Supplemental Specifications

View the file

Other files for this federal contract opportunity

Other files attached to Bryant Creek Culvert Replacement, newest first.
File Type Posted
Amdt_1.pdf PDF
site showing attendees.pdf PDF
revised schedule.docx DOCX document
revised drawing sheets.pdf PDF
Hwy WD GA100002.pdf PDF
Bid Bond_SF 24.pdf PDF
Drawings_Bryant Creek.pdf PDF
Technical Proposal Format.docx DOCX document
AG-435H-S-11-0017.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bryant Creek Culvert Replacement

Chattahoochee-Oconee National Forests Blue Ridge Ranger District

Supplemental Specifications to FP-03

These specifications supplement the Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects FP-03, U.S. Department of Transportation Federal Highway Administration, which are included in the contract by reference. They may be obtained on the internet at http://fhwapap04.fhwa.dot.gov/nhswp/library.jsp as Standard Specifications for Federal Lands Highways.

June 2011 http://fhwapap04.fhwa.dot.gov/nhswp/library.jsp�

Table of Contents

Bryant Creek Culvert Replacement Supplemental Specifications to FP-03 June 2011 Table of Contents Preface 101 - Terms, Format, and Definitions

101.03 Abbreviations

101.04 Definitions

102 - Bid, Award, and Execution of Contract 102 Bid, Award, and Execution of Contract

103 - Scope of Work Deletions

104 - Control of Work Deletions

104.06 Use of Roads by Contractor

105 - Control of Material

105.02 Material Sources

105.02(a) Government-provided sources

105.05 Use of Material Found in the Work

106 - Acceptance of Work

106.07 Delete

107 - Legal Relations and Responsibility to the Public

107.05 Responsibility for Damage Claims

107.06 Contractor’s Responsibility for Work

107.09 Legal Relationship of the Parties

107.10 Environmental Protection

108 - Prosecution and Progress 108 Delete

109 - Measurement and Payment 109 Deletions

109.02 Measurement Terms and Definitions

155 - Schedules for Construction Contracts 155 Delete

201 - Clearing and Grubbing

201.01 Description

201.04 Clearing. (c)

203 - Removal of Structures and Obstructions

203.01 Description

203.04 Removing Material

204 - Excavation and Embankment

204.06 Roadway Excavation

204.09 Preparing Foundation for Embankment Construction

204.10 Embankment Construction

204.11 Compaction

204.13 Sloping, Shaping, and Finishing

Table 204-2 Construction tolerances

204.14 Disposal of Unsuitable or Excess Material

204.15 Acceptance

Table 204-1 Sampling and Testing Requirements

208 - Structure Excavation and Backfill for Selected Major Structures 301 - Untreated Aggregate Courses

301 Title Change

301.01 Work

301.02 Material

301.03 General

301.04 Mixing and Spreading

301.05 Compacting

301.06 Surface Tolerance

Table 301-1 Field Density Requirements Table 301-1—Acceptance Sampling and Testing Requirements 301.08(b) Plasticity Index

301.09 Measurement

603 - Structural Plate Structures

603.03 General

603.04 Erecting

625 - Turf Establishment

625.04 Preparing Seedbed

625.05 Watering

625.07 Seeding. (a) Dry method

635 - Temporary Traffic Control

635.03 General

648 - Stream Simulation 718 - Traffic Signing and Marking Material

Preface Preface_wo_03_15_2004_m

Delete all but the first paragraph and add the following

The Forest Service, US Department of Agriculture has adopted FP-03 for construction of National Forest System Roads.

101 - Terms, Format, and Definitions 101.00_nat_us_07_25_2005

101.01_nat_us_04_04_2007

101.01 Meaning of Terms

Delete all references to the TAR (Transportation Acquisition Regulations) in the specifications.

101.03_nat_us_06_16_2006

101.03 Abbreviations.

AFPA

MSHA

NIST

NESC

WCLIB

Add the following to (a) Acronyms:

American Forest and Paper Association Mine Safety and Health Administration National Institute of Standards and Technology National Electrical Safety Code West Coast Lumber Inspection Bureau mp

Add the following to (b) SI symbols:

Milepost ppm Part Per Million

101.04_nat_us_03_29_2007

101.04 Definitions.

Bid Schedule--The Schedule of Items.

Delete the following definitions and substitute the following:

Br idge--No definition.

Contractor --The individual or legal entity contracting with the Government for performance of prescribed work. In a timber sale contract, the contractor is the “purchaser”.

Culver t--No definition.

Right-of-Way--A general term denoting (1) the privilege to pass over land in some particular line (including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2) Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.

Add the following:

http://www.nist.gov/�

Adjustment in Contract Pr ice--“Equitable adjustment,” as used in the Federal Acquisition Regulations, or “construction cost adjustment,” as used in the Timber Sale Contract, as applicable.

Change--“Change” means “change order” as used in the Federal Acquisition Regulations, or “design change” as used in the Timber Sale Contract.

Design Quantity--“Design quantity” is a Forest Service method of measurement from the FS-96 Forest Service Specifications for the Construction of Roads and Bridges. Under these FP specifications this term is replaced by the term “Contract Quantities”.

Forest Service--The United States of America, acting through the Forest Service, U.S.

Department of Agriculture.

Neat Line--A line defining the proposed or specified limits of an excavation or structure.

Pioneer Road--Temporary construction access built along the route of the project.

Purchaser--The individual, partnership, joint venture, or corporation contracting with the Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.

Protected Streamcourse--A drainage shown on the plans or timber sale area map that requires designated mitigation measures.

Road Order--An order affecting and controlling traffic on roads under Forest Service jurisdiction. Road Orders are issued by a designated Forest Officer under the authorities of 36 CFR, part 260.

Schedule of Items--A schedule in the contract that contains a listing and description of construction items, quantities, units of measure, unit price, and amount.

Utilization Standards--The minimum size and percent soundness of trees described in the specifications to determine merchantable timber.

Add Figure 101-1—Illustration of road structure terms:

Figure 101-1—Illustration of road structure terms.

102 - Bid, Award, and Execution of Contract 102.00_nat_us_02_16_2005

102 Bid, Award, and Execution of Contract

Delete Section 102 in its entirety.

103 - Scope of Work 103.00_nat_us_02_16_2005

Deletions

Delete all but subsection 103.01 Intent of Contract.

104 - Control of Work 104.00_nat_us_06_16_2006

Deletions

Delete Sections 104.01, 104.02, and 104.04.

104.06_nat_us_02_17_2005

104.06 Use of Roads by Contractor

Add the following subsection:

The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to the limitations and authorizations designated in the Road Order(s) or described in the contract, when such use will not damage the roads or national forest resources, and when traffic can be accommodated safely.

105 - Control of Material 105.02_nat_us_01_18_2007

105.02 Material Sources.

105.02(a) Government-provided sources.

Comply with the requirements of 30 CFR 56, subparts B and H. Use all suitable material for aggregate regardless of size unless otherwise designated. When required, re-establish vegetation in disturbed areas according to section 625.

105.05_nat_us_05_12_2004

105.05 Use of Material Found in the Work.

Materials produced or processed from Government lands in excess of the quantities required for performance of this contract are the property of the Government. The Government is not obligated to make reimbursement for the cost of producing these materials.

Delete 105.05 (a) and (b) and the last sentence of the second paragraph and substitute the following:

106 - Acceptance of Work 106.07_nat_us_05_11_2004

106.07 Delete

Delete subsection 106.07.

107 - Legal Relations and Responsibility to the Public 107.05_nat_us_05_11_2004

107.05 Responsibility for Damage Claims.

Delete the entire subsection

107.06_nat_us_06_16_2006

107.06 Contractor’s Responsibility for Work.

“except as provided in Subsection 106.07”.

Delete the following from the first paragraph.

107.09_nat_us_06_16_2006

107.09 Legal Relationship of the Parties.

107.10_nat_us_06_16_2006

107.10 Environmental Protection.

Design and locate equipment repair shops, stationary refueling sites, or other facilities to minimize the potential and impacts of hazardous material spills on Government land.

Add the following:

Before beginning any work, submit a Hazardous Spill Plan. List actions to be taken in the event of a spill. Incorporate preventive measures to be taken, such as the location of mobile refueling facilities, storage and handling of hazardous materials, and similar information. Immediately notify the CO of all hazardous material spills. Provide a written narrative report form no later than 24 hours after the initial report and include the following:

• Description of the item spilled (including identity, quantity, manifest number, and other identifying information).

• Whether amount spilled is EPA or state reportable, and if so whether it was reported, and to whom.

• Exact time and location of spill including a description of the area involved.

• Containment procedures.

• Summary of any communications the Contractor had with news media, Federal, state and local regulatory agencies and officials, or Forest Service officials.

• Description of clean-up procedures employed or to be employed at the site including final disposition and disposal location of spill residue.

When available provide copies of all spill related clean up and closure documentation and correspondence from regulatory agencies.

The Contractor is solely responsible for all spills or leaks that occur during the performance of this contract. Clean up spills or leaks to the satisfaction of the CO and in a manner that complies with Federal, state, and local laws and regulations.

108 - Prosecution and Progress 108.00_nat_us_02_16_2005

108 Delete.

Delete Section 108 in its entirety

109 - Measurement and Payment 109.00_nat_us_02_17_2005

109 Deletions Delete the following entire subsections

109.06 Pricing of Adjustments.

109.07 Eliminated Work.

109.08 Progress Payments.

109.09 Final Payment.

109.02_nat_us_06_16_2006

109.02 Measurement Terms and Definitions.

(b) Contract quantity.

Add the following

Contract quantities will be adjusted only when there are errors in the original design of 15% or more.

“(b) Cubic yard” to “(c) Cubic yard”.

Change the following:

Add the following definition

(p) Thousand Board Feet (Mbf). 1,000 board feet based on nominal widths, thickness, and extreme usable length of each piece of lumber or timber actually incorporated in the job. For glued laminated timber, 1,000 board feet based on actual width, thickness, and length of each piece actually incorporated in the job.

155 - Schedules for Construction Contracts 155.00_nat_us_05_11_2004

155 Delete.

Delete Section 155 in its entirety

201 - Clearing and Grubbing 201.01_nat_us_02_18_2005

201.01 Description

Replace with the following

This work consists of clearing and grubbing within clearing limits and other designated areas.

201.04_nat_us_02_22_2005

201.04 Clearing. (c)

(c) In areas outside the excavation, embankment, and slope rounding limits, cut stumps to within 12 inches or one-third of the stump diameter of the ground, whichever is higher, measured on the side adjacent to the highest ground. For timber sales, stump heights will meet the requirements of the Timber Sale contract.

Delete paragraph (c) and replace with the following:

201.04 Clearing.

(d) Do not cut vegetation less than 3 feet tall and less than 3 inches in diameter, that is within the clearing limits but beyond the roadway and not in a decking area, and that does not interfere with sight distance along the road.

Delete subsection (d) and replace with the following:

(e) Trim branches of remaining trees or shrubs to give a clear height of 14 feet above the roadbed unless otherwise indicated. Trim tree limbs as near flush with the trunk as practicable.

(f) Remove brush from log decks. Deck logs so that logs are piled parallel to one another; can be removed by standard log loading equipment; will not damage standing trees; will not interfere with drainage, and will not roll. Keep logs in log decks free of brush and soil.

203 - Removal of Structures and Obstructions 203.01_nat_us_02_25_2005

203.01 Description.

This work consists of disposing of construction slash and debris, salvaging, removing, and disposing of buildings, fences, structures, pavements, culverts, utilities, curbs, sidewalks, and other obstructions.

Delete and replace with the following:

203.04_nat_us_02_18_2005

203.04 Removing Material.

Where part of an existing culvert is removed, remove the entire culvert upstream from the removal. The remaining downstream culvert may be left in place if no portion of the culvert is within 12 inches of the subgrade, embankment slope, or new culvert or structure; and the culvert ends are sealed with concrete.

Replace the fourth and fifth paragraphs with the following:

Remove structures and obstructions in the roadbed to 12 inches below subgrade elevation.

Remove structures and obstructions outside the roadbed to 12 inches below finished ground or to the natural stream bottom.

203.08_nat_us_02_24_2005

203.08 Payment

Disposal of construction slash will be compensated under the designated pay item in Section 201.

204 - Excavation and Embankment 204.06_nat_us_03_02_2005

204.06 Roadway Excavation.

d) Pioneer Roads. Road pioneering, slash disposal, and grubbing of stumps may proceed concurrently with excavation. Conduct excavation and placement operations so material to be treated under Section 201 will not be incorporated into the roadway unless specified in the slash treatment method. Maintain drainage during pioneering operations.

Add the following:

Remove snow and ice in advance of the work and deposit beyond the roadway limits in a manner that will not waste material or generate sediment. Do not incorporate snow and ice into embankments. Place snow or ice in a manner to prevent resource damage.

204.06_nat_us_03_02_2005

204.06 Roadway Excavation

(a) General.

Retrieve material deposited outside of the clearing limits as directed by the CO. Place unsuitable material in designated areas.

204.09_nat_us_03_02_2005

204.09 Preparing Foundation for Embankment Construction.

(a) Embankment less than 4 feet high over natural ground. When designated, remove topsoil and break up the ground surface to a minimum depth of 6 inches by plowing or scarifying.

Compact the ground surface according to Subsection 204.11.

Delete subsection (a) and replace it with the following:

204.10_nat_us_03_02_2005

204.10 Embankment Construction.

Obtain written approval before beginning construction of embankments over 6 feet high at subgrade centerline.

(a) General.

Compact embankment side slopes flatter than 1V:1.75H with a tamping type roller or by walking with a dozer. For slopes 1V:1.75H or steeper, compact the slopes as construction of the embankment progresses.

Delete the third paragraph and add the following:

204.11_nat_us_04_11_2005

204.11 Compaction.

For compaction according to method (a), (b), or (c), use AASHTO T 27 to determine the amount of material retained on a Number. 4 sieve. For compaction methods (d) or (e) no sieve test is required.

Delete the first paragraph and replace it with the following:

Add the following compaction methods

(d) Layer Placement Method (Hauling and Spreading Equipment). Place material by end dumping to the minimum depth needed for operation of spreading equipment. Level and smooth each embankment layer before placing the next layers. Operate hauling and spreading equipment uniformly over the full width of each layer. Construct a solid embankment with adequate compaction by working smaller rock and fines in with the larger rocks to fill the voids, and by operating hauling and spreading equipment uniformly over the full width of each layer as the embankment is constructed.

(e) Layer Placement (Roller Compaction) Method. Place material by end dumping to the minimum depth needed for operation of spreading equipment. Adjust the moisture content of the material to obtain a mass that will not visibly deflect under the load of the hauling and spreading equipment. Operate compaction equipment over the full width of each layer until visible deformation of the layer ceases or, in when a sheepsfoot roller is used, the roller “walks out” of the layer. Make at least three complete passes.

204.13_nat_us_03_02_2005

204.13 Sloping, Shaping, and Finishing.

(d) Finishing. For surfaced roads, remove all material larger than 6 inches from the top 6 inches of the roadbed. For all roads, finish the roadbed to be smooth and uniform, and shaped to conform to the typical sections. Remove unsuitable material from the roadbed and replace it with suitable material. Finish roadbeds to the tolerance class shown in table 204-2.

Delete section (d) and add the following:

Ensure that the subgrade for both surfaced and unsurfaced roads is visibly moist during shaping and dressing. Scarify to 6 inches below the bottom of low sections, holes, cracks, or depressions and bring back to grade with suitable material. Maintain proper ditch drainage.

For unsurfaced roads, use one of the following methods to finish the roadbed:

(1) Method A. Remove all material larger than 6 inches from the top 6 inches of the roadbed and replace with suitable material.

(2) Method B. Use a vibratory grid roller or approved equal with a minimum weight of 10 tons. Roll at least 5 full-width passes or until visible displacement ceases.

(3) Method C. For roads designated as Construction Tolerance Class K, L, or M, finish the roadbed by spreading the excavation. Eliminate rock berms.

Add Table 204-2—Construction Tolerances:

Table 204-2 Construction tolerances.

Tolerance Class(a)

A B C D E F G H I J K L M Roadbed width (ft) +0.5 +0.5 +1.0 +1.0 +1.0 +1.0 +1.5 +1.0 +2.0 +2.0 +2.0 +2.0 +2.0

Subgrade elevation

(ft)

+0.1 +0.2 +0.2 +0.5 +0.5 +1.0 +1.0 +1.5 +2.0 +3.0 +2.0 +3.0 (c)

Centerline alignment (ft)

+0.2 +0.2 +0.5 +0.5 +1.0 +1.0 `+1.5 +1.5 +2.0 +3.0 +3.0 +5.0 (c)

Slopes, excavation, and embankment (% slope(b)

+3 +5 +5 +5 +5 +5 +10 +10 +10 +10 +20 +20 +20

a. Maximum allowable deviation from construction stakes and drawings.

b. Maximum allowable deviation from staked slope measured from slope stakes or hinge points.

c. Unless otherwise shown the centerline alignment and subgrade elevation, as built, have no horizontal curves with a radius of less than 80 feet, and no vertical curves with a curve length of less than 80 feet when the algebraic difference in the grade change is less than 10 percent, or a curve length of less than 100 feet when the algebraic difference of the grade change is greater than or equal to 10 percent. The centerline grade is not to exceed 20 percent in 100 feet of length.

204.14_nat_us_03_02_2005

204.14 Disposal of Unsuitable or Excess Material.

Dispose of unsuitable or excess material at designated sites or legally off of the project.

Delete the text of the first paragraph and substitute the following:

204.15_nat_us_02_07_2007

204.15 Acceptance

Table 204-1 Sampling and Testing Requirements.

(2) When compaction methods (d) or (e) are used AASHTO M 145, T 99, T 180, and T 310 are not required for earth embankment test methods.

Add the following note to the table:

208 - Structure Excavation and Backfill for Selected Major Structures 208.04_nat_us_06_13_2007

Construction Requirements

208.04 General.

Add the following to the end of the second sentence of the third paragraph:

"... to the CO a minimum of 5 days prior to beginning excavation work."

Add the following to the end of the third sentence of the third paragraph

"...to the CO a minimum of 15 days prior to installation."

208.09 Foundation Preparation.

Add the following after the first paragraph:

The foundation elevation is defined as the bottom of footings, for spread footing placement; the bottom of the pile cap, for construction of pile foundations; and the toe of the wall, for construction of retaining walls, except wingwalls at bridges.

Replace all material from any over-excavation below the designated footing elevation with concrete, compacted gravel, or foundation fill at the direction of the CO.

When boulders or irregular, fractured, or seamed bedrock precludes excavation to the designated footing elevation without further loosening of previously solid material, the CO may order removal of such loose material and allow payment for concrete, gravel, or structural backfill that is required to restore foundation material to the designated elevation

208.13 Measurement.

Add the following to the second paragraph

(f) Material excavated to construct end walls or wing walls which lie outside the excavation limits specified above.

Add the following paragraph

Foundation over-excavation and the resulting replacement material will not be measured for payment unless the CO determines the over-excavation was unavoidable because of the nature of the material.

301 - Untreated Aggregate Courses 301.00_nat_us_03_03_2005

301 Title Change.

Change the title to:

Section 301 Aggregate Courses

301.01_nat_us_03_03_2005

301.01 Work.

Add the following

Work includes producing aggregate by pit-run, grid rolling, screening, or crushing methods, or placing Government-furnished aggregate. Work may include additive mineral filler, or binder.

301.02_nat_us_05_16_2005

301.02 Material.

Bentonite

Add the following:

725.30

Calcium Chloride Flake 725.02

Lignon Sulfonate 725.20

Magnesium Chloride Brine or Calcium Chloride Liquid 725.02

301.03_nat_us_09_14_2005

301.03 General.

Add the following

Written approval of the roadbed is required before placing aggregate.

For pit run or grid-rolled material, furnish material smaller than the maximum size. No gradation other than maximum size will be required for pit-run or grid-rolled material. For grid rolling, use all suitable material that can be reduced to maximum size. After processing on the road, remove all oversize material from the road and dispose of it as directed by the CO.

Provide additives or binder, if required, at the proportions specified.

Develop and use Government furnished sources according to Section 105.

If the aggregate is produced and stockpiled before placement, handle and stockpiled according to Section 320. Establish stockpile sites at locations approved. Clear and grub stockpile sites according to Section 201.

301.04_nat_us_03_03_2005

301.04 Mixing and Spreading.

Ensure that aggregate and any required additives, water, mineral filler, and binder are mixed by the specified method except, if crushed aggregate products are being produced and mineral filler, binder, or additives are required, uniformly blend following crushing. Control additive proportions to 0.5 percent dry weight.

Delete the first sentence of the first paragraph and add the following:

(a) Stationary Plant Method. Mix the aggregate with other required materials in an approved mixer. Add water during the mixing operation in the amount necessary to provide the moisture content for compacting to the specified density. After mixing, transport the aggregate to the jobsite while it contains the proper moisture content, and place it on the roadbed or base course using an aggregate spreader.

(b) Travel Plant Method. After placing the aggregate for each layer with an aggregate spreader or windrow-sizing device, uniformly mix it with other required materials using a traveling mixing plant. During mixing, add water to provide the necessary moisture content for compacting.

(c) Road Mix Method. After placing the aggregate for each layer, mix it with other required materials at the required moisture content until the mixture is uniform throughout. Mix aggregate, water, and all other materials until a uniform distribution is obtained.

Spread the aggregate in a uniform layer, with no segregation of size, and to a loose depth that will provide the required compacted thickness.

When placing aggregate over geotextile, place aggregate in a single lift to the full depth specified.

Route and distribute hauling and leveling equipment over the width and length of each layer.

301.05_nat_us_05_17_2005

301.05 Compacting

Delete and replace with the following

Compact each layer full width. Roll from the sides to the center, parallel to the centerline of the road. Along curbs, headers, walls, and all places not accessible to the roller, compact the material with approved tampers or compactors.

Compact the aggregate using one of the following methods as specified:

Compaction A. Operating spreading and hauling equipment over the full width of the travelway.

Compaction B. Operate rollers and compact as specified in Subsection 204.11(a)(1).

Compaction C. Moisten or dry the aggregate to a uniform moisture content between 5 and 7 percent based on total dry weight of the mixture. Operate rollers and compact as specified in Subsection 204.11(a)(1).

Compaction D. Compact to a density of at least 95 percent of the maximum density, as determined by AASHTO T 99, method C or D.

Compaction E. Compact to a density of at least 96 percent of the maximum density, as determined by the Modified Marshall Hammer Compaction Method (available upon request from USDA Forest Service, Regional Materials Engineering Center, P.O. Box 7669, Missoula, MT 59807).

Compaction F. Compact to a density of at least 95 per-cent of the maximum density, as determined by AASHTO T 180, method C or D.

Compaction G

. Compact to a density of at least 100 percent of the maximum density as determined by the Modified Marshall Hammer Compaction Method (available upon request from USDA Forest Service, Regional Materials Engineering Center, P.O. Box 7669, Missoula, MT 59807).

For all compaction methods, blade the surface of each layer during the compaction operations to remove irregularities and produce a smooth, even surface. When a density requirement is specified, determine the in place density and moisture content according to AASHTO T 310 or other approved test procedures.

301.06_nat_us_03_03_2005

301.06 Surface Tolerance.

Add the following:

Thickness and Width requirements

The maximum variation from the compacted specified thickness is ½ inch. The compacted thickness is not consistently above or below the specified thickness and the average thickness of 4 random measurements for any ½ mile of road segment is within + ¼ inch of the specified thickness.

The maximum variation from the specified width will not exceed +12 inches at any point. The compacted width is not consistently above the specified width and the average of any four random measurements along any ½ mile of road segment is within +4 inches of the specified width.

301.08_nat_us_02_07_2007

Table 301-1 Field Density Requirements.

Table 301-1: Delete laboratory and field density requirements for base, subbase, and surfacing and replace with the followin

Material or Product g:

Type of Acceptance (Subsection)

Characteristi c

Category Test Methods Specification s

Sampling Frequency

Point of Sampling

Split Sample

Reporting Time

Base and Subbase

Measured and tested conformance (Subsection 106.04)

Moisture Density ---

Method C --- AASHTO T 99 1 per type and source of material

Source of material

Yes Before using in work

Method C-1 --- R-1 Marshall “ “ “ “

Method D --- AASHTO T 180 “ “ “ “

Method D-1 --- R-1 Marshall “ “ “ “

Compaction ---

Method C, C-1, D, D-1

--- AASHTO T 310 or other approved procedures

1 per 500 t In-place --- Before placing the next layer

Surfacing Measured and tested conformance (Subsection 106.04)

Moisture Density

Method C-1 --- R-1 Marshall “ “ “ Before using in work

Method D --- AASHTO T 180 “ “ “ “

Method D-1 --- R-1 Marshall “ “ “ “

Compaction

Method C, C-1, D, D-1

--- AASHTO T 310 or other approved procedures

1 per 500 t In-place --- Before placing the next layer

301.08_nat_us_03_03_2005

Table 301-1: Add the following:

Table 301-1—Acceptance Sampling and Testing Requirements.

Material or Product

Type of Acceptance (Subsection)

Characteristi c

Category Test Methods Specification s

Sampling Frequency

Point of Sampling

Split Sample

Reporting Time

Subbase & Base Courses L, M, N, O, P, Q, R

Measured and tested conformance

(Subsection 106.04)

Plastic Limit - AASHTO T 90 1 per each 1,000 T

From the windrow or roadbed after processing

Yes 4 Hours

Table 301-1—Acceptance Sampling and Testing Requirements.

Material or

Product Type of

Acceptance (Subsection)

Characteristi c

Category Test Methods Specification s

Sampling Frequency

Point of Sampling

Split Sample

Reporting Time

Aggregate Width Measured and tested conformance

(Subsection 106.04)

Width - - 4 per each 0.5 mi

Roadbed after processing

- 4 Hours

Aggregate Thickness Measured and tested conformance

(Subsection 106.04)

Thickness - - 4 per each 0.5 mi

Roadbed after processing

- 4 Hours

Additive Measured and tested conformance

(Subsection 106.04)

Amount of Additive - 1 per each 1,000 T

From the windrow or roadbed after processing

No 4 Hours

301.08_nat_us_03_30_2005

301.08(b) Plasticity Index.

Add the following to the first sentence

“and under 703.05(c)(1)”.

301.09_nat_us_07_07_2005

301.09 Measurement.

Replace the second paragraph with the following

Measure aggregate by cubic yard compacted in place when payment is by contract quantities.

301.10_nat_us_03_03_2005

301.10 Payment

adjusted according to Subsection 106.05 Delete the following:

603 - Structural Plate Structures 603.03_nat_us_03_02_2005

603.03 General.

Do not place or backfill structure until the CO has approved in writing the excavation and foundation. Submit four sets of shop drawings of the long-span structure to the CO at least 21 days before planned construction. Accompany shop drawings with all calculations used to determine the size, shape, location, and spacing of stiffening ribs, thrust beams, or other special structural features.

603.04_nat_us_03_02_2005

603.04 Erecting.

Torque all bolts before beginning the backfill.

Add to the third paragraph:

625 - Turf Establishment 625.04_nat_us_02_25_2005

625.04 Preparing Seedbed.

Delete “2 inches in diameter and larger,” from the second sentence.

625.05_nat_us_03_30_2005

625.05 Watering.

625.06 Fertilizing

(a) Dry method or (b) Hydraulic method Add the following:

Fertilizer shall be uniformly applied at the rate of 1000 lbs. ber acre and shall have A chemical analysis of 10% Nitrogen, 10% Phosphorus, and 10% Potassium.

625.07_nat_us_02_25_2005

625.07 Seeding. (a) Dry method.

Remove the last sentence “Lightly compact the seedbed within 24 hours after seeding.”

625.07 Seeding

Add the following:

“The seeding season shall be from January 1st to December 31st.

Seed and fertilizer shall be applied at the rates for one of the seeding periods as follows:

The clover shall be inoculated.

Fescue shall be certified by the supplier to be Endophyte Free.

See drawing EC3 for seeding mixture.

625.08 Mulching

Add the following:

Mulch shall be applied at the following rates:

Hay or straw @ the rate of 4,000 pounds per acr, wood cellulose @ the rate of 1500 pounds per acre.

635 - Temporary Traffic Control 635.03_nat_us_05_13_2004

635.03 General.

Install temporary traffic control signs to temporary posts or approved temporary sign mounts.

648 - Stream Simulation 648.00_nat_us_04_17_2008

648 – Streambed Simulation

Description

648.01 This work consists of placing rock and fill to simulate a natural streambed, profile and cross section though road stream crossings. The placement of Channel Rock for: fish rest stop, rock bands, rock weirs, stream bank rocks, and other in stream rock structures, is included within this specification.

Material

648.02 Conform to the following Subsections.

Foundation Fill 704.01

Stream Bed Simulation Material 705.07 Channel Rock 705.08

Construction Requirements

648.03 General. Place streambed simulation material on a prepared surface to form a well-graded, low permeability mass, similar in appearance and texture to the natural streambed. Do not drive metal track or rubber tired equipment directly on metal or concrete structure surfaces.

648.04 Placed Streambed Simulation Material and Channel Rock.

(a) Method A, Machine Placed. Place stream simulation rock in one or more layers with a layer depth less than 1 ½ times the maximum dimension of the stream simulation rock. Place stream simulation by methods that do not cause segregation or damage to the prepared surface. Place or rearrange individual rocks by mechanical methods to obtain a compact low permeability mass matching streambed simulation details. Fill voids before placing the next lift. Place fish rest stop, rock bands, rock weirs, stream bank rocks, and other in stream rock structures as designated.

(b) Method B, End Dumped. Dump stream simulation rock in one or more layers with a layer depth less than 1 ½ times the maximum dimension of the stream simulation rock.

Distribute larger rocks throughout the mass of stone. Obtain a uniformly dense, compact, low permeability bed with a surface matching stream simulation bed details. Fill voids before placing the next lift. Place fish rest stop, rock bands, rock weirs, stream bank rocks, and other in stream rock structures as designated.

(c) Method C, Hand Placed. Place stream simulation rock using hand labor. Material may be hand carried, or carried in wheelbarrows and end dumped to obtain its full thickness. Compact each load using hand operated or hand operated mechanical equipment to obtain a uniformly dense, compact, low permeability bed with a surface matching stream simulation bed details. Fill voids before placing the next lift. Place fish rest stop, rock bands, rock weirs, stream bank rocks, and other in stream rock structures as designated.

648.04 Foundation fill. Fill all voids left during placement of Channel Rocks and Streambed Simulation adjacent to footings, concrete structures or corrugated pipes with foundation fill. Use water pressure, metal tamping rods, and similar hand operated equipment to force material into all surface and subsurface voids between the structure and rocks and between individual rocks.

648.05 Acceptance. Placing streambed simulation material will be evaluated under Subsections 106.02 and 106.04.

Measurement

648.06 Measure the items listed in the bid schedule according to Subsection 109.02.

Payment

648.07 The accepted quantities, measured as provided in Subsection 109.02, will be paid at the contract unit price per unit of measurement for Section 648 pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section.

See Subsection 109.05

718 - Traffic Signing and Marking Material 718.05_nat_us_02_25_2008

718.05 Aluminum Panels

Delete the third paragraph and replace with the following:

Clean, degrease and properly prepare the panels according to methods recommended by the sheeting manufacturer. Conversion coatings will conform to ASTM B-921 or ASTM B-449.

Bryant Creek Culvert Replacement
Supplemental Specifications to FP-03
June 2011
Table of Contents
Preface
101 - Terms, Format, and Definitions
101.03 Abbreviations.
101.04 Definitions.
102 - Bid, Award, and Execution of Contract
102 Bid, Award, and Execution of Contract
103 - Scope of Work
Deletions
104 - Control of Work
Deletions
104.06 Use of Roads by Contractor
105 - Control of Material
105.02 Material Sources.
105.02(a) Government-provided sources.
105.05 Use of Material Found in the Work.
106 - Acceptance of Work
106.07 Delete
107 - Legal Relations and Responsibility to the Public
107.05 Responsibility for Damage Claims.
107.06 Contractor’s Responsibility for Work.
107.09 Legal Relationship of the Parties.
107.10 Environmental Protection.
108 - Prosecution and Progress
108 Delete.
109 - Measurement and Payment
109 Deletions
109.02 Measurement Terms and Definitions.
155 - Schedules for Construction Contracts
155 Delete.
201 - Clearing and Grubbing
201.01 Description
201.04 Clearing. (c)
203 - Removal of Structures and Obstructions
203.01 Description.
203.04 Removing Material.
204 - Excavation and Embankment
204.06 Roadway Excavation.
204.09 Preparing Foundation for Embankment Construction.
204.10 Embankment Construction.
204.11 Compaction.
204.13 Sloping, Shaping, and Finishing.
Table 204-2 Construction tolerances.
204.14 Disposal of Unsuitable or Excess Material.
204.15 Acceptance
Table 204-1 Sampling and Testing Requirements.
208 - Structure Excavation and Backfill for Selected Major Structures
301 - Untreated Aggregate Courses
301 Title Change.
301.01 Work.
301.02 Material.
301.03 General.
301.04 Mixing and Spreading.
301.05 Compacting
301.06 Surface Tolerance.
Table 301-1 Field Density Requirements.
Table 301-1—Acceptance Sampling and Testing Requirements.
301.08(b) Plasticity Index.
301.09 Measurement.
603 - Structural Plate Structures
603.03 General.
603.04 Erecting.
625 - Turf Establishment
625.04 Preparing Seedbed.
625.05 Watering.
625.07 Seeding. (a) Dry method.
635 - Temporary Traffic Control
635.03 General.
648 - Stream Simulation
718 - Traffic Signing and Marking Material