Exhibit A – Road Maintenance Schedule
Blue Ridge Ranger District
2016 Road Maintenance Schedule
Spot surfacing quantities shown for each individual road in the schedules below are approximate and may be adjusted depending upon road conditions at time of performance.
Award of optional maintenance items will be based upon prices submitted and funds available at the time of award and during the performance period. The USFS may also choose to supplement the maintenance schedules below with additional roads and maintenance activities from the attached Road List, Exhibit C, in Section J – also dependent upon funds available at the time of need.
Union County
Base Maintenance Items Maintenance Activity (Pay Item) 210 220 230 Road # Road Name Maint.
Level Begin Maintenance
End Maintenance
BMP EMP Blading Aggregate Surface Roads (Miles)
Clean and Reshape Drainage Structures (Miles)
Spot Surfacing (Tons)
GAB #4
Stone
42 Blue Ridge 3 Junction with Gilmer Co Rd.
(Doublehead Gap)
Spring Mtn.
Trail Head Parking Area
16.4 22.41 6 6 630 270
Total Base Maintenance Items 6 6 630 270
Option Maintenance Items
107 West Wolf Creek
3 Junction with St Hwy
0.0 3 3 3 270 90
33 Cooper Creek 3 End of Pavement on Union Co. Rd
End of Pavement on Union Co Rd
0.0 7.75 7.75 7.75 630 180
4 Mulky Gap 3 End of Pavement on Union Co. Rd
USFS Property Boundary before Jones Creek Bridge
0.0 6.5 6.5 6.5 450 180
Total Option Maintenance Items 17.25 17.25 1350 450
Lumpkin and Dawson Counties
Base Maintenance Items Maintenance Activity (Pay Item) 210 220 230 Road # Road Name Maint.
Level Begin Maintenance
End Maintenance
BMP EMP Blading Aggregate Surfaced Roads (Miles)
Clean and Reshape Drainage Structures (Miles)
Spot Surfacing (Tons)
GAB #4
Stone
28-2 Nimblewill 3 End of Pavement on Lumpkin Co Rd
Nimblewill Gap
10.9 14.23 3.33 3.33 360 216
77A West Jones Creek
2 Junction with FSR 77
End of Road 0.0 2.0 2.0 2.0 270 144
877 Jones Creek
3 Junction with FSR 77A
End of Road 0.0 1.04 1.04 1.04 180 90
Total Base Maintenance Items 6.37 6.37 810 450
Fannin and Gilmer Counties
Option Maintenance Items Maintenance Activity (Pay Item) 210 220 230 Road # Road Name Maint.
Level Begin Maintenance
End Maintenance
BMP EMP Blading Aggregate Surfaced Roads (Miles)
Clean and Reshape Drainage Structures (Miles)
Spot Surfacing (Tons)
GAB #4
Stone
58 Noontootla 3 Junction with Fannin Co Rd 218 (Double Head Gap)
Junction with FSR 42
0.0 8.14 8.14 8.14 630 180
711 Fruitkoff 3 Junction with Fannin Co Rd (Campbell Camp Rd)
USFS Property Boundary
0.0 2.04 2.04 2.04 270 90
Total Option Maintenance Items 10.18 10.18 900 270