INTEROFFICE MEMORANDUM
TO: LORI AUSTAD
FROM: DEBORAH BYRD
SUBJECT: DUNCAN RIDGE QUESTIONS
DATE: SEPTEMBER 19, 2017
CC: [NAME]
The following are answers to questions that were asked yesterday about the project.
Since the project is over two counties will it require permits from both counties?
Permits will need to come from Union and Fannin County.
Where are the expenses covered for the layout, planning and survey of the trail obliteration activities covered? Obliteration layout planning and survey and included in the LP and Sur pay items.
New Section is included to cover the linear Feet of the estimated trail obliteration.
Is a trail machine allowed on the trail to do the work of construction and obliteration? An appropriately sized trail machine is allowed to do the work. It is one that will leave the Forest Service with the desired width of trail and disturbed area.
Will shape files be made available to the contractor? The project shape files will be available to contractor.
Deborah Byrd, COR