Attachment 3 - Addendum to Supplemental Specs.doc

DOC document 23 KB Posted

Attached to
RECOVERY* Connelly Creek Bridge, National Forests in North Carolina
Solicitation number
AG-4419-S-10-0055
Issued by

About this file

Attachment 3 - Addendum to Supplemental Specifications

View the file

Other files

File Type Posted
SF30 - Amendment 3.pdf PDF
Section B - Revised Schedule of Items.pdf PDF
Section A - SF1442.pdf PDF
C - Solicitation - Sections C thru M .doc DOC document
Section B - Schedule.pdf PDF
SJ - Attachment 3 -Specifications.pdf PDF
SJ- Attachment 1 - Drawings.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Addendum to Supplemental Specifications

Connelly Creek Bridge Project

Nantahala Ranger District

Swain County, North Carolina

Solicitation Number AG-4419-S-10-0055

1. The material that is considered waste and not used on this project will be allowed to be wasted on National Forests Lands. The material shall be hauled to a location designated by the Forest Service to an area with 7 miles of the project location. The material will need to be layer placed and compacted using hauling vehicles and no extra compaction will be required. The material shall be smooth with ruts and seeded and mulched per project specifications. Silt fence shall be install downstream from the area designated for the material to be placed per FP-03. Seeding and mulching will be required for this area and is incidental to the excavation bid

2. This project has a Trout Moratorium from October 15th through April 15th. The contractor shall meet the requirements of this state enforced moratorium while working near water during those months.

3. All trees, debris and stumps to be removed with this project is the responsibility of the contractor and is to be removed off National Forests Lands and disposed of legally.