Schedule
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Brush_Hollow_vicinity_map.pdf | ||
| Brush_Hollow_riprap_outlet_detail.pdf | ||
| Brush_Hollow_FR497_Pit_Report.pdf | ||
| Experience_Capability Statement.doc | DOC document | |
| Brush_Hollow_FR-185g-Pit-Plan.pdf | ||
| FS ARRA SIGN DETAILS 2apr09.pdf | ||
| Brush_Hollow_Road Logs.doc | DOC document | |
| Brush_Hollow_culvert_details.pdf | ||
| Brush_Hollow_FR-459-Pit-Plan.pdf | ||
| Brush_Hollow_General Notes.doc | DOC document | |
| DBA_WD.pdf | ||
| Brush_Hollow_gate_detail.pdf | ||
| Brush_Hollow_FR459-Pit-report.pdf | ||
| Brush_Hollow_FR-497-Pit-Plan.pdf | ||
| SF 1442 Cont_0005.pdf | ||
| Brush_Hollow_FR185g-Pit-report.pdf | ||
| SF 1442 cvr pgs.pdf | ||
| Brush_Hollow_construction_details.pdf |
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Total
| CIM-0919-8R-413-0919-05 (ANF DEFERRED ROAD MTCE AND WATERSHED HEALTH II -- BRUSH HOLLOW ROADS) | |
| Schedule of Items | |
| Item | Amount |
| 185 | |
| 185A | |
| 239 | |
| 302 | |
| 302A | |
| 302B | |
| 304 | |
| 369 | |
| 497 | |
| 497A | |
| 497B | |
| 497C | |
| TOTAL |
| CIM-0919-8R-413-0919-05 (ANF DEFERRED ROAD MTCE AND WATERSHED HEALTH II -- BRUSH HOLLOW ROADS) | ||||||
| Schedule of Items: Brush Hollow Roads - FR 185 Base Items | ||||||
| BASE Item | Description | Method of Measure | Unit | Quantity | Unit Price | Amount |
| 01 | 151(01) - Mobilization | LS | Lump Sum | 1 | ||
| 02 | 203(05) - Removal of structures and obstructions | LS | Lump Sum | 1 | ||
| 03 | 230(50) - Brushing | CQ | Mile | 2.3 | ||
| 04 | 301(03) - Aggregate base, grading pit run, compaction method B | CQ | Cubic Yard | 72 | ||
| 05 | 303(26) - Road reconditioning | CQ | Mile | 2.3 | ||
| 06 | 602(63) - 18 inch aluminized steel, type 2, corrugated steel pipe, 0.064 inch thickness, method A | CQ | Linear Foot | 154 | ||
| 07 | 602(63) - 24 inch aluminized steel, type 2, corrugated steel pipe, 0.064 inch thickness, method A | CQ | Linear Foot | 36 | ||
| 08 | 625(03) - Seeding, hydraulic or dry method | LS | Lump Sum | 1 | ||
| 09 | 651(01) - Pit and Quarry Development | CQ | Each | 1 | ||
| TOTAL | ||||||
| QUOTERS PLEASE NOTE: | ||||||
| 1. Award will be to one contractor. | ||||||
| 2. Insert a price opposite each item for which a quantity appears. Failure to do so will preclude consideration of the quote. | ||||||
| 3. For method of measurement and standard specifications please refer to “Standard Specifications for the Construction of Roads and Bridges on Federal Highway Projects” FP-03 U.S. Customary Units, U.S. Department of Transportation – Federal Highway Administration and included special project specifications. | ||||||
| 4. As a construction project, there will be requirements for payment protection. See section I, Clause 52.228-2, 11, 13, and 14. | ||||||
| 5. This solicitation is advertised for full and open competition in accordance with the Small Business Competitiveness Demonstration program. | ||||||
| 6. Abbreviations used: LS = Lump Sum CQ = Contract Quantity |
185A
| CIM-0919-8R-413-0919-05 (ANF DEFERRED ROAD MTCE AND WATERSHED HEALTH II -- BRUSH HOLLOW ROADS) | ||||||
| Schedule of Items: Brush Hollow Roads - FR 185A - Optional Items | ||||||
| OPTIONAL Item | Description | Method of Measure | Unit | Quantity | Unit Price | Amount |
| 10 | 151(01) - Mobilization | LS | Lump Sum | 1 | ||
| 11 | 203(05) - Removal of structures and obstructions | LS | Lump Sum | 1 | ||
| 12 | 230(50) - Brushing | CQ | Mile | 0.3 | ||
| 13 | 301(03) - Aggregate base, grading pit run, compaction method B | CQ | Cubic Yard | 540 | ||
| 14 | 303(26) - Road reconditioning | CQ | Mile | 0.3 | ||
| 15 | 602(63) - 18 inch aluminized steel, type 2, corrugated steel pipe, 0.064 inch thickness, method A | CQ | Linear Foot | 24 | ||
| 16 | 625(03) - Seeding, hydraulic or dry method | LS | Lump Sum | 1 | ||
| 17 | 633(01) - Sign System | CQ | Each | 1 | ||
| 18 | 650(05) - Gate Repair | CQ | Each | 1 | ||
| 19 | 651(01) - Pit and Quarry Development | CQ | Each | 1 | ||
| TOTAL | ||||||
| QUOTERS PLEASE NOTE: | ||||||
| 1. Award will be to one contractor. | ||||||
| 2. Insert a price opposite each item for which a quantity appears. Failure to do so will preclude consideration of the quote. | ||||||
| 3. For method of measurement and standard specifications please refer to “Standard Specifications for the Construction of Roads and Bridges on Federal Highway Projects” FP-03 U.S. Customary Units, U.S. Department of Transportation – Federal Highway Administration and included special project specifications. | ||||||
| 4. As a construction project, there will be requirements for payment protection. See section I, Clause 52.228-2, 11, 13, and 14. | ||||||
| 5. This solicitation is advertised for full and open competition in accordance with the Small Business Competitiveness Demonstration program. | ||||||
| 6. Abbreviations used: LS = Lump Sum CQ = Contract Quantity |
| CIM-0919-8R-413-0919-05 (ANF DEFERRED ROAD MTCE AND WATERSHED HEALTH II -- BRUSH HOLLOW ROADS) | ||||||
| Schedule of Items: Brush Hollow Roads - FR 239 - Base Items | ||||||
| BASE Item | Description | Method of Measure | Unit | Quantity | Unit Price | Amount |
| 20 | 151(01) - Mobilization | LS | Lump Sum | 1 | ||
| 21 | 203(05) - Removal of structures and obstructions | LS | Lump Sum | 1 | ||
| 22 | 230(50) - Brushing | CQ | Mile | 0.9 | ||
| 23 | 301(03) - Aggregate base course, grading pit run, compaction method B | CQ | Cubic Yard | 1521 | ||
| 24 | 303(26) - Road reconditioning | CQ | Mile | 0.9 | ||
| 25 | 602(63) - 18 inch aluminized steel, type 2, corrugated steel pipe, 0.064 inch thickness, method A | CQ | Linear Foot | 170 | ||
| 26 | 625(03) - Seeding, hydraulic or dry method | LS | Lump Sum | 1 | ||
| 27 | 633(01) - Sign System | CQ | Each | 1 | ||
| 28 | 651(01) - Pit and Quarry Development | CQ | Each | 1 | ||
| TOTAL | ||||||
| QUOTERS PLEASE NOTE: | ||||||
| 1. Award will be to one contractor. | ||||||
| 2. Insert a price opposite each item for which a quantity appears. Failure to do so will preclude consideration of the quote. | ||||||
| 3. For method of measurement and standard specifications please refer to “Standard Specifications for the Construction of Roads and Bridges on Federal Highway Projects” FP-03 U.S. Customary Units, U.S. Department of Transportation – Federal Highway Administration and included special project specifications. | ||||||
| 4. As a construction project, there will be requirements for payment protection. See section I, Clause 52.228-2, 11, 13, and 14. | ||||||
| 5. This solicitation is advertised for full and open competition in accordance with the Small Business Competitiveness Demonstration program. | ||||||
| 6. Abbreviations used: LS = Lump Sum CQ = Contract Quantity |
| CIM-0919-8R-413-0919-05 (ANF DEFERRED ROAD MTCE AND WATERSHED HEALTH II -- BRUSH HOLLOW ROADS) | ||||||
| Schedule of Items: Brush Hollow Roads - FR 302 - Base Items | ||||||
| BASE Item | Description | Method of Measure | Unit | Quantity | Unit Price | Amount |
| 29 | 151(01) - Mobilization | LS | Lump Sum | 1 | ||
| 30 | 203(05) - Removal of structures and obstructions | LS | Lump Sum | 1 | ||
| 31 | 230(50) - Brushing | CQ | Mile | 1.9 | ||
| 32 | 301(03) - Aggregate base, grading pit run, compaction method B | CQ | Cubic Yard | 3050 | ||
| 33 | 303(26) - Road reconditioning | CQ | Mile | 1.9 | ||
| 34 | 602(63) - 18 inch aluminized steel, type 2, corrugated steel pipe, 0.064 inch thickness, method A | CQ | Linear Foot | 238 | ||
| 35 | 602(63) - 24 inch aluminized steel, type 2, corrugated steel pipe, 0.064 inch thickness, method A | CQ | Linear Foot | 38 | ||
| 36 | 602(63) - 30 inch aluminized steel, type 2, corrugated steel pipe, 0.079 inch thickness, method A | CQ | Linear Foot | 32 | ||
| 37 | 625(03) - Seeding, hydraulic or dry method | LS | Lump Sum | 1 | ||
| 38 | 651(01) - Pit and Quarry Development | CQ | Each | 1 | ||
| TOTAL | ||||||
| QUOTERS PLEASE NOTE: | ||||||
| 1. Award will be to one contractor. | ||||||
| 2. Insert a price opposite each item for which a quantity appears. Failure to do so will preclude consideration of the quote. | ||||||
| 3. For method of measurement and standard specifications please refer to “Standard Specifications for the Construction of Roads and Bridges on Federal Highway Projects” FP-03 U.S. Customary Units, U.S. Department of Transportation – Federal Highway Administration and included special project specifications. | ||||||
| 4. As a construction project, there will be requirements for payment protection. See section I, Clause 52.228-2, 11, 13, and 14. | ||||||
| 5. This solicitation is advertised for full and open competition in accordance with the Small Business Competitiveness Demonstration program. | ||||||
| 6. Abbreviations used: LS = Lump Sum CQ = Contract Quantity |
302A
| CIM-0919-8R-413-0919-05 (ANF DEFERRED ROAD MTCE AND WATERSHED HEALTH II -- BRUSH HOLLOW ROADS) | ||||||
| Schedule of Items: Brush Hollow Roads - FR 302A - Base Items | ||||||
| BASE Item | Description | Method of Measure | Unit | Quantity | Unit Price | Amount |
| 39 | 151(01) - Mobilization | LS | Lump Sum | 1 | ||
| 40 | 203(05) - Removal of structures and obstructions | LS | Lump Sum | 1 | ||
| 41 | 230(50) - Brushing | CQ | Mile | 1.3 | ||
| 42 | 301(03) Aggregate base, grading pit run, compaction method B | CQ | Cubic Yard | 879 | ||
| 43 | 303(26) - Road reconditioning | CQ | Mile | 1.3 | ||
| 44 | 602(63) - 18 inch aluminized steel, type 2, corrugated steel pipe, 0.064 inch thickness, method A | CQ | Linear Foot | 282 | ||
| 45 | 625(03) - Seeding, hydraulic or dry method | LS | Lump Sum | 1 | ||
| 46 | 633(01) - Sign System | CQ | Each | 2 | ||
| 47 | 651(01) - Pit and Quarry Development | CQ | Each | 1 | ||
| TOTAL | ||||||
| QUOTERS PLEASE NOTE: | ||||||
| 1. Award will be to one contractor. | ||||||
| 2. Insert a price opposite each item for which a quantity appears. Failure to do so will preclude consideration of the quote. | ||||||
| 3. For method of measurement and standard specifications please refer to “Standard Specifications for the Construction of Roads and Bridges on Federal Highway Projects” FP-03 U.S. Customary Units, U.S. Department of Transportation – Federal Highway Administration and included special project specifications. | ||||||
| 4. As a construction project, there will be requirements for payment protection. See section I, Clause 52.228-2, 11, 13, and 14. | ||||||
| 5. This solicitation is advertised for full and open competition in accordance with the Small Business Competitiveness Demonstration program. | ||||||
| 6. Abbreviations used: LS = Lump Sum CQ = Contract Quantity |
302B
| CIM-0919-8R-413-0919-05 (ANF DEFERRED ROAD MTCE AND WATERSHED HEALTH II -- BRUSH HOLLOW ROADS) | ||||||
| Schedule of Items: Brush Hollow Roads - FR 302B - Optional Items | ||||||
| OPTIONAL Item | Description | Method of Measure | Unit | Quantity | Unit Price | Amount |
| 48 | 151(01) - Mobilization | LS | Lump Sum | 1 | ||
| 49 | 203(05) - Removal of structures and obstructions | LS | Lump Sum | 1 | ||
| 50 | 230(50) - Brushing | CQ | Mile | 0.3 | ||
| 51 | 301(03) - Aggregate base, grading pit run, compaction method B | CQ | Cubic Yard | 376 | ||
| 52 | 303(26) - Road reconditioning | CQ | Mile | 0.3 | ||
| 53 | 633(01) -Sign System | CQ | Each | 1 | ||
| 54 | 651(01) - Pit and Quarry Development | CQ | Each | 1 | ||
| TOTAL | ||||||
| QUOTERS PLEASE NOTE: | ||||||
| 1. Award will be to one contractor. | ||||||
| 2. Insert a price opposite each item for which a quantity appears. Failure to do so will preclude consideration of the quote. | ||||||
| 3. For method of measurement and standard specifications please refer to “Standard Specifications for the Construction of Roads and Bridges on Federal Highway Projects” FP-03 U.S. Customary Units, U.S. Department of Transportation – Federal Highway Administration and included special project specifications. | ||||||
| 4. As a construction project, there will be requirements for payment protection. See section I, Clause 52.228-2, 11, 13, and 14. | ||||||
| 5. This solicitation is advertised for full and open competition in accordance with the Small Business Competitiveness Demonstration program. | ||||||
| 6. Abbreviations used: LS = Lump Sum CQ = Contract Quantity |
| CIM-0919-8R-413-0919-05 (ANF DEFERRED ROAD MTCE AND WATERSHED HEALTH II -- BRUSH HOLLOW ROADS) | ||||||
| Schedule of Items: Brush Hollow Roads - FR 304 Base Items | ||||||
| BASE Item | Description | Method of Measure | Unit | Quantity | Unit Price | Amount |
| 55 | 151(01) - Mobilization | LS | Lump Sum | 1 | ||
| 56 | 203(05) - Removal of structures and obstructions | LS | Lump Sum | 1 | ||
| 57 | 230(50) - Brushing | CQ | Mile | 1.1 | ||
| 58 | 301(03) - Aggregate base, grading pit run, compaction method B | CQ | Cubic Yard | 2326 | ||
| 59 | 303(26) - Road reconditioning | CQ | Mile | 1.1 | ||
| 602(63) - 18 inch aluminized steel, type 2, corrugated steel pipe, 0.064 inch thickness, method A | CQ | Linear Foot | 242 | |||
| 60 | 651(01) - Pit and Quarry Development | CQ | Each | 1 | ||
| TOTAL | ||||||
| QUOTERS PLEASE NOTE: | ||||||
| 1. Award will be to one contractor. | ||||||
| 2. Insert a price opposite each item for which a quantity appears. Failure to do so will preclude consideration of the quote. | ||||||
| 3. For method of measurement and standard specifications please refer to “Standard Specifications for the Construction of Roads and Bridges on Federal Highway Projects” FP-03 U.S. Customary Units, U.S. Department of Transportation – Federal Highway Administration and included special project specifications. | ||||||
| 4. As a construction project, there will be requirements for payment protection. See section I, Clause 52.228-2, 11, 13, and 14. | ||||||
| 5. This solicitation is advertised for full and open competition in accordance with the Small Business Competitiveness Demonstration program. | ||||||
| 6. Abbreviations used: LS = Lump Sum CQ = Contract Quantity |
| CIM-0919-8R-413-0919-05 (ANF DEFERRED ROAD MTCE AND WATERSHED HEALTH II -- BRUSH HOLLOW ROADS) | ||||||
| Schedule of Items: Brush Hollow Roads - FR 369 - Optional Items | ||||||
| OPTIONAL Item | Description | Method of Measure | Unit | Quantity | Unit Price | Amount |
| 61 | 151(01) - Mobilization | LS | Lump Sum | 1 | ||
| 62 | 203(05) - Removal of structures and obstructions | LS | Lump Sum | 1 | ||
| 63 | 230(50) - Brushing | CQ | Mile | 0.2 | ||
| 64 | 301(03) - Aggregate base, grading pit run, compaction method B | CQ | Cubic Yard | 336 | ||
| 65 | 303(26) - Road reconditioning | CQ | Mile | 0.2 | ||
| 66 | 602(63) - 18 inch aluminized steel, type 2, corrugated steel pipe, 0.064 inch thickness, method A | CQ | Linear Foot | 104 | ||
| 67 | 625(03) - Seeding, hydraulic or dry method | LS | Lump Sum | 1 | ||
| 68 | 651(01) - Pit and Quarry Development | CQ | Each | 1 | ||
| TOTAL | ||||||
| QUOTERS PLEASE NOTE: | ||||||
| 1. Award will be to one contractor. | ||||||
| 2. Insert a price opposite each item for which a quantity appears. Failure to do so will preclude consideration of the quote. | ||||||
| 3. For method of measurement and standard specifications please refer to “Standard Specifications for the Construction of Roads and Bridges on Federal Highway Projects” FP-03 U.S. Customary Units, U.S. Department of Transportation – Federal Highway Administration and included special project specifications. | ||||||
| 4. As a construction project, there will be requirements for payment protection. See section I, Clause 52.228-2, 11, 13, and 14. | ||||||
| 5. This solicitation is advertised for full and open competition in accordance with the Small Business Competitiveness Demonstration program. | ||||||
| 6. Abbreviations used: LS = Lump Sum CQ = Contract Quantity |
| CIM-0919-8R-413-0919-05 (ANF DEFERRED ROAD MTCE AND WATERSHED HEALTH II -- BRUSH HOLLOW ROADS) | ||||||
| Schedule of Items: Brush Hollow Roads - FR 497 - Base Items | ||||||
| BASE Item | Description | Method of Measure | Unit | Quantity | Unit Price | Amount |
| 69 | 151(01) - Mobilization | LS | Lump Sum | 1 | ||
| 70 | 203(05) - Removal of structures and obstructions | LS | Lump Sum | 1 | ||
| 71 | 230(50) - Brushing | CQ | Mile | 1.3 | ||
| 72 | 301(03) - Aggregate base, grading pit run, compaction method B | CQ | Cubic Yard | 2204 | ||
| 73 | 303(26) - Road reconditioning | CQ | Mile | 1.3 | ||
| 74 | 602(63) - 18 inch aluminized steel, type 2, corrugated steel pipe, 0.064 inch thickness, method A | CQ | Linear Foot | 318 | ||
| 75 | 633(01) - Sign System | CQ | Each | 1 | ||
| TOTAL | ||||||
| QUOTERS PLEASE NOTE: | ||||||
| 1. Award will be to one contractor. | ||||||
| 2. Insert a price opposite each item for which a quantity appears. Failure to do so will preclude consideration of the quote. | ||||||
| 3. For method of measurement and standard specifications please refer to “Standard Specifications for the Construction of Roads and Bridges on Federal Highway Projects” FP-03 U.S. Customary Units, U.S. Department of Transportation – Federal Highway Administration and included special project specifications. | ||||||
| 4. As a construction project, there will be requirements for payment protection. See section I, Clause 52.228-2, 11, 13, and 14. | ||||||
| 5. This solicitation is advertised for full and open competition in accordance with the Small Business Competitiveness Demonstration program. | ||||||
| 6. Abbreviations used: LS = Lump Sum CQ = Contract Quantity |
497A
| CIM-0919-8R-413-0919-05 (ANF DEFERRED ROAD MTCE AND WATERSHED HEALTH II -- BRUSH HOLLOW ROADS) | ||||||
| Schedule of Items: Brush Hollow Roads - FR 497A - Optional Items | ||||||
| OPTIONAL Item | Description | Method of Measure | Unit | Quantity | Unit Price | Amount |
| 76 | 151(01) - Mobilization | LS | Lump Sum | 1 | ||
| 77 | 203(05) - Removal of structures and obstructions | LS | Lump Sum | 1 | ||
| 78 | 230(50) - Brushing | CQ | Mile | 0.2 | ||
| 79 | 301(03) - Aggregate base, grading pit run, compaction method B | CQ | Cubic Yard | 299 | ||
| 80 | 303(26) - Road reconditioning | CQ | Mile | 0.2 | ||
| 81 | 602(01) - 16 inch steel pipe casing | CQ | Linear Foot | 70 | ||
| 82 | 625(03) - Seeding, hydraulic or dry method | LS | Lump Sum | 1 | ||
| 83 | 633(01) - Sign System | CQ | Each | 1 | ||
| 84 | 651(01) - Pit and Quarry Development | CQ | Each | 1 | ||
| TOTAL | ||||||
| QUOTERS PLEASE NOTE: | ||||||
| 1. Award will be to one contractor. | ||||||
| 2. Insert a price opposite each item for which a quantity appears. Failure to do so will preclude consideration of the quote. | ||||||
| 3. For method of measurement and standard specifications please refer to “Standard Specifications for the Construction of Roads and Bridges on Federal Highway Projects” FP-03 U.S. Customary Units, U.S. Department of Transportation – Federal Highway Administration and included special project specifications. | ||||||
| 4. As a construction project, there will be requirements for payment protection. See section I, Clause 52.228-2, 11, 13, and 14. | ||||||
| 5. This solicitation is advertised for full and open competition in accordance with the Small Business Competitiveness Demonstration program. | ||||||
| 6. Abbreviations used: LS = Lump Sum CQ = Contract Quantity |
497B
| CIM-0919-8R-413-0919-05 (ANF DEFERRED ROAD MTCE AND WATERSHED HEALTH II -- BRUSH HOLLOW ROADS) | ||||||
| Schedule of Items: Brush Hollow Roads - FR 497B - Optional Items | ||||||
| OPTIONAL Item | Description | Method of Measure | Unit | Quantity | Unit Price | Amount |
| 85 | 151(01) - Mobilization | LS | Lump Sum | 1 | ||
| 86 | 203(05) - Removal of structures and obstructions | LS | Lump Sum | 1 | ||
| 87 | 230(50) - Brushing | CQ | Mile | 0.2 | ||
| 88 | 301(03) - Aggregate base, grading pit run, compaction method B | CQ | Cubic Yard | 240 | ||
| 89 | 303(26) - Road reconditioning | CQ | Mile | 0.2 | ||
| 90 | 602(63) - 18 inch aluminized steel, type 2, corrugated steel pipe, 0.064 inch thickness, method A | CQ | Linear Foot | 24 | ||
| 91 | 625(03) - Seeding, hydraulic or dry method | LS | Lump Sum | 1 | ||
| 92 | 651(01) - Pit and Quarry Development | CQ | Each | 1 | ||
| TOTAL | ||||||
| QUOTERS PLEASE NOTE: | ||||||
| 1. Award will be to one contractor. | ||||||
| 2. Insert a price opposite each item for which a quantity appears. Failure to do so will preclude consideration of the quote. | ||||||
| 3. For method of measurement and standard specifications please refer to “Standard Specifications for the Construction of Roads and Bridges on Federal Highway Projects” FP-03 U.S. Customary Units, U.S. Department of Transportation – Federal Highway Administration and included special project specifications. | ||||||
| 4. As a construction project, there will be requirements for payment protection. See section I, Clause 52.228-2, 11, 13, and 14. | ||||||
| 5. This solicitation is advertised for full and open competition in accordance with the Small Business Competitiveness Demonstration program. | ||||||
| 6. Abbreviations used: LS = Lump Sum CQ = Contract Quantity |
497C
| CIM-0919-8R-413-0919-05 (ANF DEFERRED ROAD MTCE AND WATERSHED HEALTH II -- BRUSH HOLLOW ROADS) | ||||||
| Schedule of Items: Brush Hollow Roads - FR 497C - Optional Items | ||||||
| OPTIONAL Item | Description | Method of Measure | Unit | Quantity | Unit Price | Amount |
| 93 | 151(01) - Mobilization | LS | Lump Sum | 1 | ||
| 94 | 203(05) - Removal of structures and obstructions | LS | Lump Sum | 1 | ||
| 95 | 230(50) - Brushing | CQ | Mile | 0.3 | ||
| 96 | 301(03) - Aggregate base, grading pit run, compaction method B | CQ | Cubic Yard | 474 | ||
| 97 | 303(26) - Road reconditioning | CQ | Mile | 0.3 | ||
| 98 | 602(01) - 16 inch steel pipe casing | CQ | Linear Foot | 40 | ||
| TOTAL | ||||||
| QUOTERS PLEASE NOTE: | ||||||
| 1. Award will be to one contractor. | ||||||
| 2. Insert a price opposite each item for which a quantity appears. Failure to do so will preclude consideration of the quote. | ||||||
| 3. For method of measurement and standard specifications please refer to “Standard Specifications for the Construction of Roads and Bridges on Federal Highway Projects” FP-03 U.S. Customary Units, U.S. Department of Transportation – Federal Highway Administration and included special project specifications. | ||||||
| 4. As a construction project, there will be requirements for payment protection. See section I, Clause 52.228-2, 11, 13, and 14. | ||||||
| 5. This solicitation is advertised for full and open competition in accordance with the Small Business Competitiveness Demonstration program. | ||||||
| 6. Abbreviations used: LS = Lump Sum CQ = Contract Quantity |