Questions_and_Answers.docx
DOCX document 17 KB Posted
- Solicitation number
- AG-32SD-S-15-0037
View the file
Other files
| File | Type | Posted |
|---|---|---|
| S-15-0037 clz-prov 8-18-15.doc | DOC document | |
| 1445_Ded_Circuits_PBARC_FINAL_SPECS_20150311_rev1.pdf | ||
| S-15-0037 clz-prov.doc | DOC document | |
| Gen_Dec_HI150001 7-10-15.pdf | ||
| SF18.pdf | ||
| 1445_Ded_Circuits_PBARC_FINAL_DWGS_20150311.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFQ# AG-32SD-S-15-0037
Dedicated circuits, Hilo, HI The following questions and answers are provided:
1. Drawing E-202 shows multi-outlet assemblies being re-routed to new panels 2EPL6 and 2EPL7. Drawing indicates that dashed lines are existing and solid lines are new. There are three areas where the outlet assemblies have a more solid line than the other areas (RM 232 in two locations and Hallway by Rm 239). Are these new assemblies or are they existing and, if new, Identify the type of multi-outlet assembly required (manufacturer). We understand that you are trying to re-route existing circuitry to the 2 new panels (2EPL6 and 2EPL7) but want to clarify if there are to be new multi-outlet assemblies also being installed. Response: These outlets are existing.
2. Drawing E-203 shows circuitry in solid lines going to existing panel "2-HD". Are these all new circuits being installed and if so are they all surface mount? Response: These circuits are existing.
3. Drawing E-101 and also on E-601 show a new 4"C to be installed to a new JB at the existing Administration Building. Is this an underground run and identify the size of the Junction Box required. Response: This is underground run and JB size to be per NEC and minimum 30"W x 36"H x 12"D.
4. Drawing E-701 show three panel schedules. We have identified where panels 2EPL6 and 2EPL7 are located. Is panel E1LPTO as shown on the panel schedule a new panel and, if so, where is this being installed and where is it being fed from? Since this is a remodel installation are all of these panels surface mount? Response: Panel E1LPTO is existing. New panels are surface mount.