EWP_FPEBID ABSTRACT Calc.xls

XLS spreadsheet 33 KB Posted

Attached to
"RECOVERY" Demolition of Structures and Restoration of Land for the Emergency Watershed- FloodPlain Easement Program
Solicitation number
AG-3D47-S-10-0004
Issued by

View the file

Other files

File Type Posted
AG-3D47-S-10-0004.Amend 1.SF30.pdf PDF
Davis Bacon Wage Rates.Building.pdf PDF
Construction Drawings.pdf PDF
Construction Specifications.pdf PDF
SF-1442.IFB.EWP-FPE.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bid 1

ABSTRACT OF OFFERS- CONSTRUCTIONSOLICITATION NO.DATE ISSUEDDATE OPENEDPAGES
5/25/106/24/101 of 1
AG-3D47-S-10-0004
ISSUING OFFICEI CERTIFY that I have opened, read, and recorded on this abstract all offers received in response to this solicitationNAME AND TITLE OF CERTIFYING OFFICIAL (TYPE)
USDA/NRCS/////SIGNED///// Amy Bolyard, Contract Specialist
1550 Earl Core Road, Suite 200
MORGANTOWN, WV 26505Signature
PROJECT TITLE:
Emergency Watershed - Floodplain
Easement Program (EWP-FPE)
ENGINEER ESTIMATECLAUDE ERPS CONSTRUCTIONTEAYS RIVER CONSTRUCTION COMASTER MECHANICAL INSULATION, INC
Bid Schedule ABLUEFIELD, WVCROSS LANES, WVHUNTINGTON, WV
Item No.ItemQuantityUnitUnit PriceEstimated AmountUnit PriceEstimated AmountUnit PriceEstimated Amount
1Silt Fence50LF$ 19.44$ 972.00$ 10.00$ 500.00$ 3.92$ 196.00
2Seeding & Mulching0.5AC$ 2,600.00$ 1,300.00$ 6,000.00$ 3,000.00$ 1,612.00$ 806.00
3Mobilization & Demobilization1LSXXXX$ 3,642.00XXXX$ 15,000.00XXXX$ 800.00
4Site Assessments for Hazardous Material2EA$ 550.00$ 1,100.00$ 1,500.00$ 3,000.00$ 860.00$ 1,720.00
5Testing for Hazardous Material16.0EA$ 25.00$ 400.00$ 50.00$ 800.00$ 125.00$ 2,000.00
6Demolition Plan1EA$ 350.00$ 350.00$ 1,000.00$ 1,000.00$ 680.00$ 680.00
7Hazardous Material Removal30CY$ 150.00$ 4,500.00$ 200.00$ 6,000.00$ 222.00$ 6,660.00
8General Demolition Removal223TN$ 219.00$ 48,837.00$ 150.00$ 33,450.00$ 235.00$ 52,405.00
9Rubble Demolition and Site Grading2EA$ 705.00$ 1,410.00$ 2,500.00$ 5,000.00$ 2,300.00$ 4,600.00
10Septic Tank Decommissioning2EA.$ 550.00$ 1,100.00$ 1,000.00$ 2,000.00$ 785.00$ 1,570.00
11Surface Tank Removal2EA$ 251.00$ 502.00$ 250.00$ 500.00$ 300.00$ 600.00
TOTAL Schedule A$ 64,113.00$ 70,250.00$ 72,037.00
Bid Schedule B
1Silt Fence50LF$ 19.44$ 972.00$ 10.00$ 500.00$ 3.92$ 196.00
2Seeding & Mulching0.9AC$ 2,600.00$ 2,340.00$ 6,000.00$ 5,400.00$ 1,612.00$ 1,450.80
3Mobilization & Demobilization1LSXXXX$ 4,088.00XXXX$ 15,000.00XXXX$ 800.00
4Site Assessments for Hazardous4EA$ 575.00$ 2,300.00$ 1,500.00$ 6,000.00$ 860.00$ 3,440.00
5Testing for Hazardous Material32EA$ 32.00$ 1,024.00$ 50.00$ 1,600.00$ 125.00$ 4,000.00
7Demolition Plan3EA$ 287.00$ 861.00$ 1,000.00$ 3,000.00$ 681.00$ 2,043.00
9Hazardous Material Removal90CY$ 100.00$ 9,000.00$ 200.00$ 18,000.00$ 222.00$ 19,980.00
10General Demolition Removal376TN$ 158.00$ 59,408.00$ 150.00$ 56,400.00$ 276.00$ 103,776.00
11Rubble Demolition and Site Grading4EA$ 1,465.00$ 5,860.00$ 2,500.00$ 10,000.00$ 2,300.00$ 9,200.00
12Septic Tank Decommissioning1EA$ 550.00$ 550.00$ 1,000.00$ 1,000.00$ 785.00$ 785.00
Payment and Performance Bonds1LSXXXX$ 3,800.00XXXX$ 4,000.00XXXX$ 6,525.89
TOTAL Schedule B$ 90,203.00$ 120,900.00$ 152,196.69
TOTAL BIDTotal Engineer Est.TOTAL A+B$ 154,316.00TOTAL A+B$ 191,150.00TOTAL A+B$ 224,233.69

&C&"Arial,Bold"&12PAGE &P OF 3