ATTACHMENT-I Page 1 of 14
General Decision Number: MN100113 03/19/2010 MN113
Superseded General Decision Number: MN20080113
State: Minnesota
Construction Type: Building
Counties: Aitkin, Beltrami, Clearwater, Cook, Hubbard, Itasca, Kanabec, Koochiching, Lake of the Woods, Mahnomen, Pine and Wadena Counties in Minnesota.
BUILDING CONSTRUCTION PROJECTS (does not include single family homes or apartments up to and including 4 stories).
Modification Number Publication Date
0 03/12/2010
1 03/19/2010
ASBE0049-001 06/01/2009
ALL COUNTIES EXCEPT MAHNOMEN
Rates Fringes
Asbestos Workers/Insulator
(Includes the application of all insulating materials, protective coverings, coatings & finishes to all types of mechanical systems).....$ 35.81 13.80
* ASBE0133-001 07/01/2009
MAHNOMEN COUNTY
ASBESTOS WORKER/HEAT & FROST
INSULATOR (Includes application of all insulating materials, protective coverings, coatings & finishes to all types of mechanical systems)..............$ 27.87 11.20
BOIL0647-001 07/01/2009
BOILERMAKER......................$ 33.84 18.53
BRMN0001-022 05/01/2009
AITKIN (Western half)
ATTACHMENT-I Page 2 of 14
BRICKLAYER.......................$ 32.90 14.65
BRMN0003-001 05/01/2009
AITKIN (Eastern half, on a line with the northeast boundary line of Mille Lacs County), COOK, KANABEC & PINE COUNTIES
BRICKLAYER.......................$ 30.29 17.95
BRMN0015-015 05/01/2009
BELTRAMI, CLEARWATER, HUBBARD, KOOCHICHING, LAKE OF THE WOODS,
MAHNOMEN & WADENA
BRICKLAYER.......................$ 30.20 14.30
BRMN0016-001 05/01/2009
ITASCA COUNTY
BRICKLAYER.......................$ 30.04 18.20
CARP0087-020 05/01/2009
KANABEC, PINE (Southern 1/3)
CARPENTER (Including
Acoustical Ceiling
Installation, Drywall
Hanging, Form Work & Metal
Stud Installation)...............$ 31.79 16.10
CARP0361-002 08/10/2009
COOK, PINE (Northern two-thirds, North of State Highway #23 &
State Highway #48, excluding cities of Beroun, Brook Park, Henriette, Pine City, Rock Creek & West Rock):
Installation, Drywall
ATTACHMENT-I Page 3 of 14
Hanging, Form Work & Metal
Stud Installation)...............$ 26.40 13.80
CARP0606-002 08/03/2009
AITKIN, ITASCA, KOOCHICHING, LAKE OF THE WOODS
Installation, Drywall
Hanging, Form Work & Metal
Stud Installation)...............$ 25.75 12.69
CARP0606-015 06/01/2009
BELTRAMI, CLEARWATER, HUBBARD, MAHNOMEN, WADENA
Installation, Drywall
Hanging, Form Work & Metal
Stud Installation)...............$ 20.57 13.23
ELEC0110-021 11/01/2009
KANABEC (Except Brook, Ford, Krosche, Hillman, Peace & Pomroy), PINE (South of Arione, Barry, Clover, Hinckley & Ogema
Townships)
ELECTRICIAN......................$ 35.55 20.37
ELEC0242-017 05/31/2009
AITKIN, COOK, HUBBARD (Except Rockwood, Helga, Farden, Lake
Hattie, Schoolcraft, Guthrie, Hart Lake, Lake Alice, Lake
George, Hendrickson & Lakeport); ITASCA (Southerly 12 Twps.
including Harris, Feely, Blackberry, Spang, Coodland, Sago &
Wawina), KANABEC (Northern part, including Brook, Ford, Krosche, Hillman, Peace & Pomroy); PINE (Except southerly townships of Brook Park, Mission Creek, Munch, Crosby, Pokegama, Cross Lake, Chengwatana, Royalton, Rock Creek & Pine
City) & WADENA COUNTIES
ELECTRICIAN......................$ 31.24 63.5%
ELEC0294-005 06/01/2009
ATTACHMENT-I Page 4 of 14
BELTRAMI, CLEARWATER, ITASCA (Excluding section South of a line extending East & West of the South line of Grand Rapids & Trout
Lake Twps), KOOCHICHING (Western part bounded on the east by a line extending north and south from the easternmost point of the city limits of Grand Rapids) & LAKE OF THE WOODS (Except extreme NW part)
Electricians:
Electrical Installations
$3,244,800 and over.........$ 32.28 58.75%
Electrical Installations
Under $3,244,800............$ 23.44 37.5%+5.70
ELEC0294-013 05/31/2009
HUBBARD (North part bounded on the south by a line extending east & west of the south line of Lake Alice & Lake George
Townships)
ELECTRICIAN......................$ 32.28 58.75%
ELEC1426-017 06/01/2009
MAHNOMEN, LAKE OF THE WOODS (Extreme NW part)
ELECTRICIAN......................$ 24.76 10.92
ELEV0009-004 01/01/2010
ELEVATOR MECHANIC................$ 40.81 20.035
FOOTNOTE:
PAID VACATION: Employer contributes 8% of regular hourly rate as vacation pay credit for employees with more than 5 years of service, and 6% for 6 months to 5 years of service.
PAID HOLIDAYS: New Years Day, Memorial Day, Independence Day, Labor Day, Veterans Day, Thanksgiving Day, Friday after
Thanksgiving, and Christmas Day.
* ENGI0049-056 05/01/2009
AITKIN, COOK, HUBBARD, ITASCA, KANABEC, KOOCHICHING, PINE,
WADENA
ATTACHMENT-I Page 5 of 14
OPERATOR: Power Equipment
GROUP 1.....................$ 34.64 15.25
GROUP 2.....................$ 34.30 15.25
GROUP 3.....................$ 32.89 15.25
GROUP 4.....................$ 32.55 15.25
GROUP 5.....................$ 32.38 15.25
GROUP 6.....................$ 30.87 15.25
GROUP 7.....................$ 29.75 15.25
GROUP 8.....................$ 27.74 15.25
POWER EQUIPMENT OPERATOR CLASSIFICATIONS
GROUP 1: Truck & Crawler Crane with 200' of Boom & Over, including Jib ($.50 premium with 300' of Boom & over, including jib); & Tower Crane 250' & Over.
GROUP 2: Truck & Crawler Crane with 150' of Boom, up to but not including 200' of Boom, including Jib; & Tower Crane
200' & Over.
GROUP 3: Traveling Tower Crane; Truck & Crawler Crane, up to but not including 150' of Boom, including Jib; Tower Crane
(Stationary) up to 200'; All-Terrain Vehicle Crane, Dragline.
GROUP 4: Backhoe/Track/Trackhoe, Hoist (3 drums or more);
Overhead Crane (inside building perimeter).
GROUP 5: Asphalt Spreader, Bulldozer, Forklift, Compressor
450 CFM or over (2 or more machines); Boom Truck up to 100 ft, Loader over 1 cu yd, Hoist (1 or 2 drums); Roller, Scraper, Tractor over D2.
GROUP 6: Loader up to 1 cu. yd., Tractor D2 or similar size.
GROUP 7: Crane Oiler.
GROUP 8: Oiler, Greaser (Tractor/Truck).
* ENGI0049-057 05/01/2009
BELTRAMI, CLEARWATER, LAKE OF THE WOODS, MAHNOMEN
OPERATOR: Power Equipment
GROUP 1.....................$ 32.75 15.25
GROUP 2.....................$ 32.43 15.25
GROUP 3.....................$ 31.10 15.25
GROUP 4.....................$ 30.78 15.25
GROUP 5.....................$ 30.62 15.25
GROUP 6.....................$ 29.20 15.25
GROUP 7.....................$ 28.14 15.25
GROUP 8.....................$ 26.25 15.25
POWER EQUIPMENT OPERATOR CLASSIFICATIONS
ATTACHMENT-I Page 6 of 14
GROUP 1: Truck & Crawler Crane with 200' of Boom & Over, including Jib ($.50 premium with 300' of Boom & over, including jib); & Tower Crane 250' & Over.
GROUP 2: Truck & Crawler Crane with 150' of Boom, up to but not including 200' of Boom, including Jib; & Tower Crane
200' & Over.
GROUP 3: Traveling Tower Crane; Truck & Crawler Crane, up to but not including 150' of Boom, including Jib; Tower Crane
(Stationary) up to 200'; All-Terrain Vehicle Crane, Dragline.
GROUP 4: Backhoe/Track/Trackhoe, Hoist (3 drums or more);
Overhead Crane (inside building perimeter).
GROUP 5: Asphalt Spreader, Bulldozer, Forklift, Compressor
450 CFM or over (2 or more machines); Boom Truck up to 100 ft, Loader over 1 cu yd, Hoist (1 or 2 drums); Roller, Scraper, Tractor over D2.
GROUP 6: Loader up to 1 cu. yd., Tractor D2 or similar size.
GROUP 7: Crane Oiler.
GROUP 8: Oiler, Greaser (Tractor/Truck).
IRON0512-017 05/01/2009
AITKIN, BELTRAMI, CLEARWATER, COOK, HUBBARD, KOOCHICHING, LAKE
OF THE WOODS, MAHNOMEN, PINE
IRONWORKER, ORNAMENTAL,
REINFORCING AND STRUCTURAL.......$ 29.76 19.50
LABO0132-025 05/01/2009
LABORER (LANDSCAPE)..............$ 16.70 10.49
LABO0132-033 05/01/2009
PINE
LABORER
Common or General, Mason
Tender (Brick)..............$ 30.96 12.13
Pipelayer...................$ 31.46 12.13
LABO0132-034 05/01/2008
ATTACHMENT-I Page 7 of 14
AITKIN, HUBBARD, KANABEC, PINE, WADENA
LABORER (ASBESTOS ABATEMENT)
Removal from Floors, Walls
& Ceilings..................$ 28.11 10.57
LABO0563-020 05/01/2009
AITKIN, HUBBARD, KANABEC, WADENA
Laborers:
(1) Common or General
Laborer, Mason Tender
(Brick, Cement/Concrete)....$ 24.70 11.39
(2) Pipelayer...............$ 25.45 11.39
PROJECTS OVER $950,000: $1.75 additional per hour.
LABO1097-016 05/01/2009
LABORER (Projects $760,000 & over:)
(1) Common or General, Mason Tender (Brick)........$ 18.82 11.22
(2) Pipelayer...............$ 19.22 11.22
LABORER (Projects under
$760,000:)
(1) Common or General, Mason Tender (Brick)........$ 16.25 11.22
(2) Pipelayer...............$ 16.59 11.22
LABO1097-018 05/01/2009
ITASCA, KOOCHICHING
LABORER
Common or General, Mason
Tender (Brick)..............$ 22.91 11.87
Pipelayer...................$ 23.31 11.87
PAIN0061-002 05/01/2009
PINE (Southern half, on a line east and west through Hinckley)
Drywall
ATTACHMENT-I Page 8 of 14
Finisher/Taper..............$ 30.94 15.40
Sander......................$ 23.19 15.40
PAINTER
Brush, Roller, Paperhanger..$ 30.94 15.60
Spray.......................$ 31.69 15.60
PAIN0106-016 05/01/2008
COOK, HUBBARD, ITASCA, KOOCHICHING, PINE (Northern part including Hinckley and Sandstone)
PAINTER
New:
Brush, Roller, Paperhanger.$ 27.41 12.52
Spray, Drywall
Finisher/Taper.............$ 28.01 12.52
Repaint/Remodel:
Brush, Roller, Paperhanger.$ 25.91 12.52
Spray, Drywall
Finisher/Taper.............$ 26.51 12.52
PAIN0386-004 05/01/2009
KANABEC
Drywall
Finisher/Taper..............$ 29.17 17.17
Sander......................$ 21.87 17.17
PAIN0386-015 05/01/2009
Brush, Roller, Paperhanger..$ 30.60 15.94
Spray.......................$ 31.35 15.94
PAIN0884-018 06/01/2009
AITKIN, BELTRAMI, HUBBARD, LAKE OF THE WOODS, MAHNOMEN, WADENA
Brush, Roller, Paperhanger..$ 24.16 13.01
PROJECTS UNDER $8,000: Receive 80% of basic hourly rate.
PAINTER'S PREMIUM: $0.75 per hour additional for the following work: Spray, Two Component Paints, Epoxies, ATTACHMENT-I Page 9 of 14
Sandblasting & Rigging, Work done on Swing Scaffolding, Safety harness, Window Jacks, Boatswain's Chair, Coverings
& erection of scaffolding for same, Work on erected
Structural Steel, Abrasive Blasting.
PAIN0884-019 06/01/2008
AITKIN
DRYWALL FINISHER/TAPER...........$ 24.16 11.96
PROJECTS UNDER $8,000: Rate is 80% of basic hourly rate.
PAIN0884-020 06/01/2008
BELTRAMI, CLEARWATER, LAKE OF THE WOODS, MAHNOMEN, WADENA
DRYWALL FINISHER/TAPER...........$ 22.46 11.44
PROJECTS UNDER $8,000: Rate is 80% of basic hourly rate.
PLAS0633-002 05/01/2009
PINE (South of the northern boundaries of Dell Grove, Sandstone & Danforth Townships)
CEMENT MASON/CONCRETE FINISHER...$ 31.14 16.60
PLAS0633-010 05/01/2009
AITKIN, COOK & PINE (North of T 24N)
CEMENT MASON/CONCRETE FINISHER...$ 27.04 15.45
PLAS0633-060 05/01/2009
CEMENT MASON/CONCRETE FINISHER...$ 31.14 16.60
PLAS0633-061 05/01/2008
WADENA
ATTACHMENT-I Page 10 of 14
CEMENT MASON/CONCRETE FINISHER...$ 25.40 12.45
PLAS0633-062 05/01/2008
BELTRAMI, HUBBARD, ITASCA & KOOCHICHING
CEMENT MASON/CONCRETE FINISHER...$ 25.40 12.45
PLAS0633-063 05/01/2009
CLEARWATER, LAKE OF THE WOODS, MAHNOMEN
CEMENT MASON/CONCRETE FINISHER...$ 24.61 12.39
PLUM0011-004 05/01/2008
KANABEC, PINE
PLUMBER/PIPEFITTER...............$ 32.15 14.35
PLUM0011-020 11/02/2009
AITKIN, BELTRAMI, CLEARWATER, COOK (a strip 20 miles inland along the shores of Lake Superior), HUBBARD, LAKE OF THE WOODS, MAHNOMEN, WADENA
PLUMBER/PIPEFITTER...............$ 33.48 11.94
PLUM0589-008 05/01/2009
COOK (Except a strip 20 miles inland along the shores of Lake
Superior), ITASCA, KOOCHICHING
PLUMBER/PIPEFITTER...............$ 34.34 15.97
ROOF0096-012 05/01/2009
ROOFER...........................$ 25.70 9.65
ROOF0096-013 05/01/2009
ATTACHMENT-I Page 11 of 14
ROOFER...........................$ 22.89 9.65
ROOF0096-031 07/01/2009
AITKIN, HUBBARD, WADENA
ROOFER...........................$ 27.93 10.18
ROOF0096-033 06/01/2008
ROOFER...........................$ 27.85 12.40
ROOF0096-046 07/06/2009
COOK, PINE
ROOFER...........................$ 29.20 13.20
SHEE0010-011 06/01/2008
BELTRAMI, CLEARWATER, LAKE OF THE WOODS
SHEET METAL WORKER (Including
HVAC Duct and System
Installation)....................$ 27.00 11.67
SHEE0010-046 05/01/2008
Installation)....................$ 29.99 16.08
SHEE0010-073 06/01/2008
HUBARD, WADENA
ATTACHMENT-I Page 12 of 14
Installation)....................$ 29.95 14.49
SHEE0010-075 05/01/2009
AITKIN, COOK
Installation)....................$ 31.61 16.52
SHEE0010-079 05/01/2009
KANABEC, PINE
Installation)....................$ 38.46 18.34
FOOTNOTE: Paid Holiday: Labor Day
SHEE0010-080 05/01/2009
MAHNOMEN
Installation)....................$ 32.57 16.18
SUMN2009-033 07/27/2009
GLAZIER..........................$ 19.75 5.53
LABORER: Roof Tearoff...........$ 10.42 2.08
OPERATOR: Bobcat/Skid Loader....$ 20.75 0.00
OPERATOR: Excavator.............$ 17.64 2.97
OPERATOR: Mechanic..............$ 19.74 4.47
TRUCK DRIVER: Dump Truck........$ 13.92 1.08
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
ATTACHMENT-I Page 13 of 14
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29 CFR 5.5(a)(1)(ii)).
In the listing above, the "SU" designation means that rates listed under the identifier do not reflect collectively bargained wage and fringe benefit rates. Other designations indicate unions whose rates have been determined to be prevailing.
WAGE DETERMINATION APPEALS PROCESS
1.) Has there been an initial decision in the matter? This can be:
* an existing published wage determination
* a survey underlying a wage determination
* a Wage and Hour Division letter setting forth a position on a wage determination matter
* a conformance (additional classification and rate) ruling
On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.) and
3.) should be followed.
With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of
Construction
Wage Determinations. Write to:
Branch of Construction Wage Determinations
Wage and Hour Division
U.S. Department of Labor
200 Constitution Avenue, N.W.
Washington, DC 20210
ATTACHMENT-I Page 14 of 14
2.) If the answer to the question in 1.) is yes, then an interested party
(those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR
Part 7).
Write to:
Wage and Hour Administrator
U.S. Department of Labor
The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board
(formerly the
Wage Appeals Board). Write to:
Administrative Review Board
U.S. Department of Labor
4.) All decisions by the Administrative Review Board are final.
END OF GENERAL DECISION