience is relevant when the offeror has been confronted with the kinds of work or challenges that that will be present under the contract contemplated by this RFP. The offeror will be assessed by the relevant experience on the basis of its breadth and its depth. For each relevant contract or reference, the offeror shall provide:

i. Name and location of the project.

ii. Contact name and phone number of customer or their agent.

iii. Whether offeror was the prime contractor or a subcontractor.

iv. List of subcontractors and suppliers used.

v. Brief description of project and work performed.

2. Past Performance

Experience is relevant when the offeror has satisfied performance factors with customers in the past, and complied with Federal, State, and local laws and regulations. The assessment of past performance will be subjective, and based mainly on the offeror’s reputation with their customers and others. Previous references will be contacted for information regarding their opinion on the following:

i. That you were capable, efficient and effective.

ii. That your performance conformed to the terms and conditions of the contract.

iii. That you were reasonable and cooperative during performance.

iv. That you were committed to quality work and timely completion.

Contractors with no past performance will be rated as “Neutral” in this category and not necessarily be rejected.

3. Staffing

Provide names and titles of key personnel to be assigned to the project, i.e. Design Engineer, Structural Engineer, Project Manager, Project Superintendent, Project Foreman, and Quality Control Inspector. The key personnel shall be shown in an organizational chart relative to each person’s role. Indicate the qualifications of key personnel listed, showing at minimum their experience and education.

4. Quality Control and Quality Assurance Plan

Submit a proposed Quality Control and Quality Assurance (QA/QC) Plan for the project, which shall include at minimum all testing and inspections required in the contract. The QA/QC Plan shall also include, but not be limited to, all supplier and plant inspection companies, including their responsibilities.

5. Project Schedule

A proposed schedule shall be included with the offer which shall include, but not be limited to, submission of 35% review, 95% review and final design, construction surveying and construction schedule.

Price

Price proposals will be evaluated after evaluations of the technical proposals. Each price proposal will be evaluated to determine its reasonableness for the effort proposed and to determine the demonstrated understanding of the level of effort needed to successfully complete the project. Results of the price proposal evaluation, along with the results of the technical evaluation, will be the basis for the award decisions.